Professional Documents
Culture Documents
TABLE OF CONTENTS
PAGE
SCOPE ................................................................... 2
INTRODUCTION ............................................................. 2
2. REFERENCES ......................................................... 2
PAGE 1 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
SCOPE
INTRODUCTION
1. Requirements for welding and post weld heat treating are based on API
RP 582, “Welding Guidelines for the Chemical, Oil, and Gas Industries”,
First Edition, March 2001.
2. The requirements of this specification are supplementary to API RP 582.
3. Requirements are identified as additions, replacements, and deletions
to API RP 582.
4. Paragraph numbers in this specification are the same as API RP 582.
5. Requirements of API 582 that are not revised remain applicable.
PURCHASER REFERENCES
2. REFERENCES
ADD
4.4 This specification shall be used in preparation of:
1. Welding Procedure Specifications (WPS).
PAGE 2 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
2. Production welding.
3. Post weld heat treament.
4.5 WPS and PQR shall be written on forms QW 482 and QW 483,
respectively shown in ASME code, Section IX, or equivalent.
Forms shall indicate essential, nonessential, and supplementary
essential (if required) variables for each welding process.
4.6 Welding to pressure parts, including temporary attachment
welding, shall comply with this specification.
4.7 Existing pressure vessels, tanks, and piping shall be repaired
and altered in accordance with API 510, 653, and 570,
respectively.
4.8 General conditions shall comply with GEMS GC.
6.1 General
ADD
6.1.5 Carbon steel shall not be welded with carbon – 1/2 Mo or any
other low alloy welding consumable.
6.5 Submerged Arc Welding
ADD
6.5.5 Fused flux reclaimed from the SAW process shall not be used.
Unfused flux may be reclaimed/remanufactured and used, provided
it is not floor sweepings or otherwise contaminated.
6.5.6 SAW flux shall not provide any principal element to welds in
alloy material.
ADD
8.5 Interrupting of Welding/Preheating
1. Welding of butt joints that require a preheat temperature
lower than 250°F may be interrupted if both of the
following apply:
a. Thickness of deposited weld is a minimum of 25% of
joint thickness or 3/8 inch, whichever is greater.
b. Interrupted weld is cooled in still air or wrapped
with insulation until it cools to ambient
temperature.
2. If welding butt joints that require a preheat temperature
of 250°F or higher, preheat temperature shall be maintained
on weld without interruption until start of either PWHT or
an intermediate heat treatment at 500°F to 600°F for 1
hr/in., 2 hours minimum followed by slow cooling.
3. If the preheat is unavoidably interrupted before completion
of a weld, the weld shall be subjected to 100% wet magnetic
particle or liquid penetrant examination prior to
PAGE 3 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
continuation of welding.
8.6 Hydrogen Outgassing
1. For repair welding of equipment and piping that has been in
hydrogen charging service (e.g., high temperature hydrogen
or wet H2S), hydrogen outgassing shall be performed before
welding.
2. Heating to 400°F minimum (600°F preferred) for 1 hour per
inch of thickness (but not less than 2 hours total time) is
recommended.
9.1 ADD
Use of lower temperature for longer times as permitted by ASME
Code is subject to purchaser’s approval.
9.2 ADD
If partial, local, or field post weld heat treatment and/or post
weld heat treatment of lined, clad, or weld overlaid equipment is
involved, proposed post weld heat treatment shall be subject to
Purchaser approval.
ADD
9.12 Applicable Gases
PWHT shall be performed for the following cases:
1. If required by applicable code or project specifications.
2. For all carbon steel equipment and piping in rich amine and
lean amine services, regardless of operating temperature.
This requirement does not apply to fresh amine and does not
apply to tanks.
3. For all carbon steel pressure vessels in wet H2S service
(containing free liquid water) with an H2S concentration
equal to or exceeding any of the following values:
a. Partial pressure in vapor phase of 0.25 psi.
b. Content in water phase of 50 wppm.
c. Content in liquid hydrocarbon phase of 250 wppm.
d. Hardness after PWHT shall not exceed 200 Brinell.
COMMENTARY: The above values of H2S concentration are in
equilibrium to each other. There is no need to check all of
them. The judgment can be made based on any one of them
that is available.
4. For all carbon steel equipment and piping exposed to
caustic water solutions or mixtures of such solutions with
hydrocarbons under the following conditions:
PAGE 4 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
Concentration of NaOH
in Water Solution Stress Relieving Required
(Wt. Percent) For Metal Temperatures Above
2.5 180°F
10.0 175°F
20.0 160°F
30.0 140°F
40.0 125°F
50.0 118°F
COMMENTARY: The threshold temperatures for the intermediate
concentrations of NaOH can be found by interpolating. The
potential of heat traced piping/equipment being overheated
during heating to keep the caustic in solution should be
taken into account. Steaming out equipment and piping in
caustic service may also cause cracking. In these cases, PWHT
should be considered.
5. For all carbon steel equipment and piping that is in
contact with anhydrous liquefied ammonia. This requirement
shall not apply to ammonia water solutions or gaseous
ammonia.
6. Piping made from stabilized austenitic stainless steel
(e.g., 321, 347 SS), designed to operate above 700°F and
welded with fewer than three passes shall be subjected to
PWHT at 1600°F to 1650°F for a minimum of 4 hours and
cooled in still air. If the pipe is welded with three
passes or more, no PWHT shall be required. No PWHT shall be
required for external seal, fillet, or socket welds.
ADD
13.1 General
1. Nondestructive examination (NDE) procedures shall comply
with Section V of the ASME Code.
2. Amount of NDE shall comply with applicable code.
3. Specific NDE examinations, in addition to applicable code
requirements, shall be noted on Purchaser’s drawings,
specifications, or purchase orders.
4. NDE procedures shall be subject to Purchaser approval prior
to start of fabrication.
5. NDE shall be performed by Level II or III certified
personnel.
6. Evaluation of indications and their acceptance criteria for
pressure vessels and tanks shall comply with Section VIII,
Division 1 or 2, of ASME Code.
7. Visual examinations shall be subject to the following
requirement:
Cracks shall not be acceptable.
PAGE 5 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
PAGE 6 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT
DEC 01 WELDING AND POST WELD HEAT TREATING (API RP 582) GEMS G-7M7
PAGE 7 OF 7
TEXACO GENERAL ENGINEERING DEPARTMENT