Professional Documents
Culture Documents
Narrative Report
Narrative Report
NARRATIVE REPORT
Submitted By:
Submitted To:
OJT Coordinator
For us students, OJT is the most awaited part in College and we must conform such
requirements. Complying with all the requirements needed to take the Internship Program, we
proceeded to Batangas II Electric Cooperative, Inc. (BATELEC II), which is our chosen company
to help us in our training. We were then accepted to be part of them and assigned us at BATELEC
II, Area I Branch Office at San Jose Batangas. We were eight Electrical Engineering student
trainees destined here.
It was January 21, 2019 when we started our training. We were asked to join the flag
ceremony together with the employees. With this, we were able to know them. Since it was our
first day, we were excited and somewhat nervous because of the new environment and the different
people around us. Before giving our tasks, we were oriented first by our supervisor, Joel A. Flavier,
about the tasks that he may assign to us. He also had short discussion about the different class of
meters, as well as, on how to calibrate them. Also, he let us to familiarize ourselves with the
different tools and equipment they are using. Afterwards, he introduced us to their employees who
may help us throughout the training. We were assigned at Metering and Apprehension/
Confiscation Section.
Sir Marvin Olave, the Calibrator runs the Learning on how to calibrate
machine to test the meter
Sealing of meter
Covering of meter
What we have learned at Apprehension/ Confiscation Section?
Different ways of doing pilferage done by the other consumer. Some were putting
magnets around the meter where they believe that it reduces the rotation of the disk while
the others were having illegal tapping so when they consume electricity, it will not register
to the meter. We also learned that it could be possible to change the circuit inside of it by
changing the values of components like the resistor in a design that could lessen in
consuming the electricity even when there is a larger load.
Aside from what have mentioned, we were also taught by Engr. Jay-ar Macalinao about
the testing of the insulation of a transformer. There is a tester used which can detect if the insulation
is good or not. He also taught us the connection when the transformer is additive or subtractive.
Testing the insulation of the transformer Testing if the insulating material has the same
principle as the insulation of the transformer
Primary bushing (H1 connected to the primary line while H2 is connected to the ground)
Secondary bushing (X1, X2, X3 are connected to the lines going to residential houses)
Tap changer (Changes the number of turns of the primary winding that either increases
or decreases the value of the voltage also)
Pressure Relieve Valve (regulates the temperature of the transformer)
Ground
Nameplate (shows serial number, impedance, polarity, etc.)
Duplex Wire
Cut-out
- A fuse cut-out or cut-out fuse is a
combination of a fuse and a switch, used in
primary overhead feeder lines and taps to protect
distribution transformers from current surges and
overloads
Fuse Link
During our stay, we, the student-trainees were also able to visit the Main Office of
BATELEC II at Antipolo Lipa City. We were able to visit one of their section, which is the
Rewinding Section. There, we had a chance to witness what is going on in this section with the
help of Sir Mike and Renel Raian Atienza who is our co-trainee assigned there. Rewinding Section
serves as the hospital of every transformers owned by the BATELEC II and where transformers
are tested and rewinded here. They told us that there are five different tests conducted including
the Open-Circuit Test, Short-Circuit Test, Insulation Test, Turns Ratio Test, and the Dielectric Oil
Test. These tests were done to knew if they are defective or not.
Familiarizing the construction of a
Teaching us what Rewinding section is
transformer
Recommendation