Professional Documents
Culture Documents
2017
CIRCULAR
In partial modification to the existing technical specifications of electrical works, following will be
applicable to all installations:
Switch socket out lets/ light switches/ MCB DB shall be mounted, as per the CPWD general specifications
for Electrical works, Part- 1, internal 2005, at a level mentioned below unless specified otherwise. All
dimensions noted below shall be from Finished Floor Level to the bottom line of the face plate.
iii. Bathrooms/ Toilets Sockets will be 2000mm for the Geyser above FFL
and at least 1000mm away from the shower. The
switch will be at 1500 mm above FFL.
v. General Wards Nurses call bell point, Bed power point, bed light,
telephone point etc. shall be at 1250 mm above
FFL without tiles on wall. If tiles are there –total
height of tiles 150+1200+150=1500mm- height of
socket 50mm above the tiles.
vi. ICU/Pre-OT/Post OT Normally Bed head panels are provided in these
areas. For bed head one box will be provided
with 4sq.mm wire at the mounting height of bed
head unit. If no bed head panel then height will
be as per above.
1 |o f P a g e - 2
viii. Guest House Power points, light points, telephone points, on
both sides of the bed shall be 600 mm above FFL/
Depending on the height of the bed and for the
rest of the part it is 230 mm as mentioned.
Note: Height will be measured from FFL to bottom point of the Switch Socket/ MCB DB
GM (Electrical)
To:
All Concerned.
2 |o f P a g e - 2