Professional Documents
Culture Documents
PROCESS MAP
1
Pass PMP in 21 Days - ITTO Toolbox
InItIatIng PlannIng ExEcutIng MonItorIng & controllIng closIng
Develop Develop Project Management Close
IntEgratIon Project Plan Direct & Manage Project Work Monitor & Control Project Work Project
Charter or Phase
Manage Project Knowledge Perform Integrated Change Control
scoPE Plan Scope Management Validate Scope
Collect Requirements Control Scope
Define Scope
Create WBS
schEdulE Plan Schedule Management Control Schedule
Define Activities
Sequence Activities
Estimate Activity durations
Develop Schedule
cost Plan Cost Management Control Costs
Estimate Costs
Determine Budget
QualIty Plan Quality Management Manage Quality Control Quality
rEsourcEs Plan Resource Management Acquire Resources Control Resources
Estimate Activity Resources Develop Team
Manage Team
coMMunIca- Plan Communications
tIons Management Manage Communications Monitor Communications
rIsk Plan Risk Management Implement Risk Responses Monitor Risks
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
ProcurEMEnt Plan Procurement Management Conduct Procurements Control Procurements
Identify
stakEholdEr Stakeholders
Plan Stakeholder Management Manage Stakeholder Engagement Monitor Stakeholder Engagement
2
Pass PMP in 21 Days - ITTO Toolbox
PROCESS KEY
OUTPUT
3
Pass PMP in 21 Days - ITTO Toolbox
Integration management
`` Deliverables
4.3 Direct & Manage Project Work Executing `` Work performance data Doing the work
`` Issue log
4
Pass PMP in 21 Days - ITTO Toolbox
Scope Management
`` Scope baseline
5.4 Create WBS Planning Decomposing to smaller controllable work
`` Accepted deliverables
5.5 Validate Scope Monitoring & Controlling Customer acceptance
5
Pass PMP in 21 Days - ITTO Toolbox
Schedule management
Process
No Process Group Key Output Why is this process important
Name
Plan Schedule
6.1 Planning `` Schedule management plan Defining how
Management
`` Activity list
6.2 Define Activities Planning `` Activity attributes Decomposing WBS further to activity level
`` Milestone list
`` Project schedule network diagrams
6.3 Sequence Activities Planning Defining relationships between activities if any
6
Pass PMP in 21 Days - ITTO Toolbox
Cost management
`` Cost estimates
7.2 Estimate Costs Planning Working with SME to estimate for project costs
`` Basis of estimates
`` Cost baseline Getting approval from management for approved
7.3 Determine Budget Planning
`` Project funding requirements budget
7
Pass PMP in 21 Days - ITTO Toolbox
Quality Management
Process
No Process Group Key Output Why is this process important
Name
Plan Quality `` Quality management plan Defining standards, checklists, Audits cycle, test approach
8.1 Planning
Management `` Quality metrics and metrics
`` Quality reports
8.2 Manage Quality Executing Performing audits
`` Test and evaluation documents
`` Quality control measurements
8.3 Control Quality Monitoring & Controlling `` Verified deliverables Testing completed deliverables
`` Work performance information
8
Pass PMP in 21 Days - ITTO Toolbox
Resource Management
`` Resource requirements
9.2 Estimate Activity Resources Planning `` Basis of estimates Estimate how many resources
`` Resource breakdown structure
`` Physical resource assignments
`` Project team assignments Getting resources on board / getting
9.3 Acquire Resources Executing
`` Resource calendars approvals
`` EEF updates
9
Pass PMP in 21 Days - ITTO Toolbox
Communications management
`` Project communications
10.2 Manage Communications Executing Doing communications
10
Pass PMP in 21 Days - ITTO Toolbox
Risk Management
`` Risk register
11.2 Identify Risks Planning Identifying what can go wrong
`` Risk report
11.3 Perform Qualitative Risk Analysis Planning `` Project documents updates Identifying the risk priorities
11.4 Perform Quantitative Risk Analysis Planning `` Project documents updates Elaborating numerically on one risk
`` Change requests
11.5 Plan Risk Responses Planning Planning the alternates to reduce risks
`` Work performance
11.7 Monitor Risks Monitoring & Controlling information Check if new risks are present
11
Pass PMP in 21 Days - ITTO Toolbox
Procurement management
12
Pass PMP in 21 Days - ITTO Toolbox
Stakeholder management
13
Pass PMP in 21 Days - ITTO Toolbox
PMP FORMULAS
14
Pass PMP in 21 Days - ITTO Toolbox
PV Planned Value PV = BAC* Planned % Complete What your schedule says you should have spent
EV Earned Value EV = BAC * Actual% Complete How much of the project’s value you’ve really earned
EAC Estimate at Completion EAC=AC+BAC–EV If future work will be accomplished at the planned rate
ETC Estimate to complete ETC = EAC - AC The expected cost to finish remaining work
The run rate required to win the match TCPI> 1 - Harder to complete
To Complete Performance
TCPI TCPI=(BAC-EV)/(BAC-AC) (Run rate = spending rate) TCPI = 1 - Same to complete
Index
(Target Runs = Approved Budget) TCPI <1 – Easier to complete
15
Pass PMP in 21 Days - ITTO Toolbox
16
Pass PMP in 21 Days - ITTO Toolbox
1 Sigma = 68.26%
2 Sigma = 95.46%
Quality Six Sigma Values
3 Sigma = 99.73%
6 Sigma = 99.99%
17