GOVERNMENT OF KHYBER PAKHTUNKHWA

MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2019 - KPK

CHAPTER NO. 01 , CARRIAGE

DESCRIPTION OF ITEM : Spec. No : 1 , 1.5

Item Code : 01-03-b Unit 100 Rft

Item Name : Carriage of 100 nos, 50 kg cement bags : 2nd 30 meter

Detail Qty Unit Rate (Rs) Amount

EQUIPMENT
Carriage of 100 nos, 50 1.00000 Rs/2nd 30m 24.59 1 Rs/2nd 24.59
kg cement bags : 2nd 100 30m
Rft /30 meter

TOTAL EQUIPMENT 74.50 % 24.59

Cont. Profit + Over Heads (Material+Labour+Equipment) : 22.50 % 5.53

Composite Rates Per 100 Rft Rs. 30.12 Cost Per 30 Meter: 29.65
Labour Rates Per 100 Rft Rs. 0.00 Cost Per 30 Meter: 0.00

26
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2019 - KPK

CHAPTER NO. 01 , CARRIAGE

DESCRIPTION OF ITEM : Spec. No : 1 , 1.5

Item Code : 01-03-c Unit 100 Rft

Item Name : Carriage of 100 nos, 50 kg cement bags : 3rd to 12th 30 meter

Detail Qty Unit Rate (Rs) Amount

EQUIPMENT
Rate for carriage of 100 1.00000 Rs/(3rd-12th) 14.76 1 Rs/(3rd 14.76
no.50 kg bag for 3rd to 100 Rf -12th)
12th Chain=Rate for 100 Rf
carriage 2nd chain x 0.6

TOTAL EQUIPMENT 74.50 % 14.76

Cont. Profit + Over Heads (Material+Labour+Equipment) : 22.50 % 3.32

Composite Rates Per 100 Rft Rs. 18.08 Cost Per 30 Meter: 17.80
Labour Rates Per 100 Rft Rs. 0.00 Cost Per 30 Meter: 0.00