Professional Documents
Culture Documents
Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 31-Dec-14 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements (Complete SATR-A-2007, listed as Attachment 5 & use SATR-A-2011 & SATR-A-6133)
Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 31-Dec-14 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
B SAIC-A-2010 Checklist (Reinstatement Procedure & Checklist item required when bold.)
All joints including welded shall be left exposed for visual leak detection
during the strength test. External coating and priming of such joints are SAES-L-150,
B1 not allowed unless approved by the Manager of Inspection Department Para. 7.3
and the proponent Organization representative. The pipe itself can be
externally primed and coated to a final coat.
The assembly of bolted flange joints shall be in accordance with SAEP- SAES-L-450,
B2
351. Para. 9.4
Vents and drain valves, both temporary and permanent, conforms with SAES-L-105,
B4
the piping class or rating. ( Refer SAES-L-108) Para. 5.9
SAES-W-011,
Temporary welded attachments to the pipe were ground off and
B8 Para. 11.7 and
inspected by magnetic particle or liquid penetrant method
11.9
All threaded joints and faying surfaces shall be seal welded by a SAES-W-011,
B9
continuous fillet weld (required weep holes shall be left unwelded). Para. 11.15.1
No one shall approach the test area for a minimum of 10 minutes after
the test pressure is reached and before commencement of inspection of
the system, the isolation valve between the temporary test SAES-A-004,
B12
manifold/piping and the piping/equipment under pressure test shall be Para. 9.1.2
closed and the test pump disconnected. The isolation valve downstream
of the manifold shall be opened after the pump is disconnected.
Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 31-Dec-14 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
During the application of the test pressure, all in-line valves if not used SAES-A-004,
B13
as test isolation valves shall be in a partially open position. Para. 9.1.3
Vents shall be provided at all high points in the tested system as SAES-A-004,
B14
needed. Para 8.4.1
Unless the check valve has a by-pass valve, the disc of the check valve
SAES-A-004,
B16 shall be removed, and securely attached to the outside of the check
Para 8.4.3
valve prior to the pressure test.
Soft seated valves and control valves shall not be installed until after the SAES-A-004,
B19
lines have been thoroughly flushed. Para. 8.1.3
Buried pipeline are adequately bermed or covered to anchor the line SAES-L-450
B21
during pressure test. Appendix C
All gauges and recorders shall be calibrated prior to use. The calibration
interval shall not exceed one (1) month prior to the test date and SAES-A-004,
B22 calibration certificates shall be made available to Inspection personnel Para. 8.1.5.1 and
prior to commencement of the pressure test. Stickers shall be applied 8.1.5.2
indicating the latest calibration date.
All gauges shall have a range such that the test pressure is within 30 to SAES-A-004,
B23
80% of the full range. Para. 8.1.5.3
A minimum of two pressure gauges are required for the test system.
SAES-A-004,
B24 One pressure gage shall be on the test manifold and the other(s) on the
Para. 8.1.5.4
test system. Their accuracy shall be within 5% of one another.
When large systems are tested, Inspection personnel will determine the SAES-A-004,
B25
need for additional gauges. Para. 8.1.5.5
Pressure and temperature recording gauges shall be used for all buried SAES-A-004,
B26
piping systems on plot and per SAES-L-150 for pipelines. Para. 8.1.5.6
Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 31-Dec-14 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Blind flanges, Paddle or spectacle blinds shall be used to isolate test SAES-A-004,
B27
sections. Para. 8.3
A bleed valve readily accessible is provided in case immediate SAES-A-004,
B28
depressurization is required. Para. 5.5.2
Test Vents and Drains-Vents and drains used only for the pressure test SAES-A-004,
B31
shall be plugged, seal welded and penetrant tested. Para. 10.3
REMARKS:
REFERENCE DOCUMENTS:
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION TEST SYSTEM No./Test Pack No. PLANT NO.
DRAWING NUMBER (P&ID/ISO) / REV. No. PRESSURE TEST DIAGRAM NATURE OF TEST WORK PERMIT REQD?
SAUDI ARAMCO TIP (SATIP) NUMBER SATIP Activity No. SUPPORTING SAIC Number SAIC QR No.
1) This Form shall be used in conjunction with applicable Pre-Pressure Test Checklist. Refer to applicable SATIPs & See Attachment 1
2) "A" items are items required to be completed before pressure test can proceed.
3) "B" items are post-test items to be cleared immediately after pressure test (within 24 hours) with Inspection witness per procedure.
4) "B" items are completed during re-instatement per an approved Procedure before final inspection by Company (per procedure).
Note: "B" items not complete during re-instatement (by approved procedure) shall be transferred to "zFEIL Form 6133" (Attachment 2)
5) See SATR-A-2011 for Re-instatement Checklist Form.
6) ETC = Expected Time of Completion or Expected Start-up Date if ETC date is unknown (affects lay-up considerations)
I
E
Description Reference
B nator (Note 6)
complete by
PID Insp
QC A
1M Seal weld threaded nipples from headers to root valves at (5) locations (hydrocarbon SAES-L-109, RLC
service) per SAES-L-109, Section 8. A ABC/QC 1/1/2007 DEF-1/1/07
Section 8 1/1/07
2 Guides are in direct contact with piping horizontal run at 3 locations (6mm gap req'd).
SAES-L-109, RLC
Relocate guides per drawing. These are welded to the pressure boundary. A ABC/QC 1/1/2007 DEF-1/1/07
Section 8 1/1/07
3 Check valve upstream clearance is not five (5) pipe diameters (40" req'd, 20" actual),
in violation of SAES-L-108. SAES-L-108, RLC
A ABC/QC 1/1/2007 DEF-1/1/07
Section 5 1/1/07
4 Check valve is oriented in the wrong direction (flow arrow). Reverse check valve to
assure correct flow direction. Reposition valve & restore internals immediately after SAES-L-108, RLC
test, COMPANY to witness. B ABC/QC 1/4/2007 DEF-1/4/07
Section 6 1/4/07
5 Piping clearance to structural bracing is 15 mm in violation of SAES-L-310, Sect 12. SAES-L-110, RLC
(50 mm spacing req'd). Engineering! A ABC/QC 1/1/2007 DEF-1/1/07
Section 5 1/1/07
6 Install permanent gaskets at flange sets 1, 4, 5, 6 on ISO dwgs per approved torque
SAEP-351, Start-up date =
tables and install spectacle blinds oriented as per approved P&ID. B ABC/QC
Proj Dwgs 5/1/2007
7 Completely remove all water and debris from low point/valve cavity for the (3) in-line
Valves (8" - 300 #) with SS 400 trim, do so immediately after test. Clean with dry
SAES-A-007, RLC
compressed air and relubricate sealing surfaces with approved lubricant in B ABC/QC 1/4/2007 DEF-1/4/07
Para 6.2 1/4/07
preparation for "ambient" lay-up specified in test package.
2 All test vents & drains plugged and seal welded ditto
3 Lines drained and lay-up per customer approved specification ditto
4 Valves (400 SS Trim) tested in-line removed, cleaned, & lubricated for Amb lay-up ditto
5 Jacking screws, process blinds (spectacles, spades, etc) correctly installed ditto
6 Spring Hangers & components (bellows, etc) adjusted per mfg instructions. ditto
7 Weepholes plugged with heavy grease (reinforcement pad air test complete) ditto
8 Chain wheel operators installed ditto
9 All instruments, control valves & check valves reinstalled in correct flow position ditto
10 Restriction orifice/flow elements installed ditto
11 Relief Valves are Pop tested/calibrated, tagged and SAP approved/installed ditto
12 All Temporary Test Components (spools, test blinds, gaskets etc) are removed ditto
13 Correct bolts/gaskets are installed and torqued per SAEP-351 requirements ditto
14 Check Valves and internals reinstalled (Internal Cleanliness & gasket check) ditto
15 All Start-up items installed (strainers, filters, other items restricted from test) ditto
16 Chemical Cleaning completed and documented
17 Final Line Check complete & meets all special process specs. See Spec Check.