You are on page 1of 32

CHAPTER  15

Construction
Zibby Kieloch, Joao da João Batista Ferreira da Silva,
Mauro Gomes Baleeiro, Piotr Wojciechowski, Marcin Tuzim,
Mark Lancaster

15.1. Introduction 3 15.5.3. Revision and Finishing 20


15.2. Construction Surveys 3 15.5.4. Erection Method Selection Criteria 21
15.3. Right-Of-Way Clearing and Site Access 3 15.6. Conductor Stringing 21
15.4. Foundations 5 15.6.1. Preparation 22
15.4.1. Introduction 5 15.6.2. Stringing Methods 22
15.4.2. Excavation 6 15.6.3. Tension Stringing Equipment
15.4.3. Concrete and Reinforcement Works 7 and Setup 23
15.4.4. Drilling and Blasting 9 15.6.4. Conductor Sagging 25
15.4.5. Assembly and Setting of Foundations 9 15.6.5. Offset Clipping 26
15.4.6. Backfilling 9 15.6.6. Conductor Creep and Pre-stressing 26
15.4.7. Foundation Installation Challanges 11 15.6.7. Crossings 27
15.4.8. Foundation Failures 11 15.6.8. Grounding 27
15.5. Structure Assembly and Erection 12 15.7. Insulators, Hardware and Fittings 28
15.5.1. Introduction 12 15.7.1. Insulators 28
15.5.2. Installation Techniques 14 15.7.2. Conductor Hardware 29
2 Construction

15.7.3. Vibration Damping Devices 29 15.8. As-Built Inspection 30


15.7.4. Warning Devices 30 15.8.1. Needs 30
15.7.5. Conductor Fittings 30 15.8.2. Documentation Review 31
15.8.3. Field Inspection 31
15.1. Introduction 3
15.1. Introduction nents in the field are important to allow for ease
of installation and to provide safe operational per-
This chapter will address practical aspects of con- formance as intended.
structing overhead transmission lines. At this point In the past, field surveys required mostly opti-
of the transmission line project, final line design is cal instruments, various manual calculations and
completed, all the required materials are procured intensive labour resources. Presently, some of these
and the construction crews and equipment mobi- tasks are simplified thanks to the use of comput-
lized. Various aspects of material procurement, erized tools and instruments such as total station
inventory control, construction supervision and equipment or real time kinematics GPS systems
engineering support during construction are ad- based on satellite signals. Subsequently, the speed
dressed in Chapter 3 “Planning and Management of surveying and the accuracy of work have both
Concepts” Chapter of the Green Book and are not improved significantly (Figure 15.1).
addressed in this Chapter.
Material contained in this Chapter is intended
to provide a concise picture of the most common 15.3. Right-Of-Way Clearing
construction activities and installation techniques and Site Access
used in installation of an overhead transmission
line. Special attention is being paid to construction Transmission line right-of-way may require re-
activities requiring either high degree of accuracy moval of trees and shrubs to allow for construc-
or those posing high safety risks to construction tion activities. In many cases, vegetation is allowed
crews. This Chapter does not address custom type
design applications requiring very specialized and
rarely used techniques or equipment, as these is-
sues are being addressed by other chapters dealing
with either design approaches or material require-
ments.

15.2. Construction Surveys


Placement of transmission line structures in spe-
cific locations as determined during tower spotting
process is critical from legal, environmental and
technical perspectives. Field surveys are needed
to:

„ „Establish the limits of the transmission line
right-of-way,
„ „Establish transmission line centre line,

„ „Identify structure locations including indi-
vidual legs, anchors, foundations,

„ „Mark locations/zones where special con-
struction techniques are required (i.e. use
of mats to protect the soil or areas requiring
hand clearing),
„ „Identify danger tress for removal.
Figure 15.1  Modern electronic equipment used in
Accurate locations of structures and their compo- transmission line surveys.
4 Construction

within a transmission line right-of-way providing chipped/mulched down and disposed at the job
it is controlled and does not lead to operational site or within the right-of-way.
problems (i.e. tree contacts with an energized con- Access to a new transmission line right-of-way
ductor leading to line outages). needs to be provided for the construction activi-
Various techniques are used in the right-of-way ties. In many cases, temporary access roads are
clearing depending on site specific requirements developed to bring in required materials and con-
and license conditions. They range from the use of struction equipment. In some cases, these tem-
shear blades to remove most of the vegetation to porary access roads are within a right-of-way and
the use of chain saws to remove individual trees. they continue to be used later by asset owners for
In some cases, vegetation clearing is done at the maintenance purposes.
structure locations only. In other cases, no vegeta- Site access may be limited to specific periods
tion clearing is allowed at all and so called “tree of time due to either environmental constrains or
canopy” towers are used with the conductor hang- terrain conditions. In some areas with poor ter-
ing above the three tops. rain such as swamps or permafrost, access may
In some cases, selective clearing is used to mini- be restricted to winter months only with frozen
mize negative effects on the environment. This may conditions allowing the use of heavy equipment.
be required at the stream, lake or river crossing or Example of such conditions is shown in the pho-
at any environmentally sensitive locations. Selec- tograph below (Figure 15.3):
tive clearing may be done by hand clearing using Other measures to help gaining access to the
chain saws or by use of specialized equipment such transmission line construction site include the use
as feller-bunchers (Figure 15.2). of soil mats to minimize damage to the soil or the
Removal of the cut trees/vegetation will de- use of helicopters. In very remote areas, difficult
pend on the conditions of the project license. In terrain conditions or areas with severe restrictions
some cases, trees are cut and sold as merchant- to vehicular traffic, helicopters may be the only op-
able timber. In other cases, trees and shrubs are tion. In order to use helicopters for transportation,

Figure 15.2  Feller buncher used


to remove danger trees at the
edge of right-of-way.
15.4. Foundations 5
Figure 15.3  Transportation of
heavy construction equipment
over a frozen lake.

special provisions need to be made at the design


stage. For example, additional lifting brackets may
be required with the tower design (Figure 15.4).

15.4. Foundations
15.4.1. Introduction
Foundations are the most critical components of
an overhead transmission line system. They are
responsible for transfer of the line loads from the
structure onto the soil. They also provide stabil-
ity of the supporting structure and protection
from extensive deformations. Failure of founda-
tions can have catastrophic consequences to the
overall transmission line system - often causing
prolonged line outages and requirements for ex-
tensive rebuilds. In comparison, failures of other
components, such as hardware or structural mem-
bers, can be localized and may not result in line
outages at all.
Selection of foundation and anchor options for
a given project is done at the design stage. Various
foundation design options include:
„ „Spread footings (concrete, steel or lumber)
„ „Drilled concrete with reinforcing steel

„ „Piles (driven type, screw type, concrete, mi-
cropiles, single or group arrangements) Figure 15.4  Steel tower lifted by a helicopter and
„ „Direct imbedded foundations transported to the installation site.
6 Construction


„ „Anchors (helical screw, grouted, plate, single 15.4.2. Excavation
or in a group)
Foundation installation process starts with excava-
In many cases, especially when transmission line tion. Usually, a trial pit is excavated at a structure
transverses large and diverse environment, founda- type to identify the soil conditions. In case of guyed
tion designers develop multiple foundation design towers, multiple pits may be required. Selection of
options allowing the installer to choose the most the foundation type is responsibility of the contrac-
suitable option as determined at the specific site. tor. However, the final decision generally resides
CIGRE Technical Brochure 308 provides a with the site engineer/supervisor who has the right
comprehensive overview of various foundation to overwrite contractor’s selection (in cooperation
options. TB 308 also contains foundations instal- with the foundation designer).
lation guide, review of health and safety concerns Once the foundation option has been selected,
as well as assessment of environmental impacts full excavation process (if applicable) can begin.
and various mitigation measures. The work must be performed in a manner ensuring
CIGRE TB 281 deals with installation of mi- due stability of the foundation holes, surround-
cropiles and ground anchors which might be good ings (trees, roads, buildings, etc.) and safety of
foundation choices in terrain with poor soil condi- people.
tions or difficult access. Hydraulic excavators, such as the one shown
Additional source of good information on foun- in Figure 15.5 are often used for the excavation
dation installation is IEEE 977 Standard. in normal soils such as clay. Excavations with
This chapter will highlight the main challenges unshielded walls may only be performed in un-
encountered during installation of transmission saturated soils and while maintaining safe wall
structure foundations. inclination.

Figure 15.5  Hydraulic


excavator during the
work of strengthening the
foundation of 110 kV OHL.
15.4. Foundations 7
In more loose soils, internal sheeting, as shown plates, jumping jacks, vibration hammers, levelers,
in Figure 15.6, can be used to keep open access etc.
to the excavation hole. The main load-bearing ele-
ments of the structure are made as steel or wooden 15.4.3. Concrete and Reinforcement
puncheons, while the elements protecting the soil
Works
from falling are made of boards or steel sheets.
The excavated material is removed and stock- Concrete foundations are used on overhead trans-
piled. It can be later used as a fill but not as com- mission lines worldwide. Their popularity is due
pacting material. to ease of design, ease of obtaining base materials
If in the course of the foundation works the (cement, sand, water) and low installation costs.
excavation is made too deep, it should not be filled
with the excavation material, but a concrete or con- 15.4.3.1. Reinforcement
densed gravel substructure up to the foundation Foundation stub angles get positioned in the ex-
depth needs to be installed. During installation, cavation prior to insertion of steel reinforcement.
water should be prevented from entering the foun- Proper alignment of the steel stub angles is critical
dation excavation. When required, appropriate in successful tower installation and can be achieved
drainage system is used to lower the ground water by the use of rigid steel leg templates reproducing
level without causing decrease in the load-bearing the position of all four tower legs in relation to each
parameters of the surrounding soils or negative other or by the use of independent concrete slabs
impact on the environment or surrounding infra- to which individual stub angle is attached.
structure. The reinforcement bars/rods should be free
In very dense soils, heavy duty excavators are from visible defects and damages, clear from ex-
used. In rock, hydraulic hammers or explosive may cessive amounts of rust, mud and other dirt. The
be required. bars should be joined by means of tie wire or weld-
Other construction equipment used in excava- ing. To ensure proper setbacks, plastic distance
tions include: trucks, energy generators, vibration holders providing minimum distance between

Figure 15.6  A view on an properly made excavation sheeting.


8 Construction

the reinforcement and the formworks are used. Quality of the concrete mix can be checked
An additional procedure increasing the firmness of at the job site using a slump test which involves
ready-made reinforcement cages and protecting it filling a steel cone with concrete mix, removing
from canting during installation or concrete works the cone and then measurement of the concrete
is to use additional inclined bars along and across shape slump. Additional test include preparation of
the mounted reinforcement cases. concrete cubes for strength testing at the lab after
7 and 28 days to verify adequate strength.
15.4.3.2. Concrete Mixing and Placement The free drop height of the concrete mix should
The concrete used in foundation works may be be made as small as possible. It should not exceed
mixed directly on site or brought in or from the 100cm. The thinner the mix, the smaller should
concrete mixing plant. If mixed at the job site, the be the height of its drop. With liquid mixes, the
following measures must be taken: height should not exceed 50 cm. In higher trenches,
concrete should be placed with the use of tubes,

„ „Proper storage for cement, sand, stone, ag-
sleeves or chutes. Whatever the method used, the
gregate, and water is required
last stretch to be filled with concrete (50 cm) must

„ „Silos used for bulk storage of cement should
be vertical and not sloping as this prevents separa-
be weatherproof and protected from dust
tion of the mix.
pollution

„ „Bagged cement should be stored to prevent it 15.4.3.3. Concrete Consolidation
becoming damp and used in the same order
Consolidation of the concrete mix is the last pro-
as delivered
cedure but one (before curing) that determines the

„ „Cement that is adversely affected by damp
quality of both the concrete itself and the structure
should not be used
made of that concrete. For this reason:

„ „Aggregate storage areas should have adequate
drainage  mix must be consolidated until it is com-
„ „the

„ „Water should be protected against contami- pact and homogenous;
nation.  excavation must be tightly filled, and the
„ „the
reinforcement – precisely coated;
If produced at the mix plant, mixing of the concrete
 surface of the structure should be as
„ „the
should be done with the use of machines prevent-
smooth and pore-free as possible.
ing its fractions from separating and its consis-
tency from changing. For long-distance transport The most widespread method of concrete consoli-
of concrete mixes, truck concrete mixers with low dation is vibration. In practice, internal or external
rotation speed should be used to prevent segrega- vibrators are used. Vibration lasts for 10-30s, which
tion of the materials. For short-distance transport depends on the consistency and composition of the
on site, conveyor pumps are often used. concrete mix as well as the type and parameters of
Normally, concrete should be placed within the vibrator. Vibration should be discontinued as
two hours after the initial loading in a truck mixer soon as the cement wash appears on the concrete
or agitators, or within one hour if non-agitating surface.
equipment is used. These periods may be extended
or shortened, depending on climatic conditions 15.4.3.4. Concrete Curing
and whether accelerating admixtures or retarding Proper concrete curing in essential in achieving
admixtures have been used. Before the concrete desired mechanical parameters. The concrete,
is placed all rubbish should be removed from the particularly in the summer time, requires proper
formwork and the faces of form in contact with humidity to be maintained. Unrestricted water
the concrete should be cleaned and treated with evaporation can lead to undesired concrete shrink-
the suitable release agent. ing. Therefore concrete must be protected from
15.4. Foundations 9
water loss due to extensive wind and temperature, incorrect installations may lead to undesired visual
by means of using special curing compound, cover- effects. It is always recommended to use proper
ing with foil or pouring with water. During rain a surveying techniques.
fresh concrete shall be protected from direct effects In order to ensure proper steel tower stub an-
of rainwater. During winter the proper maturing chor installations in the concrete foundations, steel
conditions for concrete shall be ensured by: templates are used. They are usually made of steel
angles that are welded to the reinforcement or steel

„ „external warming of the foundation placed by
trench sheeting of the foundation. There are ready
means of e.g. straw batts, styrofoam,
made holes in templates in order to provide tem-

„ „using chemical concrete additives shortening
porary connection with the anchor of the tower.
the concrete bonding time or increasing its
Sometimes, when the foundations are very big,
temperature,
steel truss constructions are used as templates. It

„ „heating the water or the aggregates,
is recommended to place and measure all founda-
 of heating rods inside and outside the
„ „use
tions anchors of the tower at one time.
foundation,
Each country has its own installation tolerances

„ „increasing the cement content, what increas-
based on their own experiences and local regula-
es the hydratation temperature
tions. Some of the are presented in CIGRE Tech-
Concrete works in the temperature below -10 oC nical Brochure 308 “Foundation Installation – An
are not recommended. Overview.” (Figure 15.7)

15.4.4. Drilling and Blasting 15.4.6. Backfilling


In some soil conditions, foundation excavation is Proper compaction of the backfilling is crucial for
done by the means of drilling and blasting meth- achieving desired uplift resistance. Most failures
ods. In stable materials drilling should be to the of the foundations take place due to the tower leg
full depth of the excavation. According to IEEE pulled out and not pushed-in (see Figure 15.8).
977, inspection of the drilling and blasting activity The main principle of using proper backfill is to
should include monitoring to ensure that survey achieve soil characteristics close to those of natu-
controls such as tower center monuments, survey ral soil.
hubs, reference points and benchmarks are not The following methods are used to obtain the
distorted or lost. appropriate condition of the backfill:
During such drilling and blasting, work safety

„ „Backfilling should be done by placing backfill
procedures must be followed. When blasting are
in layers,
done near existing infrastructures (ie. OHL) or

„ „Use of proper backfill material which is easy
inhabitants, a “heave mat” should be placed over
to compact,
the blast area. This mat prevents or minimizes the

„ „Modification of the structure of the backfill
danger of rocks coming onto existing infrastruc-
by application of an adhesive for draining of
tures.
the moisture (e.g. lime),

„ „„Fixing” the particulates of cohesionless
15.4.5. Assembly and Setting soil (reducing its deformability) by chemi-
of Foundations cal stabilization, joining with adhesives, e.g.
cement,
Accurate placement of foundations and anchors

„ „Separating the soil and broken stone levels or
is extremely important to achieve proper installa-
reinforcing them by means of reinforcement
tion of the structures while maintaining legal com-
(e.g. geosynthetics).
mitments to the affected land owner. Additionally,
10 Construction

Figure 15.7  Foundation setting tolerances.

The most popular method used in the construc- enhancing condensation is to damp the filling soil
tion of the overhead power lines is compacting by pouring it with water and its simultaneous com-
of the backfill. Cohesionless backfill should be paction. Another method of increasing the load-
placed in layers, approximately 25-35 cm thick, bearing capacity is the stabilization with cement.
each compacted by vibration plates, jumping jacks Cohesive soils shall be condensed in layers ev-
or vibration hammers. A commonly used practice ery 20-25 cm, using non-hammering methods, e.g.
15.4. Foundations 11
tamping rollers after fragmentation of the agglom- „ „Mistakes in design calculations,
erated soil or vibration plates instead of hammer- 
„ „Improperly collected or assumed soil
type methods. Damping the filling soil with water strength parameters,
is a gross mistake. „ „Faulty materials used,
The compaction index, typically in the range „ „Improper backfilling,
of 0.96-0.98, is often specified by the foundation „ „Insufficient reinforcement or piles.
designers to be achieved during installation.
Additionally, transmission foundation failures can
occur due to the failure of other line components
15.4.7. Foundation Installation such as an insulator or a hardware string.
Challanges Catastrophic failure of a single foundation can
lead to cascading failures of several structures, es-
Installation of transmission structure foundations
pecially if a transmission line has no provisions for
presents various challenges and problems. Some
anti-cascading or “stop” type structures.
of them are:
The following are two examples of foundation
15.4.7.1. Safety failures:
During all installation foundation stages (excava- 15.4.8.1. Failure of a 220 kV OHL
tion, reinforcing, concreting, backfilling) good
The failure started at a tension tower. Over 7 km of
safety procedures must be followed in order to
OHL was destroyed (Figures 15.9 and 15.10).
avoid human injuries and equipment damages.
15.4.8.2. Failure of a 110 kV OHL
15.4.7.2. Environmental Requirements
Failure caused by a landslide (bad geotechnical
Special measures are required to minimize nega-
design). 1,3 km of OHL was destroyed (Figures
tive impact on environment and surroundings.
15.11 and 15.12).
15.4.7.3. Logistical Problems:
„ „Delays in delivery of the concrete,
„ „Improper backfill material
„ „Malfunctioning of the equipment
„ „Encounter of unexpected conditions: under-
ground infrastructure, war explosives, big
rocks, unstable soil, high ground water levels,
etc.

„ „Inexperienced construction personnel caus-
ing installation errors

15.4.7.4. Extreme Weather Conditions:


„ „heavy snow or rain,
„ „flooding,
„ „extreme cold or heat.

15.4.8. Foundation Failures


Transmission structure foundation failures may
occur as a result of either poor design or incor-
rect installation. Typical causes of such failures Figure 15.8  Foundation uplift. The pushed-in
include: foundation is intact.
12 Construction

15.5.1.1. Structure Types


The Installation Techniques may vary according to
the structure types and/or may be better suitable
or be more effective in regard to cost and time,
for one type or another. This Section focuses on
the installation of guyed and self-supporting steel
lattice tower types, designed and manufactured
using steel angles and plates, with bolted joints,
corresponding to the vast majority of the high
and extra-high voltage transmission lines built up
around the world. This construction type is the
most common in all parts of the world.

Figure 15.9  Destroyed tension tower.

Figure 15.11  Tension tower destroyed and moved


down about 14 m.

Figure 15.10  A view on the destroyed suspension


towers.

15.5. Structure Assembly


and Erection
15.5.1. Introduction
This Section provides an overview of all the activi-
ties involved in the erection of HV Transmission
Line structures, addressing the typical installation
techniques, equipment and safety requirements,
as well as general advice regarding the best and
most common industry practices used to achieve Figure 15.12  Landslide causing destruction of a road,
safe and cost effective instalation. a house and a tower.
15.5. Structure Assembly and Erection 13
CIGRE Technical Brochure 416 provides exam- partly mechanized tower erection activities -
ples of various alternate and innovative structure The medium-light category comprises small
designs used worldwide. equipment and heavier tools mainly used
for pulling ropes and lifting the tower pieces
15.5.1.2. Preparation Work and sections, or tensioning the guy wires,
Prior to commencement of tower installation, the such as hoists, handheld stuff as the come-
following preparation work must be done: alongs, small stand-alone motorized winches,
together with sets of fiber or nylon ropes,
„ „All structural design drawings including
sets of anchors, pulleys and hooks or equiva-
structure layout, erection, and bill of materi-
lent, or either hydraulic light truck-mounted
als must be available;
types; also steel or aluminum truss-type
„ „Plan and profile drawings identifying struc-
beams to be attached to the tower legs or
ture types and their locations must be avail-
masts (see illustration below) and work as gin
able;
poles; ladders.
„ „Structure and anchor foundations must be in
„ „Heavy Equipment, for the extensively mecha-
place, with their cast in metallic inserts clean
nized tower erection activities - In general,
and ready for erection start up, observing the
the heavy equipment determines the Instal-
minimum time lapse for concrete curing, as
lation Method, and vice-versa; it can be one
applicable;
or multiple gin poles, mobile-cranes, prefer-
„ „All the steel must be made available;
ably the “all terrain” on wheels types, or giant
15.5.1.3. Logistics, Site Facilities and helicopters, known as “sky-cranes”.
Mobilization „ „Auxiliary Stuff – a radio communication
system is intensively used; grounding devices
A good logistical planning and execution at site is
are mandatory to be in place, prior to any
essential for the success of the Tower Installation
tower erection work to commence; theodo-
activities, as multiple resources are applied simul-
lites are used to control leveling, alignment
taneously at multiple spots, organized in a logic
and plumbing.
sequence. Fig.1 – Towers delivered to a marshal-
ing yard (usually called “cemetery”) and bundled 15.5.1.5. Safety Requirements
by “the like pieces”. They need to bere-bundled by
The Tower Erection is amongst the activities pos-
“component”, prior to the transportation to their
ing the highest safety risks to the construction
erection spots.
crews and therefore it requires special individual
15.5.1.4. Equipment and Tools and collective protection and strict compliance to
the safety rules. As a general safety rule, all and
The typical equipment and tools used for HV
each equipment, tools, ropes, pulleys, hooks, safety
Transmission Structures Assembly and Erection
clamps, etc, need to be inspected, calibrated and
can be grouped into 4 basic categories:
have their nominal capacity tested and certified,
„ „Small Individual and Portable Tools, suitable prior to be released to the sites and/or put into
for the manual tower erection activities - The service.
ordinary individual or portable tools for
works at height consist of the fork wrenches Laws and Regulations
and torque wrenches used by the linemen. A Special provisions concerning to the management
handful electric-rechargeable battery screw of risks and safe work procedures at height apply
driver is also used for the tower preassem- to the Tower Erection activities, according to the
bling on the ground. local Laws and Regulations for each country.
„ „Medium-light Equipment and Tools, for the
14 Construction

Labor Qualification erection process. There are four main methods of


The assembly and erection of any tower requires a erection of steel lattice transmission towers which
team work, where each member of the team per- are described below:
forms a specific task that has to be perfectly or-
15.5.2.1. Manual Erection Piece by Piece:
chestrated with the others. Only well trained and
the Build-up or Piecemeal Method
certified professionals to work at height shall be
hired to perform such a job. This method consists of building up the tower, mem-
ber by member, from bottom upwards. The tower
Individual and Collective Protection members are laid down serially on the ground ac-
It is mandatory that the Employer provides and cording to the sequence and closest possible to their
assure that all his/her employees properly uses and erection positions, to avoid time loss. For the self-
continuously keep their individual and collective supporting towers, the erection procedure starts
protection devices, know and abide to the local leg- with the preparation and positioning of the first four
islation, guidance and codes of practices, whenever leg segments together with their relative step bolts,
working at the tower sites, as applicable; joint plates and splices; then lifted and tilted to the
right angle, bolted to the foundation stubs and hold
Weather Condition Restrictions their upper end firmly in their positions, by a tem-
As another safety rule, the Tower Erection activi- porary guy wire anchoring system. Linemen climb
ties shall not be performed or has to be discon- up the leg segments and stay positioned to pro-
tinued whenever subject to the risk of lightning ceed forward with the tower erection. Subsequently,
or under rainfall, snowfall, fog or haze. bracings and diagonals are rigged, lifted and ren-
dered to the linemen to be nested to their respective
joint plates, then inserting as many bolts, washers
15.5.2. Installation Techniques and nuts that corresponds to the assembly drawings
Provided that the preparation work has been prop- and to the joint holes, and tightened, in order to
erly done as above, and the towers have been sorted complete the first section, i.e., the base frame of the
out to their spots in a sequence, complete with tower. Same procedure is repeated for the follow-
their legs, extensions, bodies and accessories, ac- ing sections onwards until the tower is completely
cording to the construction lists, then the installa- erected. For the guyed towers, the procedures are
tion work shall commence. Especial attention has similar and need to be adapted to the vertical erec-
to be paid to prevent damage to the steel and to the tion of the tower mast components, anchored all
galvanizing coat, by splitting the tower members, the way up by temporary guy wires, until it reaches
and/or preassembled sections, preferably over a the final and definitive guy wire anchoring positions
timber bed and providing them with proper rig- and then the tower head is completed.
ging with fiber or nylon ropes during the lifting Generally, hoisting of members is carried out
and temporary guy wiring processes; no tower ele- manually and/or by an auxiliary beam, having
ment shall be bent or eventually subjected to undue ropes and pulleys attached to the tower legs, to
straining during erection. As a generally accepted work as a gin pole, or even assisted by small stand-
practice, the tower joints shall not have their bolts alone winches.
tightened to the prescribed torque at first, so that In spite it is still extensively used in many parts
a minimal degree of freedom is allowed in order of the world, this is a labor intensive and less pro-
to accommodate the necessary corrections in the ductive method in comparison to the others and
level, verticality and/or alignment of each tower can only be suitable and advantageous if:
section. A topographer with the theodolite has to
„ „the use of a heavy equipment, such as crane
be positioned along the tower axis line, to control
or a helicopter, is not available or is not fea-
and command these corrections, all over the tower
sible for technical or economic reasons;
15.5. Structure Assembly and Erection 15
„ „there is qualified and cheap labor available, in
abundance;
„ „there is not enough flat land near to the
tower spot available and cleared for tower
and/or tower sections preassembling;
„ „it is used as a complementary activity in spe-
cial circumstances and in combination with
other methods, such as
y y to erect the upper part of a tower, if its
height and weight exceeds the capacity
range of a crane; an illustration of the
Build-up Method as complementary to
the Section Method is provided in Fig-
ures 15.13, 15.14 and 15.15.
y y to erect a heavy tower base, especially in Figure 15.14  Build-up Method - Manual erection
case of unequal legs, in preparation for a of a self-supporting tower aided by gin poles, in a
faster helicopter erection of the remainder mountainous area; no access for cranes; no place for
parts, particularly in rough terrain with preassembling.
difficult access, or inside to a rainforest
with a narrow ROW clearance; for smaller
jobs, especially out of sequence; then to rig and lift them as units, using a gin pole,
a mobile crane or a helicopter, up to their final
15.5.2.2. Section Pre-assembling on the elevation, section by section, until the erection of
Ground and Equipment-aided Erection: the entire tower is complete. Hence, it speeds up
the Section Method the erection process and reduces the risk expo-
This method consists of the preassembling of the sure to the construction crews. Prior to commence,
major sections of the tower on the ground and

Figure 15.15  Build-up Method/Complementary


Figure 15.13  Build-up Method - Manual erection of a -Manual erection of the upper part of a self-support-
self-supporting tower aided by gin poles, in a swampy ing tower aided by gin poles; tower height exceeded
area; no access for cranes; no place for preassembling. crane capacity range.
16 Construction

an analysis of the dimensions and weight of the


tower components, as well as for the entire tower
height, per each type and quantities, need to be
conducted so that the right erection strategy is
formulated and the best suitable lifting equipment
can be selected.

Using a Gin Pole


The gin pole used consists of a steel or aluminum
truss-type beam, approximately 10m long, and is
held in place by means of guys on the side of the
tower to be erected. The erection procedures in-
herent to the Section Method are mostly the same, Figure 15.16  Section Method – Illustration of the
whether using a gin pole or a mobile-crane; however, erection of the central mast of a guyed tower using
the gin pole-aided erection has some limitations and a gin pole; mast sections were preassembled on the
depending upon the size and weight of the tower ground.
sections and members, they may have to be split;
for instance, a common practice is to divide it in
two pairs of legs forming two panels preassembled
on the ground that correspond to the opposite faces
of the tower section, then lifted, tilted, spliced to
the immediately subjacent stubs or leg segments
and anchored with temporary guy ropes. In case
only one gin pole is being used, to raise the second
face of this section, it is necessary to shift the foot
of the gin pole on the strut of the opposite side of
the tower. After the two opposite faces are raised,
the bracings on the other two sides are fitted and
bolted up by the linemen to complete the tower
section. The tower sections are lined up and made Figure 15.17  Section Method – a cross arm section of
a self-supporting suspension tower is erected using a
square to the line, as the erection develops. After
gin pole.
completing a tower section, the gin pole needs to
slide up to be able to pull up another section. The
gin pole is then made to rest on the top strut of the
tower section’s leg, immediately below the leg splice
and properly guyed into position. The last lift raises
the top of the towers. After the tower top is placed
and all side bracings have been bolted up, all the guy
are removed, except the one which is to be used to
lower the gin pole. An illustration of the gin pole-
aided erection of guyed and self-supporting towers
is provided in Figures 15.16 to 15.19.

Using a Mobile-Crane
The Section Method using a Mobile-Crane, prefer- Figure 15.18  Section Method – a cross arm section of
ably an “all-terrain-on-wheels” type, is the most an angle tower is erected using a gin pole.
15.5. Structure Assembly and Erection 17

Figure 15.19  Section Method – a cross arm section of


a tower is preassembled on the ground; this method Figure 15.21  Section Method using a Mobile Crane
speeds up the erection process. – a lateral section of a tower is preassembled on
the ground and then lifted and mounted on its final
position by the crane.

productive for the erection of self-supporting tow-


ers, particularly in flat terrain with good access consisting of angle guides and relative steel frame
conditions. An illustration of this Method is shown corner brackets need to be installed on both ends
in Figures 15.20 to 15.22. of the four corners of the tower sections to be cou-
pled. This coupling system is designed to ease and
Using a Helicopter
speed erection, to quickly release the helicopter
The Section Method using a helicopter, as an air- and to be stand alone, i.e., with no linemen at-
crane, is also very productive for the erection of tendance. Linemen will then climb up the tower
self-supporting towers, particularly in bad terrain to bolt up the remaining joints and leg splices,
with limited access conditions. Special accesso- to finalize erection and remove the coupling and
ries compounding a coupling and guiding system

Figure 15.22  Section Method using a Mobile Crane –


Figure 15.20  Section Method – tower sections a cross arm section of an angle tower is preassembled
preassembling takes place at the tower spot in on the ground and then lifted and mounted on its final
preparation for erection using a mobile crane. position by the crane.
18 Construction

Figure 15.23  Section


Method using an Air-Crane
– mid sections of a tower are
preassembled on the ground
and then lifted, flied off and
mounted by the S-64 Erickson
air-crane; linemen not
necessarily required to assist
up to this point.

guiding accessories. This method is illustrated in In some cases, it may be disadvantageous be-
Figures 15.23 to 15.25. cause it requires plenty of land cleared at the tower
spot to allow for the entire tower preassembling;
15.5.2.3. Tower Assembly on the Spot therefore, it may be subject to restrictions by the
and Mobile-crane Erection: the Tilting land owners in case a large damage to their plan-
and Stand Up Method tations or tillable areas could occur. Limitations
This method consists of assembling the whole tow- may also apply in case of hilly terrain where the
er on the ground just aside and/or closest possible assembly of complete tower on slopping ground
to the tower footings, and then tilt and stand it up, may not be possible or, either if it may be difficult
as a complete unit, using a mobile-crane, that holds to get the crane into position to raise the complete
the tower while the linemen crew connects and tower. This method may also not be useful if the
strings the guy wires to their anchoring positions. towers are too large and heavy.
This is the most usual and most productive method
for the erection of guyed towers, particularly in
flat terrain with good access conditions (Figures
15.26 to 15.29).

Figure 15.24  Section Method using an Air-Crane


– the top beam of the head of a “delta” tower is Figure 15.25  Section Method - the head of a “racket”
mounted. No linemen on the tower. tower is mounted.
15.5. Structure Assembly and Erection 19

Figure 15.26  Tilt and Stand up Method – The entire Figure 15.28  Tilt and Stand up Method – The tilting
tower is preassembled on the ground (step 1) and lifting of the entire tower continues (step 3)

15.5.2.4. Tower Assembly in a Yard, campaign, to properly rig, tilt and lift tower per
Stand up and Air Transport to the Spot: tower, as complete units, and fly over the line by
the Helicopter Method the shortest distance up to each tower spots, re-
This method consists of the setup of a batch pro- spectively, where they are placed and left in their
duction line for the entire preassembling of a group final erection positions. For the self-supporting
of towers, corresponding to the tower row in a line towers, there are special coupling and guiding
segment as per the construction sequence, alto- accessory system, disposed along with the tower
gether on a marshaling yard and prior to erection. stubs, capable to withstand the entire tower, in
Then plan for the helicopter pick up and erection order to allow for a faster release of the helicopter
back to another trip, while the linemen finally bolt

Figure 15.29  Tilt and Stand up Method – The tower


Figure 15.27  Tilt and Stand up Method – The entire is lifted and mounted in the central pin; the guy wires
tower is tilted, keeping its foot on the ground (step 2) are anchored. (step 4)
20 Construction

Figure 15.30  Helicopter


Method – an entire guyed
tower is preassembled
on the ground and then
lifted and air transported
to its erection spot by the
helicopter.

up the tower leg splices and remove the coupling 15.5.3. Revision and Finishing
accessories. For the guyed towers, a linemen crew
needs to be on the ground when the helicopter ar- It is a usual industry practice that during the course
rives and hovers on the tower spot, to assist with of erection the bolts and nuts at the tower joints
the tower placement on the central pin, as well as, receive a provisional torque, just enough to se-
to provisionally connect and string the four guy curely keep all the members together and the whole
wires to their anchoring position, for a quicker assembly to stand upright. The same procedure is
release of the helicopter. This is the most produc- applied to the guy wires. This is a strategy to speed
tive method for the erection of either guyed or up erection and push faster forward with the bulk
self-supporting towers, particularly in bad terrain erection crew and expensive equipment.
with difficult access conditions. The use of helicop- 15.5.3.1. Tower Assembly Revision and
ters, however, is expensive, weather-dependent and Tightening of Bolts at the Required
requires especial arrangments for the fuel supply.
Torque
Also, more strict and stringent safety and labor
regulations governing the aviation industry applies. However, as the joints might remain slightly loose,
This method may not be useful if the towers are too prior to commence the cable stringing, it is manda-
large and heavy (Figures 15.30 to 15.2). tory that a second and smaller crew come just be-

Figure 15.31  Helicopter Method – an entire Figure 15.32  Helicopter Method – an entire guyed
guyed tower is rigged, tilted and then lifted and air tower is air transported by the helicopter to its
transported. erection spot.
15.6. Conductor Stringing 21
hind to perform a revision of the tower assemblies. availability, access, safety, legal permits and envi-
Linemen have to check all the joints, in regard to ronmental constraints, so that, there is no universal
missing pieces and improper joint assembly and rule or single solution that would apply to encom-
then firmly tight together the members, plates, pass all these variations and constraints, in a cost-
fillers, bolts, nuts and washers at the final torque effective and timely manner. Therefore, it needs to
specified in the assembly drawings, using pre- be customized for each single transmission line
calibrated torque wrenches. The same procedure project. However, it’s been proven by the practice
applies to the guy wires, that are finally adjusted that, whichever assembly and erection method has
to the proper tension and this is the right time been chosen, the smoother is the work, the better,
to check the leveling and alignment of the cross meaning good planning in advance, continuous in
arms and verticality of the towers, and provide for sequence, keeping on schedule and having an early
necessary corrections, prior to the final tightening warning and problem resolution system in place
of the joints. The tightening shall be carried on to prevent slippage. It is of utmost relevance to
progressively from the top downwards, care be- avoid working out of sequence, moving back and
ing taken that all bolts at every level are tightened forth with the assembly and erection crews, as it
simultaneously. It is advisable to employ four per- is seen in the practice as one the major sources
sons, each covering one leg and the face to his/her of cost overrun and project delays, and particu-
right. Tolerance limit for tower verticality shall be larly because the cable stringing activities cannot
a displacement of one in 360 of the tower height. commence until a reasonably long stretch of the
line has all the structures completely erected and
15.5.3.2. Finishing and Installation of revised.
Signaling and Special Devices
If during the tower assembly revision it is found 15.5.4.1. Combining Methods
any part of the tower members and plates with Due to the high cost of mobilization and hour rates
any damage to their zinc protective coating, then of the heavy equipment, like mobile-cranes and
the affected areas must be cleaned and recoated air-cranes, it requires a minimum volume of work
with a rich zinc painting. Signaling and special to be viable, so that, in the normal course, a deci-
devices, such as numbering, phase, circuit and dan- sion has to be taken upfront on which method and
ger plates, anti-climbing devices and bird perching equipment is best suitable for the circumstances,
guards shall be installed, as applicable, according bearing in mind that a later shift from one method
to the assembly drawings. to another will be more expensive. Also, it is a
good practice to advance the structure preassem-
15.5.4. Erection Method Selection bling on the ground, before one or another type
of equipment comes in. Nevertheless, a combina-
Criteria tion of different structure assembly and erection
Achieving an optimal selection for the Structure methods may lead to an optimal Erection Plan for
Assembly and Erection Method involves a complex longer lines, provided that there are opportunities
decision matrix, as multiple variables concur and to improve cost and time, by capturing the advan-
affect each other and need to be balanced alto- tages of different erection methods in response to
gether, at the same time. Overhead transmission different work environments.
line structures vary significantly according to func-
tional and situational factors, and are designed to
enable a large spectrum of combination possibili-
15.6. Conductor Stringing
ties, in response to these variations. On its turn, Installation of a bare overhead conductor can
their assembly and erection activities are often present complex problems. Careful planning and
subject to logistical, local markets supply, land a thorough understanding of pull requirements and
22 Construction

stringing procedures are needed to prevent damage 15.6.2. Stringing Methods


to the conductor during stringing operations. The
selection of stringing sheaves, tensioning method There are two basic methods of stringing conduc-
and measurement techniques are critical factors tors, categorized as either tension or slack string-
in obtaining the desired sagging results. Conduc- ing. There are as many variations of these methods
tor stringing, sagging equipment and techniques and the selected method depends primarily on the
are discussed in detail in the IEEE Standard 524 terrain and the sensitivity to conductor surface
Guide to the Installation of Overhead Transmission damage.
Line Conductors1. Some basic factors concerning 15.6.2.1. Tension Stringing Method
installation are covered in this section.
A tension stringing method is the preferred meth-
od for installing transmission conductor. Using
15.6.1. Preparation this method, the conductor reel is mounted on a
Before conductor stringing can commence, struc- payoff that is capable of applying braking force to
tures must be equipped with required insulators the reel to maintain tension on the conductor. The
strings and hardware. In case of suspension struc- conductor is then strung (or “reeved”) through a
tures, complete insulator strings are attached to the multi-groove bullwheel tensioner so that the con-
structure. Instead of conductor clamps, running ductor is under tension during pulling and is not
blocks with stringing sheaves (pulleys) with large allowed to contact the ground (Figure 15.33). It is
diameter are attached to the bottom of the insula- important to coordinate the bullwheel speed with
tor string to allow for the movement of the conduc- the puller speed to prevent excessive sagging or
tor through the structure. On dead-end structures, dynamic loading (jerking) of the conductor dur-
running blocks are attached directly to the take-off ing the pull.
(landing) plates on the structure and the dead-end In a typical tension stringing operation, blocks
hardware assemblies are installed after the conduc- (also known as “travelers” or “sheaves”) are at-
tor is cut to its required length. tached to each structure or the end of an insulator
string. For re-conductoring applications, the exist-
ing conductor can be transferred to the blocks at
1
IEEE Standard 524 IEEE Guide to the Installation of Overhead
Transmission Line Conductors, IEEE 524-2012, Published by The each tower, then connected to the new conductor
Institute of Electrical and Electronics Engineers, Inc., New York, NY. and used to pull in the new conductor as it is re-

Figure 15.33  Trailer


mounted payoffs and a
truck mounted bullwheel
for tension stringing
(Courtesy of Southwire Co.)
15.6. Conductor Stringing 23
moved. For new construction, a pilot line is pulled
through the blocks and used to pull in a heavier
pulling line, which is then used to pull the conduc-
tor through the blocks. The tension in the conduc-
tor is controlled by coordinating the tension puller
at the pulling end and the bullwheel tensioner at
the conductor payout end of the installation. This
installation method keeps the conductor off the
ground, minimizing the possibility of surface dam-
age and limiting problems at roadway crossings.
It should be noted that the reels the conductor
is shipped on are designed only for transporta-
tion and should not be used as a tensioning device.
Minimum breaking tension should be applied to
the reel on the payoff, just enough to prevent “over- Figure 15.34  Conductor Pull-Down due to excessive
spin” when the pull is interrupted or stopped. A braking force on the payoff (Courtesy of Southwire
common problem in the field is to over tension the Co.)
conductor due to excessive braking of the payoff
reel, thus causing conductor “pull-down” (Figure
15.34). Pull-down can occur in layers under the rain with very difficult relief and access or in lo-
outer layer, thus making it appear the conduc- cations where environmental constrains prohibit
tor was not properly wound by the manufacture. traditional access to a right-of-way.
For this reason payoff tension should be carefully
monitored during pulling. 15.6.3. Tension Stringing Equipment
15.6.2.2. Slack or Layout Stringing and Setup
Method Stringing equipment and requirements can vary
Slack stringing of conductor should be limited to based on the type of conductor being installed.
lower voltage distribution lines and smaller con- The customer should always contact the conductor
ductors where some surface damage is tolerable. manufacturer for recommended guidelines when
The conductor reel(s) are placed on reel stands installing a conductor for the first time. Stringing
or "jack stands" at the beginning of the stringing equipment typically includes payoffs to support the
location. The conductor is unreeled from the ship- reel and back-tension the conductor going into the
ping reel and dragged along the ground by means bullwheel, a bullwheel for back-tensioning the con-
of a vehicle or pulling device. When the conductor ductor during stringing and sagging; blocks (travel-
is dragged past a supporting structure, pulling is ers or sheaves) at the structure attachment points
stopped and the conductor is placed in stringing to support the conductor; a puller for pulling the
blocks attached to the structure. The conductor is conductor through blocks; a means of gripping
then reattached to the pulling equipment and the the conductor; and various other special items of
pull is continued to the next structure. This method equipment.
requires heavy traffic in the right-of-way and is not During the stringing, it is necessary to use the
recommended for transmission applications. proper tool to grip the strands of the conductor
evenly to avoid damaging the outer layer of wires.
15.6.2.3. Helicopter Stringing Method The preferred type of grip is often referred to as
Conductor stringing using helicopters is rarely a basket or Kellems® grip. It is often used because
used due to high cost. This is usually done in ter- its flexibility and small size make it easily pulled
24 Construction

through blocks during the stringing operation. A


swivel should be installed between the pulling grip
and pulling line, or between grips when double-
socked, to allow free rotation of both the conductor
and the pulling line (Figure 15.35).
A stringing block consists of one or more
sheaves or pulley wheels enclosed in a frame to
allow it to be suspended from structures or insu-
lator strings (Figure 15.36). The frame must have
some type of latching mechanism to allow insertion
and removal of the conductor during the stringing
operation. Blocks are designed for a maximum safe
working load which must not be exceeded during
pulling or sagging. Sheaves are often lined with
neoprene or urethane to prevent scratching of Figure 15.36  Single and multi-grooved, lined blocks
conductor in high voltage applications; however, (Courtesy of Sherman & Reilly).
unlined sheaves are also available for special ap-
plications. Block diameters and groove design must
be properly sized for the conductor being used per minimum setback distances are shown in Figure
the conductor manufacturer’s recommendation. 15.37. It is important that the angle the conduc-
Blocks used in tension stringing must be free- tor passes over on the first “entry” block be large
rolling and capable of withstanding high running enough to prevent conductor “birdcaging”. If the
or static loads without damage. Proper mainte- recommended setback cannot be achieved, other
nance is essential. Very high longitudinal tension methods of maintaining this angle should be used,
loads can develop on transmission structures if a such as, increasing the diameter of the entry block
block should "freeze" during tension stringing, pos- or lowering the entry block on the structure.
sibly causing conductor and/or structure damage Generally, splices cannot be pulled through
and posing safety risk to the construction crews. blocks. However, some manufacturers have devel-
Significant levels of rotation resistance will also oped splices that can be used for long pulls through
yield tension differences between spans, resulting blocks. Unless approved for pulling, provision for
in incorrect sag. conductor splicing must be made at the tension site
Equipment setup is generally limited by the ter-
rain available for the payoff and pulling sites. The
recommended bullwheel and payoff setup and their

Figure 15.37  Recommended minimum bullwheel and


Figure 15.35  Basket grip and swivel. payoff setback.
15.6. Conductor Stringing 25
or mid-span sites to avoid pulling splices through
the blocks. Failure to follow manufacturer’s recom-
mendations for stringing equipment can result in
unsafe conditions, equipment damage, or conduc-
tor damage. Conductor damage can include scuff-
ing (corona issues), damage to the outer strands,
and damage to the core strands (especially critical
for composite core designs).

15.6.4. Conductor Sagging


It is important that the conductors be properly
sagged, at the correct stringing tension and refer-
ence temperature per the design. A series of sev-
eral spans, called a line section, is usually sagged
in one operation. To obtain the correct sags, and
ensure the suspension insulators hang vertically,
the horizontal tension in all spans must be equal.
Most sagging information is given relative to the
Figure 15.39  Chicago-style and pocketbook grips.
conductor temperature. A sagging thermometer
should be used to accurately determine the tem-
perature of the conductor (Figure 15.38). Each grip should be sized for the specific con-
15.6.4.1. Sagging Grips ductor it is used with and each grip has a tension
rating that should not be exceeded. Grips have spe-
Once the conductor is pulled in and lying in the cific installation methods which must be followed
blocks, the conductor can be pulled up to design to ensure proper gripping. When the needed ten-
(or “sagging”) tension. Generally the conductor is sion cannot be obtained using a single grip, grips
dead-ended to a structure at one end and the slack can be connected in tandem to achieve a higher
pulled out of the spans. Next a grip is applied to rating. However, the grip manufacturer should be
the conductor free end and the grip is attached to consulted as to the proper connection method and
a ratcheting tensioning device, like a come-along the resulting rating. In many instances the rating
to pull the conductor up to sag. There are several of tandem grips is less than twice the rating of a
types of grips available so verify the conductor single grip.
manufacturer’s recommendation. Common grip
types include scissor type (Klein “Chicago-style”) 15.6.4.2. Sagging Methods
and pocketbook (Figure 15.39). There are many different methods available for
sagging lines. Two of the most common are the
stopwatch method and the transit method. A third
method, using a dynamometer, is sometimes used
for small conductors over one or two spans but is
not recommended for transmission applications as
its accuracy diminishes with each span.
The stopwatch method is based on the principal
that a mechanical pulse imparted to a tensioned
Figure 15.38  Sagging Thermometer (Courtesey of conductor moves at a speed proportional to the
Tallman Equipment). square root of tension divided by weight per unit
26 Construction

length. Three or five return waves usually provide tain sagging tensions due to damage, corrosion
an accurate measurement of sag. The equation for or other environmental effects. In these cases it
the stopwatch method can be seen below. may be necessary to reinforce structures and cros-
2
sarms, or temporarily add reinforcement through
t (15.1) guying.
D = 0.3067  
n Sag adjustment devices such as turnbuckles or
sag adjustment plates are often used in the dead-
D = conductor sag, m. end hardware strings to allow for adjusting conduc-
t = time, sec. tor sags and make necessary sag corrections.
n = number of return waves
By initiating a pulse on a tensioned conductor and 15.6.5. Offset Clipping
measuring the time required for the pulse to move
to the nearest termination and back, the tension If conductor is to be sagged in a series of suspen-
and sag of the conductor can be determined. This sion spans where span lengths vary widely or, more
stopwatch method has come into wide use even commonly, where the terrain is steep, then clip-
for long spans and large conductors2. ping offset calculations may need to be employed
IEEE Standard 5241 lists three methods of sag- in order to yield vertical suspension strings after
ging conductor with a transit: "Calculated Angle installation (Figure 15.40). More information can
of Sight", "Calculated Target Method" and "Hori- be found in the Southwire Overhead Conductor
zontal Line of Sight". The method best suited to Manual, 2nd Edition3.
a particular line sagging situation may vary with
terrain and line design. While the transit method is 15.6.6. Conductor Creep
considered more accurate, the stopwatch method and Pre-stressing
is favored due to is relative ease and quickness.
Upon completion of conductor stringing, a time of
15.6.4.3. Sagging Accuracy up to several days may elapse before the conduc-
Sagging accuracy depends on many factors and it
is usually prescribed in construction specification 3
Thrash, Ridley, Murrah, Amy, Lancaster, Mark and Nuckles, Kim,
document used in tendering. IEEE Standard 5241 “Southwire Overhead Conductor Manual, 2nd Ed., 2007

suggests that all sags be within the less or of 13mm


(0.5 in) of the design value for every 30m (98 ft.) of
span length or 152mm (6 in.) of the design value
for any span. Additionally, possible errors in terrain
measurement, variations in conductor properties,
loading conditions and hardware installation have
led some utilities to include up to 1m (3 ft.) of
additional clearance in addition to the required
minimum ground clearance.
The type and condition of the structures can
also affect sagging accuracy. Certain structure
types (such as flexible tubular poles, tall wood
poles, etc.) can deflect under sagging tensions.
Older structures may have reduced ability to sus-

Figure 15.40  Example of a sag adjustment plate used


Overend, P.R., and Smith, S., "Impulse Time Method of Sag
2

Measurement." with a dead-end insulator string.


15.6. Conductor Stringing 27
breaking strength for 1-2 hours, creep elongation
will be temporarily halted4. For an ACSS (Alumi-
num Conductor Steel Supported) conductor, the
hold time is substantially less and greatly improves
the conductors self-damping capability.

15.6.7. Crossings
When a conductor installation is required to cross
a highway, river, rail or other sensitive area ad-
vanced planning is required. Permits should be
sought from the AHJ (Authority Having Jurisdic-
tion) over the crossing. Coordination with local
Figure 15.41  Offset clipping example3.
authorities, rail, shipping and other entities must
be made, especially where the installation requires
disruption of commercial or public transporta-
tor is tensioned to design sag. Since the conductor tion.
tension during the stringing process is normally Crossings often involve installation of tempo-
well below the initial sagging tension, and because rary intermediate structures, long pulls and high
the conductor remains in the stringing sheaves for tensions. Custom, high strength conductors and
only a few days or less, any elongation due to creep composite core conductors are often used. In many
is normally neglected. The conductor should be cases conductor and connector selection can miti-
sagged to the initial stringing sags listed in the gate tension and long pull concerns.
stringing tables. However, if the conductor ten- When stringing is done over the existing power
sion is excessively high during stringing, or the lines, these lines should be de-energized for safe-
conductor is allowed to remain in the blocks for ty reasons. When this is not possible, additional
an extended period of time, an abnormal amount safety measures are needed which may include the
of creep will occur. If this occurs, the stringing use of insulating blankets and presence of “safety
tables should be corrected to compensate for the watch” on the job site.
additional creep elongation.
When installing a new conductor that will be 15.6.8. Grounding
spliced into an aged, existing conductor it is some-
times beneficial to pre-stress the new conductor Care should be taken to ensure that the conduct
to match the aged creep of the exiting conductor. is isolated from all electrical influences during
The pre-stressing tension is normally much higher the installation procedure. This includes inciden-
than the unloaded design tension for a conductor. tal contact with nearby energized sources, static
The degree of stabilization is dependent upon the voltage buildup during pulling and induced volt-
time maintained at the pre-stressing tension. After age from nearby energized lines. All equipment
pre-stressing, the tension on the conductor is re- should be properly grounded. Conductor should
duced to stringing or design tension limits. At this be grounded, usually with a running ground, and
reduced tension, the creep or plastic elongation of all blocks should be grounded at structures.
the conductor has been temporarily halted, reduc-
ing the permanent elongation due to strain and
creep for a defined period of time. By tensioning
an ACSR (Aluminum Conductor Steel Reinforced) 4
Cahill, T., "Development of Low-Creep ACSR Conductor," Wire
conductor to levels approaching 50% of its rated Journal, July 1973.
28 Construction

15.7. Insulators, Hardware insulators should be stored above the ground in a


dry and covered area. Lids should remain closed to
and Fittings prevent entrance of rodents and to protect insula-
15.7.1. Insulators tors against weather elements.
Insulators should be delivered to a job site in
Insulators are the most important element of the their original packaging. Direct contact with the
strings connecting the electrical parts (conductors) ground must be avoided to ensure that clean units
with grounded structures. They are made of dielec- without any mechanical damage are installed on
tric materials and have dual purpose by providing the transmission line. Good solution to protect
an adequate level of electrical insulation for given insulators after removing from crates is applica-
voltage and sufficient mechanical strength to sup- tion of a wrap-on shield. The use of wrap-on shield
port mechanical loads. helps to prevent the insulator from damage during
Insulators come in different types as shown in installation or tower painting. The wrap-on must
Figure 15.42. be set up to allow the air flow, so that it keeps the
Construction techniques will vary depending insulator from getting mouldy.
on the insulator type used.
15.7.1.2. Assembling Strings
15.7.1.1. Handling
Before installation, each insulator must be re-
CIGRE Technical Brochure 184 provides full over- checked for damage. If any cuts, exposure of the
view of composite insulators handling techniques. core, torn cover, puncture or split is detected, such
However, most of the rules from the brochure also an insulator must be rejected and removed from
apply to other types of insulators (especially long- the construction site to ensure it is not inciden-
rod types). tally used.
Insulators should be delivered to the construc- Moving insulators should be performed manu-
tion site in wooden crates protecting them from ally. Extra care should be taken when lifting and
damage during transportation and handling. At moving long insulators so that no additional bend-
delivery, the crates must be thoroughly checked ing or twisting to the unit is introduced. Under no
for any damage. If you find cracks, dents or other circumstances the insulators can be pulled on the
damage to the crate, each insulator should be ex- ground or carried by rope tied under the shed.
amined for damage. Any unit with exposed core Assembly of insulator strings should be done
or affected sealing of triple point should be im- as closely to the tower as possible. A plastic foil or
mediately rejected and replaced. Crates containing canvas should be spread out so that the assembly

Figure 15.42  Main types of insulators.


15.7. Insulators, Hardware and Fittings 29
is not carried directly on the ground. Any stones tor from the stringing travellers to the suspension
and other hard objects that may cause damage to clamp accurately to ensure that the suspension
the housing of insulator must be removed. clamp is centered on the conductor contact point
All the components should be assembled with- mark.
out the use of excessive force. After assembling the
chain, one should check if the pins and the nut are 15.7.2.2. Dead-End Strings
set up correctly. Nuts and bolts should be checked The dead-end strings should be assembled near
for proper tightness. Any dirt or contamination the tower using necessary protection methods to
should be removed by with soft cloth. prevent direct contact with the ground to avoid
It is important to install corona (grading) rings contamination or damage. When fitting the chain
in proper position to achieve desired protection. particular attention should be paid to:
Installation procedures should be followed to avoid

„ „Proper alignment of arcing devices and pro-
installing the corona rings upside-down.
tective rings
15.7.1.3. Installation „ „Turning screws to the ground,
„ „Correct assembling of locking pins.
Lifting ropes should be attached to the earth-end
insulator metal fitting only. Ropes should not have Once assembled, deadend string must be con-
contact with silicon housing of composite insula- nected to the insulator string on one side, and on
tors. To tighten the screws, use the manufacturer's the other to the hook rope of tensioning system.
recommended torque. When installing, insulators Next, the dead-end string must be tied to the cros-
must not be subjected to bending or torsional lo- sarm of tension tower. For safety reasons, the in-
ads. It is forbidden to walk, sit or climb on the staller must be standing on the shaft of the tower
insulators and their corona rings. During instal- and not on the crossarm.
lation special ladders or temporary bridges must
be used.
15.7.3. Vibration Damping Devices
Ladders, tools, blocks and other equipment,
should be keptaway from the housing of an insula- Vibration dampers, spacers and spacer dampers
tor string to avoid mechanical damages. are mounted on the conductor using either bolted
Insulators damaged during hardware assembly clamps or preformed rods, depending on design.
should always be replaced and removed from the Vibration dampers must be installed at specified
site. distance from a suspension clamp, in accordance
with manufacturer’s installation instructions to
15.7.2. Conductor Hardware provide optimum damping performance. They
must also be installed in vertical position, directly
15.7.2.1. Suspension Strings below the conductor. Spacers and spacer-dampers
Suspension strings can be installed from a bucket must be installed along the conductor in specific
truck or by using mounting ladders suspended locations, in accordance with the installation spac-
from the crossarm. The length of the ladder should ing charts, to provide optimum damping perfor-
be properly matched to the length of the suspen- mance.
sion string to allow the installer to work in a stand- Installation of vibration control devices should
ing position. Strings should be pulled using lifts be carried out on aerial work platforms or from
securely attached to a crossarm and providing a cable trolley carts. During installation, special
uniform load transfer to both vertical walls of the attention should be paid in order not to distort
crossarm. The place of attachment a conductor in the conductor bundle. The manufacturer's recom-
the suspension clamp must be clearly marked and mended tightening torques should be used then
cleared. Care shall be taken to transfer the conduc- tightening the bolts. Bolt heads should be pointing
30 Construction

down so that it is easy to validate the installation The sleeves are pressed onto the conductor by
from the ground. Installation of spacers in a one means of applying mechanical pressure using hy-
section must be done only from one side. draulic dies. They require filler compound to be
inserted into the sleeve prior to compressing to
15.7.4. Warning Devices provide corosion protection.
Other types of compression sleeves use energy
Warning devices on high voltage lines are required of small impolosive charge to press the sleeve onto
in the zones where there is air traffic. They come the conductor. These sleeves do not use filler com-
as coloured balls or cones usually mounted on pound and they can be installed simultaneously
ground wires and glowing elements mounted on (Figure 15.43).
phase conductors. These devices must be placed In all cases, proper installation procedures must
in specific location along the wire/conductor to be followed to provide full strength of the fitting
satisfy local regulations. and trouble free performance.
To protect bird against collisions with overhead
wires, various warning devices, often called bird di-
verters, are being used. Common designs are flap- 15.8. As-Built Inspection
ping discs or spiral rods attached and distributed 15.8.1. Needs
along to the overhead wire. Similarly to vibration
control devices, bird diverters can be installed us- Commissioning of an overhead transmission line
ing lifts/cranes or cable trolley carts. involves an as-built inspection which is needed to
confirm full conformance of the installed line com-
ponents with design drawings and specifications
15.7.5. Conductor Fittings
as provided by the line owner. As-built inspec-
Conductor fittings used with transmission line tions are performed with due diligence, typically
overhead conductors include full tension dead- by design engineers and before transmission line
ends, full tension joints, jumper terminals, and is energized, for safety reasons. Typically, they in-
repair sleeves. These fititngs are needed to provide volve design engineers responsible for different line
for continuity of the conductor. components (electrical, mechanical, civil), contrac-
The most common conductor fittings are of a tor’s project engineers and asset owners who will
compression type involving one or more sleeves. be responsible for maintaining the new overhead

15.43  Simultaneous
instalation of multiple
implosive type sleeves.
15.8. As-Built Inspection 31
line. As-built inspections are carried out in two „ „Foundations: size and placement, condition
phases: acceptance of the “as-built” documentation of the concrete, alignment, type and condi-
and acceptance of the line components (towers, tion of backfill,
foundations, conductors…). „ „support structures: condition of all struc-
tural, completeness and tightness of all con-
15.8.2. Documentation Review nections, proper orientation of the circuits/
phases, phase and aviation plates, locations
Prior to carrying out the as-built inspection in of bird nests and foreign elements on the
the field, the contractor provides the owner with towers, condition of the warning lights, cor-
documentation which may include the following rosion of any elements,
documents: „ „insulation of the line: condition and com-
„ „Work completion certificates confirming pleteness of the insulation equipment, insula-
installation meeting all the technical require- tor string deflections,
ments, „ „phase conductors and equipment: bird-
„ „Foundation records: type of foundation in- caging and cracks of phase conductors and
stalled, size and depth, soil logs (if requested jumpers, condition of clamps and joints,
by the owner), foundations test protocols, location of foreign objects on conductors),
„ „Structure records (i.e. structural deflections, „ „vibration control devices: condition, com-
insulator string deflections, guy wire ten- pleteness and proper spacing
sions, deviations from the original structure „ „OPGW: earthing jumpers, OPGW downleads
location or orientation), to connection boxes,
„ „Conductor stringing records (temperature, „ „g rounding system: condition, completeness,
tension, sag checks made), connections,
„ „Reports of any field measurements performed „ „crossings: adequacy of conductor clearances,
(i.e. anchor pull-out, foundation deflection, proper offsets, markings of the line crossing
etc.), with roads and waterways,
„ „Reports of any material testing done (i.e. „ „site conditions: tree clearing, terrain grading,
inspection of welds), restoration of the existing fences, disposal of
„ „As- built documentation, materials.
„ „Attestations of the materials used, Upon completion of the field inspection, a detailed
„ „Warranty cards of materials and equipment report is issued capturing all the observations. All
used, deviations and non-conformances are identified
„ „Instruction of line’s operation. and presented to the contractor for corrections.
These documents are to be reviewed and accepted Once all the line components are accepted by the
by the Project Engineer and later transferred to the Project Engineer, work completion certificates are
asset owners for maintenance purposes. issued to the contractor confirming full compliance
with all the technical requirements.
15.8.3. Field Inspection
References
Following review of the above documents, field
CIGRE, Technical Brochure 308 “Foundation Installation – An
inspection is performed to assess technical con- Overview”; December 2006
dition of all the line components. The diagnostic CIGRE, Technical Brochure 281 “Design and Installation Of
procedures constitute the basic source of informa- Micropiles and Ground Anchors for OHL Support Foun-
tion concerning the current condition of the line dations; October 2005
as built. They include visual inspection, measure- IEEE, Std 977-2010 “Guide to Installation of Foundations for
Transmission Line Structures”, 2010
ments and tests of:
32 Construction

You might also like