You are on page 1of 4

DESCRIPTION OF TASK: Construction of Temporary Construction Facility for Upgrade Water Supply at KGP

WORK LOCATION: Temporary Construction Facility


REFERENCES (if any): REQUIRED SAFETY EQUIPMENT

1. Required to wear proper PPE, Safety shoes, Helmet, Glasses, hand gloves
(where applicable), ear plug/ muffs, high-visibility vest, dust mask.
2. Barricades, Sign Boards, warning sign, fire watch man, standby man, and fire
extinguishers.
Prepared by): Reviewed by : Approved by:

HSE Manager Project Manager PMT

________________________ _______________________ ________________________

Signature Signature Signature

S/N SEQUENCE OF JOB STEPS POTENTIAL HAZARDS HAZARDS CONTROLS ACTION BY


1. Both permit issuer & receiver need to
conduct a joint site inspection to discuss
the hazards & precautions required for
conducting the job safely.
2. Invite other entities with utilities that may
be affected by this activity.
3. Obtain work permit.
4. A toolbox meeting shall be conducted,
provide hard copy of JSA and discussed
Permit Issuer/Receiver
Preliminary Site Inspection 1.Injury/Incident due to falling to all manpower.
1. Site Engineer
Slipping 5. In case of any emergency all activities
Site Supervisor
should be stopped, and all employees
should move to designated safe assembly
area.
6. Non-essential personnel shall be kept
clear of the work area.
7. All the personnel should wear Safety
shoes, safety glass and hard hat and
other needed personal protective
equipment.
2. Mobilization of equipment and 1. Prepare the area and clear obstructions Subcon CM/ Site Engineer
Material to worksite 1. Traffic hazards prior to mobilization of equipment. Permit Receiver
2. Ensure all equipment/tools are properly Supervisor

SHE-JSA-002- Rev.0 Page 1 of 4


secured on trailers bed. Pre-inspection
checking to be done prior to mobilization.
2. Property damage 3. Lifting devices, electric tools to be
inspected and offload machines
3. Struck by moving /equipment in a secured.
equipment. safe way/away from moving equipment.
4. Assign trained flag man wearing high All Workers
4. Caught in between visibility vest and flag that will guide
mechanical parts. vehicle drivers and control the traffic.
5. Unattended 5. Keep unnecessary personnel away from
reversing/maneuvering equipment/location.
6. Use full time qualified supervision.

1.Trained flag men equipped with safety


vest and flag that will guide vehicle drivers
and control the traffic.
2.Certified operator must be used.
3.Keep only the needed personnel in site.

1.Conduct joint site inspection.


2.Secure a hot work permit.
3.Certified operator must be used.
1. People struck by
equipment. 1.Maintain safe distance between pipe and
Subcon CM/ Site Engineer
2. Live Pipeline struck by equipment position.
Movement and operation of Heavy Permit Receiver
3. equipment if any. 2.Valid equipment sticker / daily operator
Equipment Supervisor
3. Fire inspection check list.
Equipment Operators
4. Oil leak
5. Unqualified operator 1.Use multipurpose (ABC or ABCE) Fire
Extinguishers using dry chemical powder.
2.In case of an emergency evacuation, all
workers should move to designated
assembly area.

1.Daily operator inspection check list.

1.Certified / competent operator must be


used.
4. Backfilling & Compaction 1.Struck by moving 1. Necessary Sign Boards to be placed, Flag Subcon CM/ Site Engineer
equipment. Man to control the traffic. Permit Receiver
2. All equipment /tools shall be inspected by Supervisor
2.Slips, trips and falls a competent person. All Workers
3. A pre-task meeting shall be conducted by
a supervisor prior to start any activity.
4. Unnecessary personnel shall be kept
clear of the work site.

SHE-JSA-002- Rev.0 Page 2 of 4


5. First aid kit shall be available at site.
6. PPE should be worn at all time.

1. Identify tripping hazards; highlight all


which cannot be removed with barrier
tape.
2. PPE should be worn at all time.
1. Do not use defective tools.
2. All equipment /tools shall be inspected by
a competent person. Subcon CM/ Site Engineer
Backfilling & Compaction 3. Vibration and Noise 3. A pre-task meeting shall be conducted by Permit Receiver
5.
(continued…) hazards a supervisor prior to start any activity. Supervisor
4. Ear plugs should be used while working All Workers
near vibrators, compactors and heavy
equipment.
1. Aramco/3rd Party Certified operator and
Rigger with visibility vest only allowed
performing the activity.
2. Operator sound horn while swinging
3. Taglines should be used to control the
load while lifting the load from the trailer
1. Uncontrolled swing of load. truck.
2. Accident due to heavy 1. Wind speed to be monitored while lifting.
wind speed, rain, 2. Lifting works to be stopped if wind speed Subcon CM/ Site Engineer
Erection of the portable cabins by sandstorm and poor exceeds 20 mph or 32 km/h Permit Receiver
6. visibility.
using crane 3. Work to be stopped in case of Heavy Supervisor
3. Crane tipping over, storm or rain All Workers
uneven ground, Failure of 1. Ensure only Aramco/3rd Party approved
equipment Rigger and operators are involved in the
operation.
2. Ensure equipment is approved by SA
and maintain daily checklist.
3. Crane to be positioned on proper
leveled/compacted ground.
4. Use wooden pads below the outriggers.
1. Regular disposal of waste, debris and
scrap materials shall be carried out.
2. Metal containers for waste, used paper
cups, scrap and debris shall be provided.
Subcon CM/ Site Engineer
3. Wash, toilets and launch facilities shall be
Permit Receiver
7. House Keeping 1. Health Hazard clean.
Supervisor
4. Drinking containers shall be in good
All Workers
sanitary condition.
5. Provide collection drums for waste
materials and regularly take them to
designated dumping area.

SHE-JSA-002- Rev.0 Page 3 of 4


Recommendations/Notes

Conduct toolbox safety meeting prior to work activities.

Explain to the workers the purpose of this JSA and enforce implementation of content.

If an injury or near miss occurs and investigation suggests, the JSA shall be reviewed to determine whether changes are needed in the job procedures.

SHE-JSA-002- Rev.0 Page 4 of 4

You might also like