Maintenance Work Instruction

1 - TransLift Shipmanagement Inc

INSP1187 Inspect Cargo Pipeline 1M Issued

General Progress

Rev. No 1 Created 6/14/2019 Zabal, Mary Catherine B.


Class Approved 6/14/2019 Rimando, Alvin T.
Issued 6/14/2019 Macarandang, Ramon C.

Notes
SAFETY PROCEDURE
=============
Ensure to comply safety procedures as per company policy.

CAUTION
======
Please ensure that during any maintenance routine, all safety precautions are to be observed at all times.
Suitable warning signs must be placed when maintenance is being carried out.

PROCEDURE
========

1. Visual inspection of the Cargo Pipeline especially on the bottom part and welding seam lines.
2. De-rusting of corroded portions using non-spark tools.
3. After de-rusting and cleaning of surface, application of protective coating must be performed immediately.

NOTE: Please note of the findings that need immediate attention and report to office at once for action.