Professional Documents
Culture Documents
PMP Cost Management
PMP Cost Management
The process that establishes the policies, procedures and documentation for planning, managing, expending
Fifth Edition, Project Management Institute Inc., 2013 Figure 7-2 Page 195
Analytical Techniques
Estimate Costs
"The process of developing an approximation of the monetary resources needed to complete project
activities."
The definition shown above in italics is taken from the Glossary of the Project Management Institute, A
Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management
Fifth Edition, Project Management Institute Inc., 2013 Figure 7-4 Page 200
The process of developing an understanding of what resources are needed for the project activities
identified.
Usually expressed in monetary terms, other units such as person hours or staff days can often be
used.
Project resources include labor, materials, equipment, meeting rooms, facility fees and services
Analogous Estimating
Used when:
Bottom Up Estimating
Parametric Estimating
Used to predict total project costs by using project's characteristics in a mathematical model.
Triangular Distribution = (O + M + P) / 3
Beta Distribution = (O + 4M + P) / 6
Reserve Analysis:
A cost contingency reserve may be used to account for cost associated risks
Estimating Software
Simplify cost estimations and allow for rapid review of estimate alternatives
Responses from bidders will indicate what a project or deliverables should cost
Stage % of Total
Preliminary Survey 1
Feasibility Study 6
Systems Analysis 14
System Design 16
Programming 27
Systems Testing 13
Acceptance Testing 11
Implementation 12
-25% to +75%
Budget Estimate
-10% to +25%
Definitive Estimate
Need to engage team members using group decision making techniques to improve accuracy of estimates
Add project overheads – 5% for meetings; 15% for management time; contingency (10 – 12%)
Adding in company overheads (margin for profit, etc…) will be done later
Basis of Estimates
Assumptions made
Determine Budget
"The process of aggregating the estimated costs of individual activities or work packages to establish an
Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management
Estimating Effort
Physical Resources
Meeting rooms
People Resources
constraints
Living within your budget for each time period of the project
Example: A customer wants to spread project costs of £1,600,000 over two half years. This is one way how it
could be done:
Contingency Reserves
Guidelines:
Inform the project team that the project will be managed against a point estimate without
contingency.
Release contingency funds only through a closely controlled and well-documented process.
Example:
Contingency allowances for the 2012 Olympics, hosted by London, could have included funds for an
unforeseen problem, such as extra number of large beds required in the athletes village due to an
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Fifth Edition, Project Management Institute Inc., 2013 Figure 7-8 Page 213
"The process of monitoring the status of the project to update project costs and managing changes to he
cost baseline."
The definition shown above in italics is taken from the Glossary of the Project Management Institute, A
Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Fifth Edition, Project Management Institute Inc., 2013 Figure 7-10 Page 215
Cost Control
Any increase in the authorised budget can only be approved through 4.5 Perform Integrated Change
Control process
Ensuring that only appropriate project changes are included in a revised cost baseline
Informing project stakeholders of authorized changes to the project that will affect costs
Earned Value Analysis (or Earned Value Management (EVM) is an important way to control costs
Compares actuals for schedule and cost performance against planned performance
How much did we spend so far compared with what we budgeted (the forecast)?
Earned Value = the estimated cost of the work that was done at report point = PV x progress
Example:
If we were to look at the EV at point of measurement in the image below, this shows we are behind
schedule.
EVM measurements
Schedule variance SV = EV - PV
Cost variance CV = EV - AC
Cost variance - The difference between earned value and actual costs incurred.
CV = EV – AC.
Example 1
Nothing, there is no earned value line and we cannot determine the project status
Example 2
Time CV = -
SV = +
Example 3
CV = +
SV = +
No action needed (unless there is an issue with NOT spending the customers money)
Example 4
CV = +
SV = -
Example 5
CV = -
SV = -
PV = £290,000
EV = £260,000
AC = £140,000
Formulae:
SV = EV – PV
CV = EV – AC
SPI = EV/PV
CPI = EV/AC
Work out:
the SV
the CV
the SPI
the CPI
ETC = how much more do we estimate the project to cost from today?
VAC = the difference between original total costs and new forecast total costs
Estimate At Completion
1. If we are 80% efficient and we don't know what the problem is, then we use this formula i.e. will carry on
at 80% efficiency:
The word cumulative is used to denote the value at this point in time i.e. cumulative up to now.
2. If we are 80% efficient and we know what the problem is then we return to the budgeted rate and use this
formula
3. If past assumptions are faulty then the PM or project team have no confidence in the original estimate for
remaining work
There is an assumption that the project is over budget (negative cost performance) and the schedule has a
completion deadline
Based on actual costs of work performed to date, need to calculate cost of work remaining
If things have not been going to plan (behind schedule and over budget) will/should the actual costs be used?
ETC = EAC-AC
How different will the outturn budget be from the original forecast
What level of efficiency is required to be obtained, from the resources, for the remainder of the project
The performance level we should use from this point to get the project back to BAC (or EAC):
TCPI (BAC) =
VAC = BAC – AC
This formula for VAC is when the project has finished “normally” according to its original forecast
SV= Zero
EV = BAC
The process of aggregating the estimated costs of individual activities or work packages to
The process of aggregating the estimated costs of individual activities or work packages to
The process of monitoring the status of the project to update project costs and managing changes
to he cost baseline.
The definitions shown above in italics is taken from the Glossary of the Project Management Institute, A
Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition,