Professional Documents
Culture Documents
Table of Contents
1. Scope ................................................................................................................................................... 1
2. Codes and Standards ........................................................................................................................... 1
3. Safety Factors ...................................................................................................................................... 2
4. Site Development ................................................................................................................................. 2
5. Site Preparation and Earthwork ........................................................................................................... 3
6. Station Roadways and Parking Areas .................................................................................................. 3
7. Area Surfacing ...................................................................................................................................... 3
8. Fencing ................................................................................................................................................. 4
9. Sewers and Drainage Systems ............................................................................................................ 4
10. Potable Water Systems ........................................................................................................................ 6
11. Specification for Geotechnical Investigations ....................................................................................... 6
12. Specification for Topographic Surveys ................................................................................................. 7
13. Structural Design Requirements .......................................................................................................... 7
14. Reinforced Concrete, Foundations, and Structures Design Requirements ......................................... 7
15. Pipe Support Design........................................................................................................................... 15
16. Platforms, Stairs, Handrails, and Ladders .......................................................................................... 19
17. Prefabricated Steel Buildings ............................................................................................................. 20
18. Cranes and Hoists .............................................................................................................................. 23
19. Signage Requirements ....................................................................................................................... 23
1. Scope
This standard defines the Company requirements for design and installation of Civil and Structural
components of Company facilities.
3. Safety Factors
For load combinations considering wind, earthquake, and piping thermal loads, the minimum factor of
safety against overturning shall be 1.5. The minimum safety factor against sliding shall be 1.5. A
minimum safety factor of 1.5 shall be provided against buoyancy for substructures. Safety factors for
other load combinations shall be in conformance with the applicable code.
4. Site Development
4.1. General
The Project Manager shall consider all requirements of equipment, location, environment,
potential expansion, topography, and applicable codes in determining the projected capacity,
layout, design, and physical requirements of the location. Pre-selection of the site shall be
based upon pipeline modeling. Final selection of the site shall be performed by the Project
Manager.
4.1.1. Site Selection and Layout
In determining site selection, the Project Manager shall consider:
• Permanent Easements (e.g. Landowner Restrictions)
• Populated Areas
• Air Quality Non-Attainment Areas
• Temporary Work Spaces, Turnarounds (e.g. Construction)
• Extra Temporary Work Space (e.g. Crossings)
• Pipeyards / Material Marshalling Points
• Rig-up Space
• Mainline Valves
• Pig Launchers / Receivers
• Potential Customers
• Anticipated / Future Classification Changes
• Geotechnical Obstacles (e.g. karst topography, fault lines, bogs, rivers, rough/
impassable terrain)
• Floodplains
• Saturated Soils (e.g. negative buoyancy)
• Utility Corridors (HVAC - High voltage overhead / below grade, power lines)
• Archeological Sites
• Roadways and Railroads
• Soil Conservation requirements
• Minimizing the footprint/scale of above grade facilities
• Minimizing cleared rights-of-way through wooded areas, hilltops, and other
publicly-visible high points
• Agency regulations requiring above grade facility exteriors to be harmonious with
immediate surroundings and/or other buildings in the area.
• Locating noise-intensive above grade facilities at appropriate distances from
noise-sensitive areas
• Avoiding locations/landmarks listed on, or eligible for listing on: the National
Register of Historic Places, the National Register of Natural Landmarks, officially
designated Wild and Scenic Rivers, officially designated parks, wetlands, scenic,
recreational, and/or threatened/endangered/wildlife lands.
4.1.2. Spacing and Clearances
4.1.2.1. Spacing for buildings on Company locations shall be determined in
conformance with Standard Drawings STD-V-1200-B005.1 – Structure
Location Matrix Lighter-Than-Air Table and STD-V-1200-B005.2 –
Structure Location Matrix Heavier-Than-Air Table.
7. Area Surfacing
The Project Manager shall establish which of the following surfaces shall be used for station
roadways and parking areas and the design requirements for the selection within the Scope of Work.
• Gravel and Chat
8. Fencing
8.1. General: Fencing is required for all above grade facilities that are not within the confines of an
existing fence.
8.2. Fences shall be constructed in conformance with the requirements laid out in Typical Drawings,
and specific to the individual requirements of each project. These requirements shall be
defined in the Scope of Work. Deviations from the Scope of Work requirements shall be
reviewed and approved by the Project Manager.
8.3. Drawings: Fence requirements are specified in Company Drawing TYP-V-1200-B045 - Typical
Cyclone Fence Elevations + Details.
8.4. Numbers of gates and gate locations shall conform to the requirements of 49CFR 192. The
design, construction, type of opener, and method of opening shall be designed to meet location-
specific requirements on a project specific basis and be specified in the Scope of Work.
8.5. Materials requirements are specific to each project. Materials shall conform to the requirements
specified in Company Drawing STD-V-1200-B015_Cyclone Fence Details.
9.2.2.4. Sumps and sump pumps shall be provided in basements or pits as required.
Drains, if used, shall be installed at or below the elevation of the area to be
protected.
9.2.2.5. Systems shall be designed and constructed for storm water (including water
management), sanitary water, and process water sewers as required.
9.2.2.6. Designs shall provide separation between storm and process water to ensure
that the minimum quantity of process water is produced.
9.2.2.7. Erosion control of disturbed areas shall be provided during and after
construction.
9.2.2.8. Drainage design for vegetated areas shall include shaping and directing flow
to natural drainage channels.
9.2.2.9. Contour grading shall be limited in order to augment natural drainage
whenever possible.
9.2.2.10. Natural drainage patterns shall be maintained at property lines.
9.2.2.11. Culverts and other storm sewer piping shall be installed only where necessary
to maintain surface access across drainage areas.
9.2.2.12. Snowmelt and rainwater shall be routed to natural drainage using piping or
open ditches.
9.2.2.13. Culverts shall be provided to carry snowmelt and rain water under roads,
walkways, etc.
9.2.3. All water piping within gas compressor stations shall be constructed in conformance
with local building codes.
9.2.4. Raw water piping (between water well and treating plant) and domestic-treated water
piping shall be:
• Threaded and coupled galvanized pipe above grade
• Schedule 80 PVC pipe below grade.
9.2.5. Piping other than that used in domestic services shall be steel or shall meet
equipment Manufacturer’s specifications.
9.2.6. Domestic service piping shall comply with UPC regulations.
9.3. Process Water Drainage
9.3.1. All buildings shall have provisions to remove process water from basements, bottle
and pipe trenches, and pits.
9.3.2. The drainage system shall be routed to a localized point where the contaminated
water is collected and emptied by gravity or pump.
9.3.3. The contaminated water shall be routed to a disposal service or treated in
conformance with the discharge permit for the facility.
9.3.4. All lines shall be equipped with clean-outs, located at the beginning of the line and at
any change in direction of the line (unless a seal box is provided).
9.3.5. Industrial waste, hydrocarbon liquids, floor drains, and sanitary sewage shall not be
discharged off company property unless subjected to purification processing (prior
to disposal) in conformance with the discharge permit for the facility.
9.4. Sanitary Drainage System
9.4.1. All gray and black water produced in the station shall be treated as required by local
code.
9.4.2. Sanitary sewer lines shall be constructed of heavyweight PVC tubing/pipe. Minimum
size and slope shall be as required by local code and constructed in conformance
with local UPC code.
9.4.3. Self-contained septic systems shall be designed to meet local code and have a
minimum capacity as directed by the Project Manager.
9.4.4. Depth of cover shall be based on the frost line and shall be at a minimum of 2 feet.
9.4.5. Industrial waste and hydrocarbon liquid lines and sumps shall not be connected to
floor drains, storm and sanitary sewer lines, or septic systems.
14.7. Grout
14.7.1. See construction standard Construction Standard C1220 - Grouting for grout
specifications.
14.7.2. Inside buildings that are not subject to freezing and thawing, sand cement grout may
be used for equipment and supports not specified as requiring grout.
14.7.3. The following criteria shall be considered in grouting system selection:
• Vibration Analysis
• Foundation Size
• Foundation Reinforcement
• Centers of Mass
• Foundation Support
14.8. Design loads, definitions, and load combinations shall conform to the building code (most
recent edition) adopted by local jurisdictional agencies (for facility location). In any case,
when the referenced building code is unknown, ASCE 7 - Minimum Design Loads for
Buildings and Other Structures, or IBC Code shall be used. Any deviations from these
standards shall require review and approval by the Project Manager.
14.9. Individual footings shall be installed/extended deeply enough to avoid undercutting by
adjacent pipe trenching. Where footings are within a fill area, a lean concrete mix shall be
used to bring bottom of footing to grade, or piers shall be extended as necessary. All footings
and foundations are to be carried to firm bearing below the frost line. Except where local
building code requires a greater depth, the minimum depth shall be as tabulated in the
following table:
Depth* Amarillo Gulf Coast Storage Western Area
1' - 6" South of 111 305 & South 388
2' - 0" 111 to 103, 306, 307 & 308 184
2' - 6" 193 to 104, 309 - 310 203 N. TX, NM
3' - 0" 194 to 195, 311 206 OK.
3' - 6" 106 & North North of 311 201 & 205 KS, CO., So. NE
4' - 0" 204 601, 602, 603
5' - 0" 730, ND & SD,
No. NE., WY, MT
*Depth shown is below finished grade.
Table E1200 / 14.9 Footing Depth
14.10. All foundations shall be designed for installation on undisturbed soil or structural fill (if dictated
by site conditions). Structural fill for foundations shall be placed at minimum density of 95%
ASTM D698, or a higher value as recommended by soil consultant, verified by a testing
laboratory (during construction). Foundations shall rest on uniform soil strata to avoid
differential settlement, i.e., a unit foundation cannot rest on rock on one end and natural soil
on the other end even though both provide adequate support. Support soil shall be modified,
if necessary, to provide a uniform bearing strength.
14.11. A minimum of 6-inch clearance between pressurized below grade pipe and foundations shall
be maintained.
14.12. Design Requirements for Foundations
14.12.1. Compressor and Drive Foundations
14.12.1.1. Foundations (mat and block) for rotating machinery (including reciprocating
and centrifugal compressors and pumps, turbines, IC (internal combustion)
engines, and motors) shall be designed to account for all static and dynamic
(unbalanced) forces resulting from the operation of the equipment.
*This grating is best when used for pedestrian traffic and for very light rubber
pneumatic tired carts, dollies and hand trucks. For heavier rolling loads, use
heavy-duty steel grating.
**Contact grating manufacturers for their product recommendations and design
service substantiating their recommendations for heavy wheeled vehicle
applications
1
Load distributed evenly over the area of the grating section, pounds/square foot
2
Load concentrated over the grating width, pounds/foot of grating width.
3
The weight of a square foot of grating material, pounds per square foot.
14.12.4.3. Floating concrete floor slabs may be used in service/auxiliary and meter
buildings, garages, warehouses, weld shops, offices, and other
miscellaneous structures. Minimum slab thickness shall be 6-inches of
reinforced concrete with welded wire fabric 6 x 6 - W2.0 x W2.0. Heavy
14.14.1.21. Where possible, concrete floor and curb walls shall be designed and
constructed as a monolithic pour. If not possible, the curb-to-floor joint
shall be a minimum of 2-inches above the top of floor elevation.
14.14.1.22. Concrete sealant shall be selected based upon sealant Manufacturer’s
recommendations for the material requiring containment. Concrete joints
shall be spaced in conformance with ACI recommendations.
14.14.1.23. OSHA requirements shall be considered when locating tank systems.
Note: OSHA 29 CFR 1910.106(b)(2) contains specific requirements
regarding spacing between above ground tanks, based on the size of the
adjoining tanks.
14.14.1.24. For facilities with bulk operations, where flammable liquids are received
(by tank vessel, pipelines, tank cars, or tank vehicle) and stored or
blended (for distribution), OSHA requirements shall be considered. Note:
OSHA 29 CFR 1910.106(f) contains specific requirements for facilities with
bulk plant operations.
14.14.2. Existing Facility Upgrades
14.14.2.1. At sites without liners, or where liners need replacing, newly engineered
liners shall be installed.
14.14.2.2. A floating concrete slab containing cracks or unsealed control joints shall
not be used as a liner system.
14.14.2.3. Where the floor of a containment structure consists of an ineffective
concrete floating slab, an engineered liner shall be installed on top of the
slab (with a 3-inch sand layer between). However, where this method
results in compromising the containment volume requirement, alternate
methods shall be used.
14.14.3. Temporary Facilities
14.14.3.1. When volumes allow, tanks may be placed in a stock tank or similar
nonflammable enclosure that provides required volume containment.
When volumes do not allow, or the previous method is impractical, steel-
walled containment with an engineered liner system shall be utilized.
15.1.2. For piping runs carrying gas or air that are not to be hydrostatically tested in place,
the deflection shall be 1/2-inch. If the deflection exceeds 1/2-inch, calculations
need to be verified by a design engineer. Maximum span shall be approved by
Project Manager.
15.1.3. For supports carrying electrical conduit, the following maximum support spacing
shall be used:
Conduit Size (in Inches) Maximum Distance Between Rigid
Metal Conduit Supports (in Feet)
1/2 – ¾ 10
1 12
1-1/4 – 1-1/2 14
2 – 2-1/2 16
3-inches and larger 20
Table E1200 / 15.1.3 - Maximum Conduit Support Spacing
15.1.4. Type of Pipe Supports (Bearing Plate, Springs, Clamps, Guides, Limit-Stops, Shim
Blocks, ‘Teflon’, and ‘Flurogold’)
15.1.5 Preventing atmospheric corrosion between the pipe supports and the pipeline.
15.1.5.1 Install fiberglass reinforced plastic (FRP) spacers between the pipeline and
the pipe support when the pipes exposed to a corrosive atmosphere. Atmospheric
corrosion takes place when the surface is wet by moisture formed due to rain, fog
and condensation.
15.1.5.1.1 Install the FRP following the manufacture installation procedure.
15.1.5.1.2 Surface preparation shall be by grit blasting. The Technical Manager or Corrosion
Supervisor must approve other types of surface preparation.
15.1.5.1.3 Approved epoxies for installing FRP’s include the following –
a. Glas Mesh EPI-Seam sealer
b. Denso 7125
c. Denso 7200
• Reference Table E1200 / 15.3.1.2 with the allowable soil pressure and
thrust from Table E1200 / 15.3.1.1. The size of the applicable thrust
block will be given in Table E1200 / 15.3.1.2.
Table E1200 / 15.3.1.1 - Maximum Riser Thrust from Blowdown of Piping System
(using rounded entry frictionless risers with valves having a port area of 60%
of the riser flow area)
(Ap/Ar = 0.60), NEWTONS = LB x 4.448, BAR = PSIG/14.5
15.3.1.2. Thrust block sizes are based on the block resisting 60% of the total thrust. If
soil conditions are poor or extremely variable, additional consideration should
be taken when determining the thrust block size. Refer to the table below.
16.3.6. Stairs having treads of less than 9-inch width shall have open risers.
16.3.7. Open grating type treads shall be used for outside stairs.
16.3.8. Risers shall be uniform in height.
16.3.9. Ship ladders or lapeyre stairs may be used where space is limited. A ladder is
unacceptable.
16.4. Fixed Ladders shall conform to OSHA, 29 CFR 1910.27.
16.4.1. Fixed ladders shall be used to provide access to elevated platforms higher than 2 feet
– 6-inches from floor or grade where use of stairs is impractical or unnecessary. Fixed
ladders shall be installed in conformance with the following requirements:
16.4.2. Minimum rung diameter: 3/4-inch.
16.4.3. Minimum rung width: 16-inches.
16.4.4. Minimum and preferred rung spacing: 12-inches; with uniform spacing. Maximum
rung spacing: 16-inches.
16.4.5. Clearances: Climbing side: 2 feet – 6-inches, for a pitch of 90°. Back of rung to
nearest obstruction: not less than 7-inches.
16.4.6. Cages or ladder safety devices shall be provided on ladders of more than 20 feet
height to a maximum unbroken length of 30 feet.
16.4.7. Cages shall extend a minimum of 42-inches above the top of landing, unless other
acceptable protection is provided.
16.4.8. Cages shall extend down the ladder to a point not less than 7 feet, or more than 8
feet, above the base of the ladder, with bottom flared not less than 4-inches, or portion
of cage opposite ladder shall be carried to the base.
16.4.9. Cages shall not extend less than 27-inches, nor more than 28-inches, from the
centerline of the rungs of the ladder. Cage shall not be less than 27-inches in width.
The inside shall be clear of projections. Vertical bars shall be located at a maximum
spacing of 40° degrees around the circumference of the cage; giving a maximum
spacing of approximately 9-1/2-inches, center to center.
have a minimum thermal rating of R13, and a flame spread rating of UL 25 or less.
The Project Manager shall determine the type and thickness of thermal and acoustical
insulation based on heat loads and noise requirements specified for equipment to be
housed inside the building.)
17.2.4. Building size shall allow for normal operation and maintenance, with areas provided
for lay down of equipment. The Project Manager shall consider use of Manufacturers’
standard building sizes.
17.2.5. Eve heights shall be a minimum of 8-feet. Compressor building eve heights shall be
determined by the crane hook height requirement and the height of the equipment.
Building design shall take into consideration the most severe equipment maintenance
requirements for hook height.
17.2.6. Building designs shall comply with ADA requirements.
17.3. Compressor Buildings, and Other Hazardous Locations
17.3.1. Compressor buildings shall have a ventilation system sized in conformance with API
RP 500 - Paragraph 6.3.2.4.2, which specifies a minimum of 6 air changes per hour or
as required to dissipate the equipment and building heat loads. Heat dissipation
requirements shall be defined in the Scope of Work. Compressor buildings that do not
have forced ventilation shall, at a minimum, have a continuous ridge vent with bug
screen, manual operator, and sidewall louvers (to provide ventilation in building). In
severe climates, louvers shall be supplied with bug screens and insulated covers.
Requirements for louver’s controls (manual, pneumatic, or electric) and louver’s action
(due to ESD: open, close, etc.) shall be provided in the Scope of Work.
17.3.2. Due to noise considerations, compressor buildings shall not have windows or
translucent skylights. Other buildings without windows shall have translucent skylights
installed at the top of the sidewalls to provide natural light. Quantity of translucent
panels shall be provided in the Scope of Work or approved by the Project Manager.
17.3.3. Louver face velocity shall not be less than Manufacturer recommendations, but in no
case greater than 500 fpm.
17.3.4. If installed, powered ventilation fan(s) shall be located in the building gable ends.
Maximum fan size and sound level shall be defined in the Scope of Work. On low gas
alarm, all exhaust fan louvers shall automatically open and all fans automatically start.
Electric motors shall be explosion-proof and rated for Class 1, Division 1, Group D
service. Fan components in the air stream shall be of spark-proof construction.
17.3.5. Where natural gas and/or hazardous chemicals are present, all exit doors shall:
• Swing out.
• Be equipped with panic hardware.
17.3.6. The maximum distance from any point inside a building to an exit shall not exceed 75
feet (as measured along an unobstructed path). In all buildings, a minimum of two
exits, with panic hardware, shall be provided.
17.3.7. Unless otherwise specified, all personnel doors shall be industrial type, steel, hinged,
insulated, 36-inches wide by 7 feet high with a minimum 10-inch by 10-inch wired
glass window.
17.3.8. Overhead truck doors shall be roll-up type metal doors with full vertical lift, insulated
(or non-insulated), as specified in the Scope of Work. Doors 12 feet or less in height
may be manual lift. Doors greater than 12 feet in height shall be electric motor
operated, with manual chain. Electric motors shall be explosion-proof, and rated for
Class 1, Division 1, Group D service.
17.4. Control Buildings and Skid-Mounted Electronics Buildings
17.4.1. General
17.4.1.1. Buildings shall be located in conformance with Standard Drawings STD-V-
1200-B005.1 – Structure Location Matrix Lighter-Than-Air Table and
STD-V-1200-B005.2 – Structure Location Matrix Heavier-Than-Air Table.
Any variances from these requirements require the review and approval of
the Project Manager.
17.4.1.2. Control buildings containing any electrical system, equipment, or
instrumentation not rated for hazardous locations shall have a positive air
pressure of 0.1- to 0.2-inches of water maintained in the building.
17.4.1.3. HVAC systems shall be designed to maintain a positive pressure of 0.1- to
0.2-inches of water. A back-up blower system shall be installed for use
when the HVAC unit is out of service.
17.4.1.4. The air intake for the pressurization system shall be located and designed to
ensure a continuous supply of clean fresh air.
17.4.1.5. The Furnace shall consist of a duct blower unit with electric resistance coil or
gas-fired burner. Furnaces shall be UL approved.
17.4.1.6. Humidifiers, where specified, shall be fan-powered units operating on 115
VAC, mounted on furnace plenums.
17.4.1.7. Air-conditioners shall consist of electric, commercial grade condensing units
designed for installation on outside concrete pads, with evaporative coils,
drains, and drip pans for installation in supply ducts. The minimum
acceptable SEER value shall be as specified in the Scope of Work.
17.4.1.8. Heat pumps shall consist of electric commercial-grade systems with indoor
and outdoor units having minimum SEER ratings as specified in the Scope
of Work.
17.4.1.9. Controls shall be a fully automatic, electric temperature control system. The
sequence of operation shall be:
17.4.1.10. Heating cycle - thermostat shall cycle heating chamber and blower units to
maintain area temperature.
17.4.1.11. Cooling cycle - thermostat shall cycle condensing unit and blower units to
maintain area temperature.
17.4.1.12. Humidity cycle - humidistat shall cycle power humidifiers to maintain
humidity when heating cycle operates. Humidifiers shall not operate
during cooling cycles.
17.4.1.13. System shall include an electronic setback thermostat for both heating and
cooling.
17.4.1.14. Ductwork shall be fabricated of first quality galvanized sheet steel or pre-
insulated round ductwork. All ductwork shall be:
• Round or rectangular in cross section.
• Configured with a minimum elbow centerline radius in a round duct 1-
1/2 times the duct diameter and a minimum throat radius of a turn in a
rectangular duct 1/2 times the duct dimension in the plane of the turn.
• Permanent, rigid, non-buckling, non-rattling, and airtight.
• Equipped with adjustable, locking-type dampers (for air volume
control) installed as far from the outlet as possible, while still user-
accessible.
• Equipped with balancing dampers if return system has more than one
return intake.
Highlighting indicates revisions made as of the date on this standard. Page 22 of 23
Section: E1200
Title: Civil and Structural
ENGINEERING DESIGN MANUAL Revised: 01-May-2014
ENGINEERING DISCIPLINES