You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/277664018

Comparative Evaluation of Different Types of Permeable Pavement for


Stormwater Reduction - St. Louis Green Alley Pilot Study.

Conference Paper · January 2015


DOI: 10.1061/9780784479025.028

CITATIONS READS

3 102

1 author:

Isam Alyaseri
Al-Muthanna University
10 PUBLICATIONS   42 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Low impact development in St. Louis View project

lmproving uncertainty in life cycle assessment studies View project

All content following this page was uploaded by Isam Alyaseri on 03 February 2016.

The user has requested enhancement of the downloaded file.


Stormwater Volume Reduction in Combined Sewer
Using Permeable Pavement: City of St. Louis
Isam Alyaseri, Ph.D., M.ASCE 1; and Jianpeng Zhou, Ph.D., P.E. 2

Abstract: This paper describes findings from the City of St. Louis Low Impact Development Green Alley Pilot Study to reduce water quantity
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

in the combined sewer system. Permeable pavement is one green infrastructure technique used for water quantity reduction. The effectiveness of
permeable pavement in reducing the stormwater runoff to the combined sewer was tested. Monitored flow from reconstruction and postcon-
struction of permeable pavement are used for analysis. The separation of base flow and runoff is based on estimating the base flow in the
antecedent/subsequent dry days of the rainfall events. The comparison between runoff in the reconstruction and postconstruction of the permeable
pavement from three alleys showed different percentages of runoff reduction from different types of pavement (36, 13, and 46% from permeable
concrete, permeable asphalt, and permeable pavers respectively). Permeable asphalt had the lowest percentage reduction, most likely due to the
slope of the site and the small ratio of permeable to catchment area in this location. The permeable paver showed the highest percentage of runoff
reduction. DOI: 10.1061/(ASCE)EE.1943-7870.0001056. © 2016 American Society of Civil Engineers.
Author keywords: Combined sewer overflow; Stormwater runoff; Permeable pavement.

Introduction Permeable pavement is one of the techniques used to allow


stormwater to infiltrate into the soil and ultimately recharge the
A combined sewer system is designed to collect rainwater runoff groundwater. In areas with soil that has a low infiltration rate,
and domestic sewage in the same pipes, then transport them to the below-pavement storage can provide a storage volume to reduce
wastewater treatment plant (WWTP) for treatment prior to the final the runoff on the surfaces. This pavement is an alternative to the
discharge to the surface water. One problem with the combined conventional impervious asphalt and concrete pavement. Water
sewer occurs during the periods of heavy rainfall. If the flow in in the permeable pavement passes through several layers of per-
the combined sewer exceeded the capacity of the treatment plant meable materials and allows for reduction in the quantity of runoff
or the capacity of the conveyance system at any point along its (Collin et al. 2007).
route, it would discharge excess combined untreated wastewater Several studies have been conducted to show the effectiveness
and stormwater to the surface water, causing the problem of of permeable pavement for runoff reduction (Booth and Leavitt
combined sewer overflow (CSO). 1999; Hunt et al. 2002; Brattebo and Booth 2003; Rankin and Ball
CSO have been a significant challenge in the St. Louis area, 2004; Kwiatkowski et al. 2007; Bean et al. 2007). James (2008)
where most sewers within the city and some in the surrounding reported a reduction of 90% of the surface runoff volume due to
county are combined. There are hundreds of points in the city installing a permeable interlocking concrete paver. Collins et al.
where a combination of rainwater and wastewater has discharged (2007) also reported a reduction of 99.4% of the surface runoff vol-
into local waterways during heavy rainstorms. Without relief ume when using permeable concrete. Most of these studies were
points, basement backups or street flooding would occur. The over- designed to test the effectiveness of permeable pavement by direct
flow discharges depend upon how much rain falls over a given measurement of runoff, and were not related directly to the problem
period of time. The discharge of untreated sanitary and stormwater of CSO. It is still unknown how the results obtained from such ex-
during CSO contributes to the degradation of surface water quality periments would contribute to the reduction of flow in a combined
(Lee et al. 2007). sewer in the natural environment. While such experiments have the
One method of overcoming the problem of CSO is to reduce the ability to control variables, in which only one or two factors are
stormwater runoff by green infrastructures. They are proposed to manipulated by the experimenter(s), they did not provide sufficient
reduce the runoff from impervious areas. The selection of the green information about real-world applications. Case studies can be used
infrastructure techniques is based on the land use characteristics. to test if an engineering solution actually works in the real world.
Green infrastructures may include rain gardens, green roofs, veg- Although these case studies represent a limited number of exam-
etated curb extensions, permeable pavement, or other controls. ples, they can provide realistic understanding, likely leading to new
research directions. The case study described in this paper was de-
signed to evaluate the effectiveness of permeable pavement in
1
Visiting Assistant Professor, Dept. of Civil Engineering, Southern addressing the problem of CSO by measuring the flow in the com-
Illinois Univ. Edwardsville, Edwardsville, IL 62026-1800 (corresponding bined sewer preconstruction and postconstruction of the permeable
author). E-mail: ialyase@siue.edu pavement in the site. However, careful analysis and interpretation
2
Professor and Chair, Dept. of Civil Engineering, Southern Illinois
of data can provide confidence in the results of the case study.
Univ. Edwardsville, Edwardsville, IL 62026-1800. E-mail: jzhou@siue.edu
Note. This manuscript was submitted on May 22, 2014; approved on
In 2008, the City of St. Louis, along with several partners started
September 16, 2015; published online on January 4, 2016. Discussion per- a green infrastructure program to identify and implement projects
iod open until June 4, 2016; separate discussions must be submitted for that could significantly reduce the CSO volumes to the Mississippi
individual papers. This paper is part of the Journal of Environmental En- River. The City started a pilot study to evaluate the effectiveness of
gineering, © ASCE, ISSN 0733-9372. various green infrastructures for capturing and in-place treating of

© ASCE 04016002-1 J. Environ. Eng.

J. Environ. Eng., 04016002


stormwater by detention, infiltration into ground, or evapotranspi- A permeable paver is composed of a layer of brick pavers sep-
ration. This study tested the effectiveness of permeable pavement arated by joints filled with small stones. Water passes through the
on volume reduction in combined sewers at three alleys in the City. joints then flows through an open-graded base made of crushed
stone layers that have no fine particles. The crushed stone or ag-
gregate used in the base fills the joints typically 2 to 5 mm. Water
Study Objective that infiltrates through the openings between the blocks is stored or
infiltrated into the soil, resulting in higher reduction in runoff.
The objective of this study was to evaluate the effectiveness of per-
meable pavement to reduce the volume of stormwater in combined
sewers. The study also tried to determine if the type of permeable Study Sites and Phases
pavement affects the runoff reduction efficiency.
Three alleys (Eads, Cardinal, and Geyer) were selected for per-
meable pavement installation, monitoring, and data analysis.
The study consisted of three phases. Phase I (preconstruction) in-
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

Methodology
cluded monitoring the flow in the combined sewer where the
The study was planned to monitor and characterize flows in proposed permeable pavements were installed. This phase was con-
combined sewers for Pre- and Post- construction of permeable ducted in the year 2008. The available flow data were from March
pavement at three alleys. Flows were measured by using the 26, 2008, to July 17, 2008. Metropolitan St. Louis Sewer District
2,150 Area Velocity Flow Module and Sensor of Teledyne ISCO (MSD) installed and maintained the flow meters.
(Lincoln, Nebraska). The flowmeter measures liquid level and aver- Phase II work included installing the permeable pavements at
age stream velocity which calculates the flow rate and total flow. the three sites. The soil in the three sites was silty clay loam (hydro-
The liquid level and velocity measurements are read from an at- logic soil group of D). The threshold rainfall depth used for design
tached area velocity (AV) sensor that is placed in the flow stream. was 3.3 cm (1.3 in.) in interval events of 24 h. The drainage area for
Flow rates were calculated using a built-in program from the liquid each alley includes the alley and half of the adjacent properties that
depths and velocities that were measured by the AV sensor were assumed to drain into the alley. The rock void percentage used
(Teledyne 2009). The rainfall event included in the analysis had a to calculate the storage size ranged from 30 to 40%.
minimum depth of 0.13 cm (0.05 in.) occurring in a period of 1 day. MSD provided the design information for the three alleys. The
Eads site was originally conventional asphalt pavement with
approximately 2,590 m2 (0.64 acre) of drainage area. The imper-
Permeable Pavement Types vious pavement in the alley was changed to permeable concrete.
There are several different types of permeable pavement materials The below-pavement storage size for this site is 43.6 m3 (1,539 ft3).
such as permeable pavers, permeable asphalt, permeable concrete, The Geyer site was originally a brick alley with total of 6,637 m2
and block paving stone (Mullaney and Lucke 2014; Scholz and (1.64 acre) of drainage area. It was changed into permeable paver.
Grabowiecki 2007). The below-pavement storage size for this site is 108.8 m3 (3,843 ft3).
Three types of permeable pavement were used in this study: Cardinal site was originally brick with approximately 2,509 ~ m2
permeable concrete, permeable asphalt, and permeable pavers. (0.62 acre) of drainage area. It was changed into permeable
Permeable concrete is composed of cement materials, coarse aggre- asphalt, and the below-pavement storage size for this site was
gate, and water with little to no fine aggregates (0:1 to 1:1 fine 42.5 m3 (1,500 ft3, Table 1). Phase II was completed in the year 2009.
aggregates to cement) with a water to cement ratio of 0.35 to Phase III (postconstruction) was carried out in 2011 to 2012 and
0.40 and a void content of 15 to 25%. The typical thicknesses consisted of flow monitoring. The available flow data in this phase
for the permeable concrete range from 10 to 30.5 cm (4 to 12 in.), are from March 3, 2011, to February 6, 2012.
depending on the traffic load and other requirements (MSD 2010; Data from MSD were assessed for data quality and acceptability
Tennis et al. 2004). prior to analysis. Many factors, such as turbulence, build-up of
Permeable asphalt consists of open-graded coarse aggregate, sediments and debris over the sensor, and inadequate liquid depth
bonded together by bituminous asphalt (5.75–6.0% by weight). due to low flows can affect the quality of flow data. Negative veloc-
Polymers are sometimes added to increase strength for heavy-load ities and flows were treated as zero when there was no appropriate
applications. The thickness can range from 5 to 10 cm (2 to 4 in.) evidence to justify alternative handling. Data that unreasonably
depending on the expected traffic loads. The minimum air voids in fluctuated or were suspected to be different due to clogging in
permeable asphalt is 16% (USEPA 2009). the sensors were eliminated.

Table 1. Permeable Pavement Alleys in Three Locations with the Estimated Catchment Area, Permeable Paved Area, and Below-Pavement Storage
Site
Site characteristics Eads Cardinal Geyer
Phase I condition Conventional asphalt pavement Conventional brick pavement Conventional brick pavement
Phase III condition Permeable concrete Permeable asphalt Permeable paver
Location 3,127 Eads Avenue (parallel 1,412 Cardinal avenue (parallel to 3,217 Geyer avenue (parallel
to Compton Avenue, between Park Avenue and Caroline St., to Compton Hill Pl, between
Eads and Henrietta) between Montrose and Cardinal) Geyer and I-44)
Flow meter manholes 21F2-284 C 21E1-385 C 21F2-147 C
Rain gauge C-24 C-9 C-13
Estimated drainage area 2,590 m2 (0.64 acre) 2,509 m2 (0.62 acre) 6,637 m2 (1.64 acre)
Permeable paved area 324 m2 (0.08 acre) 231 m2 (0.06 acre) 514 m2 (0.13 acre)
Below pavement storage 43.5 m3 (1,539 ft3 ) 42.5 m3 (1,500 ft3 ) 109 m3 (3,843 ft3 )

© ASCE 04016002-2 J. Environ. Eng.

J. Environ. Eng., 04016002


Table 2. Total Volume of the Combined Sanitary and Stormwater Through the Sewer System and the Total Amounts of Rainfall in the Periods between March
26, 2008 and July 17, 2008 (Preconstruction), and between March 26, 2011, and July 17, 2011 (Postconstruction), in Three Locations
Preconstruction (2008) Postconstruction (2011)
Location Total volume [m3 (gal.)] Total rainfall [cm (in.)] Total volume [m3 (gal.)] Total rainfall [cm (in.)]
Eads 3,445 (910,173) 50.8 (20.00) 2,862 (756,216) 45.3 (17.85)
Cardinal 2,330 (615,596) 53.2 (20.96) 3,328 (879,047) 45.5 (17.91)
Geyer 2,466 (651,416) 54.5 (21.48) 456 (120,509) 58.5 (23.04)

Rainfall Data the flow. The meter malfunctioning days were also excluded. For
example, on Friday, April 29, 2011, a rainfall event of 2.43 cm
MSD maintained a network of rain gauge stations throughout the
(0.96 in.) in a duration of 15 min (8:15 to 8:30 a.m.) had occurred
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

metropolitan St. Louis area. The rain gauge station nearest to each
but the meter was not functioning. Also, the meter in the Eads lo-
site was chosen to obtain rainfall data for analysis. The cumulative
cation was not working during June, so all rainfall events were not
rainfall data at the three locations, Eads, Cardinal, and Geyer were
considered during this month. In the Geyer location, malfunction-
taken from MSD’s rain gauge stations of C24, C9, and C13 respec-
ing meters resulted in the exclusion of 15 rainfall events (out of
tively. To be consistent with the flow rate data that was provided by
37 events) in the year 2008 and 14 rainfall events (out of 37 events)
MSD at an interval of 15 min, the rainfall data was obtained as a
in the year 2011.
cumulative of 15-min intervals. The hydrographs used for illustra-
tion in this study were drawn using 15-min intervals. The minimum
rainfall that can be detected in the rain gages is 0.25 mm (0.01 in.). Preconstruction and Postconstruction Phases
A summary of site locations, manholes where flow meters were Comparison
deployed, rain gauge stations, and pavement types (both precon-
struction and postconstruction) are shown in Table 1. Volume of runoff discharged due to the rain was estimated for every
rainfall event based on the former separation method. Then, the
average volume of runoff discharged due to a rain per each
Data Analysis 2.54 m (1 in.) of this rain was calculated. The runoff discharged
The data were analyzed and compared on the basis of flow during due to rain was estimated by where
comparable time periods between Phase I and Phase III. The data Pm
Fj
for both preconstruction (2008) and postconstruction (2011) of per- Xn
Fi − ð j¼1 Þ
m
meable pavement from March 26 to July 17 were used to determine Runoff phase ¼
the effectiveness of the permeable pavement to reduce stormwater i¼1
Ri
volume in the combined sewer. The data were available from three
locations (Eads, Cardinal, and Geyer) and includes the flow rates Runoff phase = total stormwater runoff discharged into a combined
measured at 15-min intervals. In a few periods, the meters mea- sewer for a given phase per every centimeter or inch of rain; n =
sured the flow rate in an interval of 1 min and for the purpose number of rainfall events used in the analysis; m = number of dry
of analysis, these data were aggregated to the 15-min intervals. days before and after the rainfall event used to estimate the base
Volume of the discharged sanitary and stormwater was calculated flow; Fi = flow in the rainy day include sanitary, infiltration
for every 15 min. and stormwater runoff, cubic meter or gallon per day; Fj = flow
Comparison between the preconstruction and postconstruction in the dry days before or after the rainy day, cubic meters or gallons
of permeable pavement cannot be performed in the combined sewer per day; and Ri = rainfall amount in an one day period, centimeter
system by simply calculating the difference between combined or inch.
water in the before and after phases. Table 2 shows this problem The numbers of rainfall events used for runoff per rain estima-
in general. For example, in the Cardinal site, although the total tion at every site are shown in Table 3, and this estimation was
rainfall in year 2011 was less than year 2008 [45.5 cm performed for both reconstruction and postconstruction phases.
(17.91 in.) versus 53.2 cm (20.96 in.) respectively], the total The percentage reduction in runoff due to the use of permeable
volume of the combined storm and sanitary water was higher in pavement was then calculated between Runoff pre and Runoff post
year 2011 [3,328 m3 (8,79,047 gal.) versus 2,330 m3 (6,15,596 gal.) for every site.
respectively]. The fluctuation came from sanitary flow, therefore, it
has to be separated prior to any comparison between the two phases.
Results and Discussions
Base Flow Separation
Alley by Eads Avenue (Permeable Concrete)
Since the volume of stormwater discharged to the sewer cannot be
calculated unless the base flow (due to sanitary and infiltration) is The alley was changed from conventional asphalt to permeable
subtracted, the first step was to perform a separation procedure. A concrete. In the year 2008, 26 rainfall events were used to estimate
procedure used for estimation was based on the assumption that the the total stormwater volume discharged to the combined sewer
base flow in the wet days is equal to the antecedent and subsequent due to every rainfall. The average stormwater discharged to the
dry days. This procedure will be referred to as the Antecedent/ sewer system per each 2.54 cm (1 in.) of storm was calculated
Subsequent Days Estimation Method. In this procedure, the base [31.9 m3 =cm (21,372 gal:=in:)]. At the Eads site, year 2011, 27
flow for each rainfall event was estimated by averaging the flow rainfall events were analyzed to estimate the total stormwater vol-
rates in dry days before and after each rainy day. Weekend days ume discharged to the sewer due to every rainfall. The average run-
were taken from the weekends before and after as well. The hol- off discharged to the sewer per each 1 in. of storm was calculated
idays and special events were excluded due to atypical changes in and it was equal to 20.5 m3 =cm (13,775 gal:=in:).

© ASCE 04016002-3 J. Environ. Eng.

J. Environ. Eng., 04016002


Table 3. Summary for the Percentage Reduction in Runoff in the Three Locations of the Study
Preconstruction phase Postconstruction phase
Number Number Percent
of rainfall Overflow per each rain of rainfall Overflow per each reduction in
Location Type events inche [m3 =cm (gal./in.)] events rain inche [m3 =cm (gal./in.)] CSO (%)
Eads Permeable concrete 23 31.9  9.6a (21,372) 25 20.5  6.2a (13,775) 36
Cardinal Permeable asphalt 39 6.6  1.9a (4,427) 32 5.8  2.6a (3,866) 13
Geyer Permeable pavers 22 7.3  2.6a (4,915) 23 4.0  1.4a (2,652) 46
a
Confidence limit in a 95% probability.
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

Fig. 1. Rainfall–flow rate chart for the rainfall event on Sunday March 30, 2008 (preconstruction phase), in Eads Alley with conventional asphalt

Fig. 2. Rainfall–flow rate chart for the rainfall event on Monday May 23, 2011, in Eads Alley with permeable concrete

© ASCE 04016002-4 J. Environ. Eng.

J. Environ. Eng., 04016002


Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

Fig. 3. Rainfall–flow rate chart for the rainfall event on Friday April 25, 2008, in Cardinal Alley with conventional brick pavement

Comparison between the two averages of runoff per rainfall Sunday after (April 6, 2008). Fig. 1 shows the rainfall–flow rate
shows around 36% reduction in the amount of water discharged relationship for this rainfall event and it also shows the base flow
to the sewer between year 2008 and year 2011 for the storms rate day.
ranging from 15 min cumulative daily rain of 0.18–4.55 cm The second rainfall event chosen was on Monday, May 23,
(0.07–1.79 in.). This is most likely due to the installation of 2011, with a daily cumulative amount, duration, and maximum
permeable pavement in the year 2009. depth of 1.27 cm (0.5 in.), 90 min, and 0.45 cm (0.18 in.), respec-
To show this difference in more detail, two rainfall events were tively. Base flow for this rainfall event was assumed to be close to
chosen. These two rainfalls are close in their daily cumulative the flow rate in the day after (Tuesday, May 24, 2011). Fig. 2 shows
amount, duration, and maximum depth. The rainfall event on the rainfall–flow rate relationship for this rainfall event and it also
Sunday, March 30, 2008, with a daily cumulative amount, duration, shows the base flow day.
and maximum depth of 1.45 cm (0.57 in.), 150 min, and 0.35 cm Fig. 1 shows that for a rainfall intensity of 0.35 cm (0.14 in.), the
(0.14 in.), respectively, was chosen as an example. Base flow for flow rate in the sewer can reach up to 36.3 m3 =h (160 gal. per min
this rainfall event was assumed to be close to the flow rate in the or gpm), while Fig. 2 shows that for a rainfall intensity up to

Fig. 4. Rainfall–flow rate chart for the rainfall event on Friday June 17, 2011, in Cardinal Alley with permeable asphalt pavement

© ASCE 04016002-5 J. Environ. Eng.

J. Environ. Eng., 04016002


Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Rainfall–flow rate chart for the rainfall event on Friday May 30, 2008, and May 31, 2008, in Cardinal Alley with conventional brick pavement

0.45 cm (0.18 in.), the flow rate did not exceeded 25.7 m3 =h per each inch of rain. The average stormwater runoff dis-
(113 gpm). This is likely due to the ability of the permeable pave- charged to the sewer per each 1 in. of rain was calculated and
ment to reduce the peak flow. it was 5.8 m3 =cm (3,866 gal:=in:). The averages from the two
years show a reduction in the runoff due to permeable pavement
at 13%.
Alley by Cardinal Avenue (Permeable Asphalt) Four rainfall events were chosen for further analysis. The first
This alley was changed from conventional brick to permeable two rainfalls are close in their daily cumulative amount, duration,
asphalt. At this site, for the periods from March 26, 2008, to April and maximum depth. The rainfall event on Friday, April 25, 2008,
17, 2008 (preconstruction), a total of 39 rainfall events were used to with a cumulative amount, duration, and maximum depth of 1.5 cm
estimate the amount of runoff discharged to the sewer per each inch (0.59 in.), 60 min, and 1.1 cm (0.43 in.), respectively, was chosen
of rain. The average runoff discharged into the sewer per each 1 in. as an example. Base flow for this rainfall event was assumed to be
of storm was calculated to be 6.6 m3 =cm (4,427 gal:=in:). close to the flow rate in the days April 23, 2008 (Wednesday), and
In the same site, and for the period from March 26, 2011, to April 28, 2008 (Monday). Fig. 3 shows the rainfall–flow rate rela-
July 17, 2011 (postconstruction), 32 rainfall events were used to tionship for this rainfall event and it also shows the base flow rate
estimate the amount of runoff discharged to the sewer system from the dry days.

Fig. 6. Rainfall–flow rate chart for the rainfall event on Tuesday April 19, 2011, in Cardinal Alley with permeable asphalt pavement

© ASCE 04016002-6 J. Environ. Eng.

J. Environ. Eng., 04016002


Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

Fig. 7. Rainfall–flow relation for the rainfall event on Thursday March 27, 2008, in Geyer Alley with conventional brick pavement

The second rainfall event chosen was on Friday, June 17, 2011, the flow may exceed 24.9 m3 =h (110 gpm). This shows that the
with a cumulative amount, duration, and maximum depth of permeable pavement in this site is not efficiently reducing the
1.72 cm (0.68 in.), 90 min, and 1.14 cm (0.45 in.), respectively. peak flow.
Base flow for this rainfall event was assumed to be close to the The two other rainfall events are shown in Figs. 5 and 6. These
flow rate in the two Fridays before and after (June 3, 2011, and two figures show a different pattern than Figs. 3 and 4. The events
June 24, 2011). Fig. 4 shows the rainfall–flow rate relationship occurred on Friday, May 30, 2008, and Tuesday, April 19, 2011.
for this rainfall event and it also shows the base flow rate from The two events were also close in their accumulative daily rainfall
the dry days. amount, duration, and maximum depth [2.7 cm (1.08 in.), 150 min,
Fig. 3 shows for a rainfall intensity of 1.1 cm (0.43 in.) per and 0.43 cm (0.17 in.) versus 2.3 cm (0.91 in.), 165 min, and
15 min, the flow in the sewer can reach up to 13.6 m3 =h (60 gpm), 0.96 cm (0.38 in.), respectively]. Fig. 5 shows that in the year 2008,
while Fig. 4 shows that for a rainfall intensity up 1.14 cm (0.45 in.), for a rainfall intensity that reaches up to 0.94 cm (0.37 in.), the flow

Fig. 8. Rainfall–flow relation for the rainfall event on Friday April 15, 2011, in Geyer Alley with permeable paver

© ASCE 04016002-7 J. Environ. Eng.

J. Environ. Eng., 04016002


rate reached up to 38.6 m3 =h (170 gpm). However, Fig. 6 shows (a)
that in the year 2011, for the same rainfall intensity (0.94 cm) the
flow rate in the pipe did not exceed the level of 22.7 m3 =h
(100 gpm), indicating effective reduction of storm runoff.

Alley by Geyer Avenue (Permeable Paver)


The alley at this site was changed from conventional brick to
permeable paver. In this site, for the same period (March 26,
2008, to July 17, 2008) (preconstruction), 16 rainfall events were
excluded due to flow meter malfunctioning either during the day
of a rainfall event or during the days before and after. Only 22
rainfall events were used to estimate the amount of runoff dis-
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

charged to the sewer per every inch of rain. The average stormwater
discharged to the sewer per every inch of storm was equal to
7.3 m3 =cm (4,915 gal:=in:).
In the same site, and for the period from March 26, 2011 to July (b)
17, 2011 (postconstruction), 23 rainfall events were used to esti-
mate the amount of runoff discharged to the sewer system per every
inch of rain. The average stormwater discharged to the sewer per
each 1 in. of rain was equal to 4.0 m3 =cm (2,652 gal:=in:). The
averages from the two phases show a reduction in the runoff
due to the permeable paver at 46%.
Like the previous sites, two rainfall events were chosen for fur-
ther analysis. The rainfall event on Thursday, March 27, 2008, with
a cumulative amount, duration, and maximum depth of 1.5 cm
(0.60 in.), 270 min, and 0.28 cm (0.11 in.), respectively, was chosen
as an example. Base flow for this rainfall event was assumed to be
close to the flow rate on Friday, March 28, 2008. Fig. 7 shows the
rainfall–flow rate relationship for this rainfall event and it also
shows the base flow rate from the dry day.
The second rainfall event chosen was on Friday, April 15, 2011,
with a cumulative amount, duration, and maximum depth of (c)
1.72 cm (0.68 in.), 195 min, and 0.33 cm (0.13 in.), respectively.
Base flow for this rainfall event was assumed to be close to the flow
rate in the day after (April 16, 2011). Fig. 8 shows the rainfall–flow
rate relationship for this rainfall event and it also shows the base
flow rate from the dry day.
Fig. 7 shows that, for the maximum rainfall depth of 0.28 cm
(0.11 in.), the flow in the sewer can reach up to 5.7 m3 =h (25 gpm),
while Fig. 8 shows that for a rainfall intensity that exceeded
0.30 cm (0.12 in.), the flow did not exceed 2.3 m3 =h (10 gpm).
This shows that the permeable pavement in this site is efficiently
reducing the peak flow.

Discussion of Results

The results show different percentages of reduction from different Fig. 9. Comparison of runoff/rain between the preconstruction and
types of pavement (36, 13, and 46% from permeable concrete, postconstruction of permeable pavement in three alleys: (a) Eads Site;
permeable asphalt and permeable pavers, respectively). Fig. 9 sum- (b) Cardinal Site; (c) Geyer Site; the large box represents the 25th per-
marizes the comparison between the preconstruction and postcon- centile, median, and 75th percentile; the whiskers represent the 5th and
dition in the three alleys. The mean connect lines in the three alleys 95th percentiles; the small circle represents the mean
show a reduction from the preconstruction to postconstruction
condition. Statistical analysis shows significant reduction in runoff
in the Eads and Geyer sites while the reduction in the Cardinal site
was not significant. (Mullaney and Lucke 2014) which contribute to the high percent-
In this case study, results showed that the pavement type can age of reduction from this type of permeable pavement. Brattebo
affect the percent reduction. Properties like drainage rate and reten- and Booth (2003) showed that little to no runoff was evident from
tion properties of the permeable pavement may affect the percent- the pervious pavers tested on parking areas even during high peri-
age of reduction, and they are largely dependent on the pore space ods of rainfall (42 mm over 14 h). Results in the three sites are
and the particle-size distribution of the bedding materials and summarized in Table 3.
the underlying permeable layers (Anderson et al. 1999). The open The lowest reduction in the stormwater runoff was in the
space of the joints used for infiltration in the permeable pavers Cardinal site, which used the permeable asphalt (13%). This per-
represents typically between 8 to 20% of the pavement surface area cent was lower than two studies reported by the U.S. EPA (2009)

© ASCE 04016002-8 J. Environ. Eng.

J. Environ. Eng., 04016002


for volume retention of runoff from porous asphalt (96.7 and 25% University Edwardsville (SIUE). The Metropolitan St. Louis Sewer
from France and Durham, New Hampshire, respectively). In these District (MSD) undertook the flow monitoring and data collection.
two studies, the permeable asphalt is equal to the total catchment The East West Gateway Council of Governments assisted the
area (constructed experiment) while in this study related to CSO, coordination of the study. Mr. Philip Kreisman and Mr. Rex Pierce
the permeable pavement is not equal to total catchment area and reviewed the manuscript.
such a ratio would have an important role. The percentage reduc-
tion of runoff would increase due to the increase of permeable area
installed compared to the total catchment area at any site. Although Supplemental Data
the drainage or catchment areas for the manholes where the flow
meters where installed were unpredictable with the presence of Tables S1–S6 are available online in the ASCE Library (www.
many other manholes nearby, the difference in permeable area be- ascelibrary.org).
tween the sites has an effect on percentage reduction. The Geyer
site has 510 m2 (5,490 ft2), the Eads site has 304 m2 (3,267 ft2),
Downloaded from ascelibrary.org by Southern Illinois University on 02/03/16. Copyright ASCE. For personal use only; all rights reserved.

while the Cardinal site has 232 m2 (2,500 ft2) of a total permeable References
area which is consistent with the ranking of percentage reductions
from the three sites (46, 36, and 13% from Geyer, Eads, and Anderson, C. T., Foster, I. L., and Pratt, C. J. (1999). “Role of urban
Cardinal, respectively). surfaces (permeable pavements) in regulating drainage and evapora-
Another potential reason for the difference in percentage reduc- tion: Development of a laboratory simulation experiment.” Hydrol.
tion is the slope of the pavement. The Cardinal site had the steepest Processes, 13, 597–609.
Bean, E. Z., Hunt, W. F., and Bidelspach, D. A. (2007). “Evaluation of four
slope among the three sites which reduces the amount of water that
permeable pavement sites in eastern North Carolina for runoff reduction
can infiltrate through the pavement (3.5% for the Cardinal site and water quality impacts.” J. Irrig. Drain. Eng., 10.1061/(ASCE)0733
versus 1 and 0.8% for the Eads and Geyer sites, respectively). -9437(2007)133:6(583), 583–592.
Booth, D. B., and Leavitt, J. (1999). “Field evaluation of permeable
pavement systems for improved stormwater management.” J. Am. Plan.
Conclusion Assoc., 65(3), 314–325.
Brattebo, B. O., and Booth, D. B. (2003). “Long term stormwater quantity
Green infrastructure such as permeable pavement provides on-site and quality performance of permeable pavement systems.” Water Res.,
stormwater management for volume reduction from storm runoffs, 37(18), 4369–4376.
and can offer a cost-effective means to address the CSO problem Collin, K. A., Hunt, W. F., and Hathaway, J. M. (2007). “Evaluation of
especially in the alleys where the loads are expected to be low. various types of permeable pavements with respect to water quality im-
The reduction in stormwater runoff was 36, 13, and 46% from provement and flood control.” World Environmental and Water Resour-
permeable concrete, permeable asphalt, and permeable pavers, re- ces Congress, ASCE, Reston, VA, 1–12.
spectively. In this case study, the results showed that the type Hunt, B., Stevens, S., and Mayes, D. (2002). “Permeable pavement use and
of permeable pavement can affect the reduction in the CSO. research at two sites in eastern North Carolina.” Global Solutions for
Urban Drainage, ASCE, Reston, VA, 1–10.
Permeable asphalt had the lowest reduction while the permeable
James, W. (2008). “Green roads: Research into permeable pavers.”
pavers had the highest. For each tested site, factors like ratio of Stormwater, 3(2), 40–48.
permeable pavement to the total catchment area, slope, and main- Kwiatkowski, M., Welker, A. L., Traver, R. G., Vanacore, M., and Ladd, T.
tenance may affect the percentage of reduction in water quantity. (2007). “Evaluation of an infiltration best management practice utilizing
The study showed that the installation of permeable pavement in pervious concrete.” J. Am. Water Res. Assoc., 43(5), 1208–1222.
alleys can be used to reduce the flow in the combined sewer sys- Lee, H., Swamikannu, X., Radulescu, D., Kim, S. J., and Strenstrom, M. K.
tems and may represent one of the solutions for cities that are (2007). “Design of stormwater monitoring programs.” Water Res.,
experiencing CSO problems. The manual method used to calculate 41(18), 4186–4196.
the reduction in runoff was a time-consuming method, but was able MSD (Metropolitan St. Louis Sewer District). (2010). “Pervious concrete
to estimate the volume reduction in combined sewers based on pavement.” 〈http://www.stlmsd.com/portal/page/portal/engineering/
planreview/PlanReviewInformation/ProprietaryBMPs/Pervious%
detailed rainfall events analysis.
20Concrete%20-%20Final.pdf〉 (May 7, 2014).
Mullaney, J., and Lucke, T. (2014). “Practical review of pervious pavement
designs.” Clean–Soil, Air, Water, 42(2), 111–124.
Recommendations
Rankin, K., and Ball, J. E. (2004). “A review of the performance of
permeable pavers.” Univ. of New South Wales, Sydney, Australia.
Permeable pavement represents an effective technique for the re-
Scholz, M., and Grabowiecki, P. (2007). “Review of permeable pavement
duction of stormwater runoff especially in the alleys where low
systems.” Build. Environ., 42(11), 3830–3836.
loads are expected. The study had to exclude many rainfall events Teledyne Isco. (2009). “2150 area velocity flow module and sensor
due to unverified data that were caused by malfunctioned instruments. installation and operation guide.” 〈http://isco.com/pcfiles/PartPDF/
Increased frequency to verify and calibrate flow meters and automatic SL000004/UP00163Z.pdf〉 (Nov. 24, 2014).
samplers during their deployment is recommended. Tennis, P., Leming, M., and Akers, D. (2004). “Pervious concrete pave-
ments.” 〈http://myscmap.sc.gov/marine/NERR/pdf/PerviousConcrete
_pavements.pdf〉 (May 8, 2014).
Acknowledgments USEPA (United States Environmental Protection Agency). (2009).
“Porous asphalt pavement.” 〈http://cfpub.epa.gov/npdes/stormwater/
This study was funded in part by the Missouri Department of menuofbmps/index.cfm?action=browse&Rbutton=detail&bmp=
Conservation through the City of St. Louis and Southern Illinois 135&minmeasure=5〉 (May 7, 2014).

© ASCE 04016002-9 J. Environ. Eng.

View publication stats J. Environ. Eng., 04016002

You might also like