You are on page 1of 23

Siddique

From: Mohammad A. Al-Jaber <MAMJaber@se.com.sa>


Sent: Sunday, May 18, 2014 9:14 AM
To: 'Hussain AlDarorah' (hussain.aldarorah@gasarabian.com)
Cc: Ghamdi, Abdallah A (Pipelines); Shamrani, Essa F; Qahtani, Abdulwahab A(Pipelines); Issa al asker; Mousa Al Askar; shabir; mehrajmir;
Himayoun nabi; Project Engineer Siddique; S.T. Ravi (ravi@gasarabian.com); ''FaisalAl Sunaid- GASARABIAN''
(Faisal.alsunaid@gasarabian.com); VEIPPMG (I P P & New Venture DepartmentManager)
Subject: RE: QIPP_BI 21-00051 Chemical cleaning 40" Pipeline- Abqaiq

Dear Hussain,
GAS
As per your confirmation that Chemical cleaning can be started today afternoon. Kindly, communicate with UIS about the arrangements to start Chemical cleaning
today.

Regarding the gate pass it was arranged and confirmed on Friday 16,2014 to start from Saturday ( by direct supervision by myself ) and no such thing "unavailability of
gate pass" mentioned by UIS (Mr. Shabir).

Regards,

Mohammed Aljaber

From: shabir [mailto:shabira@ucsme.com]


Sent: Saturday, May 17, 2014 2:01 PM
To: mehrajmir
Cc: hussain.aldarorah@gasarabian.com; Ghamdi, Abdallah A (Pipelines); Shamrani, Essa F; Mohammad A. Al-Jaber; Qahtani, Abdulwahab A (Pipelines); Issa al asker; Mousa
Al Askar; Himayoun nabi; Project Engineer Siddique
Subject: Re: QIPP_BI 21-00051 Chemicle cleaning 40" Pipeline- Abqaiq

Dear sir
With respect to the site visit undertaken on 17/5/2014 at around 11.30 hrs fallowing are the findings
KM0 receiver area
1. Installation of one MIV was going on while as other one was present on site .
2. All lateral connections not blinded either with valves or with blind flanges .
3. Tanks transported on 13/5/2014 unloaded away from designated area. Need to relocate them once Main isolation valve erection is finished . (Have time to do that once
we start )

1
Siddique

From: Hussain Al-Darorah <hussain.aldarorah@gasarabian.com>


Sent: Thursday, June 05, 2014 1:55 PM
To: Project Engineer Siddique
Subject: Fw: BI-21-00051 QIPP Pipeline Chemical Cleaning

FYI
Best regards,
Hussain Al-Darorah

From: "Mohammad A. Al-Jaber" <MAMJaber@se.com.sa>


Date: Thu, 5 Jun 2014 10:41:18 +0000
To: hussain.aldarorah@gasarabian.com<hussain.aldarorah@gasarabian.com>
Cc: Qahtani, Abdulwahab A (Pipelines)<abdulwahab.qahtani.1@aramco.com>; Ghamdi, Abdallah A (Pipelines)<abdallah.ghamdi.9@aramco.com>;
Rentz,Gordon<gordon.rentz@aramco.com>; Nasser, Mohammed M<mohammed.nasser.4@aramco.com>; Shamrani, Essa F<essa.shamrani@aramco.com>; EVSVP (Energy
Trading & Ventures Senior VP)<EVSVP@se.com.sa>; EVIRED (IPP & Renewable Energy Sector ExecutiveDirector)<EVIRED@se.com.sa>; IPPPFDV (Independent Power
ProducersProjects Followup Division Manager)<IPPPFDV@se.com.sa>; S.T. Ravi(ravi@gasarabian.com)<ravi@gasarabian.com>; ''FaisalAl Sunaid -GASARABIAN''
(Faisal.alsunaid@gasarabian.com)<Faisal.alsunaid@gasarabian.com>
Subject: RE: BI-21-00051 QIPP Pipeline Chemical Cleaning

Dear Hussain,
GAS

As per our discussion with Aramco and the outcome of the second chemical train, SEC is in apposition to agree that the ongoing third chemical
train of chemical cleaning will be the last train. reference to this proceed for drying the gas line after third chemical train finish and prepare the
line for final to release the gas ASAP.

We appreciate all the efforts by everybody (specially from Aramco)to make the final step happened.

Mohammed Aljaber
0503204309

From: Shamrani, Essa F [mailto:essa.shamrani@aramco.com]


Sent: Wednesday, June 04, 2014 3:37 PM
To: Mohammad A. Al-Jaber; hussain.aldarorah@gasarabian.com

1
Cc: Qahtani, Abdulwahab A (Pipelines); Ghamdi, Abdallah A (Pipelines); Rentz, Gordon; Nasser, Mohammed M
Subject: RE: BI-21-00051 QIPP Pipeline Chemical Cleaning

Dear Gentlemen,

It is good to hear that the third chemical train was launched today at 1415 hours. Please arrange the following in order to have this run as a final
and getting the solid loading less than 5 Grams/Liter:
1. The launcher trap, drain & chemical manifold shall be flushed & cleaned from any remaining dirt resulted from the second batch. The
manifold has to be dismantled and cleaned separately where it was blocked several times during last sampling operation.
2. Arrange with a Saudi Aramco approved Laboratory to do the sampling analysis this time and we will double check it at our laboratory
3. The run is expected to be received during the coming weekend. Therefore, SEC has to decide from now the need of the fourth chemical
run if the solid loading is more than 5 Grams/liter in the third chemical run. This is in order to be ready and avoid any further delay.

--
Regards,
Essa F. Al-Shamrani, CMRP
QIPP Project Support
Tel: (013)-572-6954
Mob: 050-480-9745

From: Mohammad A. Al-Jaber [mailto:MAMJaber@se.com.sa]


Sent: Tuesday, June 03, 2014 8:29 PM
To: hussain.aldarorah@gasarabian.com
Cc: Qahtani, Abdulwahab A (Pipelines); Ghamdi, Abdallah A (Pipelines); Rentz, Gordon; Shamrani, Essa F; Nasser, Mohammed M; Ravi; Faisal Sunaid; ''Sainath''
(sainath@gasarabian.com); EVSVP (Energy Trading & Ventures Senior VP); EVIRED (IPP & Renewable Energy Sector Executive Director); IPPPFDV (Independent Power
Producers Projects Followup Division Manager)
Subject: RE: BI-21-00051 QIPP Pipeline Chemical Cleaning

Thank you Hussain for clearing this point and we appreciate your continuous effort .

Kind regards,

Mohammed

2
QIPP_BI 21-00051 40" PIPELINE
43KM ABQAIQ - QUARAYYAH

CHEMICAL CLEANING

DETAIL PROCEDURE

Document No: DP-01

Revision No. 00

DOCUMENT APPROVAL
Signature Date
Shabir Bhat
Submitted by UIS:

Reviewed by GAS:

Approved by SA PTSD:

Approved by SA CSD

Approved by SA PMT:

May 2014

CONFIDENTIALITY NOTICE
This document and any attachment are confidential and may be privileged or otherwise protected from
disclosure. This document is solely intended for information only and may not be copied or distributed
without the expressed consent of UIS.
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

REVISION RECORD
Document No: DP-01

Rev. No.
UIS Client Date Section(s) Page(s) Reason
0 0 11 May 2014 Initial Submission
 For Review and Approval

Page 2 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

TABLE OF CONTENTS
PAGE

REVISION RECORD ........................................................................................................................................ 2

1. PURPOSE AND SCOPE .............................................................................................................................. 4

2. REFERENCES .............................................................................................................................................. 4

3. RESPONSIBILITIES ................................................................................................................................... 5

4. SAFETY REQUIREMENTS ........................................................................................................................ 6

5. SITE ACCESS ............................................................................................................................................... 7

6. WORK PERMITS ........................................................................................................................................ 7

7. CHEMICAL CLEANING .............................................................................................................................. 7


7.1 Notification of Chemical Cleaning ........................................................................................................................... 7
7.2 Preparatory Works ................................................................................................................................................. 7
7.3 Equipment Layout .................................................................................................................................................. 9
7.4 Anticipated Chemical Cleaning Schedule (Forecast) .............................................................................................. 10
7.5 Cleaning Procedure .............................................................................................................................................. 10
7.6 Pipeline Chemical Cleaning Train Loading and Run Operation ............................................................................... 12

8. SAMPLING AND ACCEPTANCE CRITERIA......................................................................................... 18

9. EQUIPMENT............................................................................................................................................. 19

10. MANPOWER .......................................................................................................................................... 19

ATTACHMENT ............................................................................................................................................. 20

Attachment 1: Pressure Readings and Activity Log


Attachment 2: Action Item Check List

Page 3 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

1. PURPOSE AND SCOPE

The purpose of this scope is to describe the requirements of Chemical Cleaning of the following
pipelines which are an integral part of the project scope.

Cleaning train consisting of N-SPEC® 50/105 chemicals and diesel as diluents will be injected
into the pipeline in between series of scrapers propelled by nitrogen will be launched from
designated launcher to receiver.

Sections information:

Pipeline Section From To Pipe Dia. Length (KM)


QIPP_BI 1 Abqaiq Quarayyah 40” 41.585
21-00051 (KM 0.00) (KM 41.585)

2. REFERENCES

Scope of Work QIPP_BI 21-00051 Pipelines Chemical Cleaning

SAES-B-064 On-Shore and Near-Shore Pipeline Safety

SAEP-327 Disposal of Wastewater from Cleaning and Flushing

Saudi Aramco Safety Manual

G.I.2.100 Work Permit System

G.I.6.012 Isolation Lockouts and Use of Hold Tags

SAEP-388 Cleaning of Pipelines

G.I. 0430.001 Implementing the Saudi Aramco Hazardous Waste Code

API STD 2000 Venting Atmosphere and Low Pressure Storage Tanks

SAES-B-069 Emergency Eyewashes and Showers

GI.006.001 Notification Requirements for Incidents (Including Fires)

GI.007.028 Crane Lift: Types and Procedures

Page 4 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

3. RESPONSIBILITIES

Project Manager Provide the manpower and equipment required for the chemical
cleaning operation.

Project Supervisor Coordinate the chemical cleaning activities.

QC Inspector Inspect/verify the following:


 Setup of both Launcher and Receiver
 Verify the Type/Qty of batch injected
 Verify type of scrapers used
 Check Dew Point Log Sheet

UIS Overall Responsible for the planning and execution of the


chemical cleaning operation

GAS Arabian Services Safety Coordinator


Ensure compliance to safety requirement.

Work Permit Receiver


Receive the Work Permit and ensures compliance with the
requirements of the Work Permit.

Note: Contractor shall refer to the cleaning team consisting of personnel from GAS/UIS.

Page 5 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

4. SAFETY REQUIREMENTS

Steps Description Action By


4.1 All personnel shall be aware of emergency procedures and will attend UIS/GAS
safety/site induction meetings on a daily basis before the start of any
work commencing or as required to ensure that everyone understands
their responsibility and what to do in case of emergency.
4.2 First aid and fire protection equipment must be kept on the site UIS/GAS
(launcher and receiver) Minimum of 2 dry powder extinguishers (30lb)
shall be available on both sites.
4.3 All involved personnel on site shall wear proper protective equipment UIS/GAS
(PPE). This includes fire resistance coveralls, Neoprene, PVC or NBR
gloves or nitrile rubber, Safety Glasses and Steel Toed Shoes/chemical
resistant boot.
4.4 Prior to commencing chemical cleaning operations, warning signs UIS/GAS
indicating "Scraping On-going" shall be posted at launcher - Abqaiq
(KM 0.00) and receiving QIPP (KM 41.585) ends and along the
pipeline section corridor particularly at road crossings. Barriers shall
indicate the limits of pipeline leaning area. Warning signs, in English
and Arabic, shall be placed in prominent positions, such as ends of the
section to be cleaned and purged.
4.5 Use of mobile phones and smoking within the scraper trap areas is UIS/GAS
prohibited.
4.6 Any leaks and repairs identified shall only be corrected when the system GAS
under test has been depressurized to zero.
4.7 Provide an effective eye wash station and emergency shower per SAES- UIS/GAS
B-069 on both launching and receiving station.
4.8 N-Spec Chemical MSDS should be attached with the chemical UIS
containers and fully understand by all personnel handling it.
4.9 Disposal of cleaning waste shall be as per SAEP-327 UIS
4.10 Job Safety Analysis (JSA) shall be performed by the proponent before UIS/GAS/
starting the cleaning activities of pipelines SAPMT

Page 6 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

5. SITE ACCESS

Access to the location where chemical cleaning operation is being conducted will be restricted
and the area will be kept free of people who are not directly responsible for the cleaning. In
addition, the area will be barricaded and signs posted around the cleaning area notifying others
that chemical cleaning is taking place.

6. WORK PERMITS

The appropriate work permit will be obtained from the concern area Pipeline Operation and shall
be available at the site where the chemical cleaning is to be conducted.

Should any issues or incidents arises, work shall be stopped immediately and the permit will be
closed.

7. CHEMICAL CLEANING

7.1 Notification of Chemical Cleaning

UIS will notify SA PMT/Pipeline Operation at least 24-hours prior to the execution of the
chemical cleaning. QC Inspector to verify setup and raise RFI to SA PID/Operation to
witness and perform inspection.

UIS Project Supervisor shall coordinate cleaning activities.

7.2 Preparatory Works

Steps Description Action By


7.2.1 Identify the overall responsible scraping and cleaning activity SAPMT
coordinator. This coordinator must ensure that all steps in this procedure
are followed. He should also ensure all safety measures are
implemented. The implementation of this procedure shall be under the
direction and supervision of the operation site coordinator.

During the entire chemical cleaning operations, inspectors must be


present at all times on site to ensure the monitoring of the chemical
cleaning operations and that it is going according to plan. Constant
communications by personnel on site on the conditions of the chemical
cleaning operations must be done.

Page 7 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.2.2 The work must be carried out in accordance with company Standards UIS/GAS
and General Instructions. These will include but not limited to the
following:
G. I. 6.012- Isolation Lock Out and Use of Hold Tag
G. I. 2.100- Work Permit System.

7.2.3 Mobilize and install Frac (Holding) tanks to the scraper receiver site UIS/GAS
QIPP (KM 41.585).
(Refer to Table 1 “Chemical Train Composition and Run Duration)
7.2.4 Mobilize and install Nitrogen Generating Unit (NGU), compressors, UIS/GAS
chemical vessel, diluents tank and injection pump to scraper launcher
site Abqaiq (KM 0.00). (Refer to Table 1 “Chemical Train Composition
and Run Duration).
7.2.5 Re-calibrate and install pressure gauges upstream and downstream of UIS/GAS
the trap isolation valve for both launcher and receiver.
Note:
1. Only calibrated pressure gauges shall be used.
2. Pressure Gauges should be as per the requirements (30-80%) of
SA Standards.
3. Pressure ranges: 0 – 200 psi
All other measuring equipment shall be calibrated.
7.2.6 If available, reset all scraper passage signals. Ensure they are operable. GAS
7.2.7 Both Launching and Receiving Areas should be ready with the designed UIS/GAS
piping to inject and receive the chemicals.
7.2.8 Check to ensure that all scraper traps’ isolation valves and all pertinent GAS
branch valves are not passing. If valves are passing, perform the
necessary maintenance to stop passing valves.

Page 8 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.3 Equipment Layout

7.3.1 Receiver

Scraper Receiving Area QIPP (KM 41.585)


Equipment Arrangement

Scraper Receiver

E F

Sample Point

Frac. Tanks

7.3.2 Launcher

Scraper Launching Area Abqaiq (KM 0.00)


Equipment Arrangement
A V1
V2
Scraper Launcher

MIV D C

Chemical
Tanks NGU

Diesel Tanks Injection Pump

Air Compressors

Page 9 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.4 Anticipated Chemical Cleaning Schedule (Forecast)


Note: Initial Packing of the line to 40 psig with dry air is approximately 2 – 3 days before the first run.
Anticipated Chemical Cleaning Schedule
Item Activities No. of Days 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

1 Mobilization to Site 2
2 Launcher Site Preparation and Hook-up 2
3 Receiver Site Preparation and Hook-up 2
4 First Run 4
5 Second Run 4
6 Third Run 4
7 Demobilization from Site 2

7.5 Cleaning Procedure

Before performing chemical cleaning, rigorous mechanical scraping operation shall be


performed to remove as much as solids as possible from the pipeline.

Chemical Cleaning of the pipeline shall be executed to ensure the removal of any sand,
corrosion products such as iron carbonate, iron oxides and iron supplied, metallic iron,
weld spatter, salt and scale generated during the dewatering, swabbing, tie-ins and
valves installation if any.

Specific chemical cleaning train has been designed for the entire pipeline in the scope of
this procedure. The segment of pipeline from permanent launcher to permanent receiver
trap will be chemically clean by two (2) cleaning train/runs with additional optional runs
if required. Refer to Figure 1 “Chemical Cleaning Train” for its composition.

Pre-requisites:

Prior to start the chemical train run, an initial back pressure of approximately 30-40 psig
must be ensured in order to perform the run in controlled manner and within the required
velocity.

The medium to build up the back pressure and to propel the chemical cleaning train shall
be by nitrogen having a 95% nitrogen purity. Record log of the nitrogen purity shall be
maintained during the back pressure build up and the train run. Nitrogen purity reading
shall be taken as the nitrogen entering into the pipeline every 4 hours.

The planned cleaning run for the pipeline segment along with the expected amount of
chemicals and diluents are shown in Table 1.

Page 10 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

Table 1 “Chemical Train Composition and Run Duration”

QIPP

FROM TO
KM
KM 0.00
41.585
HIGH
FIRST SCRAPER --- DENSITY N/A
FOAM
N-Spec 50 gal 690
1st Batch
CHEMICAL Diesel gal 4584
CLEANING
FIRST SCRAPER Bi-Di SCRAPER N/A
RUN
Batch Diesel gal 939

SECOND SCRAPER Bi-Di SCRAPER N/A

N-Spec 105 gal 690


Batch
2nd Diesel gal 4584
CHEMICAL FIRST SCRAPER Bi-Di SCRAPER N/A
CLEANING
Batch Diesel gal 939
RUN
SECOND SCRAPER Bi-Di SCRAPER N/A

N-Spec 50 gal 690


Batch
3rd Diesel gal 4584
CHEMICAL FIRST SCRAPER Bi-Di SCRAPER N/A
CLEANING
Batch Diesel gal 939
RUN
SECOND SCRAPER Bi-Di SCRAPER N/A

* Estimated Run Duration HRS 86

*Estimated travel time is based on velocity of 0.5 kilometers per hour. Velocity, volumes of chemicals and diluents and
type of chemical, may be adjusted depending on the gathered results from the previous runs.

Vacuum Truck will be used on a regular interval to empty the tanks and dispose it to an approved waste disposal
site/company.

Page 11 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

FIGURE-1 “Chemical Cleaning Train”

Note:

Chemical and Diesel volumes will be as per the following tables and its corresponding pipeline: Table 1
“Chemical Train Composition and Run Duration”

1st and 3rd Chemical Cleaning Run

Nitrogen 939gal 4584gal 690gal Nitrogen


Diesel Diesel N-Spec 50

2nd Scraper 1st Scraper


Bi-Directional Bi-Directional
with No Brush with No Brush

2nd Chemical Cleaning Run

Nitrogen 939gal 4584gal 690gal Nitrogen


Diesel Diesel N-Spec 105

2nd Scraper 1st Scraper


Bi-Directional Bi-Directional
with No Brush with No Brush

7.6 Pipeline Chemical Cleaning Train Loading and Run Operation

Chemical cleaning will be performed as per the sequence described as follows.


Step(s) Description Action By
7.6.1 Rig up equipment for both Launcher and Receiver. UIS/GAS
7.6.2 Deploy hoses supply line for connection UIS
7.6.3 Pressurize hose against closed valve for 5 minutes to confirm UIS
connection leak test.
7.6.4 Nitrogen purity entering the pipeline should be checked and as UIS
per approved pureness of 95% minimum.

Volume and sequence will be as per Table 1 “Chemical Train


Composition and Run Duration”.
7.6.5 Prepared the chemical required quantity base on concentration UIS
of diluents slug.
Volume and sequence will be as per Table 1 “Chemical Train
Composition and Run Duration”.

Collect one set of sample per batch as per Section 8.


7.6.6 As per pre-requisite, verify and confirm that the line was UIS/GAS
packed to a minimum 30-40 psig of nitrogen. Re-packed when
necessary.

Page 12 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.6.7 Cleaning Train UIS


Diesel and Chemical Injection / Scraper Loading and Launching Sequence.

BATCH CHEMICAL
A V1
V2
Scraper Launcher

MIV D C

Chemical
Tanks NGU

Diesel Tanks Injection Pump

Chemical (N-Spec 50) & Diesel Air Compressors

Nitrogen

VALVE START-UP POSITION

VALVE STATUS DESCRIPTION


MIV CLOSED Main Isolation Valve
A CLOSED Chemical/Diesel Injection Valve
B OPENED N2/Air Main Injection Valve
C CLOSED N2/Air Branch Injection Valve
D CLOSED N2/Air Branch Injection Valve
V1 CLOSED Launcher Vent
V2 CLOSED Launcher Vent

Insert 1st Scraper


 De-pressurize Launcher Trap by opening V1 and V2 vent valve.
 Open Trap Door and insert 1st Scraper (Bi-Directional No Brush) up to launcher
reducer. Close Launcher Trap Door.
 Crack Open Valve C to purge upstream of the scraper through V1.
 Once purged, Closed V1 and inject max 3psi of nitrogen to have a positive pressure
upstream of the scraper. Closed Valve C.
 Crack Open Valve D to purge downstream of the scraper through V2.
 Once purged, close Valve V2 and D.

Page 13 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

Inject Batch of Chemical and Diesel


 Open Valve A and Inject 690 gal of chemical N-SPEC® 50 followed by the 4584 gal of
diesel. Refer to Table 1 for the batch volume.
 Once fully injected, close valve A.

Launched 1st Scraper


 Pressurize trap to equal line pressure by opening Valve C.
 Open MIV valve and Launch 1st scraper by nitrogen.
 Close C and MIV valve.

VALVE ENDING POSITION

VALVE STATUS DESCRIPTION


MIV CLOSED Main Isolation Valve
A CLOSED Chemical/Diesel Injection Valve
B OPENED N2/Air Main Injection Valve
C CLOSED N2/Air Branch Injection Valve
D CLOSED N2/Air Branch Injection Valve
V1 CLOSED Launcher Vent
V2 CLOSED Launcher Vent

Page 14 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.6.8 2nd Scraper UIS


Diesel Scraper Loading and Launching Sequence.

A V1
V2
Scraper Launcher

MIV D C

Chemical
Tanks NGU

Diesel Tanks Injection Pump

Chemical (N-Spec 50) & Diesel Diesel Air Compressors

Nitrogen

VALVE START-UP POSITION

VALVE STATUS DESCRIPTION


MIV CLOSED Main Isolation Valve
A CLOSED Chemical/Diesel Injection Valve
B OPENED N2/Air Main Injection Valve
C CLOSED N2/Air Branch Injection Valve
D CLOSED N2/Air Branch Injection Valve
V1 CLOSED Launcher Vent
V2 CLOSED Launcher Vent

Insert 2nd Scraper


 De-pressurize Launcher Trap by opening V1 and V2 vent valve.
 Open Trap Door and insert 2nd Scraper (Bi-Directional No Brush) up to launcher
reducer. Close Launcher Trap Door.
 Crack Open Valve C to purge upstream of the scraper through V1.
 Once purged, Closed V1 and inject max 3psi of nitrogen to have a positive pressure
upstream of the scraper. Closed Valve C.
 Crack Open Valve D to purge downstream of the scraper through V2.
 Once purged, close Valve V2 and D.

Page 15 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

Inject Batch of Diesel


 Open Valve A and Inject 939 gal of diesel. Refer to Table 1 for the batch volume.
 Once fully injected, close valve A.

Launched 2nd Scraper


 Pressurize trap to equal line pressure by opening Valve C.
 Open MIV valve and Launch 2nd scraper by nitrogen.

VALVE ENDING POSITION

VALVE STATUS DESCRIPTION


MIV OPENED Main Isolation Valve
A CLOSED Chemical/Diesel Injection Valve
B OPENED N2/Air Main Injection Valve
C OPENED N2/Air Branch Injection Valve
D CLOSED N2/Air Branch Injection Valve
V1 CLOSED Launcher Vent
V2 CLOSED Launcher Vent

Page 16 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

7.6.9 Continue pumping nitrogen to propel the chemical slug train until it reach to receiver trap. UIS

7.6.10 Nitrogen Purity and line pressures are to be recorded on an hourly basis at both launcher UIS
and receiving stations as well as the scraper movements.

7.6.11 With positive back pressure monitored, station contractor crew leader shall manipulate valve UIS
E and/or valve F and release pressure in a controlled manner, maintaining a balance
between nitrogen injection and release for smooth/intact chemical train movement having
an average of 0.5 to 1 km/hr speed.

7.6.12 All liquid/solid slurry shall be received in temporary tanks. UIS

Note: Vacuum Truck will be used on a regular interval to empty the tanks and dispose it to
an approved waste disposal site/company.

7.6.13 During the arrival of the Cleaning Train into the receiver, collect the liquid samples (1 UIS/GAS
compartment) as per Section 8 in the presence of SAPMT.

7.6.14 Once scrapers are inside the receiver trap, close the 40” main isolation valve. UIS

7.6.15 Ensure that the receiver is free of pressure by venting the Receiver trap from the vent, and UIS
provided that a company representative is on location. The receiver may be opened and
scrapers retrieved.

7.6.16 Contact the launch crew and instruct nitrogen injection to cease. UIS
nd rd
7.6.17 Repeat steps 7.6.7 to 7.6.16 for the 2 and 3 run as per Table 1 Chemical Train UIS
Composition.

After the scrapers have been received from the final cleaning run, the remaining collected sludge or waste
materials from the frac tanks will be transferred and disposed via vacuum tanker to an approved waste disposal
site/company by the contractor. The frac tanks will then be demobilized from the site back to contractor’s yard.

Page 17 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

8. SAMPLING AND ACCEPTANCE CRITERIA


Sampling of cleaning batch (before injection) will be taken at the launching (from tanks) and
receiving locations (from scraper trap) in order to monitor the chemical cleaning run.

Clean containers will be used to collect the samples and they must be clearly identified with the
following information:

Pipeline Name, Date, Location (KM), and Batch Number (1st, 2nd)

Samples will be sent to a laboratory for their solid in suspension counting (% in Volume).

Pipeline will be considered clean enough if the debris loading found to be equal or less than
5g/li.

Sampling at the receiver.

1. Control the chemical discharging flow rate by throttling the discharge valve.

2. A clean container should be placed under the sample valve.

3. Open the sampling valve and flush at least 500ml of fluid through the valve. Do not close
the valve after flushing.

4. Place the sample bottle under the valve and collect fluid. Do not touch the valve whilst
taking the sample as this could cause particles to loosen and be released from the valve.

5. Withdraw the sample bottle leaving the valve open. Rinse the inner surface to the bottle
with fluid and discard the fluid. Repeat Step 4 and 5 for all the bottles to be used.

6. Repeat the above without closing the valve and collect two (2) liquid samples per
chemical compartment.

7. Send one sample of fluid to an Aramco approved Lab to obtain solids contain per
volume. Second sample shall be given to Aramco Operations Representative for any
future required confirmation of results.

Page 18 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

9. EQUIPMENT

Nitrogen Generating Unit (NGU) Spread


Calibrated Dew Point Meter 1
Flow Meter 1
40” Bi-Directional Scraper No Brush As required
40” High Density and Foam Scraper As required
CI Pump 1
HP Triplex Injection Pump 1
Chemical Tanks 2
Diesel Tanks 2
Holding (Frac) Tanks As required
Hoses, Pipes, Valves and Connection /Fittings As required
Sample Bottles As required

10. MANPOWER

PROJECT COORDINATOR (1)


Launcher Crew Tracking Crew Receiver Crew Engineering Mobile
Day Shift Night Shift Day Shift Night Shift Day Shift Night Shift Support Crew
QC/QA Engineer/Inspector (1 -
Foreman/Lead Technician

Foreman/Lead Technician

Foreman/Lead Technician

Foreman/Lead Technician
Operator/Technician (2)

Operator/Technician (2)

Safety Officer(1 - GAS)


Operator/Technician (1)

Operator/Technician (1)

Lead Engineer(1)
WPR (1 - GAS)

WPR (1 - GAS)
WPR (1 - GAS)

WPR (1 - GAS)

Technician(1)

Technician(1)

Pipe Fitter(2)
Labor (2)

Labor (2)

Labor (1)

Labor (1)

Labor (2)

Labor (2)

Labor(2)
GAS)

Page 19 of 20
QIPP_BI 21-00051 40" PIPELINE

CHEMICAL CLEANING

DETAIL PROCEDURE

ATTACHMENT

Page 20 of 20

You might also like