Q.No.1
A firm manufactures 3 products A,B and C. The profits are Rs. 3, Rs.2 and Rs.4 respectively.
The firm has two machines and given in the table is the time required for processing the job
in minutes on each product
Machine Products
A B C
G 4 3 5
H 2 2 4
.
Machine G and H have 2,000 and 2,500 machine minutes respectively.
The firm must manufacture 100 A’s, 200 B’s and 50 C’s but not more than 150A’s
Set up an LP problem to maximize profit.(CO1)
Q.No.2
Q.No.4
A car hire company has one car at each of five depots a, b, c, d and e. A customer requires a
car in each town namely A,B,C,D and E. Distance in (KMs) between depots and the towns
are given in the following table
A B C D E
A 160 130 175 190 200
B 135 120 130 160 175
C 140 110 155 170 185
D 50 50 80 80 110
E 55 35 70 80 105
How should cars be assigned to customers so as to minimize the distance travelled. Solve the
problem using Hungarian method (CO5)
Q.No.5
A machine owner finds from his past records that the costs per year of maintaining a machine
whose purchase price is Rs. 6,000 are as given below
Year 1 2 3 4 5 6 7 8
Maintenance cost Rs 1000 1200 1400 1800 2300 2800 3400 4000
Resale price 3000 1500 750 375 200 200 200 200
Q.No.6
Determine the optimal sequence of performing 5 jobs on 4 machines and the total time
required. The machining of each job is required in the order of ABCD and the processing
timing are as follows
3-5 6
4-9 5
5-6 4
5-7 8
6-8 1
7-8 2
8-10 5
9-10 7