BILL OF QUANTITIES FOR PT COLLECTION TANK

Date 5/4/2019 R0

SR.NO ITEM DESCRIPTION TOTAL


1 Foundation Below GL :-
Concrete (M30) Vol. of concrete 10.32 m3

2 Vertical Wall
Concrete (M30) Vol. of concrete 200mm THICK 18.00 m3

3 Grade Slab :-
Concrete (M30) 4.40 m3

4 PCC at GL (M-10)
75mm Thick Vol. of Concrete below foundation 2.84 m3
75mm Thick Vol. of Concrete below grade slab 1.20 m3
75mm Thick Vol. of Concrete plinth protection 1.68 m3

5 Rubble Solling :- 230mm Thick 8.72 m3

6 Sand Filling :- 300mm Thick Below foundation 11.35 m3


300mm Thick Inside tank below g 35.40 m3

SUMMARY

ITEMS TOTAL WASTAGE 5% TOTAL


CONCRETE (M-30) 32.72 1.64 34.36 m3
CONCRETE (M-10) 5.72 0.29 6.01 m3
RUBBLE SOLING 8.72 0.44 9.16 m3
SAND FILLING 46.75 2.34 49.09 m3
SR.NO ITEM Description Diameter Length Nos Kg/m TOTAL
1 Vertical Bars in wall Inner Perimeter 8T 5.80m 80 0.395 183.28
Outer Perimeter 8T 5.80m 88 0.395 201.608

2 Extra Vertical Bars in wall Inner Perimeter 8T 2.10m 80 0.395 66.36


Below GL Outer Perimeter 8T 2.10m 88 0.395 72.996

3 Horizontal Bars in walls Inner Perimeter 10T 16.00m 27 0.62 267.84


Outer Perimeter 10T 17.60m 27 0.62 294.624

4 Horizontal Bars in walls Inner Perimeter 10T 9.60m 18 0.62 107.136


Rest part Inner Perimeter 10T 9.60m 18 0.62 107.136

5 Grade Slab Top & Bottom 8T 4.80m 88 0.395 166.848

6 Footing Straight Bars on 10T 5.00 40 0.62 124


all four sides
Short Pieces in 10T 1.00 128 0.62 79.36
center

7 Haunch 8T 0.40 105 0.395 16.59

1688 Kg

Total Reinforcement including 5% wastage 1772 Kg