Professional Documents
Culture Documents
net/publication/275567311
CITATIONS READS
3 641
1 author:
Funso Ariyo
Obafemi Awolowo University
22 PUBLICATIONS 38 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Funso Ariyo on 14 November 2016.
Email address:
funsoariyo@yahoo.com (F. K. Ariyo)
Abstract: The primary purpose in constructing equivalents is to represent a portion of a network containing many buses
but having only a few "boundary buses" by a reduced network containing only the boundary buses and, perhaps, a few se-
lected buses from within the original sub-network. The equivalent constructed gives an exact reproduction of the self and
transfer impedances of the external system as seen from its boundary buses. PowerFactory’s network reduction algorithm
produces an equivalent representation of the reduced part of the network and calculates its parameters. This equivalent re-
presentation is valid for both load flow and short-circuit calculations, including asymmetrical faults (that is, single-phase
faults).
Keywords: Boundary Buses, Reduced Network, Powerfactory, Load Flow, Short-Circuit Calculation
I bus is the vector of the injected bus currents; 3. Network Modeling in PowerFactory
Vbus is the vector of bus voltages measured from the Figure 1 shows IEEE nine-bus system with three syn-
reference node. chronous generators. Generator (G1 ) was selected the swing
generator. The transformer, load and generators data are
Ybus is known as the bus admittance matrix. given in Table 1, 2 and 3 respectively. The network model
In a power system, the current injection is always zero at contains the electrical and graphical information for the
buses where there are no external loads or generators con- grid. To further enhance manageability, this information is
nected; such nodes may be eliminated. Then for an n-bus split into two subfolders: diagrams and network data. An
system, the reduced admittance matrix by eliminating node additional subfolder, Variations, contains all expansion
k is: stages for planning purposes. The network model folder
contains the all graphical and electrical data which defines
Ik = 0 (2) the networks and the single line diagrams of the power sys-
tem under study. This set of data is referred as the network
data model.
where node k has zero current injection, therefore,
Ik = 0
The new bus admittance matrix is:
Yij Ykj
Yij( new) = Yij − (3)
Ykk
where i, j = 1, 2, …, n. i , j ≠ k
In stability studies, all nodes are eliminated except for
the internal generator nodes and obtain the Y matrix for the
reduced network:
I = YV (4)
where
I Y Ynr Vn
I = n = nn
Yrr Vr
(5)
0 Yrn
Figure 1. IEEE three-machine, nine-bus test system [12].
The matrix in equation (5) is the reduced matrix Y. It has
dimensions (n x n), where n is the number of generators. Table 1. Transformers data.
Network reduction can be applied only to those nodes
that have zero injection current. An equivalent represents a Tr1 Tr2 Tr3
network, which contains many buses but only a few boun-
dary buses, by a reduced network that contains only the MVA 250 200 150
boundary buses and a few of the original buses. Equivalents
are used in two circumstances: both to allow larger areas of HV (kV) 230 230 230
major interconnected systems to be represented in studies
and also to achieve improved computational speed in simu- LV (Kv) 16.5 18 13.8
lations by removing buses and branches that influence sys-
tem behavior. Table 2. Loads data.
A boundary cuts a set of tie-lines between areas or oth-
erwise identifiable sections of a network but passes through LoadA LoadB LoadC
no buses. A boundary bus is part of only one area. An
equivalent makes more efficient use of storage when the
ratio of branches to buses in the equivalent is reduced. As a MV 125 90 100
general rule, however, reducing a system into a number of
small equivalents is more efficient than reducing of a large Mvar 50 30 35
system in one step to produce a single equivalent [9-11].
American Journal of Electrical Power and Energy Systems 2013, 2(1): 1-6 3
Table 3. Generators data. The distribution network in Fig. 1 is fed by two busbars,
‘Bus 5’ and ‘Bus 6’, in the center of the transmission sys-
Parameters G1 (swing) G2 G3
tem. It is represented by Load A and Load B and the cor-
Apparent power (MVA) 247.5 192 128 responding two transformers. If the distribution system is to
Voltage (kV) 16.5 18 13.8 be studied in details, while the transmission system is to be
Power factor 1 0.85 0.85 represented only by its equivalent model. The transmission
Active power (MW) - 150 85
system has a connection to another transmission system,
which is represented by the External Grid and the connect-
Reactive power (Mvar) - 6.7 -10.9
ing line. This second transmission system shall remain as it
Voltage (p.u.) 1.04 1.025 1.025 is, the aim of the paper is to reduce only one transmission
Rotor type salient round round system. The “Boundary” (shown by dotted line in Figure 1)
Syn. reactances, xd 0.36 1.72 1.68 defines which part shall be reduced [1]. After this, the net-
Syn. reactances, xq 0.24 1.66 1.61 work is reduced using PowerFactory. The network reduc-
tion procedure will automatically create a new varia-
( )
Sub. transient x d'' 0.2 0.2 0.2
tion/system stage to represent the original grid.
Sub. transient (x )''
q
0.1 0.12 0.2 In the new system stage(s), the part of the grid which was
transient (x )
'
d
0.15 0.23 0.23 not reduced retains its full representation, whereas the part
transient (x ' ) 0.00 0.378 0.32 that was reduced is erased and the new simplified grid re-
q
Rotor resistances 0.00 0.005 0.00 presentation is added, with the connections to the other part
Time constant T d' 3.73 0.8 0.806
of the grid (that is, to the part which is not reduced). The
''
new system stage(s) will therefore represent the combined
Time constant T 0.05 0.05 0.05
d grid (retained grid and reduced equivalent). The new sys-
Accel. Time constant 9.55 4.162 2.765 tem stages will be automatically activated in the active
Leakage reactances x
l
0.083 0.141 0.0949 study case. To calculate short-circuit equivalent, this option
is used to specify whether the short-circuit equivalent shall
be calculated (option enabled) or not (option disabled). Po-
4. Network Reduction in Power Factory werFactory currently supports only the complete short-
circuit calculation method [1]. Figure 2 shows elements in
The Network Reduction function, by default, retains the
the defined boundary. These are to be reduced to an equiva-
original network data. The boundary, necessary to split the
lent three AC voltage sources (ElmVac) and three common
grid into the part to be reduced, was defined and the part to
impedances (ElmZpu) connecting the remaining busbars.
retain its detailed representation. To ensure that the boun-
dary splits the network into two regions, Check Split button
in the ElmBoundary dialogue could be used.
Terminal voltage (kV) 230 230 230 Bus 6 230 233.29 1.014 144.99
Bus 4 230 236.61 1.029 147.31
Active power (MW) 28.211 78.667 -0.00068
Bus 5 230 230.6 1.003 145.6
Reactive power (Mvar) 27.89 21.389 17.6732 Bus 7 230 234.51 1.02 149.66
[1] DIgSILENT PowerFactory Version 14.1 Tutorial, DIgSI- [9] P.M. Anderson & A.A. Fouad, ‘Power System Control and
LENT GmbH Heinrich-Hertz-StraBe 9, 72810 Gomaringen, Stability’, 2nd edition, IEEE Press Power Engineering Se-
Germany, May, 2011. ries, Wiley-Interscience, 2003.
[2] Buygi M. O., H. M. Shanechi, G. Balzer, and M. Shahideh- [10] Arthur R. Bergen & Vijay Vittal, ‘Power System Analysis’,
pour, Transmission Planning Approaches in Restructured 2nd edition, Prentice Hall, Inc., 2000.
Power Systems, IEEE Powertech, June 2006.
[11] Yao-nan Yu, ‘Electric Power System Dynamics’, Academic
[3] Ward J. B.. Equivalent circuits for power flow studies. AIEE Press, Inc., 1983.
Trans. Power App. Syst., 8:373-380, February 1949.
[12] www.sciencedirect.com.
[4] Singh H.K. and Srivastava S.C.. A sensitivity based network
reduction technique for power transfer assessment in dere- [13] Hyungseon Oh, ‘A New Network Reduction Methodology
gulated electricity environment. Transmission and Distribu- for Power System Planning Studies’, IEEE Transactions on
tion Conference and Exhibition: Asia Pacific, IEEE/PES, Power Systems, Vol. 25, No. 2, May 2010.
October 2002.