METHOD STATEMENT FOR
EARTHWORKS
06/08/2012
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
REVISION
Page 1
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
1. SCOPE 1. SCOP
1.1 The earthworks for the execution of the 1.1 Lucrarile de terasamente pentru fundarea
foundations consist of: earth digging, loading, cuprind; saparea, incarcarea in mijlocul de transport,
transportation, dispersal, levelling and compacting transportul, imprastierea, nivelarea si compactarea
for the carrying out of the foundations and pamintului pentru realizarea fundatiilor si instalatiilor
underground installations inside the buildings and subterane din interiorul cladirilor si a zonei aferente
related area which may affect the strength, stability din jurul lor, care influenteaza conditiile de
and operation conditions. The carrying out of these rezistenta, stabilitate si exploatare. Executarea
works will be normally done mechanically. The lucrarilor mentionate se va face de regula
manual method is used only for economical and mecanizat, metodele de lucru manuale fiind aplicate
organizational reasons. In case of mixed methods, numai acolo unde folosirea mijloacelor mecanice nu
the works manually executed shall be established by este justificata din punct de vedere tehnico-
the project, considering the special conditions of economic si de organizare. In cazul adoptarii unor
performance. metode mixte, volumele executate manual vor fi
stabilite prin proiect, tinind seama de conditiile
specifice ale executantului .
2. FIELD 2. DOMENIU
This procedure apply to the earthworks for the Procedura se aplica la executarea lucrarilor de
execution of: terasamente pentru fundarea:
Page 2
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
- Labor health and safety law 319/2006 and - Legea 319/2006 – legea sanatatii si securitatii
HG 300/2006 - Romanian Government, Decision no. ocupationale si
300/2006 – Minimum requirements regarding security HG 300/2006 – privind cerintele minime de
and health on temporary or mobile construction sites; securitate si sanatate pentru santierele temporare
sau mobile;
- Specification Civil Installations – Specificatii pentru lucrari civile
- HSEQM-01– Manual of quality, environment, - HSEQM-01- Manualul calitatii, mediului, sanatatii si
occupational health and safety securitatii ocupationale;
- ISO 9001 – Quality management systems . Basic - ISO 9001 - Sisteme de management al
rules and vocabulary ; calitatii.Principii fundamentale si vocabular;
- ISO 14001- Environment management systems. - ISO 14001 - sisteme de management de
Requirements and guide ; mediacerinte cu ghid de utilizare;
- OHSAS 18001- Occupational health and safety - OHSAS 18001 - sisteme de management al
management systems. Specification ; sanatatii si securitatii ocupationale.Specificatie;
- Law 10 – Law regarding the quality in constructions; - Legea 10 - Legea privind calitatea in constructii;
- HGR 273– Reception regulation of the construction - HGR 273- Regulament de receptie a lucrarilor de
works and their related installations . constructii si instalatii aferente acestora;
- HGR 766 – Regulation regarding the quality in - HGR 766 - Regulamente privind calitatea in
construction.; constructii;
- HGR 399 – Regulation regarding the elaboration of - HGR 399 - Regulament privind elaborarea
the technical requirements in construction for the reglementarilor tehnice in constructii pentm
quality system components. componentele sistemului calitatii;
- HGR 925 – Regulation of the quality technical - HGR 925 - Regulamentul de verificare si
examination and verification of projects , of works expertizare tehnica de calitate a proiectelor, a
carrying out and of constructions. executiei lucrarilor si a constructiilor;
- STAS 1243 – Foundation terrain. Land classification - STAS 1243 -Teren de fundare.Clasificare si
and identification.; identificareapamanturilor;
- STAS 1709-2 – The influence of the frost-thaw - STAS 1709-2 - Actiunea fenomenului de inghet-
process on the road works. Prevention and remedy of dezghet la lucrarile de drumuri.Prevenirea si
the damages caused by the frost-thaw process. remadierea degradarilor din inghet-dezghet
Technical requirements. Prescriptii tehnice;
- STAS 1913– Terrain for foundation. Determination - STAS 1913- Teren de fundare.Determinarea
of the compacting characteristics . PROCTOR test. caracteristicilor de compactare.Incercarea
PROCTOR;
- STAS 2914– Road works. Earthworks. Basic - STAS 2914- Lucrari de drumuri. Terasamente.
conditions of quality. Conditii generale de calitate;
- CD – 155 – Department technical instructions - CD -155 - Instructiuni tehice departamentale privind
regarding the determination of the technical determinarea starii tehnice a drumurilor modeme;
conditions of the roads.
- C29 – Standard for the improvement of the low - C29 - Normativ privind imbunatatirea terenurilor de
terrain for foundation, by mechanical procedures fundare slabe prin procdee mecanice (caietele I -
(books I-IV). IV);
- C 56 – Standard for quality verification and - C 56 - Normativ pentru verificarea calitatii si
reception of the construction works and related receptia lucrarilor de constructii si instalatii aferente;
installations.
- Instructions for work health and safety. - Instructiuni proprii de sanatate si securitatea muncii.
- General Occupational Health and Safety Plan; - Plan general de securitate si sanatate in munca;
- Environmental Management Plan. - Planul de management al mediului.
Page 3
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
5. ABBREVIATIONS
CF – team chief 5. PRESCURTARI
RSVTI – area manager for the installations CF - Conducator formatie
technical verification and RSVTI - Responsabil cu supravegherea si
HSEQM – Manual of quality, environment verificarea tehnica a instalatiilor
occupational health and safety HSEQM - Manualul calitatii, mediului, sanatatii si
PTE – Technical project of execution securitatii ocupationale
PO – Operational procedure PTE - Proiect tehnic de executie
PS – System procedure PO - Procedura operationala
AQ – Quality assurance PS - Procedura de sistem
CTC – Technical control of conformity AQ - Asigurarea calitatii
PV – Minute CTC - Controlul tehnic de conformitate
DC – Declaration of conformity PV - Proces verbal
CC – Quality certificate DC - Declaratie conformitate
PT– Project Team CC - Certificat de calitate
MP – Project manager PT- Proiect Team (Echipa de Proiect)
RNC – Corrective / preventive action report MP - Manager proiect
RNC - Raport de actiune corectiva/preventiva
6. CONTENT 6. CONTINUT
6.1. The preliminary works requested for the 6.1. Lucrarile pregatitoare ce se impun pentru
technological process commencement and inceperea si desfasurarea in bune conditiuni a
progress procesului tehnologic
The works to be executed before the earthworks Lucrarile ce se vor executa inainte de inceperea
commencement are mainly the land clearing works, lucrarilor de terasamente propriu-zise sunt in
demolition and land platform work preparation. principal cele de defrisare, demolari, amenajarea
terenului si a platformei de lucru.
The land clearing means the cutting of the trees and Defrisarea terenului consta in taierea arborilor si
bushes or, if possible, their uprootal, the removal of tufisurile sau, atunci cind este posibil, smulgerea lor
the wooden material from the land, of the leaves and din radacina, scoaterea butucilor si radacinilor
loppings, of the snow (if necessary), disposal of izolate, precum si indepartarea materialului lemnos
resulted material from the site in view of earthworks de pe suprafefele de teren pe care se vor executa
carrying out. terasamentele.
The holes remained after the uprootal, shall be filled Gropile ce ramin dupa scoaterea acestora vor fi
in with additional material and compacted. The nivelate si compactate. Suprafetele de teren ce
surfaces to be cleared will be established by the urmeaza a fi defrisate sunt stabilite prin proiect.
Page 4
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
project.
Before the commencement of the demolition works, Inainte de inceperea lucrarilor de demolari se vor
the underground water, gas, sewerage, electric examina retelele subterane ale instalatiei de apa,
installations shall be examined within the boundaries gaze, canalizare, electrice, etc. din zona
of the required area. constructiilor respective. Materialele rezultate vor fi
The materials resulted from the land clearing will be evacuate pentru a nu stinjeni lucrarile de
removed in order to not disturb the earthworks. terasamente.
The humus excavation shall be done mechanized. Excavarea stratului vegetal se va face mecanizat.
The humus obtained from the excavation, will be Pamantul vegetal rezultat dupa sapare va fi depozitat
stored outside the site area, in order to be returned to
in afara perimetrului construit in vederea redarii in
the agrarian circuit. circuitului agricol.
The drainage of the surface water to the site area will
Scurgerea apelor superficiale spre terenul pe care
be stopped by digging guard ditches in order to directse executa lucrarile de constructie va fi oprita prin
the water outside the work area. executarea de santuri de garda ce vor dirija aceste
ape in afara zonelor de lucru.
The guard ditches dimensions, the inclination and the Dimensiuniie santurilor de garda, pantele de
slope protection modality shall be made according to scurgere si modul de protejare a taluzurilor se vor
project requirements. executa conform proiectului.
6.3. The carrying out of the excavation and 6.3. Executarea sapaturilor si sprijinirilor
suspension works
At the carrying out of the foundations excavations, La executarea sapaturilor pentru fundatii trebuie sa
the project specification. se aiba in vedere cerintele proiectului.
The preparation of the fill materials for major Pregatirea umpluturii pentru cladiri importante
buildings
The bottom of the excavation for foundation must be Fundul sapaturii pentru fundatie trebuie sa fie
cleanly done. The excavation finishing will be done prelucrat ingrijit in vederea executarii fundatiei.
immediately, before the commencement of the Finisarea sapaturii trebuie facuta imediat inainte de
foundation body. inceperea executiei corpului de fundatie.
The preparation of the fill materials for minor Pregatirea umpluturii pentru cladiri cu importanta
buildings redusa
The bottom of the excavation for foundation must be Fundul sapaturii pentru fundatie trebuie sa fie
cleanly done. The excavation finishing will be done prelucrat ingrijit in vederea executarii fundatiei.
immediately, before the commencement of the Finisarea sapaturii trebuie facuta imediat inainte de
foundation body. inceperea executiei corpului de fundatie.
The preparation of the fill materials for roads Pregatirea umpluturii pentru drumuri
The bottom of the excavation for roads must be Fundul sapaturii pentru drumuri trebuie sa fie
cleanly done. The excavation finishing will be done prelucrat ingrijit in vederea executarii fundatiei.
immediately, before the commencement of the Finisarea sapaturii trebuie facuta imediat inainte de
foundation body. inceperea executiei corpului de fundatie.
The total thickness of all construction layers and the Grosimea totala a straturilor de umplutura inclusiv
frost protection layer has to have a minimum stratului antiinghet trebuie sa fie minim 0,50m la
thickness of 0.50 m at concrete paved roads and drumuri betonate si minim 0,60m la drumuri asfaltate.
0.60 m at asphalt paved roads.
Testing Verificari
Tests shall be carried out on the fill material and the Tipurile de verificari ale materialului si numarul
frequency of such tests shall be according to acestora este confom specificatiilor.
specifications.
Page 6
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
.
Tolerances Tolerante
The surface of filled areas shall be graded according Suprafete rezultate dupa compactare vor fi nivelate in
to the drawings, and no soft spots or uncompacted conformitate cu desenele, fara a se accepta zone
areas will be allowed in the work. necompactate, adancituri etc.
No grading shall be done when the material is too Nu se vor execut anivelari cand materialul este prea
wet, either from rain or from excess application of ud datorita ploilor sau excesului de apa.
water.
7. RESPONSIBILITIES 7. RESPONSABILITATI
Page 7
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
documentation PTE and PCCVI; - Efectueaza controale planificate conform PCCVI
- performs the scheduled control operations, si inopinate la lucrare.In cazul in care depisteaza o
according to PCCVI as well as those non – deficienta, are obligatia de a da dispozitii de
scheduled. In case of a deficiency, he will dispose the remediere imediata sau intreruperea lucrarii; in
repair, immediately, or the works suspension. The acest caz se descrie neconformitatea si se
deficiency will be recorded in the RNC file consemneaza actiune in RNC ;
- follows the training of the repair committee - Urmareste instruirea comisiei de remediere a
personnel and the deficiency solving within the period deficientelor si solutionarea acestora in termenul
stipulated by the RNC ; prevazut in RNC;
- follows the avoidance and the repetition of the non- - Urmareste evitarea si repetabilitatea situatiilor
conformities; neconforme ;
7.3. Technical responsible for the manufacturing 7.3. Responsabilul tehnic cu executia
process - Verifica si avizeaza PCCVI, sau dupa caz planul
- verifies and approves the PCCVI, or the works calitatii (daca clientul solicita prin contract) pentru
quality plan ( if requested by the contract ) lucrarile care urmeaza a fi executate;
- approves the works execution only on the basis of - Admite executia lucrarilor de constructii numai pe
the manufacturing project and details verified by baza proiectelor si a detaliilor de executie verificate
specialists authorized by MLPAT; de specialistii verificatori de proiecte atestati MLPAT;
- verifies and approves the technological projects and - Verifica si avizeaza fisele si proiectele tehnologice
sheets and the projects of the works organization in de executie. proiectele de organizare a executiei
view of fabrication; lucrarilor;
- elaborates and keeps to date a register file of the - Intocmeste si tine la zi un registru de evidenta a
construction works which is responsible for. lucrarilor de constructii pe care le coordoneaza tehnic
- suspend the works in case of major quality si de care raspunde;
deficiencies or deviations from the manufacturing - Opreste executia lucrarilor de constructii in cazul in
project; care s-au produs defecte grave de calitate sau
- proposes corrective actions for the works repair. abateri de la prevederile proiectului de executie ;
- Propune solutii/actiuni corective pentru remedierea
lucrarilor.
The health and safety rules including in this method Regulile de sanatate si securitate incluse in aceste
statements are complementary to General Health metodologii sunt complementare Planului General de
and Safety Plan, to the Construction Site Regulations Securitare si Sanatate in Munca, Regulamentului de
and to Romanian Sites Health and Safety Rules and Organizare si Functionare a Santierului si Regulilor
not replace this rules. de Sanatate si Securitate in Munca aplicabile
Santierelor din Romania si nu inlocuiesc aceste
For any changes in method statement the health and reguli.
safety rules will be re-examine in conformity with all In cazul aparitiilor unor schimbari in procedura de
laws and regulation officially in Romania. lucru regulile de sanatate si securitate vor fi revizuite
Page 8
Depots Revamp CON-IPR-BAC-CI-002-A
Method Statement for Earthworks
in conformitate cu legile si regulamentele oficiale in
Romania
1. Risks : 1. Riscuri:
- presence in the area of electrical cables, - prezenta cabluri electrice, risc de
electrocution risk, electrocutare, incendiu explozii;
- Breakdown - Surpare
- Uncontrolled movements of the machine cuts - Miscari necontrolate ale utilajelor, taieturi sau
or pricks provoked by manual tools intepaturi provocate de uneltele manuale
- presence in the area of pipes, explosion and - prezenta conducte, risc de expozie,
fire risk, incendiu;
- presence in the area of inflammable - prezenta material inflamabil (benzina,
materials, explosion and intoxication risk, motorina), risc de incendiu si explozie;
- presence in the area of explosion materials - prezenta material explozibil (CH4), risc de
(CH4), explosion and intoxication risk, explozie, intoxicatii;
- presence in the area of sharp objects, cutting - prezenta zone taioase si ascutite, risc de
and pricking risk, taiere sau intepare;
Page 10