Cooling Tower Structures: Concrete vs.

FRP
Subject Fiberglass Concrete
Designing and erecting a fiberglass cooling Concrete cooling towers must be thoroughly
tower is much quicker and simpler than engineered with a great deal of communication
designing and erecting a comparably sized required between the cooling tower supplier and
cast in place concrete cooling tower. Once the concrete supplier to size and locate all of the
overall size is determined the detailed drafting internal and external components. Large and
can be completed and the structure can be put expensive foundations are required to
into production. Limited equipment and accommodate the weight of the tower structure
ERECTION
scaffolding is required as the fiberglass cooling and extensive scaffolding must be used to form
tower is conveniently arranged to allow quick the concrete. Erection progress slows as the
and simple erection of light weight poured concrete must be allowed to cure before
components. The basic framework of the further work can be performed.
tower can be completed in days, not weeks.

Fiberglass is stronger and more flexible than Concrete cooling towers utilize steel
concrete, a real concern for those cooling reinforcements bars to maintain their shape and
towers located in areas that suffer strength. If the concrete tower is poorly supported
earthquakes. FRP is more resistant to or does not have ample reinforcement it can be
earthquakes then concrete and any inspections easily damaged by even the smallest earthquake.
STRENGTH AND FLEXIBILITY done after an earthquake can be quickly After an earthquake, concrete cooling towers must
performed without the need for specialists. be thoroughly inspected by qualified engineers
looking for hidden areas of damage.

Any algae or bio-films that grow in a fiberglass Concrete is porous and tends to hold dirt and bio-
CLEANING cooling tower can be washed or brushed away films more stubbornly than does fiberglass.
rather than needing to be scrubbed away.

Low maintenance FRP structure requires no Concrete cooling towers have higher long term
special attention. If ever needed, damaged maintenance costs then fiberglass cooling towers.
MAINTENANCE COSTS components can be fixed with a simple and Concrete may crack or corrode over time and
quick replacement of the damaged member repairs can be difficult and expensive. Repairs
with commonly available parts. Repairs can must be given time to cure and can take days.
be done in hours.

-Continued-
Cooling Tower Structures: Concrete vs. FRP

All FRP structural components are factory Concrete is poured in place and poor quality
produced and inspected prior to shipment. concrete cannot be detected until the concrete
Inspection of the materials is performed prior has cured, if at all. Dimensional accuracy of the
to installation assuring the quality of the finished structure is difficult to hold with any
QUALITY OF MATERIALS
product. All structural components are precision. Elevations must be constantly
predrilled and the overall dimensional checked and re-checked.
accuracy of the tower is insured and easy to
achieve.

Stair, ladders and handrails can be provided Concrete cooling tower fan decks can be
in safety yellow or any other color and never slippery when wet. Special colors must be
SAFETY requires painting. FRP decking is supplied painted on and additional maintenance is often
with a non-skid surface that offers a safe required to be done as the paint begins to
walking surface in any condition. deteriorate.

The FRP structure can be ordered with fire While concrete cooling tower structures can
retardant additives designed to quickly often survive a fire, the damage to the concrete
extinguish a fire. Damaged components are must be carefully accessed. Effects of fire
FIRE PROTECTION easily identified and can be quickly replaced fighting may have cooled some areas of the
with commonly stocked and locally available structure quickly and a loss of ductility in the
shapes. reinforcing steel often remains hidden from
view.

FRP cooling towers can be disassembled and Concrete cooling towers become a permanent
moved to another site if ever required. Cells part of the facility where they are installed. Cell
PERMANENCE can be expanded in 1.8m increments. Many expansion or other upgrades are near
possible upgrades are possible due to the impossible.
flexible design of the cooling tower structure.