Professional Documents
Culture Documents
Boiler feed pumps installed on early 500 MW units were typically as shown
in Fig 4.55; they included a long flexible shaft with about six stages and
the residual thrust from the impellers taken by a conventional balance
disc arrangement. The bearings were mounted on separate pedestals
which had to be removed before the main pump internals could be
withdrawn. Glands were of the fixed labyrinth or floating ring type, and
the main bolted casing joint was subjected to full discharge pressure.
The result of the stiff shaft is that, even with the maximum permitted
worn internal clearances, the rotor transverse critical speeds in water are
well above the operating speed range. This permits relatively high
rotational speeds (typically in the range 6500-8700 r/min) to achieve the
necessary high head per stage. Slow speed booster pumps are therefore
required to provide sufficient NPSH to limit cavitation problems on the
main pump.
4.3.2 Feed pump duty, margins, and the need for variable speed
The duty of the boiler feed pump as determined by the boiler and turbine
pressure flow conditions, is given by Fig 1.71. Shown on the diagram are
the boiler feed-pump characteristics, i.e., the relationships between the
head produced by the boiler feed pump corresponding to the particular
value of feed flow pumped, and the boiler feed pump speed. Various
head/flow characteristics corresponding to the operating range of pump
speeds are indicated. The curve denoted as ‘system resistance’ is the
relationship between feedwater flow and the head that has to be
produced by the boiler feed pump to pump the feedwater into the boiler.
Also shown in the diagram are the design values of feedwater flow for the
turbine plant, boiler plant and the feed pump itself.
As the power requirement of a boiler feed pump for a typical 500 MW unit
is approximately 10 MW, it can be seen that the choice of an economic
and technically acceptable variable-speed boiler feed pump drive is a
decision of major importance. The possible types of boiler feed pump
variable-speed drives which have been considered by the CEGB for use on
large generating units are:
•
Mechanical Seals
This case history involved converting eight multistage boiler feed pumps
from the traditional soft packing gland to a plan 23 mechanical seal
arrangement (plan 23 was illustrated in Chapter 21.4). As the reader no
doubt knows, whenever packing is used, one must reduce rubbing friction
and damage to shaft and packing. The packing gland follower must be
adjusted, and some leakage must be allowed. One aims for a drip rate of
one drop per second to assist in cooling and lubricating the shaft contact
region. As packing and shaft wear, periodic adjustment will be needed,
and a competent workforce is needed to strike a balance between
excessive tightness (too many repairs) and too much gland leakage. Ask
yourself what this labor component would cost.
In any event, the boiler feed pumps incorporated packing glands at both
drive and nondrive ends. Although installed at a power generation facility,
this arrangement is typical of many applications around the world at
chemical works and refineries. Most of the feedwater pumps installed in
this time frame had been fitted with packed glands, and many continue to
run today using this outdated approach. Leakage from the packed glands
will be a pure loss to the operation. In this example, the boiler feed was at
121°C, and losses through the packed gland had to be made up with
water from the treatment plant. The calculation of the energy loss is
based on the energy required to take the makeup water from 10°C to a
feedwater temperature of 121°C. The steam generators were gas-fired,
and the heat energy requirement could be translated into a net CO2
contribution. Because plant manpower had been reduced, gland follower
adjustments were only made when the leakage was severe. As a result,
the average leakage rate from the pumps was about 1 L/min per gland.
With eight boiler feedwater pumps and 16 glands leaking on average one
quart (roughly 1 L) per minute per gland, energy loss was calculated at
124 kW. The plant operates 24 h per day, 365 days per year, causing an
annual energy loss of 1,086,240 kWh. These energy savings are purely
based on heating requirements and do not include energy costs for water
treatment, deaeration, and pumping. It is worth noting that these energy
savings do not include possible pump power reductions. The stated
energy savings refer to the combustion process and boiler operation costs
only.
Aside from any tax issues, the curtailment of gland leakage would require
employing trained craftspeople who do the gland adjusting day in, day
out. Training, rewarding, and retaining these crafts has become an
insurmountable challenge for most facilities. Reliability-focused engineers
will make a compelling case for using mechanical seals with flushing in
accordance with plan 23.
Main Equipment
Since 1905 Sulzer has produced a large number of boiler feed pumps in
segmental or barrel casing types. Reliability is of paramount importance
for this duty. Failure of a 100% feed pump lowers the availability of a
power station with potential to disrupt the grid supply at peak load times.
According to the duty a distinction is made between boiler feed pumps for
fossil fired and nuclear power stations.
9.3.1.1 Feed Pumps for Fossil-Fired Power Stations (See FIGS 9.8 AND 9.9)
Figure 9.8. HPT boiler feed pumps are specifically designed for operation
in fossil-fired power plants
9.3.1.2 Feed Pumps for Nuclear Power Stations (See FIG. 9.10)
Most commercial reactors today are either pressurized water reactors
(PWR) or boiling water reactors (BWR) (Figs 9.11a and b).
Figure 9.10. HPTd boiler feed pumps are specifically designed for
operation in nuclear power plants
Feed pumps for nuclear power stations have heads between 500 and 800
m. Feedwater temperatures range from 130 to 185°C and the 100% flow
rate in liters per second is about 2 to 2.2 × the electrical station output in
MW. Because nuclear stations operate with much lower live steam
pressures (approx. 50 to 70 bar) than fossil-fired ones, the feedwater rate
is much greater for any given station output. The drive input to the feed
pumps claims about 1.5% of the unit output.
Due to the higher flow rate and lower head required, feed pumps for
nuclear power stations are mainly single-stage double-entry designs.
Automatic Control
To ensure the safety of large pumps, e.g., boiler feed pump (BFP),
condensate extraction pump (CEP), etc., it is essential to maintain a
minimum flow through the pump at all modes of operation. This control
valve is located on a separate line tapped from either the individual pump
discharge or the common discharge header of pumps.
Consider a large power plant with two 10,000 kW boiler feed pumps that
operate in parallel. These two pumps are scheduled for repair during the
next scheduled shutdown. There may be a tendency to interpret this as
traditional maintenance work that could be accomplished within the
scheduled time and would cost $200,000. But what if a CPRS which
fittingly stands for both competent pump repair shop and competent
pump rebuild shop could be found and it could be ascertained that this
CPRS could perform a combined maintenance and upgrade job? Suppose
the upgrade would result in an efficiency gain of 2% and power is worth
$0.07/kWh. The savings would amount to $245,280 per year. Suppose
further that the CPRS would charge $300,000 to do the work; that's an
incremental cost of $100,000 that would return handsomely, regardless of
the precise calculation method employed.
View chapterPurchase book
Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128092729000220
The loss of water in the drum may be caused by a loss of boiler feed
pump. The standby boiler feed pump should start immediately in the case
of tripping of any of the running feed pumps. Prompt operator action may
prevent outage of the unit and other consequences of loss of feedwater to
the boiler. In the case of tripping of running feed pumps and failure to
change over to standby, the load should be immediately reduced to
restore the drum level. On the other hand, if the drum water level cannot
be maintained, the fire will be immediately killed and the turbine tripped
manually or through an interlock before the water level disappears from
the drum gauge glass/level indicator.
View chapterPurchase book
Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128015759000135
All power stations require at least one CW pump and one 50% electric
boiler feed pump available and running to start up a unit. In addition,
fossil plant requires either coal mills or oil pumps and draught plant, e.g.,
FD and ID fans, PA fans, etc. Gas-cooled nuclear plant requires gas
circulators running on main motors or pony motors at approximately 15%
speed, whereas water reactors require reactor coolant pumps. Both
nuclear types require various supporting auxiliaries to be available during
the run-up stages, the poor quality steam being dumped until the correct
quality is achieved.
In an ideal Rankine cycle (Figure 1.9) both the compression in the boiler
feed pump (process 3-4) and expansion in the turbine (process 1-2) take
place isentropically (reversibly and adiabatically). Hence, the efficiency of
the ideal Rankine cycle may be regarded as the highest efficiency
achievable in practice with a straight condensing machine. However, in a
real Rankine cycle (Figure 1.10) the efficiency that could be achieved is
less than the efficiency of the ideal Rankine cycle, since none of the
compression and expansion processes are isentropic. This is because
these processes on completion are non-reversible causing entropy to
increase during compression in boiler feed pump (the isentropic process
3-4s increases to process 3-4) as well as during expansion in turbine (the
isentropic process 1-2s increases to process 1-2), which further results in
an increase in power required by the boiler feed pump and decrease in
power generated by the turbine.
Sign in to download full-size image
Further, during the process 1-2, since the vapor is moist it starts
condensing and water droplets hit the turbine blades at high speed,
causing erosion and pitting. These water droplets are very harsh,
particularly at the last few stages of a low-pressure turbine. Thus, the
efficiency of the turbine starts reducing gradually. This problem is
overcome by superheating the vapor at state 1, which will move to the
right to state 1′ (Figure 1.9) and hence produce less wet vapor after
expansion (state 2′). However, by superheating the heat addition process
in the steam generator is no longer isothermal and the average
temperature of heat reception lies somewhere between that
corresponding to states 1 and 1′, i.e., between T1 and T1′.
The real superheat cycle is slightly different from the cycle shown in
Figure 1.10. Although the liquid leaves the boiler feed pump at state 4,
steam leaves the steam generator, in lieu of a state 1, at state 1′sg (not
shown in the figure), and enters the turbine at a different state 1′t (not
shown in the figure). Further, liquid leaving the boiler feed pump must be
at a higher pressure (p4) than the steam-generator exit steam pressure
(p1′sg), which also will have to be higher than the steam pressure at turbine
inlet (p1′t) because of friction drops in the heat exchangers, feedwater
heaters, pipes connecting boiler feed pump and steam generator, pipes
connecting steam generator and turbine, bends, superheater outlet
valves, turbine throttle valves, etc. [3].
There would also be heat loss from pipes connecting the steam generator
and turbine, causing a drop in entropy from state 1′sg to state 1′t.
Example 1.5
Solution:
(Note: The results of Examples 1.2, 1.4, and 1.5, as presented in the
following table, compares the performance of the Carnot, Ideal Rankine,
and Real Rankine cycles of steam operating between 8 MPa and 9.6 kPa
pressures. It is evident from the table that even though the Carnot cycle
provides the highest cycle efficiency, its net work output is the least and
the specific steam consumption is the highest.)
Carnot Ideal saturated Real saturated
Parameters
cycle rankine cycle rankine cycle
Heat Added, kJ/kg 1441.80 2561.58 2560.16
Cycle Efficiency, % 44.01 36.61 29.19
Net Work Output, kJ/kg 634.76 937.91 747.29
Specific Steam
5.67 3.84 4.82
Consumption, kg/kWh
View chapterPurchase book