You are on page 1of 49

DOCUMENT CONTROL

Name: Mark Van Vuuren


Document Owner Position: Field Practices Coordinator
Date: March 2013

Name: Mark Van Vuuren


Approved By * Position: Field Practices Coordinator
Date: March 2013

Name: Lance Roberts


Authorisation ** Position: Manager Safety and Health
Date: March 2013

Date Created/Last Updated March 2013 / October 2018

Review Frequency *** Every 3 years

Next Review Date *** October 2021

* Must be the Process Owner and is the person assigned authority and responsibility for managing the whole process, end-
to-end, which may extend across more than one division and/or functions, in order to deliver agreed business results. The
Process Owner can also be the Document Owner.

** This person will have the power to grant the process owner the authority and responsibility to manage the process from end
to end.

*** Frequency period is dependent upon circumstances – maximum is 5 years from last issue, review, or revision whichever is
the latest. If left blank, the default will be 1 year unless otherwise specified.

STAKEHOLDERS NOTIFICATION LIST


The following positions must be consulted if an The following positions must be notified of any authorised
update or review is required: change:

Manager - Safety & Health Manager - Safety and Health

Asset Managers - Operations Manager - Engineering & Projects Services

Fields Practices Coordinator Fields Practices Coordinator

Regional Management Teams


Works Delivery Managers
(RM, AM, ASM/WDD)

Asset Services Managers Operational Staff

Copyright 2012 - Copyright is owned by Horizon Power (ACN 57 955 011 697).
All rights reserved. No part of this work may be reproduced or copied in any form or by any means (graphic,
electronic, taping or information retrieval system) without the written permission of the copyright owner.

Last review: October 2018 DM# Page | 1


Important Notice to Users

This Underground Cable Installation Manual has been developed for use by Horizon Power
employees’ and Contractors, engaged to perform construction and maintenance work on Horizon
Powers’ underground electrical distribution networks.

The manual provides guidelines for a minimum acceptable standard of underground


construction that is required by Horizon Power. To this end, this manual provides the framework
by which auditing of the underground electricity distribution network may be undertaken.

It is issued by as a controlled document by Horizon Power to Horizon Power employees’ and


Contractors on the condition that it will only be used whilst undertaking underground cable
installation work on Horizon Power underground electrical distribution networks. Underground
cable installation work will only be performed by individuals who are appropriately trained and
qualified in accordance with accepted standards within Horizon Power. This Manual is not
intended, and should not in any way be relied upon, as a substitute for such training.

Hierarchy of Documentation
WA general workplace safety legislation administered by the regulator WorkSafe WA:

 Occupational Safety and Health Act 1984


 Occupational Safety and Health Regulations 1996

WA Electrical legislation administered by the regulator EnergySafety WA:

 Electricity Act 1945


 Electricity Licencing Regulations 1991
 Electricity Regulations 1947

An illustration of the hierarchy of documentation can be seen below.

In the interest of your own personal safety, and the safety of all Horizon Power workers,
contractors and the general public it is essential that you read these standards and understand
how they relate to your work environment.

These Standards will be regularly reviewed, if there are any queries and suggestions for
improvement, then direct your queries to the Field Practices team via the Continuous
Improvement Process

Last review: October 2018 DM# Page | 2


Acts & Regulations

Codes of Practice

AS/ANZ Standards

Guidenace Notes

Horizon Power
Safety & Health
Management
Systems

Horizon Power
Electrical Safety
Standards

Horizon Power
Horizon Power Horizon Power published technical
Switching Manuals Work Instructions standards &
guidelines

Figure 1 – Illustration of the hierarchy of documentation

Last review: October 2018 DM# Page | 3


Table of Contents

Section Section Number

1 PURPOSE ............................................................................................................1-4

2 SCOPE .................................................................................................................2-4

3 DEFINITIONS AND REFERENCES .....................................................................3-5


3.1 Definitions ................................................................................................................. 3-5
3.2 References ................................................................................................................ 3-7

4 GENERAL REQUIREMENTS ...............................................................................4-8


4.1 Training and Authorisation ......................................................................................... 4-8
4.2 Job Planning and Risk Assessments (Work Planning) .............................................. 4-8
4.3 Personal Protective Equipment (PPE) ....................................................................... 4-9
4.4 Contractor Responsibilities ........................................................................................ 4-9
4.5 Traffic Management .................................................................................................. 4-9
4.6 Instructions, Procedures and Standards .................................................................. 4-10

5 SURVEYING AND “AS CONSTRUCTED” RECORDS .....................................5-11


5.1 Survey Benchmarks and Datum Points ................................................................... 5-11
5.2 As Constructed Records.......................................................................................... 5-11

6 CROSSINGS.......................................................................................................6-12
6.1 Railway Crossings ................................................................................................... 6-12
6.1.1 Planning Requirements ........................................................................................... 6-12
6.1.2 Installation of Cables and Conduits ......................................................................... 6-12
6.1.3 Installation of Cable Location Markers ..................................................................... 6-12
6.1.4 Installation of Power Cables under tracks and elsewhere on railway property ......... 6-13
6.2 Existing Pipes or Cables.......................................................................................... 6-15
6.3 Gas Mains ............................................................................................................... 6-16
6.4 Communications...................................................................................................... 6-16
6.5 Existing Underground Electrical Cables ................................................................... 6-16
6.6 Road and Vehicle Crossings ................................................................................... 6-17
6.7 Horizontal Cable Clearance to other Services at Road Crossings ........................... 6-17

7 CABLE TUNNELS AND SUPPORT SYSTEMS ...................................................7-1


7.1 General ..................................................................................................................... 7-1
7.2 Access Pits................................................................................................................ 7-1
7.3 Cable Support ........................................................................................................... 7-1

8 CABLE ON AND OFF “NORMAL” ALIGNMENT ................................................8-2


8.1 Standard Cable Alignment......................................................................................... 8-2
8.2 Alternative Cable Alignment ...................................................................................... 8-2
8.3 Easements ................................................................................................................ 8-2
8.4 Retrospective Undergrounding .................................................................................. 8-3

Last review: October 2018 DM#


9 TRENCHING AND EXCAVATION ....................................................................... 9-1
9.1 General ..................................................................................................................... 9-1
9.2 Blasting ..................................................................................................................... 9-1
9.3 Excavated Materials .................................................................................................. 9-1

10 DIRECTIONAL DRILLING .......................................................................... 10-2


10.1 Installation Principles............................................................................................... 10-2
10.2 Drilling ..................................................................................................................... 10-3
10.3 Drilling Fluids Management Plan ............................................................................. 10-3

11 PLOUGHING ............................................................................................... 11-4

12 CABLE LAYING .......................................................................................... 12-6


12.1 Drum Mounting and Inspection ................................................................................ 12-6
12.1.1 Inspection prior to installation: ................................................................................. 12-6
12.1.2 Preparation for installation ....................................................................................... 12-6
12.2 Protection of Cables during Installation ................................................................... 12-7
12.3 Cable Installation methods ...................................................................................... 12-7
12.3.1 Stocking Pulling ....................................................................................................... 12-7
12.3.2 Installation using Pulling Eyes ................................................................................. 12-7
12.3.3 Bond Pulling ............................................................................................................ 12-8
12.3.4 Armour Pulling......................................................................................................... 12-8
12.3.5 Mechanical Assisted Installation .............................................................................. 12-8
12.4 Cable Pulling Tensions ............................................................................................ 12-8
12.5 Pulling Speed .......................................................................................................... 12-9
12.6 Cable Bending Radii................................................................................................ 12-9
12.7 Maximum Number of Cable Joints ........................................................................... 12-9
12.8 Installation of Cables on Poles ................................................................................ 12-9
12.9 Bedding and Backfill ................................................................................................ 12-9
12.10 Depth of Cover for Cables ....................................................................................... 12-9
12.11 Cable Protection Covers and Marker Tapes .......................................................... 12-10
12.12 Sealing of Cables .................................................................................................. 12-10

13 CONDUITS ................................................................................................ 13-10


13.1 Application ............................................................................................................ 13-10
13.2 Requirements for cables installed outside normal alignments ............................... 13-11
13.3 Encased Conduits ................................................................................................. 13-11
13.4 Sealing of Conduits ............................................................................................... 13-11
13.5 Installation requirements for Conduits ................................................................... 13-11
13.6 Pulling Cables through Conduits ........................................................................... 13-12

14 CABLE JOINTING AND TERMINATIONS .................................................... 13


14.1 General ...................................................................................................................... 13
14.2 Cable Joint Excavations ............................................................................................. 13
14.3 Jointing....................................................................................................................... 14
14.4 Termite Proofing ......................................................................................................... 15
14.5 Terminations .............................................................................................................. 15
14.6 Working Ends ............................................................................................................. 16

15 TESTING AND COMMISSIONING ................................................................ 16

Last review: October 2018 DM#


16 REINSTATEMENT ......................................................................................... 17
16.1 General ...................................................................................................................... 17
16.2 Compaction ................................................................................................................ 17
16.3 Levelling ..................................................................................................................... 17
16.4 Restoration of Surface ................................................................................................ 18

17 DAMAGE TO PROPERTY ............................................................................. 18


17.1 General ...................................................................................................................... 18

18 PILLARS AND PITS ....................................................................................... 19


18.1 General ...................................................................................................................... 19

APPENDIX A - SERVICE ALIGNMENT, DEPTH AND COLOURS FOR GREENFIELD


SITE .............................................................................................................................. 20

APPENDIX B – CABLE INSTALLATION DATA .......................................................... 21

APPENDIX C - DIAL BEFORE YOU DIG SERVICE .................................................... 21

Last review: October 2018 DM#


1 PURPOSE
This manual specifies the technical requirements for the safe and efficient installation of
underground cables on Horizon Power’s electrical distribution networks, which provides
the minimum requirements for:

 All Horizon Power workers who work in and around excavations.

 All Horizon Power workers how undertake directional drilling.

 All Horizon Power workers engaged in installing underground cables.

 Any process that displaces soil.

This document refers to other Horizon Power documents to provide reference standards
for underground cable installation work.

2 SCOPE
This manual has been developed for use by Horizon Power workers’ and Service
Providers engaged in the installation of high and low voltage distribution cables on the
Horizon Power electrical networks.

Horizon Power workers’ and Service Providers shall comply with these requirements,
except as otherwise approved.

For subdivisional work managed by a developer where the subdivision does not require
equipment to be installed on public land, some items in this document may not be
applicable as they are specified in the Underground Distribution Scheme (UDS) Manual.

Note: Public land is land that at the time of subdivision is freely available for public
use, e.g., existing road reserves, Public Access Way (PAW), Public Open
Space (POS) etc.

Last review: October 2018 DM#


3 DEFINITIONS AND REFERENCES
3.1 Definitions

Accredited A person or an entity who has been accredited through the


Service accreditation scheme of Horizon Power to undertake any
Provider (ASP) construction work on Horizon Power underground network.

Approved Appropriate organisation endorsement in writing for a specific


function.

Authorised A person with technical knowledge or sufficient experience who


Person has been approved or delegated authority to act on behalf of
Horizon Power to perform the duty concerned.

Cable A single cable core, or two or more cable cores laid up together,
either with or without fillings, reinforcements or protective
coverings.

Conductor A wire or other form of conducting material suitable for carrying


current, but not including wire or other metallic parts directly
employed in converting electrical energy into another form.

Construction The officer appointed by Horizon Power as Horizon Power’s


Project Manager representative to whom all site contractual and technical matters
(CPM) are referred.

Earthed Directly electrically connected to the general mass of earth so as


to ensure and maintain the effective dissipation of electrical
energy.

Energised Connected to a source of electrical supply.

High voltage A nominal voltage exceeding 1,000 V ac or exceeding 1,500 V


dc.

Insulated Separated from adjacent conducting material by a non-


conducting substance or airspace permanently providing
resistance to the passage of current, or to disruptive discharges
through or over the surface of the substance or space, to obviate
danger of shock or injurious leakage of current.

Live Energised or subject to hazardous induced or capacitive


voltages.

Low voltage Nominal voltage exceeding 50 V ac or 120 V dc but not


exceeding 1000 V ac or 1500 V dc.

Safe Not posing an unacceptable risk to life, health or property.

Last review: October 2018 DM#


Safety Observer A person competent for the task and specifically assigned the
duty of observing and warning against unsafe approach to
electrical apparatus, or other unsafe conditions.

Shall A requirement is "mandatory”.

Should A requirement Is "advisory or discretionary”.

Voltage A potential difference between conductors or between


conductors and earth.

HDPE High Density Polyethylene

HV High Voltage

LV Low Voltage

MRWA Main Roads Western Australia

PTA Public Transport Authority

PAW Public Access Way

POS Public Open Space

UDS Manual Underground Distribution Schemes Manual

WAGR Western Australian Government Railway

WAPC Western Australian Planning Commission

XLPE Cross-linked Polyethylene

Last review: October 2018 DM#


3.2 References

Requirements and Information relating to this manual may be found within the source
documents detailed below:

 Utility Providers Code of Practice, Main Roads WA;

 Restoration and Reinstatement Specification for Local Governments in Western


Australia published by the Institute of Public Works Engineering Australia (available
from Main Roads WA’s web site);

 Horizon Power Instruction Manual (HIM) Section 6, Underground Work

 Horizon Power Underground Distribution Schemes (UDS) Manual;

 Horizon Power Network Standard: Testing & Commissioning – Technical


Requirements;

 Dial Before You Dig Service for lodging an enquiry and requesting a plan;

 Traffic Management for Works on Roads - Code of Practice, Main Roads WA;

 Occupational Safety and Health Act 1984 and Occupational Safety and Health
Regulations 1996.

 WorkSafe Code of Practice: Excavation

 Explosives and Dangerous Goods Act 1961 and Explosives and Dangerous Goods
(Explosives) Regulations 1963;

 AS 1742 Manual of uniform traffic control devices, Australian Standards;

 AS/NZS 3000 – Australian/New Zealand Wiring Rules; and

 AS 4799-2000 Installation of underground utility services and pipelines within


railway boundaries.

Last review: October 2018 DM#


4 GENERAL REQUIREMENTS
All Horizon Power underground cables shall be a termite protected type. Termite
protection is critical to achieve 40+ year cable life, as Horizon Power cables are often
installed in termite affected areas

Cables are termite protected using the following means:

a) inclusion of a termite protection in the outer sheath (Horizon Power method);


b) double brass tapes;
c) nylon sheaths

The cable sheath MUST NOT be scratched during installation. Scratch damage to the
outer sheath may allow termites’ mandibles (pincers) to “bite” into the cable outer
sheath.

4.1 Training and Authorisation

Underground Cable Installation work shall only be performed by individuals who are
appropriately trained, qualified and authorised in accordance with accepted standards
within Horizon Power.

Service Providers are responsible for ensuring all its employees’ and Sub-Contractor
employees’ have been authorised by Horizon Power.

They must submit to Horizon Powers site representative confirmation of authorisation


for each employee, prior to the commencement of the works.

Note: This Manual is not intended, and should not in any way be relied upon, as a
substitute for training.

4.2 Job Planning and Risk Assessments (Work Planning)

Before the commencement of work, a risk assessment must be carried out using the Risk
Analysis Procedure (OSH-3.6-1-02), to identify and document the hazards and risks
associated with the task and ensure appropriate control measures are implemented.

It is important that, appropriate control measures must be identified, documented and


implemented in order to control hazards to As Low as Reasonable Practicable
(ALARP).
The on-site job risk assessment shall include but not limited to:

 Identify and discuss the job hazards;

 Assess the risks that may result because of the hazard;

 Agree on the tasks assigned to control or remove the hazards & risks; and

 Implement the control measures

Last review: October 2018 DM#


4.3 Personal Protective Equipment (PPE)

Horizon Power Workers engaged in the installation of high and low voltage distribution
cables on the Horizon Power electrical networks shall wear the Personal Protective
Equipment (PPE) as required in accordance with Horizon power’s Instruction Manual:

 FI 2.1 Glove Protection


 FI 2.2 Head Protection
 FI 2.5 Other Personal Protective Equipment
 FI 2.6 Worksite Clothing/Personal Protective Equipment

4.4 Contractor Responsibilities

The Contractor is to provide competent, qualified and licensed Personnel to undertake


Underground Cable Installation.

All Contractor Personnel utilised to carry out work activities on or near Horizon Powers
electrical networks must have Horizon Power authorisation prior to the commencement
of the Services, refer to Field Instruction Manual:

 FI 1.2 Contractor Authorisation Process

 FI 1.3 Construction site access – minimum requirements

4.5 Traffic Management

Horizon Power Workers shall ensure that where Services are sited adjacent to existing
roads, adequate precautions are taken at all times to protect personnel, associated plant,
and the general public.

Horizon Power Workers shall comply with the Main Roads Department Traffic
Management for Road Works Code of Practice and Horizon Powers’ Network Instruction
Manual:

 FI 2.15 Temporary Safety Barriers and/or Warning Signs

 FI 2.20 Traffic Management

The Local Government Authority shall be notified of any occasion it may be necessary to
obstruct a road or footpath to carry out the Services.

Written consent shall be obtained from Main Roads Department and the relevant local
authority before creating such obstruction.

All vehicles shall be fitted with suitable warning lights.

Last review: October 2018 DM#


4.6 Instructions, Procedures and Standards

Horizon Power Workers and contractors shall comply with Horizon Power instructions,
procedures, standards and construction drawings when engaged in the installation of
high and low voltage distribution cables on the Horizon Power electrical networks.

This includes but not limited to the following Horizon Power documents:

 Horizon Power Instruction Manual (HIM)

 Electrical Safety Standards (ESS)

 “Fit for Work” Policy

 Hazard Incident Reporting Notification and Investigation Procedure

 Working Near Horizon Powers’ Underground And Overhead Electrical Networks

 Underground Distribution Schemes (UDS) Manual.

 Underground Cable Installation Manual

 Testing & Commissioning Standard

 Substation Installation Manual

 Distribution Equipment Labelling Standard

 Horizon Power Construction Drawings

Last review: October 2018 DM#


5 SURVEYING AND “AS CONSTRUCTED” RECORDS
5.1 Survey Benchmarks and Datum Points

There may be official survey benchmarks installed in the project work area. Precautions
shall be taken to avoid disturbing these markers.

 (Survey benchmark monuments are brass or metal disks in the ground. They
measure exact horizontal positions (latitude and longitude) on the Earth because this
gives surveyors a point of reference)

Some benchmarks also measure elevations. These types of benchmarks indicate the
height above or below sea level at that location.

Should any markers be disturbed, all costs associated with restoring the benchmarks to
their correct position shall be borne by those responsible for such disturbance.

5.2 As Constructed Records

Upon completion of all work, the following “As Constructed” records shall be provided to
the Horizon Powers’ Construction Project Manager (CPM):

1. Cable installation record. Where cables are installed using directional drilling, the
length and depth of cables shall be recorded.

2. Electrical test schedules.

3. HV cable joint schedule.

4. Materials & equipment schedule.

The “As Constructed” records shall meet the requirements of Section 9.10.2 of the
Underground Distribution Schemes Manual.

Standard forms for Electrical Test Schedules, HV Cable Joint Schedules and Materials &
Equipment Schedule are available for download from Horizon Power’s web site.

Last review: October 2018 DM#


6 CROSSINGS
6.1 Railway Crossings

If any works are proposed to be undertaken within or adjacent to rail reserves contact
the relevant rail authority to obtain permission and compliance requirements

6.1.1 Planning Requirements


Before commencing any works associated with railway property, it is essential that all
necessary applications are made and approvals obtained.

Details of the applications and approval process requirements are contained in the Utility
Providers Code of Practice for Western Australia.

The approval process can take several months, so appropriate planning for the works is
recommended.

In most cases, arrangements will be required to use a railway flagman at the site for the
duration of the works.

6.1.2 Installation of Cables and Conduits


Where site conditions permit, the installation shall be by boring or directional drilling for
the portion under the tracks and at least 3 m beyond the outer rails or 3 m beyond the
toe of embankment, whichever is the further.

In the case of boring, the diameter of the bored hole shall not exceed the outside diameter
of the pipe/conduit by more than 50 mm.

If the diameter of the bored hole exceeds the outside diameter of the pipe/conduit by
50 mm or the bored hole needs to be abandoned, the hole shall be backfilled and
remedial measures shall be taken to provide support for the railway.

6.1.3 Installation of Cable Location Markers


Cable marker details are available in Horizon Power’s Distribution Design Catalogue
(DDC) Section 7. Cable markers shall be installed to indicate the location of all
underground power cables.

1. The markers shall be located above or adjacent to the buried cable:

a) At points of entering and leaving the Public Transport Authority (PTA) property;
b) At changes of direction;
c) At a distance between consecutive markers of the lesser of 200 m or line of
sight; and
d) Where specified, at the ends of the under track crossing (the end of the under
track crossing is taken as the point 3 m beyond the outer rail or toe of the
embankment).

Last review: October 2018 DM#


2. The wording on the markers shall include the following:

a) The owner’s name;


b) A warning of the presence of a buried service;
c) The nature of the buried service; and
d) Contact details and advice in the event of an emergency.
3. The markers shall comply with the following requirements:

a) Stand at least 800 mm out of the ground, to the bottom of the marker plate;
b) Be of non-combustible material for the marker plates and of at least fire-
resistant material for the pole; and
c) Wording on the markers shall be legible, permanent, and formed in a non-
combustible medium, or as otherwise approved by the PTA.
4. The descriptive wording and instructions shown on the markers shall face the
railway.

6.1.4 Installation of Power Cables under tracks and elsewhere on railway property
Power cables passing under the tracks shall be enclosed in an appropriate ‘Category A’
system.
The top of the encasing pipe or conduit shall be at a depth of not less than 2000 mm
below the top of rail and shall be maintained at this depth for not less 3000 mm beyond
the outer rails, when measured at right angles to the track, unless otherwise stated in the
approved design.
A ‘Category A’ system is an underground system where:

a) Cables are enclosed in heavy duty insulating conduit without further


mechanical protection.
b) Cables are enclosed in insulating wiring enclosures encased in concrete.
c) Sheathed cables are enclosed in galvanised steel pipe without further
mechanical protection or
d) Armoured sheathed cables or neutral screened cables are buried direct in the
ground without mechanical protection.

Last review: October 2018 DM#


Dimension Description Minimum depth (mm)
X Depth between top of rail and 1200/1500 (directly buried optic)
conduit, pipe or cable 2000 (power)
Y Depth between top of rail and 1200/2000 (power)
encasing pipe

Figure 2 – Section of conduit or pipe-carrying cable under tracks

Power cables passing elsewhere on the property of the PTA shall be laid at a depth of
not less than 1000 mm below ground level, or at the same depth below the level of drain
inverts they may cross unless, otherwise stated in the approved design.

Last review: October 2018 DM#


Where specified by the PTA, the cables shall also be enclosed in conduits or covered by
protective slabs.

Figure 3 – Section of cable within and parallel to railway reserve

6.2 Existing Pipes or Cables

Whenever a crossing is made of an existing pipe or cable, such pipe or cable shall be
securely supported during the progress of the work.

The minimum spaces required between services are contained in the Utility providers
Code of Practice, summarised as follows.

Last review: October 2018 DM#


1. Electricity is to pass under gas and water at reticulation crossings.

2. The existing cable shall be protected by a split length of heavy duty conduit or
concrete slabs. If 150 mm clearances cannot be maintained then the cable shall
be sleeved with a conduit. The length of conduit shall be at least of 500 mm on
either side of the crossing.

3. A minimum clearance of 300mm is required between gas and electricity services.


If 300mm clearance cannot be achieved, approval of the Gas Service Provider
shall be obtained.

4. A minimum clearance of 150mm is required between the electricity services and


the sewer and water mains.

5. All reticulation shall be laid within ± 100 mm of the indicated centre line and
secured against movement with initial backfill.

6.3 Gas Mains

Where work is required close to the gas transmission system such work shall be
performed in accordance with Horizon Power’s Field Instruction – FI 4.1 – Work
Adjacent to Gas Mains.

6.4 Communications

The communications alignment is between 500-1300 mm from the property boundary


within the verge, and 450 mm deep.

Whenever a cable crosses is a communications cable, the cable shall be securely


supported during the process of the work and the power cable shall go under the
communications cable, maintaining a 300 mm clearance as per Utility Providers Code of
Practice.

The space between the power cable and the communications cables shall be maintained
when the trench is backfilled.

Appendix A provides the diagram for the road reserve allocation for utility providers.

6.5 Existing Underground Electrical Cables

Prior to the commencement of excavation work, all efforts must be made to determine if
underground cables are present in the vicinity of the proposed excavation. This includes
but is not limited to using the “One Call” service.

Work on or near existing underground cables shall be in accordance with Horizon


Power’s manual, Working Near Horizon Power’s Overhead and Underground Network
and Field Instruction: FI 6.4 Excavation Work and Directional Drilling.

If any unrecorded underground cables, conduits or bare earth wires are exposed, work
in the vicinity must cease and Horizon Powers’ CPM must be notified immediately.

Last review: October 2018 DM#


6.6 Road and Vehicle Crossings

All cables crossing roads and vehicle crossovers shall be installed in conduits. Road
crossings shall be installed:

a) Perpendicular to the property street boundaries; and


b) Between readily recovered target points, e.g., common property boundaries or
intersections.
For service cables and streetlight cables, the conduits shall be installed from the edge of
the cable alignment to as close as practical to the termination point (e.g. street light
column, etc.)

For cables with a large bending radius, road-crossing conduits shall extend a minimum
of 1000 mm beyond the kerb into the verge and as practically close to the termination
point.

Cable covers shall be installed over cables in the gaps between the end of conduits and
the edge of cable alignment, to ensure that the cable is protected until it enters the cable
alignment.

Where roads and vehicle crossings are already constructed, thrust boring shall be used
to install the required conduits.

Conduit crossing locations shall be permanently identified on the road kerb-face. Typical
identification methods could include a:

a) 75 mm high letter “E” embedded or cut in,


b) Proprietary brass plate/letter “E” adhered to the face.

Where conduits are installed across roadways where no kerbs


currently exist or will not be installed when the conduits are installed, conduit location as-
built drawings shall show the conduit centreline end-point relative to surveyed property
boundaries.

6.7 Horizontal Cable Clearance to other Services at Road Crossings

All cables and conduits crossing roads shall be installed with a minimum horizontal
clearance of 150 mm from other services.

Last review: October 2018 DM#


SECTION 7
Page 7-1

7 CABLE TUNNELS AND SUPPORT SYSTEMS


7.1 General

Where cable tunnels are to be used, the construction and installation requirements shall
be included on the design drawings.

Cables running through cable tunnels shall be supported on cleats with a maximum
spacing of 1500 mm or on cable ladders.

Horizontal spacing of cable and circuits shall be at least 100 mm between adjacent
circuits.

7.2 Access Pits

In circumstances where there is a significant change in direction of the cables being


installed, the design may require the installation of an access pit to be large enough to:

a) Allow two people to work comfortably on the cable.


b) install rollers; and
c) Accommodate the bending radii of the largest cable.

7.3 Cable Support

A cleat support system shall be installed in at a distance to ensure the cable is maintained
in a straight line and only minimal sagging occurs.

When using cleats, it is necessary to ensure the cable is rigidly held at the cleat position.

Cleats for long vertical runs shall be designed to support the weight of the cable.

Cleats used on single core cable shall be of non-magnetic material, such as wood or
aluminium.

Single core cables shall never be surrounded with a steel ring, as this will cause local
heating problems.

Care shall be taken to ensure the correct size cleat is used otherwise damage to the
cable may result. A tight cleat may pinch the cable whereas a loose cleat may allow
excessive cable movement.

Wooden cleats shall be used for paper/lead insulated cables.

Last review: October 2018 DM#


SECTION 8
Page 8-2

8 CABLE ON AND OFF “NORMAL” ALIGNMENT


8.1 Standard Cable Alignment

Wherever practicable, cables shall be installed in Horizon Power’s standard alignment of


0 – 500 mm from the property boundary in accordance with the “Utility Providers Code of
Practice for Western Australia” and Drawing in Appendix B;

Other services shall not be installed in the power cable alignment without written approval
from Horizon Power.

All front boundary pegs shall be identified prior to the commencement of excavation.

8.2 Alternative Cable Alignment

Cables may be installed in the 2.7m alignment where there are installation and
maintenance issues adjacent to retaining walls and other structures in the standard 0 –
500 mm alignment.

This is provided it is acceptable to the other Utility Service Providers and it does not
interfere with street trees.

In special circumstances if the 2.4 m to 3 m alignment is not available, a written request


to the other Utilities’ will be required to obtain approval to use their alignments.

8.3 Easements

Where HV and LV cables are installed outside the standard alignment or in locations
other than road reserves, including private property, public open space or public access
way, they shall be protected by surveyed and registered easements.

Two types of underground distribution easements exist.

a) Development areas controlled by the West Australian Planning Commission


(WAPC) process: Easements are arranged under Section 167 of the Planning
and Development Act 2005.
b) Other developments areas: Easements are arranged under the Energy
Operators (Power) Act 1979.
The appropriate easement shall be selected and documented in the design file for each
particular location.

Note: For subdivision developments, developers shall comply with the requirements
of the UDS Manual.

Last review: October 2018 DM#


SECTION 8
Page 8-3

8.4 Retrospective Undergrounding

Where the standard cable alignment is not practically available for retrospective
underground areas, the cable centre line shall be relocated to a centreline of 2.7 m from
the property line (i.e. the standard pole and trees alignment).

The correct property line shall be identified by survey and where there is any doubt as
to its correct location, the required directions shall be obtained from the relevant authority.

Where existing overhead electrical apparatus (poles) impedes the installation of


underground electrical apparatus (cables) in the 2.7 m alignment, approval may be
requested to install the cables on the opposite side of the road in the standard cable
alignment.

Where the poles and trees alignment is not available, special arrangements will need to
be determined and directed by Horizon Power’s Asset Management support group.

Last review: October 2018 DM#


SECTION 9
Page 9-1

9 TRENCHING AND EXCAVATION


9.1 General

All excavation work shall be carried out in accordance with the requirements of:

 WorkSafe WA Code of Practice – Excavation

 Working near Horizon Powers’ Underground and Overhead Electrical Networks


manual

 FI 6.4 Excavation Work and Directional Drilling

Trenches shall be excavated to a width sufficient for satisfactory and safe working
conditions.

Excavations shall provide the specified minimum cover so as to avoid damage or loss of
support to, obstacles such as pipes, drains, cables and other utilities and services.

The excavated area shall be reinstated in accordance with section 16 of this manual.

Note: The use of a dedicated safety observer will be required when excavating with
a machine in the vicinity of live or de-energised underground cables or ground
mounted electrical apparatus.

9.2 Blasting

On occasions blasting operations may be undertaken for excavation in rock, limestone


and clay.

Blasting is not permitted within 30 metres of other utilities and where the blasting will
affect their equipment.

Handling and use of explosives for blasting operations shall be carried out by, or under
the direct supervision of, a licensed shot-firer.

Adequate warning signs shall be displayed and all precautions against flying material
taken by the use of pegged or weighted blasting mats or similar aids

Blasting shall be limited in built up areas and shall only take place when all nearby
building occupants have been notified in writing and all buildings have been thoroughly
inspected, photographed (where required) and their condition recorded.

Note: Contractors shall pay for any damage or injury caused by blasting.

9.3 Excavated Materials

In built up areas where permitted by the relevant authorities and where practicable,
reusable top layers of excavated material such as lawns, pavers, topsoil, etc. shall be

Last review: October 2018 DM#


SECTION 10
Page 10-2

neatly stacked on one side of the trench and the bottom layer of soil shall be stacked
separately on the opposite side of the trench.

Some Local Government Authorities require all excavated materials, including paving
materials to be removed permanently from site to enable continued pedestrian access
without having to walk on the road and reduce the potential for vandalism. Unsuitable soil
shall be disposed of and graded backfill brought in.

No excavated material shall be placed, or encroach, on private property without the


written approval of the owner.

In built up areas, excavated soil shall be covered with tarpaulins or similar protection if
weather conditions will cause soil to be washed or blown away.

10 DIRECTIONAL DRILLING
10.1 Installation Principles

Directional drilling is becoming the preferred method of installation for underground works
due to improvements in technology and minimum installation disruption.

Conduits and cables shall be installed in accordance with the approved construction
drawings.

In general, the following principles shall apply:

a) Each cable shall be installed in a single way conduit.


b) Cable and conduit installations shall be installed between 900 mm minimum
depth and 1500 mm maximum depth unless other requirements of this
document (e.g. rail crossings) or local site conditions apply.
c) Cable spacing’s shall meet the requirements of Drawing R58 of the Distribution
Construction Standards Manual, or as designed for alternative installations.
d) Conduits installed by directional drilling shall not require additional cable
protection covers or cable marker tapes.
A maximum of two LV cables of 185 mm², including streetlight cables can be installed in
a common directional drilling bore if there will be no tee or service joints along the
cables.

One 35 mm² HV transformer cable and one LV cable of 185 mm² or less can be installed
in a common directional drilling bore if there will be no tee or service joints along the
LV cable.

Multiple high voltage feeder cables (185 mm², 240 mm² or 400 mm²) shall not be
combined into a single directional drilling bore.

Separate directional drilling bores shall be used between 900 mm minimum depth and
1500 mm maximum depth. Cable spacing shall meet the requirements of Drawing R58
of the Distribution Construction Standards Manual.

Last review: October 2018 DM#


SECTION 10
Page 10-3

10.2 Drilling

 During construction, continuous monitoring and plotting of the pilot drill and back
reamer progress shall be recorded to ensure compliance with the required
alignment and installation depth. Refer to Field Instruction Manual FI 6.4
Excavation Work and Directional Drilling. The monitoring may be accomplished
either by manual plotting based on the location and depth readings provided by
the tracking system or by computer-generated track logs fed by this information.
The tracking system shall provide information on:

a) Clock and pitch.


b) Alignment and Depth.
c) Position (x-y).
d) Azimuth - is defined as the direction of cable where a walkover is not
possible.
The bore logs shall show a depth and bore position from a known boundary every 3m
along the bore line. These records shall be made available to Horizon Power
electronically as a permanent record.

To prevent collapse of the borehole, drilling mud or similar material rather than just water
shall be used for both drilling and back reaming operations.

Drilling, back-reaming speeds and fluid flow shall be set to ensure spoil is removed
without putting unacceptable pressure on the surrounding soil (e.g. surface humping).

During conduit and/or cable installation, pull-back tension shall be set so as to not exceed
conduit/cable manufacturers’ maximum pulling tensions.

Note: See Appendix B or Manufacturers’ recommendations for maximum pulling


tension for various cable types and sizes.

10.3 Drilling Fluids Management Plan

A drilling fluids management plan shall be completed prior to the commencement of


directional drilling work. The plan shall contain the following:

a) Method of slurry containment.


b) Method of recycling drilling fluids and spoil if applicable.
c) Method of transporting drilling fluids and spoil off site.
d) Drilling fluid pressures.
e) Measures to contain and clean the affected area for inadvertent return of
drilling or hydraulic fluids.
f) Measures to adequately clean-up of surface seepage of drilling fluids and
spoils.

Last review: October 2018 DM#


SECTION 11
Page 11-4

11 PLOUGHING
1.1.11.1 Ploughing

Ploughing technology allows cables to be ploughed into the ground with an envelope of
clean backfill sand. Ploughing equipment has the capability of installing cables in the
following arrangements:
o Three single core cables (not twisted) in flat or trefoil (triangular)
formation. As a minimum, cores must be transposed at every drum
change.
o Triplex (twisted).
The cable configuration must be surrounded with clean sand that is free of rocks and
other hard formations:
o 150 mm underneath the cable
o 50 mm on either side of the cable
o 300 mm above the cable
Lay orange marker tape over the clean sand, as described in the Marking the ploughed
cable route section, below.
Fill the trench and compact to ground level with remaining material (ensure that stones
and rocks have been removed).

Last review: October 2018 DM#


SECTION 11
Page 11-5

Marking the ploughed cable route


Permanent above-ground cable markers must be installed along a cable route as
described in Table 1 below.

Table 1 – Cable Marking Requirements

Marker tape Above


required? ground
Alignment category Description (300 mm cable
above markers
cables) required?
Install cable at a depth of
Cable within the standard 850 mm. Use orange
A Yes No
0-500 mm alignment marker tape above
cable.
Install cable at a depth of
Cable within the 2.4 – 3.0 850 mm. Use orange
B Yes No
m alignment marker tape above
cable.
Cable outside road reserve Install cable at a depth of
(in remote area where 1200 mm. Use orange
C there are no other services marker tape above Yes Yes
or infrastructure in the cables and above
vicinity) ground cable markers.

When markers are required (per Table 1, above), they must be placed:

 on either side of the road at the crossing point


 wherever a cable crosses a boundary (e.g. road reserve property boundary, etc)
 and as close as possible to the cable installation
For cables in paddocks and open spaces:

 place markers so that the impact or damage to agriculture (including livestock) is


 kept to a minimum
 place markers at the boundaries if a cable has to cross a paddock
Markers should also be placed:

 to signify a change in direction of the cable route


 so that adjacent markers are visible from each other
 at a maximum distance of 150 m apart

Last review: October 2018 DM#


SECTION 12
Page 12-6

12 CABLE LAYING
12.1 Drum Mounting and Inspection

Prior to installation of cables, the following shall be carried out:

12.1.1 Inspection prior to installation:

Following removal of the drum battens or transport protective covering and prior to
commencing cable installation, check:
a) each drum for transport damage;
b) integrity of manufacturer’s seals on inner and outer cable ends;
c) condition of armouring, serving and sheath, particularly damage from drum
batten nails;
d) Mechanical damage, corrosion and/or leakage of impregnating oil (where
applicable).
If the cable is found to be defective, it shall not be installed and arrangements made for
it to be returned to the supplier for replacement.

12.1.2 Preparation for installation

Each drum should be mounted on jacks, cable trailer or cable stands so


the cable is preferably pulled from the top and always in the direction
opposite to that indicated by the arrow on the drum;
Lighter cables may be laid by mounting the cable drum on its side on a
truck-mounted turntable and laying the cable directly into the trench;
Prior to removing the cable drum battens, ensure the drum-spindle is level and that the
drum turns freely;
If it is necessary to roll a drum into position prior to mounting, ensure the drum is rolled
in the direction indicated by the arrow on the drum;
Cable drums should be positioned in line with the direction of cable pull;
As an alternate to a fixed mounting for the cable drum, cables may be rolled directly into
a trench from the drum mounted on mobile plant (e.g. excavator) moving along the trench.

Sealed cables may contain methane (a flammable gas)


The cable manufacturing process produces methane inside the
WARNING cable.
Where a cable has fitted with a heat shrink end cap & pressure
relief valve before the cable is cut, any pressure build up shall be Cable end cap
bled by inserting a pin into the valve until no further gas is heard to with pressure
be escaping. relief valve

Last review: October 2018 DM#


SECTION 12
Page 12-7

12.2 Protection of Cables during Installation

Cable should be fed from the top of the drum to prevent cable
slack.
When pulling from large drums, the cable should be supported
between the drum and the trench with a suitable ramp or rollers
to prevent stressing the cable;
Cables shall be kept clear of abrasive surfaces by suitable means, e.g.
rollers, etc. to prevent any damage to the cable sheath. The cable shall
be placed in the trench without sustaining abrasion damage and without
allowing rocks or debris to fall into the trench that could also damage the
sheath integrity (allowing termite attack);
Precautions should be taken to prevent the drum from over-rotating and allowing cable
slack. A suitable braking mechanism should be installed, either in the form of a drum
flange drive or an effective friction brake, e.g. plank brake shoe. Where brake shoes are
utilised, care shall be taken to ensure no damage occurs to the cable “Z” (inner) end that
protrudes through the drum flange;
On long cable runs or where a cable has significant direction changes (both horizontal
and/or vertical), rollers shall be used to ensure minimum pulling or bending of radii are
maintained to ensure a smooth pull and avoid damage to the cable;
Cables which are pulled into position by a winch, shall use suitable cable
stockings and swivels to prevent damage; and
When installing cable by directional drilling, it is essential the cable sheath is not
damaged, since damage to the outer jacket may cause sheath faults or compromise the
integrity of the cable termite protection.

12.3 Cable Installation methods

There are numerous methods by which the cable can be pulled into the final installed
position. Generally, the most economical methods employ power winches.

If considering only those pulling methods using mechanical winches, then there are four
distinct methods:

12.3.1 Stocking Pulling


Cable pulling using a steel mesh cable stocking is probably the most common form of
installation for cables up to and including 33 kV. The cable stocking is slipped on to the
end of the cable and the winch rope attached.

Application of pulling tension locks the stocking onto the cable sheath. Care shall be
taken to ensure the manufacturer’s recommended pulling tensions are nor exceeded as
cable damage will result.

12.3.2 Installation using Pulling Eyes


The strength of the cable sheath limits the length and size of the cable that can be pulled
by stocking pulling. For long and large cross section cables, pulling-eyes can be fixed
directly to cable conductors for pulling the cable.

Last review: October 2018 DM#


SECTION 12
Page 12-8

12.3.3 Bond Pulling


When likely pulling tensions may exceed the tension limit of the cable, straight end pulls
may have to be replaced by bond pulls. In this method, the cable is lashed to the pulling
rope at close intervals (e.g. every half metre for a distance of 20 metres or more) to
distribute the strain of the pulling.

Mechanical padding is required to protect the cable sheath from damage at the lashing
points.

12.3.4 Armour Pulling


This system uses the armour wires of a cable as the pulling medium. The armour wires,
left extended past the end of the cable, are formed into a pulling eye and the winch rope
attached to it.

Caution: This method shall not be used for XLPE cables.

12.3.5 Mechanical Assisted Installation


For long or difficult cable installation or large cable sizes, mechanical
assistance can be used to insist installation. Typical methods include:

a) One or more cable “caterpillars” installed mid or multi-point


along the cable route to provide intermediate cable thrust;
b) Power assisted driven cable drums.

12.4 Cable Pulling Tensions

Cable pulling tensions shall not exceed the manufacturer’s recommendations.

The maximum recommended pulling tensions when using stocking grips to install un-
armoured XLPE cables are shown in Appendix B.

The trench or conduit line should be set out so that any necessary deviations from a
straight line occur over the largest possible radius. When pulling cable into conduits
incorporating bends or pulling rope rollers, lower maximum pulling tensions may be
necessary to avoid the wire pulling rope cutting into the side of the conduit.

Any winch used to pull cables shall have either a facility to automatically limit the pulling
tension applied to a cable (a tension fuse) or a continuous reading dynamometer
incorporated in the pulling arrangement to enable the actual pulling tension to be
monitored.

In special circumstances, cable pulling pits may be required at significant changes in


cable route direction. Required pits shall be indicated on the design drawing.

On long or complicated cable installations, intermediate cable feeder equipment (or


“caterpillars”) may be required to limit pulling tensions.

Last review: October 2018 DM#


SECTION 12
Page 12-9

12.5 Pulling Speed

To avoid damage due to overruns, the cable should be pulled just fast enough to keep
the drum rotating smoothly.

Higher speeds are possible when pulling small cables into straight trenches or conduits
with good conditions at the feeding and pulling ends;

Drums with long lengths of cable should not be rotated rapidly as overrun can cause
cable damage if pulling is slowed or stopped suddenly.

12.6 Cable Bending Radii

The permissible bending radii of all cables are given in Appendix B. No twists, knots or
kinks are permitted.

Where a 3x1 core HV cable is to be laid to transformers or switchgear, the three twisted
cores can be separated at termination location (e.g. Triplex style) into three individual
cores to reduce the minimum bending radius required.

12.7 Maximum Number of Cable Joints

Underground cable joints between terminal points shall be kept to a minimum. For
information on the maximum numbers of through joints that may be installed in any
section of cable, refer to the Underground Distribution Scheme (UDS) Manual,
Section 9.2.8.7.

12.8 Installation of Cables on Poles

Where cables are installed onto termination poles, the cable shall be
installed as directly as possible from the cable trench to the pole. No
spare loop of cable is required to be installed at the base of the pole,
as it is better to joint in a new section of cable if a termination failure ty
per y
Proundar
occurs. The section of cable off the standard alignment shall be Bo

protected by cable slabs and marker tape.

12.9 Bedding and Backfill

To protect the cable sheath, all cables shall be firmly and uniformly bedded on sand free
from rocks or other hard formation. The cable shall be surrounded with a thickness of
sand prior to backfilling, bottom by 150 mm and two sides by 100 mm, top by 300 mm as
shown in drawings R 55, R 56, R 57, R 58, and R 59 of the Distribution Construction
Standards Manual. The upper 300 mm of the backfill to final ground level shall also meet
the local government authority’s requirements.

12.10 Depth of Cover for Cables

The depth of cover over cables shall not be less than 850 mm. The depth of cover shall
be increased as required to ensure that cable joints will have the required depth of cover.

Last review: October 2018 DM#


SECTION 13
Page 13-10

12.11 Cable Protection Covers and Marker Tapes

The cable covers shall comply with the requirements of clauses 3.11.3.3 of AS/NZS
3000:2000 and if required, cable covers and PVC marker tape shall be laid at the required
levels, as shown in drawing R 51 Distribution Construction Standards (Placement of Duct
beneath Road Crossings)

Where more than one cable is installed, the PVC maker tape or cable cover must be wide
enough to fully cover the cables, otherwise additional maker tapes and covers shall be
installed.

Additional cable protection shall:

1. be placed maximum 75 mm above the wiring system

2. be not less than 150 mm wide

3. overlap the wiring system by at least 40 mm on each side

4. consist of one or a combination of the following:

a) precast concrete slabs with a minimum thickness of 40 mm and a classification


of not less than grade 20 degrees in accordance with AS 3600
b) a continuous concrete pour having a thickness of not less than 75 mm
c) fibrous cement slabs having a thickness of not less than 12 mm
d) bricks (slabs) manufactured specifically for the protection of electric cables
e) polymeric cable cover strip (complying with AS 4702)
f) Other materials that offer the same degree of protection as the materials in
items (a) to (e) above.
Note: Conduits installed by directional drilling shall not require cable protection
covers and marker tapes.

12.12 Sealing of Cables

To ensure water cannot penetrate into the cable conductors or insulation, ends of cables
shall be kept sealed. On completion of the cable pulling, any damaged or non-waterproof
pulling eyes or sealing end caps should be removed and the cable resealed, unless it is
to be terminated immediately.

Where cables have been cut following installation, both the installed and drum ends shall
be sealed immediately, except where the cable is to be jointed immediately

13 CONDUITS
13.1 Application

Conduits complying with Australian Standard AS 2053 shall be used to protect cables
where they are installed in the following situations:

Last review: October 2018 DM#


SECTION 13
Page 13-11

a) in easements;
b) exit cables from a distribution substation that is set back from road or property
boundary;
c) near retaining walls where there is a danger of cable installation damage due
to foundation subsidence;
d) crossing roads;
e) crossing water courses and drains;
f) crossing high pressure gas pipelines;
g) crossing under railway lines or restricted access areas such as airports; and
h) Within bridge crossings.

13.2 Requirements for cables installed outside normal alignments

Where cables are installed outside the 0-500 mm standard alignment or the 2400–
3000 mm alignment as approved by Horizon Power for street installation, conduits are
NOT required. The cables shall be direct buried, laid in accordance with and protected
with cable slabs as shown in Drawing in R 51 Placement of Duct beneath Road Crossings
in the Distribution Construction Standards Manual.

13.3 Encased Conduits

In some locations PVC conduits may be encased in concrete pipes, steel pipes or
concrete encased steel pipes. Unless approved by Horizon Power, cables shall not be
installed directly in concrete conduits due to potential damage to sheaths during
installation.

13.4 Sealing of Conduits

All conduits, including spare conduits, shall be effectively sealed at the ends and at
couplings;

Sealing of conduits is required to prevent the ingress of water and any foreign material
that may cause blockage or flooding of cable pits, basement-type substations and switch
rooms;

Wherever possible, suitable conduit plugs or covers should be used for sealing of
conduits in lieu of taping or other makeshift arrangements.

Conduit joints and couplings shall be installed and sealed in accordance with the
manufacturer’s instructions.

13.5 Installation requirements for Conduits

Where conduits are installed in excavations, they shall be installed:

a) with a minimum cover of 850 mm to the top of the conduit;


b) not more than 1100 mm cover as approved by Horizon Power;

Last review: October 2018 DM#


SECTION 13
Page 13-12

c) where all cables in the trench are all installed in conduits, excavated soil may
be used for bedding and backfill, provided it is free of organic matter and rocks
of 50 mm diameter or larger;
d) normally in flat, horizontal formation for up to four cables, thereafter in tier
formation;
e) for road crossings, in accordance with Section 6.6 – Road and Vehicle
Crossings;
f) sealed with suitable end caps;
g) with approved ”draw wires” provided in every conduit;
h) When installed prior to the main cable trenching, installed with marker tape
300 mm above the conduit. The marker tape shall be brought out to ground
level at each end, with the conduit end position also being marked with a peg.
The most economical method shall be used to install conduits across roads. Subject to
cost, boring is preferred for single or double conduit crossings, where conduits of 100 mm
size or larger are required.

For locations where more than two conduits are to be installed together, open excavation
methods may be used for crossing roads.

13.6 Pulling Cables through Conduits

Care shall be taken to avoid damaging the outer sheath of the cable where it enters and
leaves the duct. Single core bundled XLPE high voltage cables are particularly
susceptible due to their uneven shape and thin outer sheath.

To prevent future cable failure a suitable lubricant should be used to reduce the friction
between the cable and the duct.

A tapered or belled entry shall be used at the entry end of ducts during pulling to prevent
damage to cable.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 13

14 CABLE JOINTING AND TERMINATIONS


14.1 General

Underground cable jointing is based on the following “Principles of Good Cable Jointing”:

1. Safety shall never be compromised;


2. Jointing pits should be large enough to allow jointers to work freely;
3. Before joining any cable it must be positively identified by approved testing
methods and marked at both ends of the cable;
4. Water barrier within the cables to checked prior to joining the cables:
5. The correct kit for joint and cable size shall be selected;
6. Manufacturers’ jointing instructions shall be followed unless practicalities suggest
a variation. Where fixture torque are recommended, apply those with torque
wrench;
7. Accurate measuring, cutting, stripping and torque settings and workmanship shall
be in accordance with the manufacturer’s instructions;
8. Ground covers shall be used to keep tools & equipment and jointing components
clean throughout the job –. (Ensure joints don’t get contaminated with surrounding
soil, sand, or moisture);
9. Ensuring enough spare cable so that the cable stripping distances are suitable for
lay of cable (after cable is manipulated to correct position) to complete the joint(s)
in accordance with the manufacturers requirements;
10. All cable ends are to be sealed after cutting. Where they are not sealed they are to
be considered suspicious and checked for water ingress prior to use.
11. Housekeeping – keep the work environment clean by placing used packaging in
box as work progresses.

14.2 Cable Joint Excavations

There is no standard size for a jointing pit, however joint sizes vary and therefore the size
of the pit in which to carry out the jointing will vary.

To facilitate the joining of Cables and to reduce the impacts on the health and safety of
the employee/contractor completing the joints, as a minimum, a pit in the trench should
be excavated to the following dimensions:

a) 2 meters wide;
b) 2 meters in either direction (4 meters long) of the joint; and
c) At the same depth as the trench.
Depending upon the depth of the trench / lay of cable; an additional step should be to
excavate in the pit to either side of the cable joint to allow for ease of access and facilitate
the joiner working on the joint. Fig 1 illustrates the concept.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 14

Figure 4 – Cable joint pit dimensions

The sides of the pits should be covered with tarpaulins or similar to prevent soil from
being dislodged while working in the pit.

14.3 Jointing

Before joining any cable it must be positively identified by approved testing methods and
marked at both ends of the cable.

Water barrier within the cables must be checked prior to joining the cables to ensure no
moisture has penetrated into the cable. (Moisture barrier turns green when water is
present) If moisture is detected, the cable must be strip the cable back to the point where
no moisture is present.

All jointing equipment shall be installed in accordance with the manufacturer’s instructions
supplied with the equipment kit to which they relate.

The use by date of the jointing equipment shall be checked prior to use. Where the used
by date has expired, the jointing equipment shall be removed from service and returned
to the depots store for disposal.

Ensure no conductive material is left on the XLPE cable. If necessary remove any
remaining semi-con material with abrasive paper (sandpaper) then clean with a solvent
wipe.

Note: Never use a knife to cut the semi-con. This can create a void and could result
in the delaminating of the XLPE screen below the ring cut. When stripping the
semi-con screen and you score the XLPE insulation, sandpaper the damaged
area to smooth out the void/irregularities

The installer identification tags are required on all joints. They shall be marked and fitted
adjacent to the joint or termination equipment as per drawing R39 in the Reference
section of the Distribution Construction Standards Manual.

All 22KV rated cables requiring transition joints shall use HU28 or HU29 joint assembly
as appropriate.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 15

Shear bolts ends shall be filed back to prevent the sharp edges creating a stress point
within the cable joint.

14.4 Termite Proofing

Termite proofing shall be installed over all XLPE to XLPE HV straight joints.

The preferred method of termite proofing shall be of the stocking type, which is fitted
over the cable prior to joining. Where the stocking type is not available, termite sheeting
may be used in conjunction with heat shrink outer seal of the entire termite protection
area. Full heat shrink sleeve as provided in kit or zip shrink if jointing area is restricted

On completion of the joint, the termite stocking can be moved over the joint with a
minimum cable overlap of 200mm. The ends of the termite stocking shall be sealed with
brass roll springs as provided within termite protection kit.

The remaining overlap of termite sheeting over the joint body should be secured evenly
in intervals every 150mm to 200mm with the use of 5mm stainless steel cable ties

14.5 Terminations

All Low Voltage terminations shall be completed in accordance with Part 5 - Low
Voltage Underground of the Distribution Construction Standards Manual.

Where no termination drawing exists, all equipment shall be installed in accordance with
the manufacturer’s instructions supplied with the equipment kit to which they relate.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 16

14.6 Working Ends

If a cable for a future scheme/connection is laid from a universal pillar, kiosk or a low
voltage frame unit in an existing scheme, then the remote end of this cable must not be
left on a cable drum.

The cable must be made off, insulated to approved methods and placed in a mini pillar
with its top painted white.

In areas where it is not possible to install a pillar, then the remote end of this cable must
be made off in a joint/shell located in Horizon Power’s cable alignment. When this
method is utilised, the location of the joint/shell (e.g. distance from closest property
boundary) must be recorded accurately in GIS.

15 TESTING AND COMMISSIONING


Testing and commissioning shall only be carried out by qualified and Horizon Power
authorised personnel and in accordance with:

 Horizon Power’s Network Testing & Commissioning Standards

 VLF Testing of HV Cables manual

Available on Power Link and the Horizon Power external web site, under Network
Contractors.

The Tester-in-Charge shall be responsible for carrying out tests in accordance with
these standards and recording all test results and additional comments where relevant.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 17

16 REINSTATEMENT
16.1 General

The excavated or disturbed land shall be restored to its original condition. Backfilling and
reinstatement of road verges and vehicle crossings as necessary shall be completed
within three working days from the time the cables are laid and jointed.

Road reserves and all work sites shall be levelled and left clean and tidy. Debris, trees,
stumps and excess soil dug from the excavation shall be removed from site when trench
backfilling has been finished.

All materials, stakes, plant and equipment used during installation shall be removed and
all work sites left in a safe condition.

All material off cuts, waste materials and general rubbish shall be removed from site and
disposed of in accordance with the Local Government Authority’s requirements.

The initial backfill over the bedded cables shall be carried out in accordance with
Section 12.9 – Bedding and Backfill of this manual.

Trenches shall be backfilled, reinstated and compacted to their original level and/or in
accordance with the requirements for footpaths by the Local Government Authority.

16.2 Compaction

Spoil or other approved filling shall be carefully placed in layers into the trench. Stones,
rocks and paving material shall be removed from site and not used as backfill.

All backfilling shall be compacted to a minimum 90% of the density as the surrounding
soil in accordance with Horizon Powers’ Network Instruction Manual: FI 5.23 Soil
Compaction Testing Requirements to prevent future subsidence.

All results shall be compiled on the “Compaction Test Certificate”

16.3 Levelling

Backfilled excavations shall be levelled so as not to constitute a hazard and shall be to


the same as the original unexcavated land.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 18

16.4 Restoration of Surface

On completion of any operations affecting pavements or constructed surfaces, except


Greenfield subdivision the pavements or constructed surfaces shall be restored in
accordance with the Restoration and Reinstatement Specification for Local Governments
in Australia Published by the Institute of Public Works Engineering Australia, which is
available at Traffic/Road-works/Working on main roads from Main Roads WA’s web site
or through the Institute of Public Works Engineering Australia (WA Division) on the
IPWEA website.

Restoration of surface includes restoration of all type of footpath materials, e.g. bitumen,
brick paving, liquid limestone, etc.

Where cement footpath slabs have been removed to allow cable trench excavation, they
shall be replaced and reinstated in accordance with the Local Government Authority’s
requirements unless otherwise directed by the Horizon Power.

17 DAMAGE TO PROPERTY
17.1 General

In all areas where cable installation work has been carried out, except as approved by
Horizon Power, property or services damaged shall be repaired or replaced as soon as
possible after making safe.

Fences around areas holding livestock shall be secured at all times and if damaged during
construction shall be repaired or made safe immediately to prevent the stock from
straying.

Damage to reticulation systems and underground services that are disturbed or damaged
shall be restored to working order.

Trees planted in the road verge shall be protected as far as possible. Tree limbs
interfering with the construction shall be removed appropriately by pruning and sealing
and the trees left in a reasonable condition.

Inspection shall be done of any structures located along the cable trench route prior to
the commencement of works and arrangements shall be made to protect these structures
if there is a possibility of damage or hazards occurring.

Horizon Power’s CPM shall be notified in all cases of such damage or hazards occurring.

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 19

18 PILLARS AND PITS


18.1 General

Where approved by Horizon Power, service pillars shall be located within the lot
boundaries at the corner, adjacent to common boundaries where possible, refer to the
Utilities Code of Practice for Western Australia for Road Reserve allocations.

Uni Pillar Mini pillar

Horizon Power Unmetered Pit

Last review: October 2018 DM#


APPENDIX A - Service Alignment, Depth And Colours For Greenfield Site
Page 20

APPENDIX A - SERVICE ALIGNMENT, DEPTH AND COLOURS FOR GREENFIELD


SITE

850mm

Source: Figure B2 – Utility Provider Code of Practice

Note: The minimum depth of cover required for Horizon Power’s cables is 850 mm.
However, the depth of cover of cables in nominal cable alignment shall be increased as required
so that cables joints will have the necessary depth of cover.

Standard Service and Pipe Colours:

Utility Service and Pipe Colours


Gas Yellow pipe or Yellow Striped pipe

Electrical Orange pipe or Orange Striped black pipe or Orange


electrical tape for directly buried black sheathed cable
MRWA
a) Traffic Signals a) Orange pipe
b) Roadside Lighting b) Orange pipe
c) ITS c) Orange pipe (power) and White pipe
(communications)
Telecommunications White pipe or black pipe with White Stripe

Water Blue pipe or Blue Striped pipe

Sewerage Cream pipe or Grey pipe or Cream/Grey Striped pipe

“Third Pipe”/Effluent Purple pipe


Reuse

Note: Colours of pipe relate only to PVC and polyethylene pipe and other materials could be used,
particularly in older established areas unless otherwise stated. Some services can be buried
directly in the ground and not in conduits.
WARNING In existing areas, pipes and conduits of other Utilities may not
conform to these standards

Last review: October 2018 DM#


APPENDIX B – Cable Installation Data
Page 21

APPENDIX B – CABLE INSTALLATION DATA


Typical cable reference data, including data relating to cable installation, is shown below.
Type of Volts No of Cable Cond’r Drum Nominal Nominal Maximum Pulling Tension (kN) Minimum Bending
Cable (kV) Cores Size Material Length Cable Overall Radii
(mm 2) (m) core Cable (Bundle/One Cable)
Dia Dia
(mm) (mm) 1 x Sheath 3 x Sheath Conductor Pulling Set
stocking stockings grip (mm) (mm)
over all cores one on each (per core)
core
(per core)
Transformer 33 3x1c 50 Al 250 34.4 80 (3c) 7.5 7.5 2.5 1120/860 740/520
cable Triplex
HV Feeder 33 3x1c 95 Al 250 37.9 94 (3c) 9.8 13.5 4.7 1220/950 820/570
Cable Triplex
HV Feeder 33 3x1c 185 Al 250 42.8 97 (3c) 11.1 15.3 9.2 1390/1070 920/640
Cable Triplex
HV Feeder 33 3x1 630 Cu 500 30.9 65.4(1c) 7.95 1640 980
Cable
HV Feeder 33 3x1 1000 Al 500 39.7 72.2(1c) 8.86 1805 1085
Cable
Transformer 12.7/22 3x1c 35 Al 250 27 69 (3c) 5.2 5.2 1.75 870/680 580/410
cable Triplex
HV Feeder 12.7/22 3x1c 185 Al 250 36.4 87 (3c) 9.4 4.4 9.25 1210/930 810/560
cable Triplex
HV Feeder 12.7/22 3x1c 240 Cu 250 38.7 95 (3c) 10 4.6 16.8 1310/1010 870/610
cable Triplex
HV Feeder 12.7/22 3x1c 400 Al 250 48.8 105 (3c) 12.6 5.9 20 1480/1140 980/690
cable Triplex
LV Feeder 0.6/1 1x3c 120+ Al 250 NA 38.7 5.2 NA NA 565 375
cable Wave N
LV Feeder 0.6/1 1x3c 185+ Al 250 NA 46 7.7 NA NA 880 590
cable Wave N
LV Feeder 0.6/1 1x3c 240+ Al 250 NA 51 10 NA NA 970 650
cable Wave N
Service 0.6/1 1x3c 25+ Cu 250 NA 26 2.2 NA NA 220 220
Wave N
Street 0.6/1 1 10+ Cu 1000 NA 13 1.0 NA NA 100 100
Lighting Wave N
Street 0.6/1 1 16+ Cu 1000 NA 14 1.5 NA NA 120 120
Lighting Wave N

APPENDIX C - DIAL BEFORE YOU DIG SERVICE


C1 General

Dial Before You Dig Service (sometimes referred as One Call


System) provides a single National point of contact between
excavators and utilities that own assets including buried pipes and
cables, as well as the owners of other buried services.
This free service makes it safer and easier for people undertaking excavation activities.

C2 Further information

For further information on Dial Before You Dig, telephone (08) 9424 8116 or (08) 9424
8117 during office hours (Perth). Further information on Telstra assets can be obtained
directly by telephoning 1800 806 246.

Last review: October 2018 DM#

You might also like