Location &

Si.No Pic Action By Current status


Description

Zone-3 Departure
Soffit Grid I’-J’/9t-
Work in
1 12t Mr.Arun
progress
CJ offset to be
rectified

8t grid Mezzanine
2 beam rebar cutting Mr.Karthick Completed
& finishing

9t-E’ Gird Lift wall


blockwork pointing
3 Mr.Shivakumar Completed
& bond beam
finishing

9t/E’-D’ Mezzanine
CJ offset
slab soffit CJ offset
4 Mr.Arun rectification
& column slurry
balance
leakage

10t-E’ grid escalator


5 pit de-shuttering & Mr.Arun Pending
finishing

11t-12t/C’-D’ grid
Departure slab
6 Mr.Arun Pending
soffit De-shuttering
& tie rod cutting

Firefighting pipe
over coated with
7 ceiling paint at Mr.Rehman Pending
service corridor
11t/G’ grid
Column Slurry leaks
8 Mr.Arun Pending
12t-G’ L01-L02

Half area
CIP soffit CJ loose
9 Mr.Arun completed Half
material 11t-G’
area balance

Column
10 Honeycomb 11t- Mr.Arun Completed
10t/D’ L02-L03

Pointing work in Half area


11 Blockwork 4t-5t/G’- Mr.Shivakumar completed Half
E’ L02-L03 level area balance

Slurry lekage in
12 column 9t-J’ L00- Mr.Arun Pending
L03

Slab chipping not


13 finished 8t-9t/J’-K’ Mr.Karthick Completed
L01 level

CJ joint rectification
to be done Grid 8t-
14 Mr.Karthick Completed
9t/D’ Departure
Soffit
Slurry leakage in Half area
15 column 8t/E’-D’ Mr.Karthick completed Half
L01-L02 level area balance

Pipeline Slurry
spillage concrete to Shall be
16 Mr.Ranjith
be taken care in ensured
future

Beam bottom
plywood & Minor
17 Honeycomb Grid- Mr.Arun Pending
12t/D’-E’ Departure
Soffit

masking tape
embedded in
18 concrete to be Mr.Arun Pending
removed Grid-9t-
10t/D’-E’ CIP soffit

Beam side Bulging


19 & Plumb out 4t-G’ Mr.Sathish Pending
CIP slab

CJ loose joint to be
20 rectified. Grid-9t- Mr.Arun Pending
10t/G’-E’ CIP soffit

Slurry leakage in Half area


21 column 10t/G’ L02- Mr.Arun completed Half
L03 level area balance
Resource Requirement

1. Grinding Machine-Done
2. Grinding wheel-Reached
3. Supreme Filler Board-Not Finalised
4. Curing Compound – Received