Professional Documents
Culture Documents
Half 1, 2019
J F M A M
1 KS ORKA - SOKORIA GEOTHERMAL INDONESIA PROJECT 92 days Sun 3/1/20 Sun 5/31/20
2 TRANSMISSION LINES 86 days Sun 3/1/20 Mon 5/25/20
3 GENERAL 30 days Sun 3/1/20 Mon 3/30/20
4 Land Acquisition 30 days Sun 3/1/20 Mon 3/30/20
5 Final Site Survey and Tower Plotting 30 days Sun 3/1/20 Mon 3/30/20
6 ENGINEERING 15 days Sun 3/1/20 Sun 3/15/20
7 Schedules 7 days Sun 3/1/20 Tue 3/10/20
8 Tower Schedule 0 days Sun 3/1/20 Sun 3/1/20
9 Foundation Schedule 0 days Sun 3/1/20 Sun 3/1/20
10 Material Schedule (Insulator, Conductor, OPGW & GSW, Fitting insulator
7 Accessories)
days Mon 3/2/20 Tue 3/10/20
11 Material List Tower (All Types) 7 days Mon 3/2/20 Tue 3/10/20
12 Sagging Schedules 7 days Mon 3/2/20 Tue 3/10/20
13 Technical Particular Guarantee 7 days Mon 3/2/20 Tue 3/10/20
14 Technical Particular Guarantee - Conductor 7 days Mon 3/2/20 Tue 3/10/20
15 Technical Particular Guarantee - OPGW 7 days Mon 3/2/20 Tue 3/10/20
16 Technical Particular Guarantee - GSW 7 days Mon 3/2/20 Tue 3/10/20
17 Technical Particular Guarantee - Steel Tower 7 days Mon 3/2/20 Tue 3/10/20
18 Technical Particular Guarantee - Fitting Insulator & Accessories 7 days Mon 3/2/20 Tue 3/10/20
19 Calculation 7 days Mon 3/2/20 Tue 3/10/20
20 Static Calculation Tower (all types) 7 days Mon 3/2/20 Tue 3/10/20
21 Static Calculation Foundation Design 7 days Mon 3/2/20 Tue 3/10/20
22 PROCUREMENT 7 days Sun 3/1/20 Sat 3/7/20
23 70kV Transmission Tower 0 days Sun 3/1/20 Sun 3/1/20
24 70kV ACSR Cable 0 days Sun 3/1/20 Sun 3/1/20
Page 1
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
25 OPGW Cable 0 days Sun 3/1/20 Sun 3/1/20
26 GSW Cable 0 days Sun 3/1/20 Sun 3/1/20
27 Grounding System 0 days Sun 3/1/20 Sun 3/1/20
28 Transmission Tower Accessories and Equipment Fittings 7 days Sun 3/1/20 Sat 3/7/20
29 MOBILIZATION 15 days Sun 3/1/20 Sun 3/15/20
30 70kV Transmission Tower 10 days Fri 3/6/20 Sun 3/15/20
31 70kV ACSR Cable 0 days Sun 3/1/20 Sun 3/1/20
32 OPGW Cable 0 days Sun 3/1/20 Sun 3/1/20
33 GSW Cable 0 days Sun 3/1/20 Sun 3/1/20
34 Grounding System 0 days Sun 3/1/20 Sun 3/1/20
35 Transmission Tower Accessories and Equipment Fittings 10 days Fri 3/6/20 Sun 3/15/20
36 CONSTRUCTION 61 days Sun 3/1/20 Thu 4/30/20
37 Soil Excavation 33 days Sun 3/1/20 Thu 4/2/20
38 Transmission Tower - N1 0 days Sun 3/1/20 Sun 3/1/20
39 Transmission Tower - N2 7 days Sun 3/1/20 Sat 3/7/20
40 Transmission Tower - N2A 7 days Sun 3/1/20 Sat 3/7/20
41 Transmission Tower - N4 7 days Fri 3/27/20 Thu 4/2/20
42 Transmission Tower - N5 7 days Wed 3/18/20 Tue 3/24/20
43 Transmission Tower - N6 7 days Fri 3/20/20 Thu 3/26/20
44 Transmission Tower - N7 7 days Sun 3/22/20 Sat 3/28/20
45 Transmission Tower - N8 0 days Sun 3/1/20 Sun 3/1/20
46 Transmission Tower - N9 7 days Fri 3/20/20 Thu 3/26/20
47 Transmission Tower - N10 0 days Sun 3/1/20 Sun 3/1/20
48 Transmission Tower - N11 0 days Sun 3/1/20 Sun 3/1/20
Page 2
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
49 Transmission Tower - N12 0 days Sun 3/1/20 Sun 3/1/20
50 Transmission Tower - N13 0 days Sun 3/1/20 Sun 3/1/20
51 Transmission Tower - N14 0 days Sun 3/1/20 Sun 3/1/20
52 Transmission Tower - N15 0 days Sun 3/1/20 Sun 3/1/20
53 Transmission Tower - N16 0 days Sun 3/1/20 Sun 3/1/20
54 Transmission Tower - N17 0 days Sun 3/1/20 Sun 3/1/20
55 Transmission Tower - N18 0 days Sun 3/1/20 Sun 3/1/20
56 Pouring Concrete 48 days Sun 3/1/20 Fri 4/17/20
57 Transmission Tower - N1 0 days Sun 3/1/20 Sun 3/1/20
58 Transmission Tower - N2 14 days Mon 3/9/20 Sun 3/22/20
59 Transmission Tower - N2A 14 days Mon 3/2/20 Sun 3/15/20
60 Transmission Tower - N3 14 days Mon 3/9/20 Sun 3/22/20
61 Transmission Tower - N4 14 days Mon 3/9/20 Sun 3/22/20
62 Transmission Tower - N5 14 days Sat 4/4/20 Fri 4/17/20
63 Transmission Tower - N6 14 days Thu 3/26/20 Wed 4/8/20
64 Transmission Tower - N7 14 days Sat 3/28/20 Fri 4/10/20
65 Transmission Tower - N8 0 days Sun 3/1/20 Sun 3/1/20
66 Transmission Tower - N9 14 days Mon 3/2/20 Sun 3/15/20
67 Transmission Tower - N10 0 days Sun 3/1/20 Sun 3/1/20
68 Transmission Tower - N11 0 days Sun 3/1/20 Sun 3/1/20
69 Transmission Tower - N12 0 days Mon 3/2/20 Mon 3/2/20
70 Transmission Tower - N13 0 days Sun 3/1/20 Sun 3/1/20
71 Transmission Tower - N14 0 days Sun 3/1/20 Sun 3/1/20
72 Transmission Tower - N15 0 days Sun 3/1/20 Sun 3/1/20
Page 3
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
73 Transmission Tower - N16 0 days Sun 3/1/20 Sun 3/1/20
74 Transmission Tower - N17 0 days Sun 3/1/20 Sun 3/1/20
75 Transmission Tower - N18 0 days Sun 3/1/20 Sun 3/1/20
76 Tower Construction & Installation Materials 61 days Sun 3/1/20 Thu 4/30/20
77 Transmission Tower Structure and Accessories - N1 5 days Thu 3/26/20 Mon 3/30/20
78 Transmission Tower Structure and Accessories - N2 5 days Sun 4/5/20 Thu 4/9/20
79 Transmission Tower Structure and Accessories - N2A 5 days Sun 4/12/20 Thu 4/16/20
80 Transmission Tower Structure and Accessories - N4 5 days Sun 4/19/20 Thu 4/23/20
81 Transmission Tower Structure and Accessories - N5 5 days Wed 4/22/20 Sun 4/26/20
82 Transmission Tower Structure and Accessories - N6 5 days Sun 4/12/20 Thu 4/16/20
83 Transmission Tower Structure and Accessories - N7 5 days Sun 4/26/20 Thu 4/30/20
84 Transmission Tower Structure and Accessories - N8 0 days Sun 3/1/20 Sun 3/1/20
85 Transmission Tower Structure and Accessories - N9 5 days Sun 4/12/20 Thu 4/16/20
86 Transmission Tower Structure and Accessories - N10 5 days Thu 3/26/20 Mon 3/30/20
87 Transmission Tower Structure and Accessories - N11 5 days Thu 3/26/20 Mon 3/30/20
88 Transmission Tower Structure and Accessories - N12 5 days Mon 3/23/20 Fri 3/27/20
89 Transmission Tower Structure and Accessories - N13 5 days Tue 3/24/20 Sat 3/28/20
90 Transmission Tower Structure and Accessories - N14 5 days Thu 3/19/20 Mon 3/23/20
91 Transmission Tower Structure and Accessories - N15 0 days Mon 3/2/20 Mon 3/2/20
92 Transmission Tower Structure and Accessories - N16 5 days Wed 4/1/20 Sun 4/5/20
93 Transmission Tower Structure and Accessories - N17 5 days Tue 3/24/20 Sat 3/28/20
94 Transmission Tower Structure and Accessories - N18 5 days Tue 3/24/20 Sat 3/28/20
95 Fitting and Accecoriss 45 days Sun 3/15/20 Tue 4/28/20
96 Transmission Tower N1 3 days Thu 3/26/20 Sat 3/28/20
Page 4
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
97 Transmission Tower N2 3 days Sun 4/5/20 Tue 4/7/20
98 Transmission Tower N3 3 days Sun 4/12/20 Tue 4/14/20
99 Transmission Tower N4 3 days Sun 4/19/20 Tue 4/21/20
100 Transmission Tower N5 3 days Wed 4/22/20 Fri 4/24/20
101 Transmission Tower N6 3 days Sun 4/12/20 Tue 4/14/20
102 Transmission Tower N7 3 days Sun 4/26/20 Tue 4/28/20
103 Transmission Tower N8 3 days Wed 3/18/20 Fri 3/20/20
104 Transmission Tower N9 3 days Sun 4/12/20 Tue 4/14/20
105 Transmission Tower N10 3 days Thu 3/26/20 Sat 3/28/20
106 Transmission Tower N11 3 days Thu 3/26/20 Sat 3/28/20
107 Transmission Tower N12 3 days Mon 3/23/20 Wed 3/25/20
108 Transmission Tower N13 3 days Tue 3/24/20 Thu 3/26/20
109 Transmission Tower N14 3 days Thu 3/19/20 Sat 3/21/20
110 Transmission Tower N15 3 days Sun 3/15/20 Tue 3/17/20
111 Transmission Tower N16 3 days Wed 4/1/20 Fri 4/3/20
112 Transmission Tower N17 3 days Tue 3/24/20 Thu 3/26/20
113 Transmission Tower N18 3 days Tue 3/24/20 Thu 3/26/20
114 Stringing 66 days Wed 3/18/20 Fri 5/22/20
115 Sort and Set string set 7 days Wed 3/18/20 Tue 3/24/20
116 Erection String set 36 days Sun 3/22/20 Sun 4/26/20
117 Stringing sec 1 T1 to T11 15 days Sun 4/12/20 Sun 4/26/20
118 Sagging and final check 7 days Sun 4/26/20 Sat 5/2/20
119 Sort and Set string set 7 days Wed 3/18/20 Tue 3/24/20
120 Erection String set 7 days Sun 3/22/20 Sat 3/28/20
Page 5
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
121 Stringing sec 2 T11 to T18 14 days Wed 4/1/20 Tue 4/14/20
122 Sagging and final check 7 days Tue 4/14/20 Mon 4/20/20
123 Stringing ACSR Cable - Ende 1 14 days Tue 4/28/20 Fri 5/15/20
124 Stringing ACSR Cable - Ropa 1 14 days Wed 4/15/20 Mon 5/4/20
125 Confirmation Ready to Shutdown 4 days Tue 5/19/20 Fri 5/22/20
126 Termination to Tower N139 5 days Wed 5/6/20 Tue 5/12/20
127 Termination to Tower N140 5 days Thu 5/14/20 Wed 5/20/20
128 SUBSTATIONS 61 days Sun 3/1/20 Mon 5/25/20
129 PROCUREMENT 14 days Sun 3/1/20 Sat 3/14/20
130 0.4kV Switchgear 0 days Sun 3/1/20 Sun 3/1/20
131 11kV Switchgear 0 days Sun 3/1/20 Sun 3/1/20
132 Lighting and Small Power Distribution Panel 0 days Sun 3/1/20 Sun 3/1/20
133 Station Service Transformer 0 days Sun 3/1/20 Sun 3/1/20
134 Main Transformer 0 days Sun 3/1/20 Sun 3/1/20
135 LV Power and Control Cables 0 days Sun 3/1/20 Sun 3/1/20
136 MV Power Cables 0 days Sun 3/1/20 Sun 3/1/20
137 Lighting Fixtures 0 days Sun 3/1/20 Sun 3/1/20
138 Receptacles 0 days Sun 3/1/20 Sun 3/1/20
139 Grounding System 0 days Sun 3/1/20 Sun 3/1/20
140 Lightning Protection System 0 days Sun 3/1/20 Sun 3/1/20
141 110V DC Charger System + Battery 0 days Sun 3/1/20 Sun 3/1/20
142 48V DC Charger System + Battery 0 days Sun 3/1/20 Sun 3/1/20
143 Cable Tray / Ladder 14 days Sun 3/1/20 Sat 3/14/20
144 Emergency Diesel Generator 10 days Sun 3/1/20 Tue 3/10/20
Page 6
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
145 Control and Protection Panels 0 days Sun 3/1/20 Sun 3/1/20
146 Substation Automation System 0 days Sun 3/1/20 Sun 3/1/20
147 Gas Insulated Substation 10 days Sun 3/1/20 Tue 3/10/20
148 ACSR & GSW Cable 0 days Sun 3/1/20 Sun 3/1/20
149 Lightning Arrester 0 days Sun 3/1/20 Sun 3/1/20
150 MOBILIZATION 44 days Sun 3/1/20 Mon 4/13/20
151 0.4kV Switchgear 0 days Sun 3/1/20 Sun 3/1/20
152 11kV Switchgear 0 days Sun 3/1/20 Sun 3/1/20
153 Lighting and Small Power Distribution Panel 0 days Sun 3/1/20 Sun 3/1/20
154 Station Service Transformer 0 days Sun 3/1/20 Sun 3/1/20
155 Main Transformer 0 days Sun 3/1/20 Sun 3/1/20
156 LV Power and Control Cables 0 days Sun 3/1/20 Sun 3/1/20
157 MV Power Cables 0 days Sun 3/1/20 Sun 3/1/20
158 Lighting Fixtures 0 days Sun 3/1/20 Sun 3/1/20
159 Receptacles 0 days Sun 3/1/20 Sun 3/1/20
160 Grounding System 0 days Sun 3/1/20 Sun 3/1/20
161 Lightning Protection System 0 days Sun 3/1/20 Sun 3/1/20
162 110V DC Charger System + Battery 0 days Sun 3/1/20 Sun 3/1/20
163 48V DC Charger System + Battery 0 days Sun 3/1/20 Sun 3/1/20
164 Cable Tray / Ladder 9 days Sun 4/5/20 Mon 4/13/20
165 Emergency Diesel Generator 35 days Sun 3/1/20 Sat 4/4/20
166 Control and Protection Panels 0 days Sun 3/1/20 Sun 3/1/20
167 Substation Automation System 0 days Sun 3/1/20 Sun 3/1/20
168 Gas Insulated Substation 35 days Sun 3/1/20 Sat 4/4/20
Page 7
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
169 ACSR & GSW Cable 0 days Sun 3/1/20 Sun 3/1/20
170 Lightning Arrester 0 days Fri 3/6/20 Fri 3/6/20
171 CONSTRUCTION 86 days Sun 3/1/20 Mon 5/25/20
172 CIVIL WORKS 86 days Sun 3/1/20 Mon 5/25/20
173 Soil Works (Back Filling, and Compacting) 14 days Sun 3/1/20 Sat 3/14/20
174 Electrical Building Area 7 days Sun 3/1/20 Sat 3/7/20
175 Security Building Works 2 days Sun 3/1/20 Mon 3/2/20
176 Shelter (EDG and Service Station Transformer) Area 7 days Sun 3/8/20 Sat 3/14/20
177 Main Transformer Area 0 days Sun 3/1/20 Sun 3/1/20
178 Switchyard Area 7 days Sun 3/1/20 Sat 3/7/20
179 Access Road 7 days Sun 3/8/20 Sat 3/14/20
180 Electrical Building Works 51 days Sun 3/8/20 Mon 4/27/20
181 Wall 30 days Sun 3/8/20 Mon 4/6/20
182 Concrete Roof and waterproof 7 days Thu 4/16/20 Wed 4/22/20
183 Floor and Ceilling 15 days Mon 4/13/20 Mon 4/27/20
184 Door, Window and Painting 14 days Sun 3/22/20 Sat 4/4/20
185 Security Building Works 16 days Sun 3/1/20 Mon 3/16/20
186 Foundation 7 days Tue 3/3/20 Mon 3/9/20
187 Pouring Concrete, and Curing 7 days Tue 3/10/20 Mon 3/16/20
188 Wall 7 days Sun 3/1/20 Sat 3/7/20
189 Concrete Roof and Curing 7 days Sun 3/1/20 Sat 3/7/20
190 Floor and Ceramic 3 days Sun 3/8/20 Tue 3/10/20
191 Door, Window and Painting 4 days Sun 3/1/20 Wed 3/4/20
192 Shelter (EDG & Service Station Transformer) Works 21 days Mon 3/2/20 Sun 3/22/20
Page 8
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
193 Foundation 7 days Mon 3/2/20 Sun 3/8/20
194 Pouring Concrete, and Curing 14 days Mon 3/9/20 Sun 3/22/20
195 Switchyard Works (Foundation, and Fence) 86 days Sun 3/1/20 Mon 5/25/20
196 Foundation (NGR,Firewall) 7 days Fri 3/13/20 Thu 3/19/20
197 Pouring Concrete, and Curing 24 days Sun 3/1/20 Tue 3/24/20
198 Drainage Work 36 days Sun 3/1/20 Sun 4/5/20
199 Demarcation and Security Fence 30 days Tue 4/7/20 Wed 5/6/20
200 Access Road Work 30 days Thu 4/16/20 Fri 5/15/20
201 Cable Duct Work 7 days Mon 3/2/20 Sun 3/8/20
202 Sanitation 14 days Tue 5/12/20 Mon 5/25/20
203 ELECTRICAL WORKS 74 days Sun 3/1/20 Wed 5/13/20
204 Construction and Installation 74 days Sun 3/1/20 Wed 5/13/20
205 0.4kV Switchgear 7 days Thu 4/30/20 Wed 5/6/20
206 11kV Switchgear 10 days Thu 4/30/20 Sat 5/9/20
207 Lighting and Small Power Distribution Panel 7 days Thu 4/30/20 Wed 5/6/20
208 Station Service Transformer 7 days Thu 4/30/20 Wed 5/6/20
209 Main Transformer 0 days Mon 3/2/20 Mon 3/2/20
210 LV Power and Control Cables 7 days Thu 4/30/20 Wed 5/6/20
211 MV Power Cables 14 days Thu 4/30/20 Wed 5/13/20
212 Lighting Fixtures 7 days Thu 4/30/20 Wed 5/6/20
213 Receptacles 7 days Thu 4/30/20 Wed 5/6/20
214 Grounding System 30 days Sun 3/1/20 Mon 3/30/20
215 Lightning Protection System 7 days Thu 4/30/20 Wed 5/6/20
216 110V DC Charger System + Battery 7 days Thu 4/30/20 Wed 5/6/20
Page 9
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
217 48V DC Charger System + Battery 7 days Thu 4/30/20 Wed 5/6/20
218 Cable Tray / Ladder 14 days Sun 4/12/20 Sat 4/25/20
219 Emergency Diesel Generator 7 days Sun 4/5/20 Sat 4/11/20
220 Control and Protection Panels 14 days Thu 4/30/20 Wed 5/13/20
221 Substation Automation System 14 days Thu 4/30/20 Wed 5/13/20
222 Gas Insulated Substation 14 days Sun 4/5/20 Sat 4/18/20
223 Structure 7 days Mon 3/16/20 Sun 3/22/20
224 ACSR Cable 7 days Fri 3/20/20 Thu 3/26/20
225 Lightning Arrester 10 days Tue 3/17/20 Thu 3/26/20
226
227 Test and acceptable 5 days Mon 4/20/20 Fri 4/24/20
228 0.4kV Switchgear 5 days Mon 4/20/20 Fri 4/24/20
229 11kV Switchgear 5 days Mon 4/20/20 Fri 4/24/20
230 Lighting and Small Power Distribution Panel 5 days Mon 4/20/20 Fri 4/24/20
231 Station Service Transformer 5 days Mon 4/20/20 Fri 4/24/20
232 Main Transformer 5 days Mon 4/20/20 Fri 4/24/20
233 LV Power and Control Cables 5 days Mon 4/20/20 Fri 4/24/20
234 MV Power Cables 5 days Mon 4/20/20 Fri 4/24/20
235 Lighting Fixtures 5 days Mon 4/20/20 Fri 4/24/20
236 Receptacles 5 days Mon 4/20/20 Fri 4/24/20
237 Grounding System 5 days Mon 4/20/20 Fri 4/24/20
238 Lightning Protection System 5 days Mon 4/20/20 Fri 4/24/20
239 110V DC Charger System + Battery 5 days Mon 4/20/20 Fri 4/24/20
240 48V DC Charger System + Battery 5 days Mon 4/20/20 Fri 4/24/20
Page 10
ID Task Name Duration Start Finish
Half 1, 2019
J F M A M
241 Cable Tray / Ladder 5 days Mon 4/20/20 Fri 4/24/20
242 Emergency Diesel Generator 5 days Mon 4/20/20 Fri 4/24/20
243 Control and Protection Panels 5 days Mon 4/20/20 Fri 4/24/20
244 Substation Automation System 5 days Mon 4/20/20 Fri 4/24/20
245 Gas Insulated Substation 5 days Mon 4/20/20 Fri 4/24/20
246 Structure 5 days Mon 4/20/20 Fri 4/24/20
247 ACSR Cable 5 days Mon 4/20/20 Fri 4/24/20
248 Lightning Arrester 5 days Mon 4/20/20 Fri 4/24/20
Page 11
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
1%
0%
0%
0%
0%
0%
3/1
3/1
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
3/1
3/1
Page 12
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
3/1
3/1
3/1
0%
0%
0%
3/1
3/1
3/1
3/1
0%
3%
16%
3/1
0%
0%
0%
0%
14%
100%
3/1
0%
3/1
3/1
Page 13
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
3/1
3/1
3/1
3/1
3/1
3/1
3/1
0%
3/1
0%
0%
0%
0%
0%
0%
0%
3/1
0%
3/1
3/1
3/2
3/1
3/1
3/1
Page 14
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
3/1
3/1
3/1
0%
0%
0%
0%
0%
0%
0%
0%
3/1
0%
0%
0%
0%
0%
0%
3/2
0%
0%
0%
0%
0%
Page 15
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Page 16
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
0%
0%
0%
0%
0%
0%
0%
0%
0%
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
0%
0%
Page 17
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
3/1
3/1
0%
3/1
3/1
0%
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
3/1
0%
0%
3/1
3/1
0%
Page 18
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
3/1
3/6
0%
0%
0%
0%
0%
0%
3/1
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Page 19
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
3/2
0%
0%
0%
0%
0%
0%
0%
Page 20
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Page 21
Half 2, 2019 Half 1, 2020
M J J A S O N D J F M A M J
0%
0%
0%
0%
0%
0%
0%
0%
Page 22
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
1%
Page 23
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
Page 24
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
Page 25
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
Page 26
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
0%
Page 27
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
0%
%
0%
0%
0%
0%
Page 28
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
Page 29
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
0%
0%
Page 30
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
0%
%
0%
0%
0%
0%
%
0%
%
%
%
0%
%
%
%
%
Page 31
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
%
0%
0%
Page 32
Half 2, 2020 Half 1, 2021 Half 2, 2021
J J A S O N D J F M A M J J
Page 33