Date : 25-Feb-19

Construction 2B+G+P+13 - Slab Pouring Schedule

Slab Pouring Target Date

10th Floor – 08-June-19

9th Floor – 31-May-19

8th Floor – 23-May-19

7th Floor – 15-May-19

6th Floor – 07-May-19

5th Floor – 29-Apr-19


4th Floor – 21-Apr-19
10-Apr-19
3rd Floor – 13-Apr-19
02-Apr-19

2nd Floor – 05-Apr-19


25-Mar-19
1st Floor – 27-Mar-19
16-Mar-19
Podium Upper +5950 – 18-Mar-19
07-Mar-19
Podium Lower – 08-Mar-19 / 10 –Mar-19
(+2450 /+4200) 28-Feb-19

Ground Floor – 25-Feb-19 / 26-Feb-19


(2 Pour) 13-Feb-19
Basement 1 – 28-Jan-19

Raft – 25-Dec-18

Completed In progress Remaining


Ground Floor to Podium Lower – Verticals – Pouring Schedule

Pour 1
Target to Cast
On 01-Mar-19

Pour 2
Target to Cast
On 03-Mar-19

GF Verticals - Pour 1 Ground Floor Verticals


Activity Start Finish
Description Unit Total Pour 1 Pour 2
Rebar 26-Feb-19 28-Mar-19
Shutter 27-Feb-19 01-Mar-19
Column / Shear Wall Nos 33 15 18
Concrete 27-Feb-19 01-Mar-19 Core Wall Nos 2 1 1
Ground Floor Verticals
GF Verticals - Pour 2
Activity Start Finish
Description Unit Total Pour 1 Pour 2
Rebar 27-Feb-19 02-Mar-19 Reinforcement MT 46.3 15.9 30.5
Shutter 28-Feb-19 03-Mar-19 Formwork SQM 1084.0 425.0 659.0
Concrete 28-Feb-19 03-Mar-19 Concrete Cum 201.5 69.0 132.5
Podium Lower Level Slab

Area 1 - PL Lower Slab (+2450 Lvl)


Activity Start Finish
Slab Formwork 28-Mar-19 02-Mar-19
Bottom
Reinforcement
Work 02-Mar-19 03-Mar-19 Podium
MEP 1st Fix and Box Podium Lower Slab
Cutouts 02-Mar-19 03-Mar-19 Lower
Area 2 (B) +2450
Post Tension Work 04-Mar-19 05-Mar-19 Ramp Slab
Shuttering – 120 Sqm (aprox) Area
Top Reinforcement Area
Bottom Reinf – 6.8 MT (aprox) 1
Work 06-Mar-19 07-Mar-19 2 (B)
Top Reinf – 4.5 MT (aprox)
Consultant Area 1
Inspection &
Approval 07-Mar-19 07-Mar-19 Shuttering – 487 Sqm (aprox)
Trakhees inspection Bottom Reinf – 23.57 MT (aprox)
and Slab Casting 08-Mar-19 08-Mar-19
Top Reinf – 19.28 MT (aprox)
Area 2 (A) - Ramp Podium
Activity Start Finish Lower Slab
Slab Formwork 01-Mar-19 03-Mar-19 +4200
Bottom
Reinforcement Area
Work 04-Mar-19 05-Mar-19 3
MEP 1st Fix and Box
Cutouts 04-Mar-19 05-Mar-19 Area 2 (B)
Top Reinforcement Shuttering – 467 Sqm (aprox)
Work 06-Mar-19 07-Mar-19
Consultant Bottom Reinf – 22.6 MT (aprox)
Inspection & Top Reinf – 18.49 MT (aprox)
Approval 07-Mar-19 07-Mar-19
Trakhees inspection
and Slab Casting 08-Mar-19 08-Mar-19

Area 3 - PL Lower+ 4200 Lvl


& Area 2(B) Ramp Podium
Lower
Activity Start Finish
Ramp
Area 2 (A)
Slab Formwork 01-Mar-19 04-Mar-19 Slab
Shuttering – 320 Sqm (aprox)
Bottom Area
Bottom Reinf – 18.24 MT (aprox)
Reinforcement 2 (A)
Work 04-Mar-19 05-Mar-19 Top Reinf – 12.16 MT (aprox)
MEP 1st Fix and Box
Cutouts 04-Mar-19 05-Mar-19
Post Tension Work 06-Mar-19 07-Mar-19
Top Reinforcement
Work 08-Mar-19 09-Mar-19
Consultant
Inspection & Podium Lower Floor Slab
Approval 09-Mar-19 09-Mar-19
Trakhees inspection Area 1,2 (A) Trakhees Inspection & Concrete Pour - 08 Mar 2019
and Slab Casting 10-Mar-19 10-Mar-19
Area 3,2 (B) Trakhees Inspection & Concrete Pour - 10 Mar 2019
Podium Lower – Verticals – Pouring Schedule

Pour 1
Target to Cast
On 12 Mar 19

Pour 2
Target to Cast
On 16 Mar 19

PL Verticals - Pour 1 Podium Lower Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 09-Mar-19 11-Mar-19 Column / Shear Wall Nos 35 19 16
Shutter 10-Mar-19 12-Mar-19
Core Wall Nos 2 2
Concrete 10-Mar-19 12-Mar-19

PL Verticals - Pour 2
Podium Lower Verticals
Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 11-Mar-19 14-Mar-19 Reinforcement MT 45.1 26.2 18.9
Shutter 13-Mar-19 15-Mar-19 Formwork SQM 1160.5 624.1 536.4
Concrete 13-Mar-19 15-Mar-19
Concrete Cum 196.2 113.9 82.3
Podium Upper Level Slab

Podium Upper Slab & Ramp


Activity Start Finish
Slab Formwork 12-Mar-19 13-Mar-19
Bottom
Reinforcement 13-Mar-19 14-Mar-19
Work
MEP 1st Fix and Box
13-Mar-19 14-Mar-19
Cutouts
Post Tension Work 15-Mar-19 16-Mar-19 Podium Upper
Top Reinforcement Shuttering – 797 Sqm (aprox)
16-Mar-19 17-Mar-19
Work
Consultant Bottom Reinf – 38.57 MT (aprox)
Inspection & 17-Mar-19 17-Mar-19 Top Reinf – 31.56 MT (aprox)
Approval
Trakhees inspection
18-Mar-19 18-Mar-19
and Slab Casting

Ramp PL to PU
Shuttering – 137 Sqm (aprox)
Bottom Reinf – 7.8 MT (aprox)
Top Reinf – 5.2 MT (aprox)

Podium Upper Floor Slab


Trakhees Inspection & Concrete Pour - 18-Mar-19
Podium Upper Verticals – Pouring Schedule

Pour 1
Target to Cast
22-Mar-19

PU Verticals - Pour 1 Podium Upper Verticals


Activity Start Finish Description Unit Total Pour 1
Rebar 19-Mar-19 21-Mar-19
Column / Shear Wall Nos 19 19
Shutter 20-Mar-19 22-Mar-19
Concrete 20-Mar-19 22-Mar-19 Core Wall Nos 2 2

Podium Upper Verticals


Description Unit Total Pour 1
Reinforcement MT 28.9 28.9
Formwork SQM 687.6 687.6
Concrete Cum 125.5 125.5
First Floor Slab

Area 1 - 1F Floor Slab


Activity Start Finish
Slab Decking 15-Mar-19 18-Mar-19
Bottom Rebar 17-Mar-19 19-Mar-19

Podium Podium
Lower Lower
Area 2 - 1F Floor Slab
Slab Slab
Activity Start Finish
Area Area
Slab Formwork
above Podium 22-Mar-19 23-Mar-19
1 2
Upper +5950 Lvl First Floor Slab – Area 2
Bottom First Floor Slab – Area 1 Shuttering – 902 Sqm (aprox)
Reinforcement
23-Mar-19 24-Mar-19 Shuttering – 554 Sqm (aprox) Bottom Reinf – 43.6 MT (aprox)
Work (Balance
Area) Bottom Reinf – 26.81 MT (aprox) Top Reinf – 35.7 MT (aprox)
MEP 1st Fix and Top Reinf – 21.93 MT (aprox)
23-Mar-19 24-Mar-19
Box Cutouts
Post Tension
24-Mar-19 25-Mar-19
Work
Top
Reinforcement 25-Mar-19 26-Mar-19
Work
Consultant
Inspection & 26-Mar-19 26-Mar-19
Approval
Trakhees
inspection and
27-Mar-19 27-Mar-19
Slab Casting
(Area 1 &2)

First Floor Slab


Area 1 & 2 Trakhees Inspection & Concrete Pour - 27-Mar-19
First Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
30-Mar-19

Pour 2
Target to Cast
31-Mar-19

Casting to be done with


Jump Form System

1F Verticals - Pour 1 First Floor Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 28-Mar-19 29-Mar-19 Column / Shear Wall Nos 16 16
Shutter 29-Mar-19 30-Mar-19 Core Wall Nos 1 1
Concrete 29-Mar-19 30-Mar-19
First Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 16 19
Formwork SQM 624 306 318
Concrete Cum 120 54 67
Second Floor Slab

2F Floor Slab
Activity Start Finish
Slab Formwork 30-Mar-19 31-Mar-19
Bottom
Reinforcement 31-Mar-19 01-Apr-19
Work
MEP 1st Fix and
31-Mar-19 01-Apr-19
Box Cutouts
Post Tension
01-Apr-19 02-Apr-19
Work
Top
Reinforcement 04-Apr-19 04-Apr-19
Work
Consultant
Inspection & 04-Apr-19 04-Apr-19 Second Floor Slab
Approval Shuttering – 726 Sqm (aprox)
Trakhees
inspection and 05-Apr-19 05-Apr-19
Bottom Reinf – 35.13 MT (aprox)
Slab Casting Top Reinf – 28.75 MT (aprox)

Second Floor Slab


Trakhees Inspection & Concrete Pour - 05-Apr-19
Second Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
06-Apr-19

Pour 2
Target to Cast
10-Apr-19

Casting to be done with


Jump Form System

2F Verticals - Pour 1 Second Floor Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 06-Apr-19 07-Apr-19 Column / Shear Wall Nos 16 16
Shutter 07-Apr-19 08-Apr-19 Core Wall Nos 1 1
Concrete 07-Apr-19 08-Apr-19
Second Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 19 16
Formwork SQM 624 318 306
Concrete Cum 120 67 54
Third Floor Slab
3F Floor Slab
Activity Start Finish
Slab Formwork 08-Apr-19 09-Apr-19
Bottom
Reinforcement 09-Apr-19 10-Apr-19
Work
MEP 1st Fix and
09-Apr-19 10-Apr-19
Box Cutouts
Post Tension
11-Apr-19 11-Apr-19
Work
Top
Reinforcement 12-Apr-19 12-Apr-19
Work
Consultant
Inspection & 12-Apr-19 12-Apr-19 Third Floor Slab
Approval Shuttering – 747 Sqm (aprox)
Trakhees Bottom Reinf – 36.19 MT (aprox)
inspection and 13-Apr-19 13-Apr-19 Top Reinf – 29.58 MT (aprox)
Slab Casting

Third Floor Slab


Trakhees Inspection & Concrete Pour - 13-Apr-19
Third Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
12-Apr-19

Pour 2
Target to Cast
18-Apr-19

Casting to be done with


Jump Form System

3F Verticals - Pour 1 Third Floor Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 14-Apr-19 15-Apr-19 Column / Shear Wall Nos 16 16
Shutter 15-Apr-19 16-Apr-19 Core Wall Nos 1 1
Concrete 15-Apr-19 16-Apr-19
Third Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 19 16
Formwork SQM 624 318 306
Concrete Cum 120 67 54
Fourth Floor Slab
4F Floor Slab
Activity Start Finish
Slab Formwork 16-Apr-19 17-Apr-19
Bottom
Reinforcement 17-Apr-19 18-Apr-19
Work
MEP 1st Fix and
17-Apr-19 18-Apr-19
Box Cutouts
Post Tension
19-Apr-19 19-Apr-19
Work
Top
Reinforcement 20-Apr-19 20-Apr-19
Work
Consultant Fourth Floor Slab
Inspection & 20-Apr-19 20-Apr-19 Shuttering – 729 Sqm (aprox)
Approval Bottom Reinf – 35.24 MT (aprox)
Trakhees
Top Reinf – 28.8 MT (aprox)
inspection and 21-Apr-19 21-Apr-19
Slab Casting

Fourth Floor Slab


Trakhees Inspection Concrete Pour - 21-Apr-19
Fourth Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
18-Apr-19

Pour 2
Target to Cast
24-Apr-19

Casting to be done with


Jump Form System

4F Verticals - Pour 1 Fourth Floor Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 22-Apr-19 23-Apr-19 Column / Shear Wall Nos 16 16
Shutter 23-Apr-19 24-Apr-19 Core Wall Nos 1 1
Concrete 23-Apr-19 24-Apr-19
Fourth Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 19 16
Formwork SQM 624 318 306
Concrete Cum 120 67 54
Fifth Floor Slab
5F Floor Slab
Activity Start Finish
Slab Formwork 24-Apr-19 25-Apr-19
Bottom
Reinforcement 25-Apr-19 26-Apr-19
Work
MEP 1st Fix and
25-Apr-19 26-Apr-19
Box Cutouts
Post Tension
27-Apr-19 27-Apr-19
Work
Top
Reinforcement 28-Apr-19 28-Apr-19
Work
Consultant Fifth Floor Slab
Inspection & 28-Apr-19 28-Apr-19
Approval
Shuttering – 729 Sqm (aprox)
Trakhees Bottom Reinf – 35.24 MT (aprox)
inspection and 29-Apr-19 29-Apr-19 Top Reinf – 28.8 MT (aprox)
Slab Casting

Fifth Floor Slab


Trakhees Inspection Concrete Pour - 29-Apr-19
Fifth Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
24-Apr-19

Pour 2
Target to Cast
02-May-19

Casting to be done with


Jump Form System

5F Verticals - Pour 2 Fifth Floor Verticals


Activity Start Finish Description Unit Total Pour 1 Pour 2
Rebar 30-Apr-19 01-May-19 Column / Shear Wall Nos 16 16
Shutter 01-May-19 02-May-19 Core Wall Nos 1 1
Concrete 01-May-19 02-May-19
Fifth Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 19 16
Formwork SQM 624 318 306
Concrete Cum 120 67 54
Sixth Floor Slab
6F Floor Slab
Activity Start Finish
Slab Formwork 02-May-19 03-May-19
Bottom
Reinforcement 03-May-19 04-May-19
Work
MEP 1st Fix and
03-May-19 04-May-19
Box Cutouts
Post Tension
05-May-19 05-May-19
Work
Top
Reinforcement 06-May-19 06-May-19
Work
Consultant Sixth Floor Slab
Inspection & 06-May-19 06-May-19
Approval
Shuttering – 729 Sqm (aprox)
Trakhees Bottom Reinf – 35.24 MT (aprox)
inspection and 07-May-19 07-May-19 Top Reinf – 28.8 MT (aprox)
Slab Casting

Sixth Floor Slab


Trakhees Inspection Concrete Pour - 07-May-19
Sixth Floor – Verticals – Pouring Schedule

Pour 1
Target to Cast
30-Apr-19

Pour 2
Target to Cast
10-May-19

Casting to be done with


Jump Form System

5F Verticals - Pour 1 Sixth Floor Verticals


Activity Start Finish Description Unit Total Pour 1
Rebar Work 08-May-19 09-May-19 Column / Shear Wall Nos 16 16
Formwork 09-May-19 10-May-19 Core Wall Nos 1 1
Concrete 09-May-19 10-May-19
Sixth Floor Verticals
Description Unit Total Pour 1 Pour 2
Reinforcement MT 35 19 16
Formwork SQM 624 318 306
Concrete Cum 120 67 54
Seventh Floor Slab
7F Floor Slab
Activity Start Finish
Slab Formwork 10-May-19 11-May-19
Bottom
Reinforcement 11-May-19 12-May-19
Work
MEP 1st Fix and
11-May-19 12-May-19
Box Cutouts
Post Tension
13-May-19 13-May-19
Work
Top
Reinforcement 14-May-19 14-May-19
Work
Consultant Seventh Floor Slab
Inspection & 14-May-19 14-May-19
Approval
Shuttering – 729 Sqm (aprox)
Trakhees Bottom Reinf – 35.24 MT (aprox)
inspection and 15-May-19 15-May-19 Top Reinf – 28.8 MT (aprox)
Slab Casting

Seventh Floor Slab


Trakhees Inspection Concrete Pour - 15-May-19