Min Max planning is one of the inventory planning method where when quantity reaches min level, system auto
create purchase requisition to order material from supplier or can create a move order to transfer material from
other Sub-inventory based on our setups. Min Max planning can be done both at sub inventory level or Inv org
level. In org level the item quantity is checked in all subinventories
Setups
1) Create a Min Max Item. take template of purchase item.
2) Set planning method as Min Max in General Planning tab.
3) Navigate to Setup>Organization>Subinventories. Here in Item/subinventory specify Min and Max Quantities
and Min /Max order Quantities.
4) Specify a Source in General Planning tab. We will take source as Subinventory to create a move order when
demand arises.
Here system see on hand balances, Supply like PO and demand like Sales order at subinventory level
Step 1) Create a "MIN MAX" item and apply Purchase Item template
Step 2) Navigate to General Planning tab, Here specify the planning method as Min Max Planning. you can
specify the Min Max quantities and Min Max Order Quantities but when planning at subinventory level this will
get overridden by the values at subinventory level.
http://mandeeporacle.blogspot.in/2014/04/min-max-planning-min-max-planning-is.html 1/6
8/4/2014 Oracle Min Max Planning | Simplifying Oracle E Business Suite
Step 4) Here First in Planning tab enter Item and specify min max quantities. Also Tick Min max planning
check Box.
http://mandeeporacle.blogspot.in/2014/04/min-max-planning-min-max-planning-is.html 2/6
8/4/2014 Oracle Min Max Planning | Simplifying Oracle E Business Suite
Step 5) Now go to next tab "Order Modifiers". Specify a Minimum and Maximum order Quantities.
Step 6) Now navigate to next Tab "Sourcing". Here mention sourcing subinventory
Note: Other methods of Sourcing are Suppliers and Inventory. If you choose "Supplier" system will create a
Purchase requisition and if you choose "Inventory" system will create an internal requisition.
After that if you want you can optionally specify the lead times.
http://mandeeporacle.blogspot.in/2014/04/min-max-planning-min-max-planning-is.html 3/6
8/4/2014 Oracle Min Max Planning | Simplifying Oracle E Business Suite
Test case
Step 1) After doing setups please perform miscellaneous transaction to receive some quantities in
subinventory FGI for MIN MAX item
Step 2) Now run "Min-max planning report". You can choose the parameters as shown in below screenshots.
Restock Option should be Yes.
http://mandeeporacle.blogspot.in/2014/04/min-max-planning-min-max-planning-is.html 4/6
8/4/2014 Oracle Min Max Planning | Simplifying Oracle E Business Suite
You can see the values shown in report are from subinventory level and not from master item level.
If something fails, you can run "Requisition Import Exception Report" to find out the errors.
http://mandeeporacle.blogspot.in/2014/04/min-max-planning-min-max-planning-is.html 5/6
8/4/2014 Oracle Min Max Planning | Simplifying Oracle E Business Suite
Thanks
Mandeep