Professional Documents
Culture Documents
3
Lecture 7:
Excavation Support Methods
4
Outline
5
Common reasons
Excavation
In general, excavation means to loosen and take out materials leaving
space above or below ground. Sometimes in civil engineering term
earthwork is used which include backfilling with new or original materials
to voids, spreading and levelling over an area.
British Standard CP6031 gives standards and recommendation to
earthworks covering embankment and cuttings, levelling and compacting,
and the use of earthmoving plants etc.
6
Common reasons
Dangers
From 2000 to 2009, an average
of 35 workers died every year in
trenching or excavation cave-ins,
according to Bureau of Labor
Statistics data.
Being struck or crushed by
equipment, dropped loads,
equipment rollovers,
electrocutions, and other events
account for the remainder.
Much more dangerous in mining.
Coal burst (煤爆) is a violent
collapse of coal walls and/or
roofs in underground coal mines.
7
Common reasons
Design codes and guides
GEOGUIDE 01
GCO Publication No. 1/90
BS 8002
BD 42/00
Piling handbook
DD ENV
CIRIA 104
8
Outline
9
Supporting method for trenches
Trench vs. Excavation
Excavation - any man cut, cavity,
trench, etc., formed by earth
removal. Excavations can include
a building basement, roadbed or
trench.
Trench - narrow underground
excavation that is deeper than it is
wide and no wider than 15 feet.
All trenches are excavations, but
not all excavations are trenches.
Trenches are usually more
dangerous.
10
Supporting method for trenches
Four-foot rule
OSHA (Occupational Safety
and Health Adminstration)
requires that workers have a
means to get in and out of a
trench if it is four or more feet
deep.
You must not have to travel
more than 25 feet to reach the
means of egress.
11
Supporting method for trenches
Five-foot rule
OSHA requires protection from
cave-ins by protective systems
unless the excavation is:
(a) Entirely in stable rock, or
(b)Less than five feet and the
competent person inspects the
excavation and determines
there is no indication of a
potential cave-in.
12
Supporting method for trenches
CEDD - Guide to Trench Excavations
For trench excavation with a
depth greater than 1.2 m,
adequate support must be
installed in a timely manner and
ahead of excavation as far as is
practicable.
If the depth of the excavation
exceeds 1.2 m or the
consequence of failure of any
slopes affected by the trench
excavation is considered
significant, the contractor must
employ a foreman.
13
Supporting method for trenches
Soil type can be used to determine what
Soil classification (OSHA) type of protective system can be used.
14
Supporting method for trenches
15
Supporting method for trenches
Trench Sloping
Trench Simple
Bench
Trench Multiple
Bench
16
Supporting method for trenches
17
Supporting method for trenches
18
Supporting method for trenches
19
Supporting method for trenches
Safety checklist
1) Construction vehicles, excavated spoil, materials, etc. are being kept at least 1.5 m
away from the edge of the excavation.
2) Spoil heaps are being properly placed and covered, and will be kept sheltered in
wet weather, or will be removed for maintaining access for pedestrians and traffic.
3) Necessary arrangements (e.g. stop boards) are made to prevent vehicles driving
into the excavation.
4) Adequate safe access to and egress from any trench is being provided and
properly maintained.
5) The open trench is properly lit and fenced off in accordance with Code of Practice
for the Lighting, Signing and Guarding of Road Works (HyD, current version).
6) The location of any buried services has been identified and clearly marked.
7) Crossing services are properly supported.
20
Supporting method for trenches
Safety checklist
8) Trenches are being supported according to the design and contract specifications.
9) The workers are working at safe distances from each other.
10) The assumptions used in the design are still valid.
11) There is no movement or deterioration of the ground that may put adjacent
services, roads, structures or slopes at risk.
12) The area is unaffected by vibration induced by the operation of heavy machinery.
13) The ground water level is as used in the design (i.e. not higher).
14) The work is being done in accordance with the specifications/drawings. If not, is
the variation permissible?
15) Unsupported trench faces are safe, with no sign of peeling away, progressive
collapse, etc.
16) The method of withdrawing support during backfilling is safe.
17) Backfill material is being properly compacted. 28
Supporting method for trenches
Safety checklist
Ramps or ladders
Hard hats
Ventilation equipment may be required
if there is a possibility of an
atmospheric hazard.
Connect support system members
securely.
Avoid overloading system members.
Install other structural members to carry
loads imposed on the support system
when you need to remove an individual
member.
Backfill the excavation as soon as
possible. 29
Supporting method for trenches
Safety checklist
Safety checklist
Safety checklist
No means of egress
Shoring not complete
Missing backfill
No edge stabilization
No hard hats
No air monitoring (One of the
greatest hazards of confined
spaces - and one generally
present in excavations - is air
quality. )
Material too close to the edge
What’s wrong with this trench?
25
Outline
26
Deep excavation and supporting system
27
Deep excavation and supporting system
Supporting & construction method
Retaining system
Sheet pile wall; pipe pile wall; soldier pile wall; secant pile wall;
diaphragm wall; soil mixing wall (jet grouting); cantilever wall;
combined pile wall; soil nail wall (also belonging to propping
system)
Retaining
Propping system
Internal bracing; ground anchor
Propping
Construction method
Dumpling method; cofferdam; top down method
28
Deep excavation and supporting system
29
Deep excavation and supporting system
32
Deep excavation and supporting system
33
Deep excavation and supporting system
34
Deep excavation and supporting system
Propping system – ground anchor
35
Deep excavation and supporting system
Propping system – ground anchor
36
Deep excavation and supporting system
Construction – dumpling method
This is used where there are buildings or street in the proximity. The method is to
construct a series of retaining wall in trench, section by section, around the site
perimeter ,leaving a centre called "dumpling"
37
Deep excavation and supporting system
Construction – cofferdam
A cofferdam may be defined as a temporary box structure constructed in earth or water
to exclude soil or water from a construction area, such as for foundation or basement
works.
Use of cofferdam suitable for excavation of
larger scale can be of :
https://dawsonwam.co.uk/projects/bp1-cofferdam-canary-wharf
Double-walled types of cofferdams are used when the area of construction site
is large and depth of water is high. In this place use of single walled cofferdam
becomes uneconomical as the supports are to be increased. So double walled
cofferdam is used.
The space between the walls are filled with soil. To prevent the leakage from
47
the ground below, the sheet piles are driven to a good depth in the bed.
Deep excavation and supporting system
Construction – bottom-up method
https://mymrt-underground.com.my/construction/station-construction/
41
Deep excavation and supporting system
Construction – top-down method
https://mymrt-underground.com.my/construction/station-construction/
42
Deep excavation and supporting system
Construction – top-down method
43
Deep excavation and supporting system
Construction – stability analysis
Hand calculation: GCO Publication No. 1/90
2D Finite element method: Plaxis, SAFE
3D Finite element method: 3D FLAC, DYNA
Thanks!