Professional Documents
Culture Documents
PDF Mass Con Pak Suradjin 2 PDF
PDF Mass Con Pak Suradjin 2 PDF
By
Table of Contents
Page
1.) Purposes 3
2.) Scope of Works 4
3.) Controlling Temperatures in the Mass Concrete 4
3.1 ) Concrete Mixing & Supply 4
3.2) Concrete Placement 6
3.3) Curing Procedure 6
4.) Illustration Picture from Other Similar Projects 8
1.) PURPOSES
This method statement describes the work procedures to be carried out during an
execution stage of Pelletizer Structure foundations at gridlines
51A/511,51A/512,51A/513,51B/511,51B/512 and 51B/513 respectively, of which the
character of the concrete is technically specified as a mass concrete foundations viz. they
are concrete structures with large dimensions simply figured of greater than 1.50 meters
for all dimensions.
The entire procedure can be organized into 3 steps. First step is a pre-cooling procedure
with will be applied at the concrete batching plant to achieve a minimum concrete
temperature supply. Second step is to minimize time delivery of concrete since being
dispatched from batching plant to the workface and to minimize time spending before
concrete placement at the workface and third step is a post-cooling procedure with will
be applied during concrete curing upon a completion of concrete placement.
A temperature differential between the center of the concrete mass and any about the
outside faces will be kept minimum ( Basically , heat on the surface of the concrete is
easily released toward the ambient whereas the center remains its high temperatures , this
follows that the temperature differential will induce the internal restraint and
subsequently introduce thermal contraction cracks.
The method statement also includes details of temperature differential control procedure
during concrete placement with related to pouring sequence.
Special care and planning is required as the volume of pour is large in relation to those
normally being place on the workface.
1
ACI 116R : Cement and Concrete Terminology concrete, mass—any volume of concrete with dimensions large enough to
require that measures be taken to cope with generation of heat from hydration of the cement and attendant volume change, to
minimize cracking.
ACI 207 ,4R-93 : Cooling and Insulation System for Mass Concrete—2.3-Structure dimensions Where the least
dimension of a concrete unit is not large, the concrete mixture is low in heat evolution, and the heat of hydration can escape
readily from the two boundary surfaces (forms not insulated), the maximum temperature rise will not be great.
Note :
Because the definition does not provide a specific measure, many agencies have developed their own definitions of mass
concrete.
This method statement includes e.g. pre-cooling procedure before & during concrete
mix, supply & delivery of concrete, inspection of concrete at the workface and post-
cooling by a proper cooling upon a completion of concrete placement.
3.1) Concrete Mixing & Supply: With a large concrete pour of this magnitude it is
essential that proper pre-construction planning methods and proper checks be in place
prior to execution of the works. A mass pour is considered to be demanded a special
attention to be given to logistical and technical considerations such as concrete supply,
casting sequence and temperature differential control by thermal quilts curing method
etc. Finally, a report of temperature monitoring will be conducted.
(a) Use of ice as part of mixing water2: This application is effective in reducing
concrete temperature, because on melting alone, to absorb heat. The following
measures will be applied:
2
ACI 207 ,4R-93 : Cooling and Insulation System for Mass Concrete— 3.3.2 Using ice as batch water -One lb (kg) of
ice absorbs 144 Btu’s (334 kJ) when it changes from ice to water; thus, the use of ice is one of the basic and most efficient
methods to lower concrete placing temperatures. The earliest method involved the use of block ice that was crushed or chipped
immediately before it was batched. Later methods utilized either ice flaking equipment, where ice is formed on and scraped from
a refrigerated drum that revolves through a source of water; or equipment where ice is formed and extruded from refrigerated
tubes and is clipped into small biscuit-shaped pieces as it is extruded.
¾ Add ice as a part of mixing water for the concrete mix to reduce the water
temperature. The ice will be added until the water temperature is reduced to
reach 8-10 Celsius Degree. The amount of ice added to the water is dependent
on the air temperature at the certain mixing day.
¾ Spray cool water to the trucks mixers to reduce the temperature of the trucks
mixers.
¾ At the batching, the first batch of the concrete shall be checked its
temperature. The water temperature will be continued to reduce until the
concrete temperature is lower than 30 Celsius Degree prior to the delivering to
the workface.
¾ The above process will be regularly done during the entire period of supply to
ensure that the same degree of temperature always be maintained.
¾ At the workface upon a delivery of the concrete, the fresh concrete will be re-
measured whether the temperature is still within the specified tolerance.
(b). Using Low Heat Concrete: mix design for low heat concrete mix will be submitted
for approval prior to use. In addition, trail mix will be done prior to use.
Concrete Delivery4 : since the temperature rise can be increased with a passage
of time thus the period between mixing and delivery will be kept to an absolute
minimum. Attention will be given to coordinating and dispatching of the mixing
trucks with the rate of placement to avoid delays in delivery. Details are as
follows:
Access: Designated site access routes for concrete supply will be prepared and
traffic control measures implemented. The proper access must be organized to
enable a continuous transportation of the concrete during the entire period of
pouring so that the required temperature of concrete pour will be maintained.
Supply: Concrete batching plant capacity and numbers of delivery trucks will be
planned to maintain a continuous supply of concrete so that an introducing to
3
ACI 207 ,4R-93 : Cooling and Insulation System for Mass Concrete— 3.4- Aggregate cooling Although most rock
minerals have a comparatively low unit heat capacity, aggregates comprise the greatest proportion of concrete mixtures.
Therefore, the temperature of the aggregates has the greatest influence on the temperature of the concrete. Under the most
severe temperature conditions of construction, the objectives of a comprehensive temperature control program cannot be
achieved without some cooling of the concrete aggregates. 3.4.3 Sprinkling of coarse aggregate stockpiles-Misting or
sprinkling water onto coarse aggregate stockpiles is an inexpensive but limited means of reducing coarse aggregate temperatures.
The amount of cooling that can be obtained depends upon the cooling effect of natural evaporation, which in turn, depends
upon the ambient conditions of temperature, wind, and relative humidity.
4
ACI 305R-99 Hot Weather Concreting—3.4—Delivery : Cement hydration, temperature rise, slump loss, aggregate
grinding, and either loss or, occasionally, gain of air content all occur with the passage of time while the concrete is in the mixer;
thus, the period between start of mixing to start of placement of the concrete should be minimized. Coordinating the dispatching
of mixer trucks with the rate of concrete placement avoids delays in arrival or waiting periods until discharge. On major concrete
placements, provisions should be made to have good communications between the job site and concrete-production facility.
Major placements should be scheduled during periods of lower urban traffic loads. When placement is slow, consideration should
be given to reducing load size, using set-retarding admixture, or using cooled concrete.
Quality Control: Sufficient quality control measures will be set up in place for
checking concrete supply and deliveries throughout the duration of the pour.
3.2) Concrete Placement: Due to one-go casting of each raft foundations /structures
the concrete pouring should be executed during the night time in order that the workface
temperature can be minimized during the entire placement period.
Sufficient concrete pumps will be engaged for concrete placement in order that a flow
pouring can be achieved. As such parking time of the concrete trucks waiting for pouring
can be kept minimized thus the required placing temperature will be maintained.
The set of foams and plastic sheets will be used for curing purposes. This will be done
immediately once the concrete is reached its stiffening time by fully cover the whole
concrete surface and spread the sand (approximately 10 mm. thick.) onto the whole area
of plastic sheets to prevent concrete temperature loss too quick and result high
temperature differential between the surface and at the middle. Care must be taken
during the entire curing to ensure by reading its temperature through a set of
thermocouples that the temperature at the middle of the concrete and any outer surface
to be kept minimum.
As soon as the concrete has reached its stiffening time approximately 1 hour after
pouring a set of plastic sheet will be covered fully the concrete surface. Sand will be filled
fully onto the whole area where the plastics sheet cover with approximately 10mm. thick.
The plastics cover and the side forms will be maintained to ensure that the temperature
differential between the middle of concrete mass and any outer surface can be kept
minimized
In general case the maximum temperature of mass concrete will peak at 48 hours after
pour and will be constant for 7 days and will decrease to the air temperature after 14 days
Equipment Installation:
The end of each thermocouple wire(s) were fixed to the designated position to the
concrete mass prior to pouring. The others ends were linked to the rear panel of the
digital thermometer which is set to read the temperature at every 60 minutes for at least 3
day.
As previously described the temporary control have been controlled in various possible
means as illustrated below.
At the concrete batching plant approximately 3-4 hours in advance pre-cooling of the
mixing components were done as follows.
Pre-Cooling water to the water tanks for 3-4 hours in advance has been done prior to
concrete mixing in order to effect a moderate reduction in concrete placing. Pre-Cooling
in water temperatures were accomplished by mechanical refrigeration, using ice as part of
mixing water.
Because on melting alone it absorbs heat at the high rate, just 1-2 hours prior to concrete
mixing thus to be the most effective the crushed ice were placed directly into the mixing
water in the tanks. The ice will be added until 8-10 Celsius Degree of water temperature
is reached and to maintain until the total volume of concrete is poured.
Fig (2)
Fig (2) At the batching plant, approximately 2-3 hours in advance prior to concrete mixing, the
aggregate were sprayed continually at every 30 minutes interval with water to minimize its temperature.
Fig (3)
Fig (3) Cement in the silos being pre-cooled with water sprayed at every 30
minutes interval. This was done at approximately 2 hour in advance prior to
concrete mixing
4 (a) 4 (b)
4 (c) 4 (d)
Fig (4)
Fig 4: A set of thermocouple were installed at the selected locations.4 (a) The thermocouples were
installed at the nominated exterior points. 4(b) The thermocouples were installed at the nominated
interior points.4(c), 4(d) All the concrete trucks prior to pouring at the workface were parked at the QC
Inspection Station to test and keep records for their slumps and temperatures. The allowable slump is
between 7.5-12.5 cm. and the allowable arrival temperatures are not beyond 30 degree Celsius.
Fig (5)
Fig (5): On a completion of concrete placement, as soon as the concrete reached a stiffening point, the
entire surface area of concrete was immediately covered with 2 inch thick foams, plastic sheet and 10
cm. thick layer of sand for the 1st, 2nd and 3rd layer respectively. The side form was left un-dismantling
for 2 weeks. The temperatures were recorded for every 1 hour at the first 48 hours after concrete
placement and at every 2 hours for the rest.
APPENDIX: