Professional Documents
Culture Documents
Construction
Zibby Kieloch, Joao da João Batista Ferreira da Silva,
Mauro Gomes Baleeiro, Piotr Wojciechowski, Marcin Tuzim,
Mark Lancaster
within a transmission line right-of-way providing chipped/mulched down and disposed at the job
it is controlled and does not lead to operational site or within the right-of-way.
problems (i.e. tree contacts with an energized con- Access to a new transmission line right-of-way
ductor leading to line outages). needs to be provided for the construction activi-
Various techniques are used in the right-of-way ties. In many cases, temporary access roads are
clearing depending on site specific requirements developed to bring in required materials and con-
and license conditions. They range from the use of struction equipment. In some cases, these tem-
shear blades to remove most of the vegetation to porary access roads are within a right-of-way and
the use of chain saws to remove individual trees. they continue to be used later by asset owners for
In some cases, vegetation clearing is done at the maintenance purposes.
structure locations only. In other cases, no vegeta- Site access may be limited to specific periods
tion clearing is allowed at all and so called “tree of time due to either environmental constrains or
canopy” towers are used with the conductor hang- terrain conditions. In some areas with poor ter-
ing above the three tops. rain such as swamps or permafrost, access may
In some cases, selective clearing is used to mini- be restricted to winter months only with frozen
mize negative effects on the environment. This may conditions allowing the use of heavy equipment.
be required at the stream, lake or river crossing or Example of such conditions is shown in the pho-
at any environmentally sensitive locations. Selec- tograph below (Figure 15.3):
tive clearing may be done by hand clearing using Other measures to help gaining access to the
chain saws or by use of specialized equipment such transmission line construction site include the use
as feller-bunchers (Figure 15.2). of soil mats to minimize damage to the soil or the
Removal of the cut trees/vegetation will de- use of helicopters. In very remote areas, difficult
pend on the conditions of the project license. In terrain conditions or areas with severe restrictions
some cases, trees are cut and sold as merchant- to vehicular traffic, helicopters may be the only op-
able timber. In other cases, trees and shrubs are tion. In order to use helicopters for transportation,
15.4. Foundations
15.4.1. Introduction
Foundations are the most critical components of
an overhead transmission line system. They are
responsible for transfer of the line loads from the
structure onto the soil. They also provide stabil-
ity of the supporting structure and protection
from extensive deformations. Failure of founda-
tions can have catastrophic consequences to the
overall transmission line system - often causing
prolonged line outages and requirements for ex-
tensive rebuilds. In comparison, failures of other
components, such as hardware or structural mem-
bers, can be localized and may not result in line
outages at all.
Selection of foundation and anchor options for
a given project is done at the design stage. Various
foundation design options include:
Spread footings (concrete, steel or lumber)
Drilled concrete with reinforcing steel
Piles (driven type, screw type, concrete, mi-
cropiles, single or group arrangements) Figure 15.4 Steel tower lifted by a helicopter and
Direct imbedded foundations transported to the installation site.
6 Construction
Anchors (helical screw, grouted, plate, single 15.4.2. Excavation
or in a group)
Foundation installation process starts with excava-
In many cases, especially when transmission line tion. Usually, a trial pit is excavated at a structure
transverses large and diverse environment, founda- type to identify the soil conditions. In case of guyed
tion designers develop multiple foundation design towers, multiple pits may be required. Selection of
options allowing the installer to choose the most the foundation type is responsibility of the contrac-
suitable option as determined at the specific site. tor. However, the final decision generally resides
CIGRE Technical Brochure 308 provides a with the site engineer/supervisor who has the right
comprehensive overview of various foundation to overwrite contractor’s selection (in cooperation
options. TB 308 also contains foundations instal- with the foundation designer).
lation guide, review of health and safety concerns Once the foundation option has been selected,
as well as assessment of environmental impacts full excavation process (if applicable) can begin.
and various mitigation measures. The work must be performed in a manner ensuring
CIGRE TB 281 deals with installation of mi- due stability of the foundation holes, surround-
cropiles and ground anchors which might be good ings (trees, roads, buildings, etc.) and safety of
foundation choices in terrain with poor soil condi- people.
tions or difficult access. Hydraulic excavators, such as the one shown
Additional source of good information on foun- in Figure 15.5 are often used for the excavation
dation installation is IEEE 977 Standard. in normal soils such as clay. Excavations with
This chapter will highlight the main challenges unshielded walls may only be performed in un-
encountered during installation of transmission saturated soils and while maintaining safe wall
structure foundations. inclination.
the reinforcement and the formworks are used. Quality of the concrete mix can be checked
An additional procedure increasing the firmness of at the job site using a slump test which involves
ready-made reinforcement cages and protecting it filling a steel cone with concrete mix, removing
from canting during installation or concrete works the cone and then measurement of the concrete
is to use additional inclined bars along and across shape slump. Additional test include preparation of
the mounted reinforcement cases. concrete cubes for strength testing at the lab after
7 and 28 days to verify adequate strength.
15.4.3.2. Concrete Mixing and Placement The free drop height of the concrete mix should
The concrete used in foundation works may be be made as small as possible. It should not exceed
mixed directly on site or brought in or from the 100cm. The thinner the mix, the smaller should
concrete mixing plant. If mixed at the job site, the be the height of its drop. With liquid mixes, the
following measures must be taken: height should not exceed 50 cm. In higher trenches,
concrete should be placed with the use of tubes,
Proper storage for cement, sand, stone, ag-
sleeves or chutes. Whatever the method used, the
gregate, and water is required
last stretch to be filled with concrete (50 cm) must
Silos used for bulk storage of cement should
be vertical and not sloping as this prevents separa-
be weatherproof and protected from dust
tion of the mix.
pollution
Bagged cement should be stored to prevent it 15.4.3.3. Concrete Consolidation
becoming damp and used in the same order
Consolidation of the concrete mix is the last pro-
as delivered
cedure but one (before curing) that determines the
Cement that is adversely affected by damp
quality of both the concrete itself and the structure
should not be used
made of that concrete. For this reason:
Aggregate storage areas should have adequate
drainage mix must be consolidated until it is com-
the
Water should be protected against contami- pact and homogenous;
nation. excavation must be tightly filled, and the
the
reinforcement – precisely coated;
If produced at the mix plant, mixing of the concrete
surface of the structure should be as
the
should be done with the use of machines prevent-
smooth and pore-free as possible.
ing its fractions from separating and its consis-
tency from changing. For long-distance transport The most widespread method of concrete consoli-
of concrete mixes, truck concrete mixers with low dation is vibration. In practice, internal or external
rotation speed should be used to prevent segrega- vibrators are used. Vibration lasts for 10-30s, which
tion of the materials. For short-distance transport depends on the consistency and composition of the
on site, conveyor pumps are often used. concrete mix as well as the type and parameters of
Normally, concrete should be placed within the vibrator. Vibration should be discontinued as
two hours after the initial loading in a truck mixer soon as the cement wash appears on the concrete
or agitators, or within one hour if non-agitating surface.
equipment is used. These periods may be extended
or shortened, depending on climatic conditions 15.4.3.4. Concrete Curing
and whether accelerating admixtures or retarding Proper concrete curing in essential in achieving
admixtures have been used. Before the concrete desired mechanical parameters. The concrete,
is placed all rubbish should be removed from the particularly in the summer time, requires proper
formwork and the faces of form in contact with humidity to be maintained. Unrestricted water
the concrete should be cleaned and treated with evaporation can lead to undesired concrete shrink-
the suitable release agent. ing. Therefore concrete must be protected from
15.4. Foundations 9
water loss due to extensive wind and temperature, incorrect installations may lead to undesired visual
by means of using special curing compound, cover- effects. It is always recommended to use proper
ing with foil or pouring with water. During rain a surveying techniques.
fresh concrete shall be protected from direct effects In order to ensure proper steel tower stub an-
of rainwater. During winter the proper maturing chor installations in the concrete foundations, steel
conditions for concrete shall be ensured by: templates are used. They are usually made of steel
angles that are welded to the reinforcement or steel
external warming of the foundation placed by
trench sheeting of the foundation. There are ready
means of e.g. straw batts, styrofoam,
made holes in templates in order to provide tem-
using chemical concrete additives shortening
porary connection with the anchor of the tower.
the concrete bonding time or increasing its
Sometimes, when the foundations are very big,
temperature,
steel truss constructions are used as templates. It
heating the water or the aggregates,
is recommended to place and measure all founda-
of heating rods inside and outside the
use
tions anchors of the tower at one time.
foundation,
Each country has its own installation tolerances
increasing the cement content, what increas-
based on their own experiences and local regula-
es the hydratation temperature
tions. Some of the are presented in CIGRE Tech-
Concrete works in the temperature below -10 oC nical Brochure 308 “Foundation Installation – An
are not recommended. Overview.” (Figure 15.7)
The most popular method used in the construc- enhancing condensation is to damp the filling soil
tion of the overhead power lines is compacting by pouring it with water and its simultaneous com-
of the backfill. Cohesionless backfill should be paction. Another method of increasing the load-
placed in layers, approximately 25-35 cm thick, bearing capacity is the stabilization with cement.
each compacted by vibration plates, jumping jacks Cohesive soils shall be condensed in layers ev-
or vibration hammers. A commonly used practice ery 20-25 cm, using non-hammering methods, e.g.
15.4. Foundations 11
tamping rollers after fragmentation of the agglom- Mistakes in design calculations,
erated soil or vibration plates instead of hammer-
Improperly collected or assumed soil
type methods. Damping the filling soil with water strength parameters,
is a gross mistake. Faulty materials used,
The compaction index, typically in the range Improper backfilling,
of 0.96-0.98, is often specified by the foundation Insufficient reinforcement or piles.
designers to be achieved during installation.
Additionally, transmission foundation failures can
occur due to the failure of other line components
15.4.7. Foundation Installation such as an insulator or a hardware string.
Challanges Catastrophic failure of a single foundation can
lead to cascading failures of several structures, es-
Installation of transmission structure foundations
pecially if a transmission line has no provisions for
presents various challenges and problems. Some
anti-cascading or “stop” type structures.
of them are:
The following are two examples of foundation
15.4.7.1. Safety failures:
During all installation foundation stages (excava- 15.4.8.1. Failure of a 220 kV OHL
tion, reinforcing, concreting, backfilling) good
The failure started at a tension tower. Over 7 km of
safety procedures must be followed in order to
OHL was destroyed (Figures 15.9 and 15.10).
avoid human injuries and equipment damages.
15.4.8.2. Failure of a 110 kV OHL
15.4.7.2. Environmental Requirements
Failure caused by a landslide (bad geotechnical
Special measures are required to minimize nega-
design). 1,3 km of OHL was destroyed (Figures
tive impact on environment and surroundings.
15.11 and 15.12).
15.4.7.3. Logistical Problems:
Delays in delivery of the concrete,
Improper backfill material
Malfunctioning of the equipment
Encounter of unexpected conditions: under-
ground infrastructure, war explosives, big
rocks, unstable soil, high ground water levels,
etc.
Inexperienced construction personnel caus-
ing installation errors
Using a Mobile-Crane
The Section Method using a Mobile-Crane, prefer- Figure 15.18 Section Method – a cross arm section of
ably an “all-terrain-on-wheels” type, is the most an angle tower is erected using a gin pole.
15.5. Structure Assembly and Erection 17
guiding accessories. This method is illustrated in In some cases, it may be disadvantageous be-
Figures 15.23 to 15.25. cause it requires plenty of land cleared at the tower
spot to allow for the entire tower preassembling;
15.5.2.3. Tower Assembly on the Spot therefore, it may be subject to restrictions by the
and Mobile-crane Erection: the Tilting land owners in case a large damage to their plan-
and Stand Up Method tations or tillable areas could occur. Limitations
This method consists of assembling the whole tow- may also apply in case of hilly terrain where the
er on the ground just aside and/or closest possible assembly of complete tower on slopping ground
to the tower footings, and then tilt and stand it up, may not be possible or, either if it may be difficult
as a complete unit, using a mobile-crane, that holds to get the crane into position to raise the complete
the tower while the linemen crew connects and tower. This method may also not be useful if the
strings the guy wires to their anchoring positions. towers are too large and heavy.
This is the most usual and most productive method
for the erection of guyed towers, particularly in
flat terrain with good access conditions (Figures
15.26 to 15.29).
Figure 15.26 Tilt and Stand up Method – The entire Figure 15.28 Tilt and Stand up Method – The tilting
tower is preassembled on the ground (step 1) and lifting of the entire tower continues (step 3)
15.5.2.4. Tower Assembly in a Yard, campaign, to properly rig, tilt and lift tower per
Stand up and Air Transport to the Spot: tower, as complete units, and fly over the line by
the Helicopter Method the shortest distance up to each tower spots, re-
This method consists of the setup of a batch pro- spectively, where they are placed and left in their
duction line for the entire preassembling of a group final erection positions. For the self-supporting
of towers, corresponding to the tower row in a line towers, there are special coupling and guiding
segment as per the construction sequence, alto- accessory system, disposed along with the tower
gether on a marshaling yard and prior to erection. stubs, capable to withstand the entire tower, in
Then plan for the helicopter pick up and erection order to allow for a faster release of the helicopter
back to another trip, while the linemen finally bolt
up the tower leg splices and remove the coupling 15.5.3. Revision and Finishing
accessories. For the guyed towers, a linemen crew
needs to be on the ground when the helicopter ar- It is a usual industry practice that during the course
rives and hovers on the tower spot, to assist with of erection the bolts and nuts at the tower joints
the tower placement on the central pin, as well as, receive a provisional torque, just enough to se-
to provisionally connect and string the four guy curely keep all the members together and the whole
wires to their anchoring position, for a quicker assembly to stand upright. The same procedure is
release of the helicopter. This is the most produc- applied to the guy wires. This is a strategy to speed
tive method for the erection of either guyed or up erection and push faster forward with the bulk
self-supporting towers, particularly in bad terrain erection crew and expensive equipment.
with difficult access conditions. The use of helicop- 15.5.3.1. Tower Assembly Revision and
ters, however, is expensive, weather-dependent and Tightening of Bolts at the Required
requires especial arrangments for the fuel supply.
Torque
Also, more strict and stringent safety and labor
regulations governing the aviation industry applies. However, as the joints might remain slightly loose,
This method may not be useful if the towers are too prior to commence the cable stringing, it is manda-
large and heavy (Figures 15.30 to 15.2). tory that a second and smaller crew come just be-
Figure 15.31 Helicopter Method – an entire Figure 15.32 Helicopter Method – an entire guyed
guyed tower is rigged, tilted and then lifted and air tower is air transported by the helicopter to its
transported. erection spot.
15.6. Conductor Stringing 21
hind to perform a revision of the tower assemblies. availability, access, safety, legal permits and envi-
Linemen have to check all the joints, in regard to ronmental constraints, so that, there is no universal
missing pieces and improper joint assembly and rule or single solution that would apply to encom-
then firmly tight together the members, plates, pass all these variations and constraints, in a cost-
fillers, bolts, nuts and washers at the final torque effective and timely manner. Therefore, it needs to
specified in the assembly drawings, using pre- be customized for each single transmission line
calibrated torque wrenches. The same procedure project. However, it’s been proven by the practice
applies to the guy wires, that are finally adjusted that, whichever assembly and erection method has
to the proper tension and this is the right time been chosen, the smoother is the work, the better,
to check the leveling and alignment of the cross meaning good planning in advance, continuous in
arms and verticality of the towers, and provide for sequence, keeping on schedule and having an early
necessary corrections, prior to the final tightening warning and problem resolution system in place
of the joints. The tightening shall be carried on to prevent slippage. It is of utmost relevance to
progressively from the top downwards, care be- avoid working out of sequence, moving back and
ing taken that all bolts at every level are tightened forth with the assembly and erection crews, as it
simultaneously. It is advisable to employ four per- is seen in the practice as one the major sources
sons, each covering one leg and the face to his/her of cost overrun and project delays, and particu-
right. Tolerance limit for tower verticality shall be larly because the cable stringing activities cannot
a displacement of one in 360 of the tower height. commence until a reasonably long stretch of the
line has all the structures completely erected and
15.5.3.2. Finishing and Installation of revised.
Signaling and Special Devices
If during the tower assembly revision it is found 15.5.4.1. Combining Methods
any part of the tower members and plates with Due to the high cost of mobilization and hour rates
any damage to their zinc protective coating, then of the heavy equipment, like mobile-cranes and
the affected areas must be cleaned and recoated air-cranes, it requires a minimum volume of work
with a rich zinc painting. Signaling and special to be viable, so that, in the normal course, a deci-
devices, such as numbering, phase, circuit and dan- sion has to be taken upfront on which method and
ger plates, anti-climbing devices and bird perching equipment is best suitable for the circumstances,
guards shall be installed, as applicable, according bearing in mind that a later shift from one method
to the assembly drawings. to another will be more expensive. Also, it is a
good practice to advance the structure preassem-
15.5.4. Erection Method Selection bling on the ground, before one or another type
of equipment comes in. Nevertheless, a combina-
Criteria tion of different structure assembly and erection
Achieving an optimal selection for the Structure methods may lead to an optimal Erection Plan for
Assembly and Erection Method involves a complex longer lines, provided that there are opportunities
decision matrix, as multiple variables concur and to improve cost and time, by capturing the advan-
affect each other and need to be balanced alto- tages of different erection methods in response to
gether, at the same time. Overhead transmission different work environments.
line structures vary significantly according to func-
tional and situational factors, and are designed to
enable a large spectrum of combination possibili-
15.6. Conductor Stringing
ties, in response to these variations. On its turn, Installation of a bare overhead conductor can
their assembly and erection activities are often present complex problems. Careful planning and
subject to logistical, local markets supply, land a thorough understanding of pull requirements and
22 Construction
length. Three or five return waves usually provide tain sagging tensions due to damage, corrosion
an accurate measurement of sag. The equation for or other environmental effects. In these cases it
the stopwatch method can be seen below. may be necessary to reinforce structures and cros-
2
sarms, or temporarily add reinforcement through
t (15.1) guying.
D = 0.3067
n Sag adjustment devices such as turnbuckles or
sag adjustment plates are often used in the dead-
D = conductor sag, m. end hardware strings to allow for adjusting conduc-
t = time, sec. tor sags and make necessary sag corrections.
n = number of return waves
By initiating a pulse on a tensioned conductor and 15.6.5. Offset Clipping
measuring the time required for the pulse to move
to the nearest termination and back, the tension If conductor is to be sagged in a series of suspen-
and sag of the conductor can be determined. This sion spans where span lengths vary widely or, more
stopwatch method has come into wide use even commonly, where the terrain is steep, then clip-
for long spans and large conductors2. ping offset calculations may need to be employed
IEEE Standard 5241 lists three methods of sag- in order to yield vertical suspension strings after
ging conductor with a transit: "Calculated Angle installation (Figure 15.40). More information can
of Sight", "Calculated Target Method" and "Hori- be found in the Southwire Overhead Conductor
zontal Line of Sight". The method best suited to Manual, 2nd Edition3.
a particular line sagging situation may vary with
terrain and line design. While the transit method is 15.6.6. Conductor Creep
considered more accurate, the stopwatch method and Pre-stressing
is favored due to is relative ease and quickness.
Upon completion of conductor stringing, a time of
15.6.4.3. Sagging Accuracy up to several days may elapse before the conduc-
Sagging accuracy depends on many factors and it
is usually prescribed in construction specification 3
Thrash, Ridley, Murrah, Amy, Lancaster, Mark and Nuckles, Kim,
document used in tendering. IEEE Standard 5241 “Southwire Overhead Conductor Manual, 2nd Ed., 2007
15.6.7. Crossings
When a conductor installation is required to cross
a highway, river, rail or other sensitive area ad-
vanced planning is required. Permits should be
sought from the AHJ (Authority Having Jurisdic-
tion) over the crossing. Coordination with local
Figure 15.41 Offset clipping example3.
authorities, rail, shipping and other entities must
be made, especially where the installation requires
disruption of commercial or public transporta-
tor is tensioned to design sag. Since the conductor tion.
tension during the stringing process is normally Crossings often involve installation of tempo-
well below the initial sagging tension, and because rary intermediate structures, long pulls and high
the conductor remains in the stringing sheaves for tensions. Custom, high strength conductors and
only a few days or less, any elongation due to creep composite core conductors are often used. In many
is normally neglected. The conductor should be cases conductor and connector selection can miti-
sagged to the initial stringing sags listed in the gate tension and long pull concerns.
stringing tables. However, if the conductor ten- When stringing is done over the existing power
sion is excessively high during stringing, or the lines, these lines should be de-energized for safe-
conductor is allowed to remain in the blocks for ty reasons. When this is not possible, additional
an extended period of time, an abnormal amount safety measures are needed which may include the
of creep will occur. If this occurs, the stringing use of insulating blankets and presence of “safety
tables should be corrected to compensate for the watch” on the job site.
additional creep elongation.
When installing a new conductor that will be 15.6.8. Grounding
spliced into an aged, existing conductor it is some-
times beneficial to pre-stress the new conductor Care should be taken to ensure that the conduct
to match the aged creep of the exiting conductor. is isolated from all electrical influences during
The pre-stressing tension is normally much higher the installation procedure. This includes inciden-
than the unloaded design tension for a conductor. tal contact with nearby energized sources, static
The degree of stabilization is dependent upon the voltage buildup during pulling and induced volt-
time maintained at the pre-stressing tension. After age from nearby energized lines. All equipment
pre-stressing, the tension on the conductor is re- should be properly grounded. Conductor should
duced to stringing or design tension limits. At this be grounded, usually with a running ground, and
reduced tension, the creep or plastic elongation of all blocks should be grounded at structures.
the conductor has been temporarily halted, reduc-
ing the permanent elongation due to strain and
creep for a defined period of time. By tensioning
an ACSR (Aluminum Conductor Steel Reinforced) 4
Cahill, T., "Development of Low-Creep ACSR Conductor," Wire
conductor to levels approaching 50% of its rated Journal, July 1973.
28 Construction
down so that it is easy to validate the installation The sleeves are pressed onto the conductor by
from the ground. Installation of spacers in a one means of applying mechanical pressure using hy-
section must be done only from one side. draulic dies. They require filler compound to be
inserted into the sleeve prior to compressing to
15.7.4. Warning Devices provide corosion protection.
Other types of compression sleeves use energy
Warning devices on high voltage lines are required of small impolosive charge to press the sleeve onto
in the zones where there is air traffic. They come the conductor. These sleeves do not use filler com-
as coloured balls or cones usually mounted on pound and they can be installed simultaneously
ground wires and glowing elements mounted on (Figure 15.43).
phase conductors. These devices must be placed In all cases, proper installation procedures must
in specific location along the wire/conductor to be followed to provide full strength of the fitting
satisfy local regulations. and trouble free performance.
To protect bird against collisions with overhead
wires, various warning devices, often called bird di-
verters, are being used. Common designs are flap- 15.8. As-Built Inspection
ping discs or spiral rods attached and distributed 15.8.1. Needs
along to the overhead wire. Similarly to vibration
control devices, bird diverters can be installed us- Commissioning of an overhead transmission line
ing lifts/cranes or cable trolley carts. involves an as-built inspection which is needed to
confirm full conformance of the installed line com-
ponents with design drawings and specifications
15.7.5. Conductor Fittings
as provided by the line owner. As-built inspec-
Conductor fittings used with transmission line tions are performed with due diligence, typically
overhead conductors include full tension dead- by design engineers and before transmission line
ends, full tension joints, jumper terminals, and is energized, for safety reasons. Typically, they in-
repair sleeves. These fititngs are needed to provide volve design engineers responsible for different line
for continuity of the conductor. components (electrical, mechanical, civil), contrac-
The most common conductor fittings are of a tor’s project engineers and asset owners who will
compression type involving one or more sleeves. be responsible for maintaining the new overhead
15.43 Simultaneous
instalation of multiple
implosive type sleeves.
15.8. As-Built Inspection 31
line. As-built inspections are carried out in two Foundations: size and placement, condition
phases: acceptance of the “as-built” documentation of the concrete, alignment, type and condi-
and acceptance of the line components (towers, tion of backfill,
foundations, conductors…). support structures: condition of all struc-
tural, completeness and tightness of all con-
15.8.2. Documentation Review nections, proper orientation of the circuits/
phases, phase and aviation plates, locations
Prior to carrying out the as-built inspection in of bird nests and foreign elements on the
the field, the contractor provides the owner with towers, condition of the warning lights, cor-
documentation which may include the following rosion of any elements,
documents: insulation of the line: condition and com-
Work completion certificates confirming pleteness of the insulation equipment, insula-
installation meeting all the technical require- tor string deflections,
ments, phase conductors and equipment: bird-
Foundation records: type of foundation in- caging and cracks of phase conductors and
stalled, size and depth, soil logs (if requested jumpers, condition of clamps and joints,
by the owner), foundations test protocols, location of foreign objects on conductors),
Structure records (i.e. structural deflections, vibration control devices: condition, com-
insulator string deflections, guy wire ten- pleteness and proper spacing
sions, deviations from the original structure OPGW: earthing jumpers, OPGW downleads
location or orientation), to connection boxes,
Conductor stringing records (temperature, g rounding system: condition, completeness,
tension, sag checks made), connections,
Reports of any field measurements performed crossings: adequacy of conductor clearances,
(i.e. anchor pull-out, foundation deflection, proper offsets, markings of the line crossing
etc.), with roads and waterways,
Reports of any material testing done (i.e. site conditions: tree clearing, terrain grading,
inspection of welds), restoration of the existing fences, disposal of
As- built documentation, materials.
Attestations of the materials used, Upon completion of the field inspection, a detailed
Warranty cards of materials and equipment report is issued capturing all the observations. All
used, deviations and non-conformances are identified
Instruction of line’s operation. and presented to the contractor for corrections.
These documents are to be reviewed and accepted Once all the line components are accepted by the
by the Project Engineer and later transferred to the Project Engineer, work completion certificates are
asset owners for maintenance purposes. issued to the contractor confirming full compliance
with all the technical requirements.
15.8.3. Field Inspection
References
Following review of the above documents, field
CIGRE, Technical Brochure 308 “Foundation Installation – An
inspection is performed to assess technical con- Overview”; December 2006
dition of all the line components. The diagnostic CIGRE, Technical Brochure 281 “Design and Installation Of
procedures constitute the basic source of informa- Micropiles and Ground Anchors for OHL Support Foun-
tion concerning the current condition of the line dations; October 2005
as built. They include visual inspection, measure- IEEE, Std 977-2010 “Guide to Installation of Foundations for
Transmission Line Structures”, 2010
ments and tests of:
32 Construction