METHOD STATEMENT FOR
EXCAVATION WORKS

06/08/2012
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

REVISION

Eremia Barboiu Cristian


A 06/08/2012 ISSUED FOR IDC VASILE DUMITRU SIMION

Rev. Date Issue, Modification Prepared Checked Approved

Page 2
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

METHOD STATEMENT FOR EXCAVATION WORKS METODA DE LUCRU PENTRU LUCRARI DE


EXCAVATII

1. SCOPE 1. SCOP

This procedure refers to the site preparation Procedura se refera la activitatea de pregatire
activity groundwork and excavation in view of a amplasamentului, prin lucrari de terasamente si
achieving the proposed objective. excavatii pentru realizarea obiectivului propus.
The excavation works are digging works Lucrarile de excavatii sunt lucrari de sapatura
executed with mechanic equipments: excavators, cu volum mare ce se executa cu mijloacele mecanice:
bulldozers, scrapers, graders, etc. excavatoare, dragline, graifere, screpere, buldozere.
gredere.
The selection of the appropriate equipment and Alegerea utilajului optim si a metodei de
excavation method shall be done considering the executie excavatie se va face tinand cont de
followings: urmatoarele:
a) configuratia terenului (panta, denivelari) si
a) Configuration of terrain (slope, accident), soil
natura suprafetei solului, existenta vegetatiei;
nature, vegetation;
b) Land type and its characteristics; b) felul terenului si caracteristicile lui fizico-
c) Works nature (block, embankment, levelling, mecanice;
ditches, foundation pits, profiles); c) natura lucrarilor (de bloc, ramblee, nivelari,
santuri, gropi fundatie, taluzari, profiluri);
d) Works size; d) volumul lucrarilor de executie;
e) Type of excavation (in dry or below water level) e) felul sapaturii (in uscat sau sub nivelul apei);
f) Transport distance of the excavated ground f) distanta de transport a pamantului excavat si
and its destination ; destinatia lui;
g) Position of the working area compared with the g) pozitia frontului de lucru fata de nivelul solului;
ground level; h) forma sapaturii si dimensiunile frontului de
h) Excavation form and size of the working area;
lucru;
i) durata executiei;
i) Duration of execution;
j) Cost of works; j) costul lucrarilor,
k) Duration of execution and the weather influence k) perioada de executie a lucrarii si influenta
intemperiilor asupra terenului;
l) Contractor’s possibility to provide excavation l) posibilitatile executantului de a procura
equipment. utilajele de sapat.

2. DOMAIN 2. DOMENIU

This procedure applies to the excavation works. Its Procedura se aplica in cadrul activitatilor de
knowledge and observance does not exclude the excavare. Cunoasterea si respectarea ei nu exclude
responsibility of the involved personnel to apply the responsabilitatea personalului executiv de a cunoaste
contract conditions and the project provisions. si aplica prevederile proiectului de executie si
caietului de sarcini impuse de proiectant.
3. DOCUMENTS 3. DOCUMENTE DE REFERINTA
- Specific working instructions - Instructiuni de lucru specifice lucrarii;
- Instructions for first aid in case of accident;
- Instructiuni proprii pentru acordarea primului ajutor in
caz de accidentare;
- Instruction for fire prevention and extinguishing; - Instructiuni de prevenire si stingere a incendiilor;

Page 3
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

- Specification Civil Installations; - Caiet de sarcini pentru lucrari civile;


- STAS 1913/1 –Foundation soil. Determination of STAS 1913/1 -Teren de fundare.Determinarea
volume weight on field; greutatii volumetrice pe teren;
- STAS 10473/1 –Road works. Layers of natural - STAS 10473/1 -Lucrari de drumuri. Straturi din
aggregate or soil stabilized with cement. Technical agregate naturale sau pamanturi stabilizate cu
conditions of quality; ciment.Conditii tehnice generale de calitate;
- C29 –95- Standard regarding the improvement of - C29 -95-Normativ privind imbunatatirea
mild foundation soil by mechanical procedures. terenurilor de fundare slabe prin procedee
(books I-IV); mecanice (caietele I-IV);
- C 156 –Standard for quality verification and reception - C 156 -Normativ pentru verificarea calitatii si receptia
of the construction works and related installations. lucrarilor de constructii si instalatii aferente;
- NE 012 –Standard for the execution of concrete and - NE 012 -Normativ pentru executarea lucrarilor din
steel concrete works; beton si beton armat;
- Guide for quality control planning of site works – - Ghid pentru programarea controlului calitatii
C.O.C.C.S.A. 1997; executarii lucrarilor pe santier - C.O.C.C.S.A. 1997;
- Low 319 – Low of occupational health and safety; - Legea 319 - Legea sanatatii si securitatii
ocupationale;
- C 83- Guide for detailed laying-out works; - C 83- Indrumator privind executarea trasarii de
detaliu in constructie;
- General Occupational Health and Safety Plan; - Plan general de securitate si sanatate in munca;
- Environmental Management Plan. - Planul de management al mediului.

4.TERMENI SI DEFINITE
4. TERMS AND DEFINITIONS
- Terasamente - lucrari de deplasari de pamant
- Groundwork – earth moving works (digging, filling-
(sapatura, umplutura si transport pamant), care se
up, transport)
executa cu scopul de a se realiza o constructie;
- Positive slope –groundwork executed in view of land - Rambleu - lucrare de terasament executata in
elevation at the requested level necessary for scopul ridicarii unui teren la nivelul necesar
construction works; constructiei unei cai ferate, sosele, dig;
- Negative slope – the excavation done under the - Debleu - sapatura facuta sub nivelul terenului
ground level in view of the execution of a road natural in vederea executarii platformei unui drum,
platform, railway or opened channel cale ferata sau constructia unui canal deschis;
- Embankment – slanted surface which borders a - Taluz - suprafata inclinata care margineste lateral
cutting or an earthwork; un rambleu sau debleu, teren in panta;
- Dewatering – exhaust of underground water from the - Epuisment - evacuarea sau coborarea apelor
foundation terrain. subterane din zona terenului de fundare.

5. ABBERVIATIONS 5. PRESCURTARI
- HSEQM – Quality, environment and occupational - HSEQM - Manualul calitatii,mediului,sanatatii si
health and safety manual securitatii ocupationale
- PTE – technical project - PTE - Proiect tehnic de executie
- PO – operational procedure - PO - Procedura operationala
- PS – system procedure - PS - Procedura de sistem
- AQ – quality assurance - AQ - Asigurarea calitatii
- CTC – technical control of conformity - CTC - Control tehnic de conformitate
- PV – minutes - PV - Proces verbal
- CC – quality certificate - CC - Certificat de calitate
- FB – concrete sheet - FB - Fisa de betoane
- PT – project team
- PT - Proiect Team (Echipa de Proiect)
- MP – project manager
- MP - Manager proiect
- PCCVI – quality control, verification and testing plan
- RNC – corrective/preventive action report - PCCVI - Plan de control calitate, verificari si incercari
- RNC - Raport de actiune corectiva/preventiva

Page 4
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

6. DESCRIEREA PROCEDURII
6. PROCEDURE DECSRIPTION
6.1 Utilajele necesare pentru procesul tehnologic
6.1. Equipments requested by the technological
process
La executarea mecanizata a sapaturilor se vor alege
Suitable equipments will be selected for the utilaje potrivite si se va tine seama de indicatiile
execution of the works under the following urmatoare privind domeniul de folosire a principalelor
recommendations: tipuri de utilaje de sapat :
a) Excavatoarele cu cupa dreapta sunt indicate la
a) The bucket excavators are suitable for opened sapaturi deschise in spatii intinse avind adincimi peste
diggings in large area, over 2 m deep. 2 m.
b) Excavatoarele cu cupa inversa se utilizeaza
b) The back-acting excavators are suitable for the pentru executarea sapaturilor sub nivelul terenului pe
digging under their area level, for foundation holes with care sunt asezate.
vertical walls. c) Excavatoarele cu greifer se utilizeaza la saparea in
c) The clamshell excavators are suitable for the digging terenuri usoare , terenuri foarte umede sau la
of simple terrains, wet soil or under water soil. paminturi sub apa.
d) Buldozerele sunt utilaje cu un domeniu de folosire
d) The bulldozers have a large area of applicability and foarte variat putind executa concomitent saparea,
can execute simultaneously the digging, the leveling nivelarea si transportul pamintului.
and the soil transport. e) Grederele sunt utilaje destinate in special la
e) Graders are suitable for land works finishing and finisarea lucrarilor de pamint, putind fi folosite si la
small diggings, as ditches for drainage, groundwork of executarea unor sapaturi mici, cum ar fi santurile
small height or cuttings. pentru drenuri sau chiar a unor deblee sau ramblee
de inaltime mica.

6.2 Required technological organization 6.2 Organizarea tehnologica necesara

a) After the excavation works to the level provided by a) Dupa executarea lucrarilor de sapaturi la cota din
design, the composition of the soil shall be verified by proiect se verifica natura terenului de fundare prin
laboratory-tests, by static or dynamic insertion. If at the probe de laborator prin penetrare statica sau
level established by the project the soil nature does not dinamica; in toate cazurile in care se constata ca la
comply with the design requirements, the solution for cota de nivel stabilita pentru proiect natura terenului
performance of the work shall be established by the nu corespunde cu aceea avuta la proiectare, solutia
designer by means of a site instruction confirmed by de continuare a lucrarilor nu poate fi stabilita decat pe
the checker; baza unei dispozitii scrise a proiectantului, cu acordul
verificatorului de proiect;
b) In case the digging is executed in many stages , the b) In cazul in care sapaturile se efectueaza in mai
works shall comply with the project provisions and with multe etape, se va urmari incadrarea lucrarilor
the technical regulation in force (standard C 56-85); executate in prevederile proiectului si prescriptiilor
tehnice in vigoare (Normativul C 56-85);
c) During the execution there will be issued hidden c) Pe parcursul executiei se intocmesc procese
works reports. The laboratory test results will be verbale de lucrari ascunse la care se anexeaza
added, as well as the designer instructed measures in rezultatele determinarilor de laborator si masurile
case of discrepancies between the site conditions and indicate de proiectant in cazul unor neconcordante
the design; fata de situatia prevazuta la proiectare;
d) Soil transport can be done: by direct dropping (at 3 d) Transportul pamantului se poate face; prin
m maximum), wheel barrow (up to 100 m), by lorry aruncarea directa (la 3 m maximum), cu roaba (pana
(big distance), tractors (large distance), by bulldozer la 100 m), cu autocamioane basculante (distante mai
(up to 110 m), trucks with trailer(large distance), with mari), tractoare cu remorci (distante mai mari), cu
bulldozer(up to 110m), with the grader (up to 500 m); buldozerul (pana la 110 m), cu grederul (pana la 500
m);
e) During the execution there will be verified if the e) La executia sapaturilor trebuie verificat daca

Page 5
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

embankments established by the project are in dimensiunile taluzelor prevazute in proiect corespund
compliance with the soil nature in order to avoid soil naturii terenului respectiv, pentru a nu se produce
collapsing. accidente.
f) For the foundations digging shall be considered the f) La executarea sapaturilor pentru fundatii trebuie sa
followings: se aiba in vedere urmatoarele:
I. Maintenance of the natural balance around the I. Mentinerea echilibrului natural al terenului in jurul
foundation pit, or around the existing gropii de fundatie sau in jurul fundatiilor existente
foundations in order to not compromise the pe o distanta suficienta, astfel incit sa nu se
adjacent constructions and installations. pericliteze instalatiile si constructiile invecinate.
II. Cind turnarea betonului in fundatie nu se face
II. If the concrete casting is not executed
imediat dupa executarea sapaturii, aceasta va fi
immediately after digging, the digging will be
done at a higher level than the final level in oprita la o cota mai ridicata decit cota finala pentru
order to avoid the modification of the soil a impiedica modificarea caracteristicilor fizico-
characteristics under the foundation base. The mecanice ale terenului de sub talpa fundatiei.
digging walls will be supported if necessary, Necesitatea sprijinirii peretilor sapaturilor se va
considering the digging depth, the soil stabili tinind seama de adincimea sapaturii, natura,
humidity, composition, stratification, and omogenitatea, stratificatia, coeziunea, gradul de
underground water drainage, climatic fisurare si umiditatea terenurilor, regimul de
conditions during execution, technology and scurgere a apelor subterane, conditiile
duration of works. meteorologice si climaterice din perioada de
executie a lucrarilor de terasamente, tehnologia de
executie adoptata, etc

g) Excavation executed by excavators will not g) Sapaturile ce se executa cu excavatoare nu


exceed the design profile. The digging shall be finished trebuie sa depaseasca in nici un caz profilul
with 20 - 30 cm above the digging profile. For the rest proiectat al sapaturii. In acest scop sapatura se va
of the distance will be used other equipments opri cu 20 - 30 cm deasupra cotei profilului
(bulldozers, graders), or the digging will be done sapaturii, diferenta executindu-se cu alte utilaje
manually. mecanice de finisare (buldozere, gredere) sau
The digging dimensions, level and flatness of the manual. Dimensiunile in plan, cotele si gradul de
excavated surfaces shall mandatory ensure the planeitate sau prelucrare a suprafetelor sapaturilor
conditions of safety work and the quality of the work,
vor asigura conditiile tehnologice de securitate a
according to the regulation in force.
muncii si calitatii lucrarilor in conformitate cu
legislatia in vigoare.
h) in case of terrain responsive to the water action, the h) In cazul terenurilor sensibile la actiunea apei,
digging will be finished at a level higher than that sapatura se va opri la un nivel superior cotei
established in the project: prevazute in proiect.
- for fine sand : - 0.20 - 0.30 m - pentru nisipuri fine: - 0.20 - 0.30 m
- for clay soil:- 0.25 - 0.50 m - pentru paminturi argiloase:- 0.25 - 0.50 m
- soil responsive to mechanization :- 0.40 - 0.50m - pentru paminturi sensibile la mecanizare:- 0.40 -
0.50m
The digging of this layer will be done before the
foundation execution. Saparea si finisarea acestui strat se va face imediat
inainte de inceperea executiei fundatiei.
j) Any modification of the designed level shall be made j) Orice modificari de cote fata de proiect se vor face
only with the approved and order of the designer. numai cu acordul si dispozitia proiectantului.
k) In case of digging close to existing constructions or k) In cazul executarii de sapaturi langa constructii
constructions in progress, the project will establish existente sau in curs de executie, se vor prevedea
provisions to ensure their stability. prin proiect masuri speciale pentru asigurarea
stabilitatii acestora.
l) During the works, the contractor will ask for the l) Pe parcursul executarii lucrarilor, executantul are
presence on site of the designer and geologist when

Page 6
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

the foundation level was reached or in case of obligatia de a solicita prezenta proiectantului,
differences to the provisions of the geotechnical plan geotehnicianului pe santier la atingerea cotei de
and underground water. fundare si ori de cite ori se constata neconcordanta
fata de prevederile studiului geotehnic, nivelului si
caracterului apelor subterane. etc.
6.3 Excavation works execution and supervision 6.3 Tipuri de excavatii, executie si supraveghere
Excavation is performed : Excavatiile se pot executa :
a) above the subsurface water. a) deasupra nivelului apelor subterane.
b) below the level of underground water or in soil
b) sub nivelul apelor subterane sau terenuri cu
with intense water infiltration.
For the works supervision is responsible the engineer. infiltratii puternice de apa.
Supravegherea lucrarilor va fi in sarcina inginerului
de executie.
6.3.1 Execution of excavation above the 6.3.1 Executarea sapaturilor deasupra nivelului
subsurface water. apelor subterane.

a) Excavation with vertical non-supported walls can a. Sapaturi cu pereti verticali nesprijiniti se pot executa
be done up to : pina la adincimi :
I. 0.70 m in case of cohesive and low cohesive I. 0.70 m in cazul terenurilor necoezive si slab
soil; coezive;
II. 1.00 m in case of middle cohesive soil; II. 1.00 m in cazul terenurilor cu coeziune mijlocie;
III. 1.50 m in case of high cohesive soil. III. 1,50 m in cazul terenurilor cu coeziune foarte
mare.
In case of digging with vertical non-supported walls , In cazul sapaturilor cu pereti verticali nesprijiniti se vor
for the borders stability, the following protective lua urmatoarele masuri pentru mentinerea stabilitatii
measures will be taken : malurilor:
IV. The terrain around the excavation will not be I. terenul din jurul sapaturii sa nu fie incarcat si sa
loaded and will not be affected by vibrations; nu sufere vibratii;
V. The earth resulted from the digging will be II. pamintul rezultat din sapaturi sa nu se
stored at minimum 1 m distance. depoziteze la o distanta mai mica de 1 m de la
marginea gropii de fundatii.
The water resulted from rainfall or accidentally III. se vor lua masuri de inlaturare rapida a apelor
accumulated shall be immediately evacuated. de precipitatii sau provenite accidental.
b) diggings with vertical supported walls are suitable b. Sapaturi cu pereti verticali sprijiniti se utilizeaza in
in the following situations : urmatoarele cazuri:
I. If the depth exceeds the above-mentioned I. Cind adincimea sapaturii depaseste adincimea
dimension indicata la tipul anterior.
II. When the excavation with supported walls is II. Cind din calculul economic rezulta eficienta
more efficient. sprijinirilor fata de sapatura executata cu taluz.
The type of the support will be established Tipul de sprijinire se va stabili in functie de natura
according to the soil composition and digging terenului si dimensiunile sapaturii.In cazul in care in
dimensions. timpul lucrarilor se constata ca sunt necesare sprijiniri
In case during the execution of works additional suplimentare, acestea se vor adauga.
supports are required the contractor will proceed Se va lua in considerare in calculul sprijinirilor situatia
with the installation. The calculations will take reala din teren care sa tina cont de cladiri adiacente si
into account existing buildings and on going alte lucrari in desfasurare.
activities adjacent to the excavations. Depending In raport de situatia din teren sprijinirile se pot
on the site conditions sheeting and bracing will b incorpora in umplutura pana la o elevatie considerata
e incorporated into the backfilling to an elevation ca fiind nepericuloasa.
that is considered safe. Sprijinirile se vor indeparta cu grija in asa fel incat sa
Sheeting and bracing removal will be performed nu pericliteze alte constructii din vecinatate.
in a manner that will not affect existing buildings Golurile rezultate dupa evacuare se vor umple cu
and ongoing works in the vicinity. material corespunzator care se va compacta.

Page 7
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

Voids that might result after evacuation will b e Sapaturi cu peretii in taluz se pot executa in orice fel
filled in with suitable backfilling material that will de faze cu respectarea urmatoarelor conditii:
be compacted. a) Pentru adincimea pina la 2 m :
The following conditions must be I. pamintul are o umiditate naturala de 12 - 18 % si
completed on the excavation with embankment: se asigura conditiile ca aceasta sa nu creasca.
a) For depth up to 2 m : Sapatura de fundatie nu sta deschisa mult timp.
I. The soil has a natural humidity of 12 - 18 % II. Panta taluzului sapaturii definite prin tangenta
which will no increase. The foundation digging unghiului de inclinare fata de orizontala (tgB = h/b),
will not remain opened for a long time. sa nu depaseasca valorile maxinie admise pentru
II. The slope defined by the tangent of the angle of diverse categorii de pamint:
slope (tgB = h/b), shall not exceed the maximum -nisip, balast 1/1
admitted values for different type of soil: -nisip argilos 1/1.1,25
-argila nisipoasa 2/3
-sand 1/1 -argila 1/2
-clay sand 1/1, 1,25 -loess 4/3
-sandy clay 2/3 -roca friabila 2/1 ...4/1
-clay 1/2 -stanca 4/1 ...7/1
-loess 4/3
-brittle rock 2/1 ... 4/1 b) In cazul sapaturilor manuale cu adincimi peste 2 m,
-stone 4/1 ... 7/1 taluzul trebuie executat in trepte prevazindu-se pe
inaltimi banchete care sa permita evacuarea
b) in case of by hand diggings with the depth over pamintului prin relee; banchetele vor avea inaltimea
2 m, the slope shall be executed in steps, with
0.6 - 1.00 m si distanta intre ele de 2 m.
benches which allow the earth removal .The
benches will be of 0.6 - 1.00 m high and the
distance between them will be of 2 m. 6.3.2 Sapaturi sub nivelul apelor subterane

In cazul in care se estimeaza inundarea excavatiilor


6.3.2 Excavations with embankment cauzata de panza freatica sau apa rezultata din
fenomene meteorologice, Contractorul va pregati si
In case underground and rain water is forseen to trimite spre aprobare un plan de epuisment.
appear during the execution of excavation works, the Acesta va contine descrierea amplasarii pompelor si
Contractor will submit the proposed program for echipamentelor utilizate precum si detaliile digurilor
dewatering and avoidance of flooding. de protectie.
This shall include a detailed description of all pumping
Digurile se vor construi la cel putin 5m distanta de
arrangements, equipments to be used as well as plans
for the dykes around the excavation. marginea excavatiei. Zona indiguita va avea panta
Earth dykes shall not be constructed within 5 meters of spre scurgere pentru a evita acumularile de apa.
the top of slope of an open excavation. The area Materialul excavat devenit necorespunzator pentru
enclosed by the dyke shall be sloped to drain to alte lucrari ca urmare a unui epuisment
prevent gathering of water. necorespunzator se va indeparta din santier si inlocui
Soil below normal grade, which becomes cu material corespunzator.
unsatisfactory as a result of inadequate dewatering ,
shall be removed and replaced.
7 RESPONSABILITATI

7.1 Inginerul de executie


7 RESPONSIBILITIES - Raspunde de executia incredintata, cu respectarea
stricta a prevederilor proiectului de executie, caietului
7.1 Engineer de sarcini;
- Is responsible for the execution of the works - Preia pe baza proces verbal de trasare a lucrarilor,
according to the project provisions and to the contract reteaua de coordonate inainte de inceperea executiei
conditions; lucrarilor si asigura trasarea corecta a lucrarii;
- Takes over the coordinate scheme based on the - Intocmeste procesul verbal de verificare a cotei de
minutes of the works tracing, before the fundare, impreuna cu reprezentantii proiectantului si

Page 8
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

commencement of the works; clientului;


- Issues, together with the designer and client’s - Intocmeste procesul verbal de verificare a naturii
representatives, the report of the verification of the terenului de fundare, impreuna cu reprezentantii
foundation level ; proiectantului si clientului;
- Issues, together with the designer and client’s - Are obligatia de a informa permanent despre stadiul
representatives, the report for the verification of the soil si calitatea lucrarilor executate;
composition; - Urmareste indeaproape respectarea prevederilor de
- Informs permanently about the stage and quality of executie, detaliilor de executie, precum si prescriptiile
the works; tehnice impuse de standardele de constructie in
- Pursues the observance of the execution provisions, vigoare;
details and technical requirements; - Intocmeste necesarul de utilaje, materiale si forta de
munca ;
- Raspunde de instruirea personalului cu prevederile
- Issues the bill of the equipment and personnel; PTE si intocmeste procesul verbal de instruire ;
- Colaboreaza cu celelalte servicii din societate in
- Is responsible for the personnel training according to vederea asigurarii resurselor necesare desfasurarii
PTE provisions; activitatii;
- Cooperates with the other departments in view of the - Verifica intocmirea la timp a inregistrarilor de calitate
good performance of the works; de baza la lucrari;
- Sprijina activitatea responsabilului CQ pe lucrare,
- Checks the quality records of the works; verifica stadiul fizic al lucrarilor si calitatea lor si ia
masuri, cand este cazul, pentru indepartarea situatiilor
- Supports the quality representative of the works , negative depistate de acesta, urmarind aplicarea
verifies the stage and quality of works and takes corecta a solutiilor de remediere propuse ;
measures, if necessary, for the good performance of - Propune PT pentru schimbarea tehnologiei de
the works with the application of correct solutions; executie atunci cand situatia reala pe teren este alta
decat cea prevazuta prin proiectul de executie;
- Proposes the modification of the technology - Initiaza actiuni corective si preventive in vederea
according to the situation on the field; imbunatatirii activitatii in cadrul santierului.

- Initiates corrective actions for the works improvement 7.2 Responsabilul CTC
- Urmareste permanent respectarea tuturor cerintelor
7.2 Quality control supervisor de calitate prevazute in documentatia de executie PTE
si PCCVI;
- Follows permanently the compliance with the PTE
and PCCVI requirements; - Efectueaza controale planificate conform PCCVI si
inopinate la lucrare.In cazul in care depisteaza o
deficienta in executie, are obligatia de a da dispozitii
- Controlling the works according to PCCVI conditions .
de remediere imediata sau intreruperea lucrarii; in
In case of defective work shall immediately suspend
acest caz se descrie neconformitatea si se
the works in view of repair. In this case the non-
conformity shall be registered in NCR; consemneaza actiune in RNC ;
- Urmareste evitarea si repetarea situatiilor
neconforme ;
- Face propuneri sefului CTC pe societate pentru
- Follows the avoidance or repetition of non- imbunatatirea activitatii cu modificari sau completari la
conformities. PTE;
- Is proposing solutions for the activity improvement; 7.3 Responsabilul tehnic cu executia
- Urmareste in executie aplicarea PCCVI si planul
7.3. Technical responsible for completion calitatii pentru lucrarile care urmeaza a fi executate;
- Checks the PCCVI, or the quality plan (if required by - Admite executia lucrarilor de constructii numai pe
the contract) related to the works which shall be baza proiectelor si a detaliilor de executie verificate de
performed specialistii verificatori de proiecte atestati MLPAT ;

Page 9
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

- Accepts the construction works perfomance based on - Verifica si avizeaza fisele si proiectele tehnologice de
the construction checker certified by MLPAT ; executie, proiectele de organizare a executiei
lucrarilor;
- Intocmeste si tine la zi un registru de evidenta a
- Checks and certifies the technological sheets and lucrarilor de constructii pe care le coordoneaza tehnic
projects and the works planning; si de care raspunde;
- Opreste executia lucrarilor de constructii in cazul in
- Records and updates the works that he coordinates
care s-au produs defecte grave de calitate sau abateri
and is accountable for;
de la prevederile proiectului de executie;
- Suspends the works in case of quality deficiency or - Propune solutii/actiuni corective pentru remedierea
project deviations. lucrarilor.

- Proposes solutions/corrective actions if necessary 8 ANEXE SI INREGISTRARI


- Proces verbal predare — primire a amplasamentului
si a bornelor de repere, inainte de inceperea
8 ANNEXES AND ABBREVIATIONS obiectivului obiectului de investitie;
- Proces verbal de trasare a lucrarilor,inainte de
- Delivery-receiving report of the site and land mark inceperea executiei lucrarilor;
before the commencement of the works; - Proces verbal de verificare cotei de
fundare,inceperea lucrarilor;
- Report of the works marking, before the start of - Proces verbal de receptie calitativa a naturii terenului
works; de fundare, inainte de inceperea lucrarilor;
- Report of the verification of the foundation level; - Proces verbal de verificarea calitatii lucrarilor ce
- Report of the foundation soil composition , before the devin ascunse,pentru turnarea betonului de egalizare;
commencement of the works, - RNC - Raport de actiune corectiva/preventiva.
- Report of quality verification of the works which will
become covered; 9. PREVENIRE RISC SI INSTRUCTIUNI SSM
RNC – report of corrective/ preventive actions. 9.1 Riscuri:
9.RISK PREVENTION AND HSE INSTRUCTIONS
• -Surpare
• -cadere de la inaltime
9.1 Risks :
• -caderea pe cap, pe picioare, pe masini a
materialelor manipulate ;
• -Breakdown
• -cadere de la acelasi nivel, impiedicare ,loviri
• -falling from height
sau striviri provocate de utilaje in miscare
• -fall of the handled materials on the head, cars
• -miscari necontrolate ale utilajelor
or feet
• taieturi sau intepaturi provocate de uneltele
• -falling from the same level, stumbling blows or
manual
crushing provoked by moving machines
• -uncontrolled movements of the machines
• cuts or pricks provoked by manual tools
9.2 Principalele masuri de prevenire si protectie:

• Sapaturile de cercetare se vor face numai sub


supravegherea conducatorilor locurilor de munca.
9.2 The main prevention and protection
measures: • Inainte de inceperea lucrarilor de sapaturi sau
umpluturi se va face un instructaj temeinic cu privire la
• The research works will only be performed
metodele de executie, sculele sau utilajele de
under the supervision of the working places team
constructii ce se vor folosi, repartizarea personalului
leaders.
muncitor la locul de munca ;
• Thorough instruction must be provided
• .In cazul in care in timpul executiei sapaturilor
before the beginning of excavation or filling works
se depisteaza instalatii subterane necunoscute initial
regarding the execution methods, the available tools or

Page 10
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

construction machines,the distribution of the working si care nu sunt indicate in documentatia tehnica de
staff in the working places. executie se va opri imediat executia si se vor evacua
• If during the performance of the excavations oamenii din zona de lucru.
underground installations are identified that had not • -Executarea manuala a lucrarilor de
been known initially and that are not indicated in the sapaturi in apropierea cablurilor electrice, subterane
technical execution documentation, the execution will sub tensiune se va face numai dupa oprirea
be stopped at once and the people will be evicted from curentului. Daca nu se poate opri curentul se vor lua
the working area. masuri special care sa asigure securitatea
• The manual execution of the excavation works personalului [folosirea sculelor din lemn si
close to the underground live power cables will only be supravegherea stricta a lucratorilor de catre
done after interrupting the power. If it is not possible to conducatorul locului de munca]. Se interzice
interrupt the power special precautions will be taken to categoric in aceste cazuri folosirea de unelte si scule
ensure personnel safety [the use of the wooden tools metalice
and the strict surveillance of the workers by the • Saparea gropilor de fundatie cu adancime
working place leader]. The use of metallic tools and mica in terenuri cu umiditate naturala si unde nu exista
devices is completely forbidden in these cases. ape freatice de suprafata se vor executa fara
• The excavation of the foundation holes depth consolidari sau sprijiniri dupa cum urmeaza :
ditches into natural humidity grounds free of surface • in teren usor [nisip, umpluturi] pâna la
waters will be performed without consolidations or adâncimea de 70 de cm.
props, as follows: • -in teren mijlociu [manual] pâna la adâncimea
• in soft ground [sand, fillings] down to 70 cm de un metru.
depth. • -in teren tare [manual ] pâna la adâncimea de
• in average ground [manual] down to 1 m 1,6 metri.
depth. • in teren foarte tare, se sapa [manual] pâna la
• in hard soil [manual] down to 1.6 m depth adâncimea de 2 metri.
• Pentru eliminarea pericolului de accidentare
• in very hard soil the [manual] excavation prin surpare de maluri la sapaturi, se va supraveghea
goes down to 2 m. si controla zilnic starea terenului unde se executa
• The state of the ground where such works are asemenea lucrari. Acolo unde sunt posibile surpari
performed must be supervised and checked daily in sau alunecari de mase de pamânt, indiferent daca
order to eliminate bank collapse accident risks sunt sau nu sunt facute sprijiniri, se vor lua imediat
during excavations. Where soil mass collapse or masuri de consolidare. Numai dupa aceea se va con
gliding is possible, regardless of the fact that props tinua executarea sapaturilor
may or may not be performed, immediate • -Daca se folosesc mai multe utilaje in acelasi
consolidation measures will be taken. Only punct de lucru distanta dintre ele nu trebuie sa fie
afterwards excavations can be continued mai mica de 10 m.
• -If several machines are used in the same • -Executarea de sapaturi mecanizate fara
working point, the distance between sprijiniri se poate face fie in taluz liber, fie in trepte
them must not be smaller than 10 m. cu pereti verticali. Amplasarea utilajelor pentru
• -The mechanized excavations without shoring sapaturi sau umpluturi va fi facuta astfel incât sa nu
may be performed either in free bank, or in vertical existe pericolul alunecarii sau rasturnarii acestora in
wall steps. The excavation or filling machines must incinta sapaturilor.
be placed so as to avoid danger of sliding or • -Toti lucratorii care lucreaza direct sau indirect
upturning within the excavations area. cu utilajele de constructii sau cu mijloacele
mecanizate vor fi instruiti in privinta tuturor masurilor
• -All those working directly or indirectly with the speciale de securitatea muncii pe care trebuie sa le
construction machines or the mechanized means respecte. Aceste masuri vor fi inscrise in fisele de
must be instructed on all the special safety instructaj individual.
measures they must observe. These measures will
be written in the individual instruction sheets.

9.3 Echipament Individual de Protectie


• casca
• bocanci

Page 11
Depots Revamp CON-IPR-BAC-CI-001-A
Method Statement for Excavation Works

• salopeta
9.3 Individual protection equipment • ochelari
• helmet • manusi [daca este cazul]
• boots • centura de siguranta tip HAM [daca este cazul]
• overall • antifoane [daca este cazul]
• glasses
• gloves [if necessary]
• HAM-type safety belt [if necessary]
• soundproofing devices [if necessary]