PERFECT”)
Total floor area that renovated are around 1570 square meter
Total Air volume circulation require = 1570sqm x 4meter x 10 ACH x 0.5 hours (30 min)
Total exhaust Fan capacity (EF-1 to 5) = 1,200cfm + 1,200cfm + 750cfm + 1350cfm + 450cfm
= 4,950 cfm = 8,418 cmh
Note: All door should remain open to allow air flow from once space/room to the others.
AHU should remain running and fresh air Volume damper to be manually fully open to allow fresh air
make up from every air conditioning space that serve by the AHU main duct.
Requirement: Continuous 1 ACH during the initial 14 days occupancy of the completed building
Total exhaust Fan capacity (4,950cfm/ 8,418 cmh) are actually producing 1.34 ACH as showed below:
Tenant just have to make sure all the exhaust Fan are manually open for the initial 14 days.