Compressive Strenght Test PT.

Koin Konstruksi Periode October, 28 to November, 03 2019

NO CASTING DATE TEST DATE AGE STRUCTURE VOLUME QUANTITY SAMPEL FC'
1 21-Oct-19 28-Oct-19 7 GT & ST Turbin Building (Lean Concrete) 6 m³ 3 15 Mpa

2 30-Sep-19 28-Oct-19 28 GT & ST Turbin Building + DB 01 (Lean 33 m³ 3 15 Mpa


Concrete)
3 30-Sep-19 28-Oct-19 28 Auxiliary(Slab) + Admin Builidng Pile Cap 110 m³ 9 28 Mpa
F2b +Pedestal Transformer 4 Pcs
HV Cable Trench, EMH 09 (Slab) + GT & ST
4 21-Oct-19 28-Oct-19 7 89 m³ 6 28 Mpa
Turbine Builiding (Pile Plug 3 pcs)
5 1-Oct-19 29-Oct-19 28 HV Cable Trench (LC) 12 m³ 3 15 Mpa
Admin Building grid AC4=4,5 m + Wall auxiliary =
23m + Wall EMH 17 = 9m + Wall HV Cable Trench
6 22-Oct-19 29-Oct-19 7 47 m³ 3 28 Mpa
= 9,5m + PHT fuel gas = 0,5m + Pipe rise DB 08b =
0,5m
7 23-Oct-19 30-Oct-19 7 HV Cable Trench + Laydown (LC) 30 m³ 3 15 Mpa
8 23-Oct-19 30-Oct-19 7 DB 30C, 30D, 30E, 30G, 30H, 19E 28 m³ 3 28 Mpa
DB (07, 08, 11) (Concrete Full) + Pendestal
Transformer + EMH 15 (Wall Slab), DB (17 & 18)
9 1-Oct-19 30-Oct-19 28 72 m³ 6 28 Mpa
(FullConcrete) + Blow Down Tank 4Pcs (Pile
Plug)
10 23-Oct-19 30-Oct-19 7 Tower Crane (Slab) 86 m³ 6 35 Mpa
11 24-Oct-19 31-Oct-19 7 DB 26D, EMH 10 (Full Concrete) 36 m³ 3 28 Mpa

Admin Building F9B, F3A (Concrete Pile Cap) + DB


12 3-Oct-19 31-Oct-19 28 01 6 Pcs ( Pile Plug ) + DB 30E dan 30F (Lean 30 m³ 3 28 Mpa
Concrete) + EMH 04 (Concrete Slab)
EMH 11,14 (Concrete Slab) + Admin Building F3
(Concrete Pile Cap) + Pendestal Transformer +
13 4-Oct-19 1-Nov-19 28 76 m³ 6 28 Mpa
DB 25 (FullConcrete) + HV Cable Treanch 19 Pcs
(Pile Plug) + Pedestal Transformer (Middle)

Pipe & Cable Trench (Wall) = 8m + EMH 14 =


14,5m + DB 10 = 20, 5m + EMH 12 = 10,5m +
14 26-Oct-19 2-Nov-19 7 Coloumn Admin Builidng C6 = 0,5m + WWTP 101 m³ 6 28 Mpa
Chemical Slab
15 26-Oct-19 2-Nov-19 7 Condenser Wall 127 m³ 9 35 Mpa
16 5-Oct-19 2-Nov-19 28 HRSG Foundation 400 m³ 24 35 Mpa
17 6-Oct-19 3-Nov-19 28 HRSG Foundation 1150 m³ 69 35 Mpa
18 7-Oct-19 4-Nov-19 28 HRSG Foundation 149m³ 9 35 Mpa
Compressive Strenght Test PT. Koin Konstruksi Periode November, 03 to 09 2019

NO CASTING DATE TEST DATE AGE STRUCTURE VOLUME QUANTITY SAMPEL FC'
1 6-Oct-19 3-Nov-19 28 HRSG Foundation 1150 m³ 69 35 Mpa

2 28-Oct-19 4-Nov-19 7 Sludge Enrichment Tank + Waste Water 27 m³ 3 15 Mpa


Storage Pond (LC) + Fill Concrete
3 28-Oct-19 4-Nov-19 7 DB 16 (Full Concrete) 24 m³ 3 28 Mpa
4 28-Oct-19 4-Nov-19 7 Clarifier Wall + DB 16 Full Concrete 60 m³ 6 35 Mpa
5 7-Oct-19 4-Nov-19 28 HRSG Foundation 149m³ 9 35 Mpa
Pile Plug Sludge Enrichment Tank, EMH 05 = 15
1 29-Oct-19 5-Nov-19 7 m, EMH 12 = 14m, DB 06 = 6m, DB 02 = 12m, DB 59 m³ 6 28 Mpa
03C (Riser Pipe Concrete)

Pedestal Transformer (North), Admin Building F4


2 8-Oct-19 5-Nov-19 28 (Pile Cap), Admin Building F1A, F2C (Lean 46 m³ 3 28 Mpa
Concrete)

HV cable Trench (Wall), DB 26, EMH 19, GT & ST


1 30-Oct-19 6-Nov-19 7 Turbin Builidng (Wall), Sludge Enrichment Tank 114 m³ 9 28 Mpa
(LC), Central Monitoring Basin (Slab)

PIT GT & ST Turbine building (Concrete Slab), GT


2 9-Oct-19 6-Nov-19 28 & ST Turbine Building area (5pcs) (Pile Plug), DB 168 m³ 12 28 Mpa
33 (Slab), Pedestal WWTP
1 31-Oct-19 7-Nov-19 7 Oil Separator, Ground bean zone 2 (LC) 11m³ 3 15 Mpa
2 10-Oct-19 7-Nov-19 28 Pipe & Cable Trench (LC) 4 m³ 3 15 Mpa

1 31-Oct-19 7-Nov-19 7 Pipe & Cable Trench, DB 27A, DB 27B (Riser Pipe) 24 m³ 3 28 Mpa

DB 23 (Full Concrete), GT & ST Turbine Building


area (6pcs) (Pile Plug), EMH 06 (Wall Concrete),
2 10-Oct-19 7-Nov-19 28 53 m³ 6 28 Mpa
Pipe Trench (Slab), Pipe Trench & F2 2 Pcs, F1 1
Pcs (Pile Plug)
3 10-Oct-19 7-Nov-19 28 Condenser (Slab) 291 m³ 18 35 Mpa
1 11-Oct-19 8-Nov-19 28 DB ( 03B, 03C, 03D) (Full Concrete) 66 m³ 6 28 Mpa
EMH 03 5m³,04 11m³ ( Concrete Wall), Duct
Bank 01 ( Full Concrete), Duct Bank 29 ( Full
1 12-Oct-19 9-Nov-19 28 Concrete), Pedestal WWTP , Monitoring basin 131 m³ 9 28 Mpa
( Concrete Slab )
Compressive Strenght Test PT. Koin Konstruksi Periode November, 11 to

NO CASTING DATE TEST DATE AGE STRUCTURE


EMH 13 ( Concrete Wall) + Duct Bank 19 ( Full
14-Oct-19 11-Nov-19 28
Concrete) + EMH 10 ( Concrete Slab)
5-Nov-19 12-Nov-19 7 Condenser LC + Ground Beam LC
Transformer Wall + Admin Building F1A,
15-Oct-19 12-Nov-19 28 F2C (Concrete Pile Cap) + Admin Building
F1A (Lean Concrete )
6-Nov-19 13-Nov-19 7 Ground Beam LC
Wall & Pedestal Chemical Tank + GT & ST
6-Nov-19 13-Nov-19 7
Turbine Building (Slab Foundation)
16-Oct-19 13-Nov-19 28 GT & ST Turbine Building Slab
6-Nov-19 13-Nov-19 7 Neutralization Wall

7-Nov-19 14-Nov-19 7 DB 12=4m + Ground Beam=2m (Lean Concrete)

7-Nov-19 14-Nov-19 7 DB 06, Wall Elevator, Wall Cable Trench


GT & ST Turbine Building Slab + GT & ST Turbine
17-Oct-19 14-Nov-19 28
Building Pile Plug + Laydown LC
18-Oct-19 15-Nov-19 28 Neutralization (LC)
8-Nov-19 15-Nov-19 7 Cable Trench, EMH 19, Transformer (Wall)
DB 30, 30A, 01, Pile Cap F1B, F4, F8, F3, Wall
18-Oct-19 15-Nov-19 28 EMH 11 + DB 14 (Full Concrete) + Admin Building
F1b, F4, F8 dan F3 (Pile Cap) + EMH 11 (Wall
Concrete)
19-Oct-19 16-Nov-19 28 Pipe Cable Treanch (Lean Concrete)

Blow Down Tank (Concrete Slab) + Pipe and


19-Oct-19 16-Nov-19 28 Cable Tranch (Pile Plug) + WWTP (Pile Plug)

19-Oct-19 16-Nov-19 28 Neutralization ( Concrete Slab)


ksi Periode November, 11 to 16 2019

VOLUME QUANTITY SAMPEL FC' Supplier

21 m³ 3 28 Mpa VUB

19 m³ 3 15 Mpa VUB

22 m³ 3 28 Mpa VUB

6 m³ 3 15 Mpa VUB

155m³ 9 28 Mpa JKB

572 m³ 28 Mpa VUB


10 m³ 3 35 Mpa JKB

6 m³ 3 15 Mpa JKB

25 m³ 3 28 Mpa JKB

28 Mpa VUB

5 m³ 3 15 Mpa VUB
98 m³ 6 28 Mpa JKB

192 m³ 12 28 Mpa VUB

10 m³ 3 15 Mpa VUB

60 m³ 6 28 Mpa VUB

17 m³ 3 35 Mpa VUB
Compressive Strenght Test PT. Koin Konstruksi Periode November, 18 to 24 2019

QUANTITY
NO CASTING DATE TEST DATE AGE STRUCTURE VOLUME SAMPEL FC' Supplier
1 21-Oct-19 18-Nov-19 28 GT & ST Turbine Building (LC) 6 m³ 3 15 Mpa VUB
2 11-Nov-19 18-Nov-19 7 EMH 09, DB 14, DB 12 48 m³ 3 28 Mpa JKB
HV Cable Treanch ( Slab Concrete), EMH
3 21-Oct-19 18-Nov-19 28 09 ( Slab Concrete), GT & ST Turbin Building 89 m³ 6 28 Mpa VUB
3Pcs (Pile Plug)
4 11-Nov-19 18-Nov-19 7 Wall Condenser 66 m³ 6 35 Mpa JKb
1 22-Oct-19 19-Nov-19 28 GT & ST Turbine Building (LC) 10m³ 3 15 Mpa VUB
2 12-Nov-19 19-Nov-19 7 Lean Concrete Pipe Cable Trench 5,5 m³ 3 15 Mpa JKB

Transformer + Blow Down Tank (Wall), Slab PIT


3 12-Nov-19 19-Nov-19 7 GT & ST Turbine Building, Pipe & Cable Trench + 114 m³ 9 28 Mpa JKB
DB 12 + EMH 02 (Pile plug Use Sika Control)

Admin Building grid AC4=4,5 m + Wall auxiliary =


4 22-Oct-19 19-Nov-19 28 23m + Wall EMH 17 = 9m + Wall HV Cable Trench 47 m³ 3 28 Mpa vUB
= 9,5m + PHT fuel gas = 0,5m + Pipe rise DB 08b =
0,5m
1 23-Oct-19 20-Nov-19 28 DB 30C, 30D, 30E, 30G, 30H, 19E 28 m³ 3 28 Mpa VUB
2 23-Oct-19 20-Nov-19 28 Tower Crane (Slab) 86 m³ 6 35 Mpa VUB
DB 26C, 26D, 24(full concrete) EMH 10 (Wall
1 24-Oct-19 21-Nov-19 28 Concrete) DB 23A, 23C, 23F (Raiser Pipe), 36 m³ 3 28 Mpa VUB
Ultrapure (Pile Plug)

1 15-Nov-19 22-Nov-19 7 Turboset Area (Slab Foundation) waiting 35 Mpa JKB


report
Pipe & Cable Trench (Wall) = 8m + EMH 14 =
14,5m + DB 10 = 20, 5m + EMH 12 = 10,5m +
1 26-Oct-19 23-Nov-19 28 101 m³ 9 28 Mpa VUB
Coloumn Admin Builidng C6 = 0,5m + WWTP
Chemical Tank (Slab)
2 26-Oct-19 23-Nov-19 28 Condenser Phase 5 (Wall) 127 m³ 12 35 Mpa VUB
waiting
3 16-Nov-19 23-Nov-19 7 Turboset Area (Slab Foundation) report 35 Mpa JKB

1 17-Nov-19 24-Nov-19 7 Turboset Area (Slab Foundation) waiting 35 Mpa JKB


report