You are on page 1of 2

BENGSON vs CHAN

Need for Prior Arbitration | G.R. No. L-27283 | Aquino, J. | ISSUES/HELD:


Emma 1. W/N the failure to resort to arbitration warrants the
dismissal of a complaint – NO
FACTS:  Bengson’s distinction between the contract for the
1. Bengson and Chan entered into a contract for the construction of the building and the construction of
construction of a 6-story building on Bengson’s lot. In the building is not convincing.
that contract, Bengson found herself to pay Chan, the  SC ruled that although the causes of action in the
contractor, P352k for the materials labor and complaint are covered by the clause, her failure to
construction expenses. resort to arbitration does not warrant the dismissal
2. They stipulated that: of her complaint. Arbitration may be resorted to
a) Construction starts on July 5, 1955 during the pendency of the case.
b) 1st and 2nd stories, as well as the theater should be o Arbitration Law Sec 6 provides that an
completed for use within 5 months aggrieved party by the failure, neglect or
c) Construction should be finished within 12 calendar refusal of another to perform under an
months agreement in writing providing for
3. The arbitration clause provides that any disputes arbitration may petition the court for an
arising between the parties relative to the construction order directing the such arbitration
of the building shall be determined by arbitration of 2 proceed in the manner agreed upon. Sec
persons, each chosen by the parties themselves. The 7 provides that in any suit brought upon
determination of the arbitration shall be final, an issue arising out of an agreement
conclusive and binding upon the parties UNLESS they providing for the arbitration, the court in
choose to go to court, in which case the determination which such suit is pending, upon being
by arbitration is a condition precedent for taking any satisfied that the issue involved in such
court action. Expense shall be borne equally by the suit is referable to arbitration, shall stay
parties. the action or proceeding until an arbitrary
4. Bengson filed an action for damages against Chan has been had. Provided, that the
alleging that Chan violated the contract when it failed applicant for the stay is not in default in
to finish the 1st and 2nd stories within the 5 month proceeding with such arbitration.
period.  In this case, the failure of Bengson to resort to
5. Chan and his sureties (Leoncio Chan –owner of arbitration may be regarded as a refusal to comply
Universal Construction Supply and Mutual Security with the stipulation for arbitration. Defendants
Insurance Corp) alleged that: defense that arbitration is a condition precedent of
a) They stopped the construction because Bengson a court action may be interpreted as a petition for
refused to pay for the 90% of the work already an order that arbitration should proceed.
accomplished  Instead of dismissing the case, the proceedings
b) Construction really started in Feb because of the should be suspended and parties should be
changes requested by Bengson directed to go through the motions of arbitration
c) The 5 month period was novated by the parties atleast within 60 days. With the consent of the
6. They also alleged as an affirmative defense that parties, TC may appoint a 3rd arbitrator to prevent
complaint states no cause of action since Bengson did a deadlock between the 2 arbitrators. If the dispute
not submit the controversy for arbitration as stipulated could not be settled by such, then the hearing of
in their contract. the instant case should be resumed.
7. TC ruled that the COAs were embraced under the
contract hence they should’ve brought it up to the RULING: The trial court's order of dismissal is reversed and set
arbitration first. TC dimissed! So P Bengson appealed. aside. If the parties cannot reach an amicable settlement at this
8. P Bengson argues that the contract refers to disputes late hour, then the trial court should give them at least sixty days
as to the “technical process of putting up the building” from notice within which to settle their disputes by arbitration
and that her causes of action for damages do not and, if no settlement is finalized within that period, it should hold
involve question as to the construction but it is “based a pre-trial and try the case. No
on violation of the contract for construction.” Bengson costs.chanroblesvirtualawlibrarychanr
also argues that if arbitration is proper, TC should have
required the parties to proceed to arbitration (not
dismissal) The Arbitration Law provides:
9. R argues that it is not restricted to disputes relative to
the technical process of putting up the building.
SEC. 6. Hearing by court. — A party aggrieved by the failure,
neglect or refusal of another to perform under an agreement in
writing providing for arbitration may petition the court for an
order directing that such arbitration proceed in the manner
provided for in such agreement. Five days notice in writing of
the hearing of such application shall be served either personally
or by registered mail upon the party in default. The court shall
hear the parties, and upon being satisfied that the making of the
agreement or such failure to comply therewith is not in issue,
shall make an order directing the parties to proceed to
arbitration in accordance with the terms of the agreement. If the
making of the agreement or default be in issue the court shall
proceed to summarily hear such issue. If the finding be that no
agreement in writing providing for arbitration was made, or that
there is no default in the proceeding thereunder, the proceeding
shall be dismissed. If the finding be that a written provision for
arbitration was made and there is a default in proceeding
thereunder, an order shall be made summarily directing the
parties to proceed with arbitration in accordance with the terms
thereof.

The court shall decide all motions, petitions or applications filed


under the provisions of this Act, within ten days after such
motions, petitions, or applications have been heard by it.

SEC. 7. Stay of civil action. — If any suit or proceeding be


brought upon an issue arising out of an agreement providing for
the arbitration thereof, the court in which such quit or
proceeding is pending, upon being satisfied that the issue
involved in such suit or proceeding is referable to arbitration,
shall stay the action or proceeding until an arbitration has been
had in accordance with the terms of the agreement: Provided,
That the applicant for the stay is not in default in proceeding
with such arbitration.

You might also like