You are on page 1of 5

Document No & Rev: JOB SAFETY ANALYSIS

Effective Date: Job Duration: Agency: INDUS PROJECTS LIMITED JSA No.
1 Job Title: EXCAVATION ,REINFORCEMENT, DEMOLISHING, SHUTTERING, DESHUTTERING
2 Project: UP GRADATION OF FIRE FIGHTING NETWORK
3 Defination: To identify the hazard before starting the work to avoid incident & accident.
4 Scope: As per safety rules and standards.
To provide safe working environment & promote a safety awarness for staff / Workers. To Protect public from injury and to damage properties . To ensure Safe works without
5 Objectives:
disruption & to complete them within target in terms of safety and time.
6 Procedure: To identify probable hazards & risk, then the Risks are ranked. Find out counter measures & Safety key points to minimize probability of hazards.
7 Used abriviations: LTI-Lost Time Injuries,MTC-Medical Treatment Cases, FAC-First Aid Cases.
P1 Potential Death, Permanent Disability or Major Structural Damage, P2 Potential Temporary Disability or Minor Structural Damage, P3 Reportable Injuries /Environmental
8 RISK CLASS : Hazards,P4 First Aid Cases.

Sl. Activity Example Picture Probable Risk Risk By


Counter Measures Safety key Points Revised Job Responsibility
No. Hazard rank risk

1) Appropriate PPEs should be used 1) All workers / operators should be 1) Site


2) Access should be free from all obstacles inducted before start of work. Engineer
3) Work Permit should be taken with the 2) All drawing should be approved.
approval 3) All markings should be done as per 2) Site
1) Personal 4) Surveying the area as per drawing. drawings & surveyor instructions. Supervisor
1) LTI
Marking the Injuries 5) Ensure that all staff & workers should
1 P2 wearing all PPEs P4 3) Site safety
excavation area 2)MTC
2) Trip Officer
Hazards
3)FAC

1) Appropriate work permit will be 1) Operators & Drivers should be 1) Site


obtained with approval. experienced & trained with safety Engineer
2)Underground utility will be checked. induction.
3) The Machine should be inspected & 2) Tool box talk done by concerned 2) Site
approved before start the work. supervisor. Supervisor
4) Operator & Drivers should have valid 3) Vehicles Speed should be
license. controlled .4) After parking wheel 3) Site safety
5) Proper access should be provided for stopper should be applied. Officer
vehicle movement. 5) Ensure the safe parking area for
6) Ensure that electrical cables should not vehicles.
1) Vehicle obstruct the way for excavator.
1)LTI
JCB and tractor may hit 7) Each equipment/vehicle will have
2 comes to the P2 helper with flag for guidance to operator. P4
2)MTC
marked area. 2) Vehicle 8)All basic PPEs should be provided.
may topple 3) FAC 9) All vehicles pre- checklist will be
displayed.
10) SWMS will be followed

1) Unauthorized entries should be 1) Machine movement area will be 1) Site


prevented cleared from all unwanted materials Engineer
2) Signal to be given by one person to and traffic.
operator. 2) Vehicle should be checked along with 2) Site
3) Operator should be trained & the checklist and pre-entry check list Supervisor
experienced with valid license. will be displayed on the vehicle.
4) Continuous supervision should be done. 3) Proper leveled area should be used 3) Site safety
5)Proper access should be provided. for machine movement and banks man Officer
1)Fatal 6) Hand breaks & access should be safe on should guide properly
Hit Hazard the machine. 4) Tool box talk to be done before
Starting the 2)LTI 7)Signage should be displayed starting the work.
3 excavation with Traffic P1 8) Ensure that no electrical cable or any 5)Work will be carried out under the P4
slope cutting hazard, 3)MTC kind pipeline should be laid in under strict supervision
ground.
4) FAC 9)Reverse horn will be used.
10)SWMS will be followed,

1) Appropriate work permit will be 1) Operators & Drivers should be 1) Site


obtained with approval experienced & trained with safety Engineer
2) The Machine should be inspected & induction.
approved before start the work. 2) Tool box talk done by concerned 2) Site
3) Drivers should have valid license. supervisor. Supervisor
4) Proper access should be provided for 3) Vehicles Speed should be controlled .
vehicle movement. 4) After parking wheel stopper should 3) Site safety
1)Fatal 5) Ensure that electrical cables should not be applied. Officer
Tractor to carry 1) Hit Hazard obstruct the way for tractor. 5) Ensure the safe parking area for
2)L T I 6) The tractor must have helper for vehicles.
the excavated
4 2)Toppling P1 guidance to driver. P4
soil for dumping
away from pit Hazard 3)MTC 7)All basic PPEs should be provided.
8) All vehicles pre- checklist will be
4)FAC displayed.
9) SWMS will be followed

1.) Work Permit should be obtained with 1) Ensure that all workers got the safety 1) Site
approval. induction before deploying the work. Engineer
2) Sufficient manpower should be 2) Tool Box Meeting should be
deployed for handling the barricading conducted on daily basis. 2) Site
works. 3) Vehicle movements should be Supervisor
3) Workers must be used appropriate controlled if any;
1) Personal PPEs which should be ensured by 4)Do not start any machinery work near 3) Site safety
Providing the Injuries 1)LTI concerned safety officer/supervisor. where the manpower deployed. Officer
5 hard barricading P2 4) Do not use any defective tools. 5) Ensure that P4
for the excavated 2)Trip 2)MTC 6) Maintain the good housekeeping. there is no electrical wires passing
pit hazard through work location on the ground
3)FAC level.

1.) Work Permit should be obtained with 1) Work permit will be closed on daily 1) Site
approval. basis after the completion of particular Engineer
2) Access should be free from all task.
Vehicle will be 1) Personal obstacles. 2)Worked area and machines should be 2) Site
parked in the Injuries 3)Checking will be done regarding any inspected for its safe condition Supervisor
designated area hydraulic/oil leakages.
6 1)FAC P3 4)After parking, wheel stopper should be P4 3) Site safety
after the 2)Trip
completion of hazard applied. Officer
work 5)SWMS should be followed

Job Safety Analysis Page 1 of 5


Sl. Probable Risk By Revised Job Responsibility
No. Activity Example Picture Hazard Risk rank Counter Measures Safety key Points risk

1) Appropriate work permit will be 1) Drivers should be experienced & 1) Site


obtained with approval trained with safety induction. Engineer
2) The Machine should be inspected & 2) Tool box talk done by concerned
approved before start the work. supervisor. 2) Site
3)Driver should be trained enough to do 3) Ensure the safe parking area for Supervisor
1) Hit Hazard the job. roller.
Use of roller / 1)LTI
earth ramer for 4) Proper access should be provided for 3) Site safety
7 P2 vehicle movement. P4 Officer
compacting and 2) Personal 2)MTC
leveling of soil. 5) Ensure that electrical cables should not
Injury 3)FAC obstruct the way for roller.
7)All basic PPEs should be provided.

1) Hard barricading should be provided 1) All workers / operators should be 1) Site


around the excavated pit inducted before start of work. Engineer
2)Appropriate caution board should be
2) Appropriate PPEs should be used. displayed according to the nature of 2) Site
work Supervisor
3) Access should be free from all obstacles 3) All markings should be done as per
1) Fall drawings & surveyor instructions. 3) Site safety
1) LTI 4) Work Permit should be taken with the 4) Access/egress arrangement should Officer
Excavated pit is Hazards
8 made ready for P2 approval be provided for excavated pits. P4
2)MTC 5) Concerned engineer/supervisor must 5) All drawing should be approved.
PCC 2) Trip
Hazards be presented and monitored the activities 6) Vehicle's legal documents will be
3)FAC for ensuring the safe working checked before they entering to site
environment. premises

1) Appropriate work permit will be 1) Site


obtained with approval. Engineer
2) The vehicle should be inspected &
approved before start the work. 2) Site
3) Drivers should have valid license. 1) Operators & Drivers should be Supervisor
1)Fatal 4) Proper access should be provided for experienced & trained with safety
vehicle movement. induction. 3) Site safety
1)Hit Hazard 2)L T I 5) Ensure that electrical cables should not 2) Tool box talk done by concerned Officer
Transit Mixer is obstruct the way for vehicle.
9 approaching near P1 supervisor. P4
2) Topple 3)MTC 6) The vehicle must have reverse horn 3) Vehicles Speed should be
to the pit and helper for guidance to operator.
Hazard controlled .4) After parking wheel
4) FAC 7)All basic PPEs should be provided. stopper should be applied.
8) SWMS will be followed 5) Ensure the safe parking area for
vehicles.

1) Reverse horn must be ensured for the 1) Drivers should be experienced & 1) Site
vehicle. trained with safety induction. Engineer
2) Appropriate PPEs must be used. 2) Tool box talk done by concerned
2) Unauthorized entry should be supervisor. 2) Site
prevented around the vehicle and work 3) Vehicles Speed should be controlled Supervisor
1)Fatal spot. 4) After parking wheel stopper should
1) Hit Hazard 3) Electrical cables should not obstruct the be applied. 3) Site safety
Plain cement way for vehicle. 5) Ensure the safe parking area for Officer
2)L T I
concrete will be 4) Access should be free from all obstacles vehicles.
10 2)Toppling P1 P4
poured in the for vehicles.
Hazard 3)MTC
excavated area. 4) FAC 5) Sufficient illumination should be
provided during the night work.

1.) Work Permit should be obtained with


approval.
2)
Sufficient manpower should be deployed
1) Fall of for unloading the shuttering material.
objects 3) Workers 1) Site
must be used appropriate PPEs. which 1) Ensure that all crew got the safety Engineer
1) LTI
Transportation 2) Hit Hazard should be ensured by concerned induction before deploying the work. 2)
11 reinforcement & 2) MTC P2 engineer. 4) Tool Box Meeting should be conducted P4 2) Site
steel shutter 3)Trip Short cut is not allowed. on daily basis.3) Vehicle movements Supervisor
materials to site hazard 5)Safety gloves should be should be controlled if any;5) Ensure
3) FAC
worn by personal unloading the material. that all the personal wear safety gloves 3) Site safety
4)Personal Officer
injuries. 6) Safe handling of materials should be
ensured. 7).Before entering the vehicle
into site, make sure that per-entry
checklist filled and submitted to the FABS
EHS dept.

1) Approved work permit will be obtained


from FABS.
1)Property
damage. 2) Wood and steel material will be 1) Site
stacked properly. 1)Ensure that all stacked material
1) MTC Engineer
Unloading of 2) Don't stack the material above 6ft should be well barricaded
2)Personal
reinforcement & Injuries. 2) Fatal 3) Barricades should be made to all 2) Place signage 2) Site
12 steel shutter P1 stacked material and tag line to be 3) Control of vehicle speed limit will be P4
Supervisor
Board at Site ensured while unloading the lifted load. maintanied
Yard As per JSA 3)Hit Hazard 3) LTI 4) Movement of vehicles and personal 4) Appropiate PPEs will be provided and
3) Site safety
shall be restricted to avoid damage to ensured by concerned supervisor.
4) Vehicle 3) FAC Officer
toppling man and materials.
5) Avoid standing/ working under the
lifted load.

1) Fall
1.) Work Permit should be obtained with
hazard
Making of approval. 1) Ensure that all crew got the safety
2)Trip 1) Site
channel in steel 1) Fatal 2)Workers must be used appropriate induction before deploying the work.
hazard Engineer
yard and cutting 3)Electrical PPEs which should be ensured by 2)Tool box talk done by concerned
of reinforcement 2) LTI concerned engineer. supervisor or safety officer .
13 as per drawing shock P1 3)Allow only trained crew to use power 3) Strict Monitoring by supervisor or P3 2) Site
with the use of (electrocutio 3) MTC tools with precautions. concerned engineer. Supervisor
n)
portable 4)All cables should be overhead. 4) All electrical connection through
4)Fire hazard 3) Site safety
electrical 4) FAC 5.All elctrical connection must be through ELCB.
tools/hand tools. ELCB. Officer
5) Personal
bruises 5)Use only Inspected and approved tools.

Job Safety Analysis Page 2 of 5


Sl. Probable Risk By Revised Job Responsibility
Activity Example Picture Risk Counter Measures Safety key Points
No. Hazard rank risk

1) Walk way should be free from all 1) Safety Induction should be given 1) Site
obstacles. before engaging to site activities. Engineer
2) Appropriate PPEs should be worn I.e 2)Medical check-up should have done
1)Hit Hazard hand gloves, shoulder pad etc. for all members before engaging to site 2) Site
Shifting of 3) Site vehicle's speed should be activities Supervisor
1) LTI controlled. 3)All workers should be undergone in
reinforcement 2)Trip
14 and shuttering Hazard P2 4)All electrical cables should be daily Tool Box Meeting. P4 3) Site safety
2)MTC overdrawn. 4)Work can be carried out under the Officer
boards from yard
to work spot. 3) Personal 5)Un authorized entries should be strict supervision
Injury 3) FAC prevented
6) Continuous supervision should be done.

1)Fall hazard 1) Work permit should be obtained with


approval,prior commence of work.
1) All crew should be experienced & 1) Site
Shifting of 2)Material 2) Manual material handling training to be
trained with safety induction. Engineer
reinforcement , damage provided. 2) Tool box talk done by concerned
channel and 1)MTC 3) Workers must use appropriate PPEs
15 Flooring material 3)Personal P2 like (hand gloves ,shoulder pad )which supervisor. P4 2) Site
3)Ensure that all the crew wear the PPE. Supervisor
from yard to injury 2)FAC should be ensured by concerned
4)Work must be carried out under the
work spot engineer.
strict supervision 3) Site safety
(Manually) 4)Muscle 4)Access should be clear from
Officer
skeletal obstructions.
disorders

1) Appropriate work permit will be 1) Safety Induction should be given 1) Site


obtained with approval before engaging to site activities. Engineer
2) Access/egress arrangement should be 2)Medical check-up should have done
1) Trip provided for the excavated pit. for all members before engaging to site 2) Site
Laying and tying Hazard 1) L T I 3) Appropriate PPEs should be used. activities Supervisor
of 4) All materials should stack properly. 3)All workers should be undergone in
vertical ,horizont 2) Fall 2)MTC 5)Unwanted materials should be removed daily Tool Box Meeting. 3) Site safety
16 P2 from the work location. 4)All equipments and tools should be in P4 Officer
al and circular Hazard
reinforcement on 3)FAC 6) SWMS will be followed good condition.
the marked area. 3) Personal 5)All electrical cables should be
Injury overdrawn.

1.) Work Permit should be obtained with


1) Fall approval. 1) Site
Ready made Hazard 1)LTI 2) Experienced and Sufficient crew should 1) Ensure that all workers got the safety Engineer
channel will be 2)Fall of be deployed for fixing of channel . induction before deploying to the work.
channel 3) Workers must 2) Tool Box Meeting should be 2) Site
17 fixed on the 2) Hit Hazard 2)MTC P2 be used appropriate PPEs which should be conducted on daily basis. P3 Supervisor
edges of floor 3)Trip ensured by concerned engineer. 3) Work must be carried out under strict
reinforcement. 3)FAC
hazard supervision. 3) Site safety
4) Officer
Maintain the good housekeeping

1) Appropriate work permit will be 1) Safety Induction should be given 1) Site


obtained with approval before engaging to site activities. Engineer
2) Access/egress arrangement should be 2)Medical check-up should have done
provided for the excavated pit. for all members before engaging to site 2) Site
1) Trip 1) L T I 3) Appropriate PPEs should be used. activities Supervisor
Shuttering will be Hazard 4) All materials should stack properly. 3)All workers should be undergone in
done around the 5)Unwanted materials should be removed daily Tool Box Meeting. 3) Site safety
2)MTC
18 laid P2 from the work location. 4)All equipments and tools should be in P4 Officer
reinforcement at 2) Fall
Hazard 3) 6) SWMS will be followed good condition.
required height. 5)All electrical cables should be
FAC
overdrawn.

1) Appropriate work permit will be 1) Safety Induction should be given 1) Site


obtained with approval before engaging to site activities. Engineer
2) Access/egress arrangement should be 2)Medical check-up should have done
provided for the excavated pit. for all members before engaging to site 2) Site
1) Trip 3) Appropriate PPEs should be used. activities Supervisor
Readymade Steel 4) All materials should stack properly. 3)All workers should be undergone in
Hazard 1) L T I
Shutter Boards 5)Unwanted materials should be removed daily Tool Box Meeting. 3) Site safety
19 Will be Fixed in 2)MTC P2 P4
2) Fall 3)FAC from the work location. 4)All equipments and tools should be in Officer
Around the Hazard 6) SWMS will be followed good condition.
Reinforcement 5)All electrical cables should be
overdrawn.

1) Appropriate work permit will be


obtained with approval.
2) The vehicle should be inspected &
approved before start the work. 1) Operators & Drivers should be
1) Fatal 3) Operator & Drivers should have valid experienced & trained with safety 1) Site
license. induction. Engineer
1)Hit Hazard 2) L T I 4) Proper access should be provided for 2) Tool box talk done by concerned
Entering Transit
20 Mixure vehicle to P1 vehicle movement. supervisor. P4 2) Site
2) Topple 3) MTC 5) Ensure that electrical cables should not 3) Vehicles Speed should be controlled . Supervisor
site.
Hazard obstruct the way for vehicle. 4) After parking wheel stopper should
4) FAC 6) Each vehicle should have reverse horn be applied. 3) Site safety
and helper for guidance to operator. 5) Ensure the safe parking area for Officer
7)All basic PPEs should be provided. vehicles.
8) All vehicles pre- checklist will be
displayed.
9) SWMS will be followed.

1)Personal 1) Work permit should be obtained with


injury approval,prior commence of work. 1) All crew should be experienced & 1) Site
Engineer
2) Manual handling training to be trained with safety induction.
Fixing of
2)Muscle 1) MTC provided. 3) Workers must use 2) Tool box talk done by concerned
21 concrete pump skeletal P2 appropriate PPEs like hand gloves which supervisor. P4 2) Site
pipe to the disorders 2) FAC should be ensured by concerned 3)Ensure that all the crew wear the PPE. Supervisor
flooring area.
engineer. 4)Work must be carried out under the 3) Site safety
3) Hit Hazard 4)Access should be clear from strict supervision
Officer
obstructions.
4)Trip
hazard

Job Safety Analysis Page 3 of 5


Sl. Probable Risk By Revised Job Responsibility
Activity Example Picture Risk Counter Measures Safety key Points
No. Hazard rank risk

1) Reverse horn must be ensured for the


vehicle.
1) Fatal 2) Helper must be there to guide the
1) Operators & Drivers should be
operator. experienced & trained with safety
Pouring 1) Hit Hazard 2) L T I 3) Only trained person should operate the induction.
concrete into the transit mixute vehicle.
22 concrete pump 2)Personal 3)MTC P1 3) Electrical cables should not obstruct the 2) Tool box talk must be done by P4
concerned supervisor.
by Transit Mixer Injury way for vehicle.
3) Vehicles Speed should be controlled .
4) FAC 4) Access should be free from all obstacles
for vehicles.
5) Pre- Check list will be displayed for all
vehicles.

1) Personal
1.) Work Permit should be obtained with 1) Site
Injuries. 1) Ensure that all workers got the safety
approval. Engineer
Pouring 2) Hit 1) LTI 2) Separate Crew should be deployed for induction before deploying the work.
concrete on the Hazard. concrete. 2) Tool Box Meeting should be 2) Site
23 3)Trip P2 conducted on daily basis. P4
floor with hazard. 2) MTC 3) Workers must be used appropriate 3) Proper Gloves and nose masks shall Supervisor
concrete pump. PPEs which should be ensured by
4)Skin and be provided.
3) FAC concerned engineer. 3) Site safety
eye irritation
Officer

1) Work Permit should be obtained with 1) Ensure that all crew got the safety 1) Site
approval. induction before deploying the work. Engineer
2) Workers must be used appropriate 1) Tool box
PPEs which should be ensured by talk done by concerned supervisor or 2) Site
concerned engineer. safety personal. Supervisor
3) Unauthorised enty should be prevented 3) Vehicles Speed should be controlled.
around the vehicle and work spot. 4) After 3) Site safety
4) Manual handling training parking wheel stopper should be Officer
1) Personal 1)Fatal to be provided. applied.
Injuries by 5) Electrical cables should not obstruct the 5) Strict Monitoring by supervisor or
Concrete will be Hit/trip 2)L T I way for vehicle. concerned engineer. 6)All
poured inside the 6) Access should be free from all obstacles equipments and tools should be in good
24 shuttered board Hazard P1 P4
3)MTC for vehicles. condition.
by transit 7) Sufficient illumination should be
2)Toppling
mixture. provided during the night work. 8)
Hazard 4) FAC
Continuous supervision should be done

1.) Work Permit should be obtained with


1) Personal
approval.
Injuries 1) Ensure that all crew got the safety
Electrical 2)Workers must be used appropriate induction before deploying the work. 1) Site
Vibrator will be 2)Electrocuti PPEs which should be ensured by 2)Tool box talk done by concerned Engineer
1) LTI concerned engineer.
applied on the on 3)Allow only trained crew to use vibrator supervisor or safety officer . 2) Site
25 poured concrete 2) MTC P2 m/c with precautions. 3) Strict Monitoring by supervisor or P4 Supervisor
for its 3) Hit Hazard concerned engineer.
4)All cables should be overhead.
compaction / 4) All electrical connection through
3)FAC 5)All electrical connection must be 3) Site safety
settlement. 4)Trip through ELCB. ELCB. Officer
hazard
6)Vibrator m/c must be Inspected and
approved.

1. Proper access/egress arrangement will 1) Safety Induction should be given 1) Site


be provided for the workmen to work before engaging to site activities. Engineer
inside the pit. 2)Medical check-up should have done
2) Appropriate PPEs must be used. for all members before engaging to site 2) Site
1) Trip 1)L T I 3)Sufficient illumination should be activities Supervisor
Concrete will be Hazard provided during the night work. 3)All workers should be undergone in
26 leveled in proper 2)MTC P3 4)Unwanted materials should be removed daily Tool Box Meeting. P4 3) Site safety
manner 2) Fall from the work location. 4)Work can be carried out under the Officer
manually. Hazard 3) FAC 5)Access should be free from all obstacles strict suprevision

1) Worker must be inducted and Tool Box


1)Skin Talk must be done before deploying to
work.
Irritation
2)Workers must be used appropriate PPEs 1) Site
1) Ensure that all crew got the safety
like rubber handloves ,gum boot etc. Engineer
2)Personal induction before deploying the work.
Mannual Injury 1)FAC which should be ensured by concerned 2)Tool box talk done by concerned
Levelling of engineer. 2) Site
27 concrete by P2 3)Allow only trained crew to do the supervisor or safety officer . P4 Supervisor
3)Trip 2)MTC 3) Strict Monitoring by supervisor or
screed vibrator. levelling of concrete.
Hazard concerned engineer.
4)All cables should be overhead. 3) Site safety
5)All elctrical connection must be through 4) All electrical connection through ELCB Office
4)2)Electroc
ELCB.
ution
6)Screed Vibrator m/c must beInspected
and approved.

1) Personal
1) Work Permit should be obtained with
Injuries 1) Ensure that all crew got the safety
approval.
1) LTI induction before deploying the work.
2) Workers must be used appropriate
Application of 2) Skin 2)Tool box talk done by concerned
28 hardner irritation 2) MTC P2 PPEs I.e hand gloves ,nose mask and supervisor or safety officer .
safety googles which should be ensured
by concerned engineer. 3) Strict Monitoring by supervisor or
3) Eye 3) FAC concerned engineer.
3) Strict supervison of the usage of PPEs.
Irritation

Job Safety Analysis Page 4 of 5


Sl. Probable Risk By Revised Job Responsibility
Activity Example Picture Risk Counter Measures Safety key Points
No. Hazard rank risk

1.) Work Permit should be obtained with


1) Personal approval.
Injuries 2.) Workers must be used appropriate 1) Ensure that all crew got the safety 1) Site
1) LTI PPEs which should be ensured by induction before deploying the work. Engineer
2)Electrocuti concerned engineer. 2)Tool box talk done by concerned
Application of on 3.) Allow only trained worker should use supervisor or safety officer . 2) Site
29 power flotter. 2) MTC P2 Power Flotter m/c with precautions. 3) Strict Monitoring by supervisor or P4 Supervisor
3) Hit Hazard 4.)All cables should be overhead. concerned engineer.
3)FAC
5.)All elctrical connection must be through 4) All electrical connection through 3) Site safety
4)Trip ELCB. ELCB. Office
hazard 6.)Power Flotter m/c must be Inspected
before use.

1) work permit should be obtained with


1)Fall hazard approval. 1) Site
2) Manual handling training to be Engineer
All side channel 2)Personal 1) LTI provided. 3) Workers must be 1) Ensure that all workers got the safety
will be removed injury used appropriate PPEs which should be induction before deploying the work. 2) Site
30 and stacked after 2) MTC P2 P4
ensured by concerned engineer. 2) Tool Box Meeting should be Supervisor
24 hrs of
3)Muscle 4)Access should be clear from conducted on daily basis.
concreting. skeletal 3) FAC obstructions. 5)channels should be 3) Site safety
disorders stacked properly. Officer
5) Housekeeping to be maintained.

1) Work Permit should be obtained with


1) Personal approval.
Injuries 2) Workers must be used appropriate 1) Ensure that all crew got the safety 1) Site
PPEs which should be ensured by induction before deploying the work. Engineer
2)Electrocuti 1) LTI concerned engineer. 2)Tool box talk done by concerned
Floor grove on 3) Allow only trained worker should use supervisor or safety officer . 2) Site
31 cutting with 2) MTC P2 P4
Power Flotter m/c with precautions. 3) Strict Monitoring by supervisor or Supervisor
machine
3) Hit Hazard 3)FAC 4)All cables should be overhead. concerned engineer.
5)All elctrical connection must be through 4) All electrical connection through 3) Site safety
4)Trip ELCB. ELCB. Office
hazard 6)Power Flotter m/c must be Inspected
before use.

1) Work permit should be obtained with


Deshuttering will
1)Fall hazard approval. 1) Site
be done and
2) Material 2) Manual handling training to be 1) Ensure that all workers got the safety Engineer
materials will be
damage 1) LTI provided. 3) Workers must be induction before deploying the work.
stacked 3) Personal used appropriate PPEs which should be 2) Tool Box Meeting should be 2) Site
32 properly.Material injury 2) MTC P2 ensured by concerned engineer. conducted on daily basis. P4 Supervisor
s will be shifted
to yard for 4)Muscle 4)Access should be clear from
skeletal 3) FAC obstructions. 5)Boards should be 3) Site safety
cleaning and
disorders stacked properly. Officer
reuse
5) Housekeeping to be maintained.

1) Work permit should be obtained with


approval.
2) Manual handling training to be
1) Hit Hazard 1)Site
provided. 3) Workers must be 1) Ensure that all workers got the safety
Housekeeping 1) LTI Engineer
used appropriate PPEs which should be induction before deploying the work.
33 and Material 2)Trip P3 ensured by concerned engineer. 2) Tool Box Meeting should be P4 2)Site
stacking will be hazard 2) MTC 4)Access should be clear from conducted on daily basis. Supervisor
ensured. 3)Site safety
3) Dust 3) FAC obstructions. 5) Material should 3) Good supervision Officer
hazard be stacked properly and in its designated
places

JSA Prepared by - EHS Officer JSA Reviewed by EHS - JSA Approved by EHS - TPI

Job Safety Analysis Page 5 of 5

You might also like