Professional Documents
Culture Documents
WBS: 30-22117
1
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
INDEX
SN PAGE
1. PURPOSE 3
2. SCOPE OF WORK 3
3. DEFINITIONS 3
4. REFERENCE DOCUMENTS 3
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
1. PURPOSE
The purpose of this method of statement is to define the methods that will be
adopted during the erection/ installation of piping work and installation of
equipment’s for the construction activities of ENB Truck Loading Facility in order to
qualify and comply with all required standards.
2. SCOPE OF WORK
This document defines the working procedure, governing the storage, handling, and
Erection/ Installation of piping, Scaffold works, supports, Valves and Equipment
work at the ENB Truck Loading Facility.
In case of conflicts between this document and requirements of project specification
and code, the contractual documentation shall prevail.
3. DEFINITIONS
Project : ENB Truck Loading Facility
Contractor : Mansour Al Mosaid Co.
Client : Petro Rabigh
4. REFERENCE DOCUMENTS
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
5.3 Superintendent/Supervisor
The Superintended/Supervisor are responsible to implement the proper
working procedure and strict- adherence of the HSE policy related to Piping,
pipe support erection and House keeping the work explained herein.
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
5.4 Safety Officer
The Safety Officer shall review prior to the start of the work Safe Work Plan
and work permit, if required prior to submittal to the Contractor which
must be implemented and observed during the erection works.
The Safety Officer shall:
Provide appropriate Safety and Health, accident prevention and
investigation.
Implement all safety aspects.
Ensure work permit procedures are followed.
Ensure the safety inspection are conducted at field by safety officers
and site supervisors and participating in safety activities and report
to HSE manager for any violation.
Conduct Site HSE Inspections and maintain the records.
Prepare the analysis report for the daily Safety Inspection and
work permit audits.
Read and understand Petro Rabigh Safety Rules and Policies.
Implement the requirements at contractor worksites.
5.5 Site Engineer is responsible for the overall activities related to the piping
and support erection. Manpower under him will consist but not limited to
the following:
Mechanical/Piping Supervisor
Mechanical/Piping Foreman
Welding Foreman
Pipefitters/Fabricator
Mill Wright Technician for Pump and Arm Alignment.
Steelworker
Welders
Beveling Machine Operators
Riggers
Safety officers
QC Inspectors
Helpers
6.1 Equipment
Crane
Boom truck
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Air compressor set
6.1.2 Tools
Cold Cutting Machine
Chain Blocks
Scaffolding tubes, Clamps etc.
Guy Wires I nylon Slings
Nylon Rope I Shackle
Wrenches I Drift pin I Padding
Welding Machine
Mill Wright tools (Dial Gauge, Vernier, Inside/Outside Micro meter, Scale, Mirror, Filler
Gauge, Magnetic and alignment Stand, Spanners, Rubber Hammer, Grease, shim
Plates).
Survey Total Station for Mechanical equipment
Pencil Grinder
Chain puller
Rigging gears, Ladder, Hand tools, Power Tools
Wrenches
Magnetic/Spirit level
Torque wrench
Paint Brush
Fitter/Welder Tool box
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Monthly.
Prior to piping erection works, ensure scaffoldings are sufficiently
installed for access of workers during fit-up, and full welding/bolting
of pipe joints. Install lifelines as needed.
Prepare manpower, tools, equipment and other logistics for
installation.
Check the location for possible obstruction before erection.
Storage
All piping materials shall not be stored directly on the ground. Pipe
shall be placed on rock free mounds covered with polyethylene or
sleepers, at least 150 mm off the ground.
Fittings and valves shall be stored in shipping crates or on racks.
End protectors on pipes, flanges, weld bevels, threads, and socket ends
shall be firmly attached at all times without exception.
Adhesive for RTR piping shall be stored in an enclosure where
temperature do not exceed 38⁰C
All Equipment like Pump and Loading/Unloading ARM shall be handled with
care during Lifting (lift hooking in specified safe point), Assembly and
Installation to prevent damage.
Transportation
Ensure that all the equipment used in transporting and lifting shall be
PRC approved third party certified
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Ensure that all piping materials to be transported from warehouse/ lay
down area to the work area complies with the project specifications.
Site handling and identification of all piping materials and components
shall be in accordance with SAES-L-350, 0l-SAMSS-024.
Proper transport of piping materials shall be observed at all times with
the use of appropriate material-handling equipment.
Check and verify for any damage, and if end cover is in place before
transporting to the work area. Pipe materials of doubtful condition or
quality shall be immediately segregated from the job site, an NCR
raised and the material shall not be used.
During transportation, spools shall be adequately secured with soft
lines to prevent damage. Where practicable, end cap I protectors shall
be installed to prevent ingress of any foreign objects and damage to
weld preps. Flange covers shall be left in position on valves and spools
until the time of installation. Over hanging from the trailer / truck
body of any piping materials are not allowed.
Pipe Spools/Equipment to be transported from lay-down to erection
area shall be properly secured and safely shackled/ secured to the
trailer platform.
Adhesive containers shall be protected from direct sunlight.
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
“Requirements for Scaffolding PR/IS/SFD/P-011”
All scaffolding erection should comply with PR/IS/SFD/P-011,
scaffolding supervisor, inspector and erection must be competent and
have a valid PRC 3rd party certification or approval.
When working on platforms over 6ft. in height where full decking or
guardrails cannot be provided, workers are required to wear full body
harness equipped with shock absorbing, lanyards attached ABOVE
WAIST to safety line or anchor point rated by manufacture at 2450 kg.
(5400 lbs.). Exposed roof or beam erection work when using a
nonstandard scaffold above 6 ft, only approved full harness with shock
absorbing lanyard attached to a rated safety line/anchor point will be
use.
All scaffold will be tag with appropriate Petro Rabigh tagging system,
i.e., Red Tag – not inspected or not safe to use.
Green Tag: complete, inspected and safe for use (freestanding scaffold
inspection good for 2 weeks – rolling scaffold cannot be “Green Tag”).
Yellow Tag – inspected, can be used only by workers wearing properly
anchored personal fall arrest system including a full body harness and
lanyard (Yellow Tag is required on rolling scaffold as it must be re-
inspected each time the units is moved).
All Scaffolding Shall be erect under the supervision of a qualified
Scaffolding Supervisor.
Scaffolding Taller than 6 meters both Supervisor and Inspector should
inspect.
Special Scaffolds and scaffolds over 12.2 m tall shall only be designed,
erected, altered, inspected, and dismantled by a Specialized Scaffold
Erector (organization).
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
PRC approved third party certified
Assess and Check whether the grade or ground where the crane is
positioned has been stabilized and ensure that working area was
compacted and stable for the crane during lifting.
Make ready all lifting accessories which are required for lifting
process.
Only certified crane operators, and riggers will be involved in all lifting
activities.
Relative positioning of crane and trailer and all the lifting/erection
operation of above ground piping's shall be under the control and
supervision of certified rigger, assisted by additional certified riggers,
to control the crane movement during the upending operation.
All operations will be controlled using either hand held radio or visible
hand signals.
Provide warning sign and sufficient barricade on working area and
only assigned personnel will be allowed in the said area.
During assembly and erection, ensure that no foreign materials (such
as welding consumables, lumbers, gloves, etc.) are left inside the piping
system.
Pipe spools such as expansion loops, branch take-offs, others will be
placed directly in position using cranes and/or chain blocks where
required. Fit up and welding of spooled pieces will be done in place
utilizing the extended cantilever floor type scaffold or localized
scaffold.
For pipelines without attachments; a double-ended welding execution
will be adopted- i.e. the first two random length rigged to position will
be fitted up and full welded together. The succeeding lengths will be
installed in the same manner. The double-ended lengths are then
welded together until the entire run is completed.
Prior to closure of piping sections, full compliance with cleanliness
inspection and documentation shall be insured.
Position of piping spool will be done through Northing and easting
coordination reference points. Elevation and slope requirement shall
be followed.
Temporary supports maybe provided in lieu of permanent supports
during erection phase.
Ensure to install pipe supports, guides in accordance with the latest
IFC isometrics & support drawings
Welding ground cables shall be attached adjacent to the place where
the weld is being made. The welding clamps shall be clamped onto the
pipe near the weld and the welding machine properly grounded.
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Spring-type alligator clamps shall not be used. Ground leads shall not
be attached to any part of the machinery or their skid auxiliary
systems, or supports for any reason.
Fit-up spools using appropriate pipe clamps, check the gaps us gap
gauge. Check for squareness and levelness using appropriate level and
steel square. Check plumpness (vertical pipes) using plumb bob. Tack-
weld directly on the bevel of pipes after checking. Tack welding shall
be done on four quadrants.
Prior to full welding of pipes, QC inspector shall conduct inspection to
document work compliance. Following are items to be verified:
o Bevel angle, root opening, and tack weld shall be in accordance with
the approved Welding Procedure Specification and ASME B31.3 Sec.
328.4.2 & 328.4.3.
o All surfaces to be welded shall be clean and free from paint, oil, dirt,
scale and foreign material detrimental welding as specified in A
SME B31 .3 Sec. 328.4.1.
o Defects such as cracks, inadequate penetration of temporary weld
and/or tack welds shall be removed.
o The welding consumables to be used are in accordance with
approved WPS.
o Qualified welders following approved WPS which are qualified
accordance with ASME Code Sec. IX shall do full welding of joints.
During the welding process, in-process inspection will be verifying the
following items;
During and after welding is completed, visual inspection shall be done
to check the following items as applicable:
o The root passes in accordance with ASME B31.3 Table 341.3.2. Arc
strikes in areas not covered by the finished weld shall be cleared.
and PT or MT examined to ensure that the material surface is not
cracked. Temporary materials used are already removed.
o Check for surface porosities, under bead, undercut, etc. Internal
flushing of orifice flange was done. Cleanliness of pipe shall be
maintained. The weld spatter, slag, flux and other foreign materials
are removed.
o The weld no. and line no. shall be marked with metal marker on the
pipe adjacent to the weld. The completed weld will be subjected to
the required NDE. Document inspections in accordance with
approved ITP.
At the end of each work shift, the open ends of the installed pipe shall
be secured/ covered using frame supported polyethylene I tarpaulin
sheets or pipe caps to prevent ingress of any foreign objects or living
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
organism.
The same methodology shall be applied for the erection/ installation of
the next succeeding pipe spool to the lower level until the last pipe
spool is fully installed to complete the piping systems.
Ensure that line is blinded as per the marked P&ID by PRC operation
for the Tie-in activity.
Ensure that the line is purged and gas detection is done before cold
cutting.
Ensure that there is no any gas is coming from the line before welding.
If required use mechanical plugs.
PIPING RTR
Excavate trenches to ensure that sides will be stable under all
working conditions. Slope trench walls or provide supports in
conformance with safety standards.
The trench width must be maintained within certain limits. A very
wide trench will increase the volume of backfilling material
required and compaction labor and effort. The minimum trench
width(W) at the bottom of the trench for a single pipe shall be:
W=1.25XOD+300mm Note: - Project specific AWWA-M45
calculation shall be referred for each project.
Manual lowering of small diameter pipes into the trench can be
executed by at least two men. It is recommended that the weight
carried by one man do not exceed 20 kg. Pipes weighing up to 120
kg can be lowered by means of two ropes. The ropes must be
anchored to stakes.
Mechanical Crane lowering is used for larger diameter pipes,
especially when combined with pipe assembly in the trench.
Road crossings require special attention and requirements.
Precautions shall be taken to protect the pipes, which cross
underneath roads against the possible consequences of traffic
loads. The influence of the wheel load of traffic passing a buried
pipe reduces with increased burial depth.
Minimum cover depth can be reduced with special installation
such as:
Sleeve pipe.
Concrete Protection Slabs.
Concrete encasement of the pipe
The Geotextile Filter Fabric shall consist of thermal bonded/needle
punched synthetic polymer fibers. Composed of at least 85 percent
by mass polyolefins, polyesters, polypropylene, polyethylene or
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
polyamides. They shall be formed into a network such that the
filaments or yarns retain dimensional stability relative to each other,
including selvages.
Geotextile filter fabric shall be lined at the bottom, sides and top of the
pipe embedment zone. This can be same as a gift-wrapping method
along with the backfill material.
Sequence of Geotextile application.
1. Placing the geotextile to line the trench bottom and sides.
2. Bedding and Pipe laying on the geotextile.
3. Backfilling with appropriate backfill materials.
4. Covering the embedment zone with geotextile.
Permanent sheeting can be used to distribute the pipe’s lateral loads
appropriately. The sheeting should be at least 300 mm higher than
the pipe crown level and driven below the foundation level. The
sheeting system is to be designed by a specialist and the material to
be of quality to last the lifetime of the pipe.
Glass Reinforced Plastic pipes are generally joined using Double Bell
Couplings in buried installation. Other jointing system such as
flanges (inside chambers), adhesive bonded joints, mechanical
couplings, Rubber seal lock joints, REKA Seal Lock Joints and
lamination joints may also be used for joining the Glass Reinforced
Plastic pipes.
A prepared surface is a surface on the inside of a bell or on the outside
of a pipe end that has been abraded manually or mechanically. By the
abrasion process, the reinforcement of the composite may come in
direct contact with the environment and is therefore sensitive for
contamination.
Drying of wet surfaces is performed using a clean, dry and non-fluffy
cloth and is followed by heating of the bonding areas.
The temperature of the bonding surfaces of spigot and bell during the
bonding procedure should be kept between 15 0C and 40 0C, but
also at least 3 0C above dew the point.
A machined, prepared or sanded bonding surface that has been in
contact with oil or grease shall not be used and must be cut.
Machined, prepared or sanded bonding surfaces that are contaminated
by other means than oil or grease can be cleaned by sanding.
Bonding surfaces must be sanded equally in a circumferential
direction. The bonding surface must stay smooth by applying even
pressure on the sanding equipment.
Break sharp edges of the tip of the machined spigot end. The bonding
surface is cleaned using a dry and clean dust bristle.
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Ensure that the pipe is adequately supported or clamped on a pipe
vice. Use rubber padding having a minimum thickness of 2 mm to
protect the pipe from damage.
Determine the required length from the product drawing or by
measurement. Scribe the pipe at the required length, using a
pipefitters’ wrap-around the minimum cut length shall be as per the
product drawing.
Cut the pipe square using a diamond or carbide coated hacksaw or an
abrasive wheel.
Various types of shavers are available. To operate the shaver, carefully
follow the applicable shaver instructions.
The pipe end to be shaved shall be clean.
Start the shaving procedure using a maximum shaving feed of 2 mm.
Be careful shaving the first layer as the pipe wall might have an
unequal thickness over the circumference.
Repeat the shaving action until the required spigot dimension as per
the product drawing is achieved. Measurement of the nose thickness
(T) at several spots (3 – 6) in the circumference of the head of the
spigot with a Vernier calliper can be used to obtain an indication of
having achieved the required spigot diameter (S1).
Use an unprepared (dummy) bell to check the correctness of the
shaved spigot end dimensions by determining the actual insert depth
of the spigot in the bell. Mark the actual insert depth of the spigot in
the (dummy) bell on the section containing the spigot end.
The spigot diameter (S1) is checked by comparing the actual insert
depth with the allowable values of the insert depth.
The actual insert depth shall comply with the following requirement:
The actual insert depth shall be: - Equal to or smaller than the
maximum insert depth, but also - Equal to or greater than the
minimum insert depth. (Minimum insert depth <= Actual insert
depth <= Maximum insert depth).
The eccentricity of the shaved spigot diameter (S1) relative to the
inner diameter (ID) is determined from a number (>= 6) of
measurements of the nose thickness (T) in the circumference of the
spigot diameter (S1).
The maximum number of sanding operations for each of the bonding
surfaces, either the bell or the spigot, is two. In case a bonding
surface is subjected to more than two sanding operations the
dimensions shall be checked by determination of the insert depth of
the spigot in the bell to be bonded.
In this situation, the check of the insert depth shall be performed with
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
the actual bell of the joint to be made, instead of using a dummy bell
end
The actual bonding starts with the preparation of the adhesive and
finishes when the adhesive between the jointed parts is cooled down
to ambient temperature, after completion of the curing of the
adhesive.
Use a fresh spatula or adhesive scraper for the application of adhesive
on the freshly prepared bonding surfaces. In case the spatula used
for mixing is also used for the application of the adhesive, the spatula
must be cleaned firs
Wet the sanded surfaces of bell and spigot end with some force with a
thin, uniform coating of adhesive.
Apply a thin (≈ 0.5 mm) and uniform layer of adhesive on the adhesive-
coated bonding surface of the spigot end.
Make sure to apply an adhesive layer on the cut end of the spigot and
to apply enough adhesive on the cylindrical end of the spigot that
will be covered by the bell
Protect the adhesive coatings on the bonding surfaces and prevent any
contamination.
Parts to be jointed shall be aligned as true as possible.
Insert the spigot into the bell and pay attention to the alignment mark
on the outer surface in line to the orientation of the parts to be
jointed.
Hook the winches, apply an equal load on each winch and pull the
sections to be bonded in a smooth movement together until the
spigot does not enter any more into the bell; respect the marking on
the outer surface. Make sure that the spigot is inserted centrally into
the bell until the joint is firmly fixed together.
The curing time starts when the required surface temperature of the
jointed components is reached. Write the starting time of the curing
on the pipe, next to the heating blanket . Curing time is 60 minutes @
125°C (See Note-5) after the heating up the curing surface. Table
9.4.f provides a guideline for the heating up .
CLIENT
RABIGH REFINING AND PETROCHEMICAL COMPANY
– PETRO RABIGH
WBS No. 30-22117
PROJECT
ENB TRUCK LOADING FACILITY
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Installation of Valves
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
carried out in accordance with SAEP-351. Bolts should extend
completely through their nuts, i.e. full thread engagement, flush with
nut.
Gaskets shall be suitable for the intended service and compatible with
IFC last Rev. ISO and with a flange rating and bolting. Not more than
one gasket shall be used between mating surfaces.
Flanges shall be arranged in such a manner that the bolt holes equally
straddle the main axes. Flanged joints shall be aligned with their axis
center and the flange faces matching the gasket as accurately as
possible, as per SAES- L-350 Para 9.
Hydrotest of pipeline:
Ensure that the line is ready for the hydrotest as per the limits of the
hydrotest to be done.
Ensure that blinds used for hydrotest are calculated as per the
hydrotest pressure.
Ensure that the water used for hydrotest should be portable and the
testing of water is done.
Ensure that Manifold and PZV used is as per the hydrotest pressure.
Ensure that there is no any check valve installed during the hydrotest.
Hydrotest pressure should be increased in 25% of test pressure and
after each 25% of increase of pressure hold for 5mintues.
Once the hydrotest pressure is reached hold for 30 minutes and check
whole piping for any leakage and inspection is done by QC.
After the inspection is done release the pressure from the high vent
point.
After the release of hydrotest pressure drain the line to the nearest
drain point as confirmed by operation or use the PVC tank.
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
10. PUMP AND EQUIPMENTS INSTALLATION AND ASSEMBLY
PUMP INSTALLATION & ALLIGNMENT
Ensure the foundation survey level and elevation, followed by initial
marking.
Perform chipping at uneven surface and packer plate to ensure the
equipment is not misaligned.
Installation and erection of Pumps and motor by lifting crane , followed
by Master Level alignment using shim plate.
Drilling or Core cutting on the marked foundation where the bolting
has to be done and after cleaning fixing the Pumps/Equipment’s with
Anchor bolts (Chemical)
Pre-alignment of the Pumps and Equipment’s followed by Grouting.
Solo run by applying rated voltage and/or frequency to the motor with
“no load” coupled to the shaft.
Final alignments -Pump connections with Pipe along bolt torqueing ,
Install coupling Shaft and commissioning.
All stages of work shall be inspected and documented in accordance with the
Approved Project Quality Procedure, which contains the corresponding ITP.
DESCRIPTION
Revision 0
METHOD STATEMENT FOR
No.
ERECTION / INSTALLATION OF PIPING (AG& RTR) AND
EQUIPMENT
Job safety plan and work permit shall be implemented
Proper access shall be provided.
Proper PPE shall be applied and must be used
Waste bin shall be available at the job site to maintain cleanliness at the
working area.
"Work in Progress" Safety Signboard shall be placed around working area to
warn the personnel.
To avoid any fall injury from higher elevation proper hook-up of safety
harness is required.
Safety officer will ensure that all construction activity is being performed in
compliance with project safety norms.