You are on page 1of 25

. .

__

I
TABLE OF CONTENTS
Pre-Installation ..................................................................................................................... ..4
A. Introductory Remarks........................................................................................... ..4
B. Safety Precautions............................................................................................... ..4
C. Shipping and Receiving ....................................................................................... ..4
D. Handling .............................................................................................................. ..4
E. Inlet Box Placement............................................................................................. ..5
F. Storage................................................................................................................ ..5
1. Standard Requirements ................................................................................. ..5
2. Long-term Requirements................................................................................ ..5
3. Bearing Protection ......................................................................................... ..5
G. Foundations......................................................................................................... ..6
H. Duct Design......................................................................................................... ..6
Installation . ........................................................................................................................... ..6
A. Recommended Torques for Bolts and Studs ........................................................ ..6
B. Housing Alignment............................................................................................... ..8
C. Setting and Alignment of Bearing Pedestals......................................................... ..8
D. Rotor Assembly Preparation ................................................................................ ..8
E. Setting of Inlet Pieces .......................................................................................... ..9
F. Bearing preparation and Setting of Rotor Assembly ............................................. ..9
1. Sleeve — Dodge Plain and XC, RT, RXT ....................................................... ..9
2. Anti-Friction — Solid Pillow Block................................................................... ..9
3. Anti-Friction (Roller) — Adapter Mount, Split Pillow Block............................... ..9
G. Rotor and Housing Alignment .............................................................................. 10
H. Setting and Alignment of Bearings ....................................................................... 10
I. Coupling Installation and Alignment ..................................................................... 10
J. Inlet Alignment..................................................................................................... 11
K. Fan Drivers (Motors, Engines, Turbines) .............................................................. 11
1. Starting Time ................................................................................................. 11
2. Motor Overcurrent Protection ......................................................................... 13
3. Starters and Controls ..................................................................................... 13
4. Variable Frequency AC Applications .............................................................. 13
5. Synchronous Motors ...................................................................................... 14
6. Motor Bearings .............................................................................................. 14
L. V-Belt Drive Alignment......................................................................................... 14
M. Bolted Inlet Box Construction ............................................................................... 14
N. Grouting Index ..................................................................................................... 14
O. Special Features.................................................................................................. 14
1. Dampers ........................................................................................................ 14
2. Shaft Seals .................................................................................................... 15
3. High Temperature Fans ................................................................................. 15
a. High Temperature Design Limits .............................................................. 15
b. Temperature Rate-of-Change................................................................... 16
c. High Temperature Emergency Shutdown & Auxiliary Drives ..................... 16
d. High Temperature Corrosion .................................................................... 16
e. Clearances............................................................................................... 16
f. Heat Flingers............................................................................................ 16
g. Bearing Base ........................................................................................... 16
h. Water Cooled Shaft Steel ......................................................................... 16
i. Center Supported Housings...................................................................... 16
j. Expansion Joints ...................................................................................... 17
k. Insulation ................................................................................................. 17
1. Factory............................................................................................... 17
2. Field................................................................................................... 17
4. Spark Resistant Fans..................................................................................... 18
5. Access and/or Inspection Doors ..................................................................... 18
6. Elastomeric Coatings (Rubber, Butyl, Neoprene, etc.) .................................... 18
7. Temperature Detectors .................................................................................. 18
8. Sound Considerations.................................................................................... 18
9. Vibration Isolation .......................................................................................... 19
10. Vibration Detectors ........................................................................................ 19
11. Paint .............................................................................................................. 19
TABLE OF CONTENTS
Operation…........................................................................................................................... 19
A. Recommended Operational Parameters .............................................................. 19
1. Bearing Vibration Limits ................................................................................. 19
2. Bearing Temperature Limits ........................................................................... 19
3. Cooling Water Flow and temperature ............................................................. 19
B. Start-up ............................................................................................................... 19
C. Trouble-shooting.................................................................................................. 21
1. Trouble-shooting Guide.................................................................................. 21
2. Vibration Diagnostic Chart.............................................................................. 22
D. Maintenance........................................................................................................ 22
1. Water Spray Cleaning Systems...................................................................... 22
2. Balancing....................................................................................................... 22
3. Field Repairs.................................................................................................. 22
4. Lubrication ..................................................................................................... 22
a. Bearing .................................................................................................... 22
1. Circulating Oil..................................................................................... 22
2. Static Oil ............................................................................................ 22
3. Others (Grease, Oil Mist).................................................................... 22
4. Special Instructions for Vertically Mounted Fans ................................. 23
b. Coupling .................................................................................................. 23
5. Inspection ...................................................................................................... 24
6. Rotor and Shaft Removal ............................................................................... 25
7. Spare Parts List ............................................................................................. 25
8. Predictive Maintenance.................................................................................. 25
Warrantie s............................................................................................................................. 25
A. Terms and Conditions of Sale .............................................................................. 25
Inserts …………………………………………………………………………………………….Attached
I. PRE-INSTALLATION 10.. Inspect the fan rotor on a regular basis. The rotor is subjected
to stresses from centrifugal force and vibration. It may also be ex-
A. INTRODUCTORY REMARKS posed to particulate erosion (wear) and/or corrosion attack. A care-
This manual is published to assist the customer in the storage, ful visual inspection of the cleaned rotor by a knowledgeable in-
installation, operation, and maintenance of Robinson lndus- spector should be performed periodically to insure that no crack-
tries heavy centrifugal fans. Due to the wide variety of arrange- ing or other structural damage has occurred. Do not operate the
ments and custom-built features, WORK THIS MANUAL WITH fan if it has cracks or structural damage.
ROBINSON ASSEMBLY DRAWING to insure complete satis-
faction in installation and operation of equipment. 11. The vibration of the fan bearings (or of the shaft surface on
units with sleeve bearings) should be carefully monitored. Ob-
These instructions have been developed as a guide in in-
stallation of heavy duty fan equipment and erection personnel
serve the “alarm” and “shutdown” limits shown in Figure 41 of this
have found the procedures and methods described herein to be manual. Be sure that vibration instruments are operating properly
satisfactory under usual conditions. These instructions are not and that they are calibrated frequently.
considered complete in themselves, but as supplemental to 12. For further safety practices, refer to AMCA Publication 410.
general erection techniques. Robinson Industries does not take
responsibility for any omissions in this manual or on assembly
FIGURE 1
drawings of details commonly considered good practice by
competent erectors.
Should any questions or suggestions arise pertinent to these
instructions, your correspondence will gladly be received at:
ROBINSON INDUSTRIES, INC.
P.O. BOX 100
ZELIENOPLE, PA 16063
PHONE: (412) 452-6121
FAX: (412) 452-0388
Robinson Industries warrants against defects in workmanship
and material, refer to standard warranty.
Please note that all information specifically outlined by
Robinson Industries in this manual and on assembly drawings
supersedes that of any sub-vendor mentioned herein.

B. SAFETY PRECAUTIONS
It is the responsibility of the purchaser to insure that installation
is handled by qualified personnel experienced in installing this
type of equipment. FIGURE 1 ILLUSTRATES USE OF PROTECTIVE GUARDS ON SHAFT AND
V-BELT DRIVE
THE FOLLOWING SAFETY PRECAUTIONS MUST ALWAYS
BE OBSERVED: Back
1. Maximum operating temperature and speed for fan equipment C. SHIPPING AND RECEIVING
must not be exceeded. Refer to assembly drawings for the maxi- Upon arrival of the equipment, check that all items on bill of
mum speed and temperature for your equipment. lading and/or invoice have been received. Partial shipments are
often made.
2. Bearing temperature must not be exceeded. Refer to Bearing
Temperature Limits located in “OPERATION”. All shipments are thoroughly inspected prior to shipment.
Regardless, rough handling enroute may damage the fan
3. Protect properly against electrical hazards related to motor components. The receiving party must thoroughly inspect all
operation. Refer to specific information supplied on motor instal- shipments for possible damage. Any damaged parts are the
lation. responsibility of the carrier and should be reported to him
immediately upon arrival.
4. Protective guards for shaft, coupling, heat flinger and belts
must be provided and in place during operation. See Figure 1. Robinson cannot be held responsible for adjustment of such
claims if the delivery receipt is signed without specific notation
5. Inlet and outlet screens must be provided and in place to of shortage or damage. Any damages noticed after delivery
prevent entrance of clothing or flesh into rotating parts. should be reported to the carrier at once. Request their
inspection of the shipment and fill out a concealed damage
6. Access doors to fan or duct system must never be opened inspection report.
during operation of fan. Those located on the discharge side of
the fan may open violently if opened while fan is operating. Robinson Industries must be notified in writing immediately of
any lost or undelivered parts. Complaints issued more than 30
7. To provide against possible electrical start-up of fan during days after delivery will not be reviewed by Robinson Industries.
maintenance, be sure to electrically lock-out equipment before
working on fan. D . HANDLING
8. Beware of hot surfaces. Allow sufficient cool-down period UNITS SHIPPED COMPLETELY ASSEMBLED
before beginning any maintenance work.
Fans arriving at the job site assembled can be picked up using
9. Remove all loose materials from inside of housing and ductwork slings and padding or spreaders to avoid damage. Where slings
prior to start up. Check the quality of air inside the fan and provide are used, they should be placed under the bearing and at lifting
a watchman outside the fan before allowing anyone to enter. lugs. ALWAYS MAKE SURE THAT ALL LIFTING AND
HANDLING EQUIPMENT AND TECHNIQUES CONFORM TO
CURRENT SAFETY STANDARDS.

Contents 4
Avoid lifting fans or parts of fans in a way that will concentrate them during shipment to the job site and for a reasonable period
stresses which may bend or distort fan parts. Never pass slings before installation (1 month). This normally includes protecting
or timbers through the inlets of the fan housings. the shaft with a soluble removable coating and wooden slats,
For shipment of assembled fans, the rotor may be blocked or
strapped to avoid rotation during shipment. Be sure to remove
UNITS SHIPPED DISASSEMBLED the blocks or straps prior to operation.
Special coverings such as rubber, phenolic enamels, etc.
require care as they are easily damaged. Touch up any chips or
LONG-TERM REQUIREMENTS
breaks prior to erection. Refer to sections on paint and
elastomeric coated fans for more information on special If fans must be stored for an extended period, the storage site
coatings. Many rotor and shaft assemblies are shipped on a should be a clean, dry, well-ventilated, properly drained, tempera-
fabricated wood rotor cradle for ease of handling in shipment ture controlled environment (60-90º). For preassembled units,
and unloading. To remove the rotor and shaft assembly from the include room for inspection, lubrication, and maintenance,
cradle, place slings around the shaft as close to either side of the such as turning the fan rotor by hand to make certain all parts
rotor as possible. A spreader bar must be used during lifting to retain proper lubrication and shaft does not take a set. Remove
help eliminate damage to the rotor. Refer to Figure 2. shaft protective coating once every two months and inspect
shaft journal surface for possible corrosion. Replace the com-
plete protective system prior to returning to storage. The rotor
THE FOLLOWING MUST ALSO BE OBSERVED DURING should be rotated ten times every week using the following
HANDLING: sequence for final resting position:
1. Never allow chains to be in contact with the rotor during
lifting. 1. WEEK 1: 360°
2. Be sure that slings are not damaged in any way and are rated 2. WEEK 2: 90°
to lift the weight of the fan equipment. 3. WEEK 3: 180°
4. WEEK 4: 270°, etc.
3. Never lift rotor by blades or flanges.
4. Never roll rotor. BEARING PROTECTION (PERTAINING TO BOTH SHORT
5. Never rest entire rotor weight on the housing side plates; AND LONG TERM STORAGE)
block to prevent this. Ball Bearings:
6. Never set rotor down so that it supports the shaft; use wood Prior to shipment, fans with these pillow blocks are usually
supports under shaft to support rotor by shaft. factory tested. These bearings are prelubricated and should not
require additional grease for start-up. If fan is not expected to be
7. Never ship rotor leaning over and supported by the shaft; put into use immediately, it is advisable to add lubricant so as to
this can result in a bent shaft. destroy any air gaps in the bearing reservoir which may collect
8. Never lift double width, double inlet housing by putting moisture. At start-up, excess lubricant will be released through
timber or sling through inlets. To lift use skid under housing, or the seals. This is a normal purging action which will permit
sling around housing or through lift lugs provided in side sheet cooler operation, and the lubricant should not be replaced. Any -
bracing. time the fan unit is not in operation, the bearings should be
protected by waterproof paper to avoid contamination.
9. Never lift rotor by shaft sleeves or in bearing journal area (if
applicable). SAF Spherical Roller Bearings:
These bearings may be factory or field mounted depending on
fan size and design. If factory mounted, they may or may not
FIGURE 2 LIFTING ROTORS have been test run, depending upon size. Factory mounted
bearings have been lubricated with correct amount of lubricant
to permit operation upon installation. We advise that the bearing
caps be removed, the bearing inspected for moisture
contamination, and lubricant level confirmed prior to start-up.

Back TAKE SPECIAL CARE If field mounted, note that bearings are shipped with a preserva-
N tive only and bearing must be lubricated before operation
AREAS
begins. If unit is not to be put into operation immediately, pillow
block and bearing should be hand packed full of grease. Care
must be taken to insure that no moisture or dirt particles are
entrapped during this procedure. Label the bearing that it
contains too much lubricant for operation and cover with
waterproof paper. When preparing the unit for operation, the
bearing cap is to be removed and all lubricant removed using a
MINIMAL DISTANCE
clean instrument and unsoiled cloth. Inspect bearings, then
apply fresh lubricant as specified. Greasing is complete if
E. INLET BOX PLACEMENT grease appears on the opposite side. Pack the bearing housing
reservoir to a height roughly even with the bottom of the shaft.
Inlet boxes may be shipped separate from housing but are then
bolted to the housing in the field and field welded after NOTE: Extreme caution must be taken not to contaminate
alignment. See Figure 26. All welding is to be done after bearings when working on them. Bearings which have top or
installation of fan unit is complete. Refer to “Bolted Inlet Box side caps removed should never be left unprotected.
Construction” for specific welding specifications. Upon removal from storage, the following procedures should
take place:
F. STORAGE Back 1. Removal of rust preventative from shaft journals
STANDARD REQUIREMENTS 2. Thorough examination to insure that no build-up of foreign
Robinson fans are suitably prepared at the factory to protect material has occurred from the elements or near-by processes.

Contents 5
3. Examination to make certain that paint or coating is still in Fans installed above ground level should be located near to or
first-class condition. above a rigid wall or heavy columns. An overhead platform or
support must be rigidly constructed level and securely braced
4. Bearings relubricated to specifications as described in
independently from the fan in all directions. In any above
lubrication section and on assembly drawing. Do not use
ground installation, design of the structure should permit field
substitute lubricants unless approved by Robinson.
revisions (e.g: knee braces) if initial operation indicates a need
for increased stiffness. Spring mounted vibration isolation
G . FOUNDATIONS bases are recommended for many fans mounted on structural
A rigid, level foundation is essential for every fan set-up. This steel to avoid vibration transmission problems. (Refer to section
insures smooth, quiet operation, good performance, and on “Vibration Isolation”).
reduces excess vibration and maintenance costs. The sub- Anchor bolts in concrete should be “L” or “T” shaped (see
foundation (soil, stone, rock, etc.) should be firm enough to Figure 3), and should be placed in pipe or sheet metal sleeves
prevent uneven settlement of the structure, and have adequate roughly 2” larger in diameter than the anchor bolts to allow for
stiffness characteristics to avoid rocking or translational adjusting the bolts in case they move slightly when concrete is
vibration resonances. Foundation bolt locations are found on poured. Foundations must be level, and allowance must be
the assembly drawings. An improperly constructed foundation made for a minimum of 1” of shimming and grouting when
may cause vibration and possible misalignment of the rotating determining the top surface of the foundation. Jacking bolts
assembly. must be removed and hold-down bolts tightened prior to
If the fan is to be mounted with sole plates under the bearing grouting. All space under the base angles should be grouted.
supports, make allowances for dimensions of sole plates and Foundation bolts should be tightened and base rechecked for
grouting when preparing the foundation. Fan foundation must level.
be flat, level, and rigid. On all large fans, foundations should be keyed to bedrock, and
Poured concrete under the fan and all drive components is the use of pilings may be necessary. A civil engineer should be
preferred fan foundation. consulted before such a foundation is constructed.

A generally accepted rule of thumb is that the weight of the


foundation mat be at least five times the total weight of the H . DUCT DESIGN
equipment it will support. This weight acts as an inertia block to Improper duct design can cause system effect that decreases
stabilize the foundation. The foundation should be flared or the fan performance. Some guidelines are shown in Figure 4. Also
footing course increased in size to resist settling. The top of the refer to AMCA Publication 201. Expansion joints and/or flexible
foundation should extend at least 6” outside the outline of the connections are essential and must be provided at fan inlet and
fan base and should be beveled on the edges to prevent outlet in order to isolate fan from duct temperature expansion
chipping. The drive end and opposite drive end pedestals loads, duct static loads, and vibration loads. (See Figure 4).
should each have a minimum weight equal to that of the wheel Flexible connections may be multiple bellows expansion joints,
and shaft assembly. The sides of these pedestals should slope banded slip joints or fabric or sheet plastic flexible joints. The
away a minimum of 15º starting at the top, unless the drive end type of expansion joint is dependent on fan operating conditions,
pedestal is common with the motor pedestal. In that case, the such as temperature, etc. Flexible connections may require
sides may be vertical. acoustic treatment to reduce noise. Ducts must be anchored
Very large fans and/or variable speed drive fans require special near the fan. Refer to sound considerations section for more
foundation considerations. The purchaser may elect to perform information on flexible connections.
a system forced response analysis to determine the natural Avoid elbows immediately adjacent to the fan inlet and outlet.
frequencies and expected vibration amplitudes with reasonable Butterfly dampers are not recommended for throttling at the fan
rotor unbalance forces. (See AMCA Publication 801). inlet. Refer to AMCA Publication 201 “Fans and Systems” for
When a structural steel foundation is necessary, it must be additional information on duct design and system effects.
sufficiently rigid to assure permanent alignment. It must be
designed to carry, with minimum deflection, the weight of the II. I N S T A L L A T I O N
equipment plus the loads imposed by centrifugal forces set up
by the rotating element (generally 50% of rotating weight). NOTE: BE SURE THAT ALL EQUIPMENT IS ELECTRICALLY
LOCKED OUT DURING ALL PHASES OF INSTALLATION.

FIGURE 3
A . RECOMMENDED TORQUES FOR BOLTS AND STUDS
If no specific torque value is shown on the assembly drawing,
then use the torques per the following table:
TABLE I.
NOMINAL BOLTS STUDS
SIZE (ft-lbs) (ft-lbs)

1/4-20 5.5 5.5


5/16-18 11 11
3/8-16 20 18
Back 7/16-14 32 28
1/2-13 50 39
5/8-11 100 83
3/4-10 175 105
7/8-9 170 160
1-8 250 236
1 1/8-7 350 –
1 1/4 500 –

Contents 6
FIGURE 4 INLET CONNECTIONS

WRONG RIGHT WRONG RIGHT W R O N G RIGHT

==8

WRONG RIGHT WRONG RIGHT


Back

OUTLET CONNECTIONS

W R O N G RIGHT WRONG RIGHT RIGHT


l

WRONG RIGHT WRONG RIGHT RIGHT WRONG RIGHT

WRONG RIGHT

FIGURE 5 DRIVE ARRANGEMENTS FOR CENTRIFUGAL FANS

O P T I O N A L I N L E T BOX D=DRIVE SIDE BEARING


/-- O=OPPOSITE DRIVE SIDE BEARING

ARR. 1 SWSI WITH INLET BOX ARR. 3 SWSI WITH INLET BOX ARR. 3 DWDI WITH INLET BOX
For belt drive or direct connec- AND INDEPENDENTPEDESTALS AND INDEPENDENT PEDESTALS
tion. Impeller overhung, two bear- For belt drive or direct connection For belt drive or direct connectlon
ings on base. Inlet box may be fan. Housing is self-supporting. fan. Housing is self-supporting.
self-supporting. O n e bearing on each side sup- O n e bearing on each side sup-
ported by independent pedestals ported by independent pedestals
with shaft extending through inlet with shaft extending through inlet
box. box.

,-- OPTIONAL INLET BOX O P T I O N A L INLE T BOX


y.1
I-
I
I 0 D
I

A R R . 4 SWSI For direct drive. ARR. 7 SWSI WITH INLET BOX ARR. 9 SWSI For belt drive. Im-
I m p e l l e r o v e r h u n g o n prime Common steel base for bearing p e l l e r o v e r h u n g , t w o bearings.
mover shaft. No bearings on fan. a n d prime m o v e r c e n t e r h u n g with prime m o v e r m o u n t e d o n
Prime m o v e r b a s e m o u n t e d o r Impeller. bearing base.
Interally directly connected.

Adapted by permission from AMCA Publication 99-83 Standards Handbook

Contents 7
B. HOUSING ALIGNMENT 3. Adjustment of “L” or “T” anchor bolts is helpful in leveling
Erection of Arrangement 3 SWSI and DWDI fans with indepen- sole plate. After final alignments are made, place stainless steel
dent pedestals is covered in the following passage. See Figure 5 shims next to each “L” or “T” bolt and at the shaft centerline
for modifications used for other arrangements. (both sides) under the sole plate before grouting. (Figure 6).

Arrangement 1 and 8: 4. Temporarily bolt down bearing pedestals. (Shims running


1. Using a spirit level on shaft between bearings, shim at the the full length and half the width of the bearing sole plate and
foundation anchor bolts to attain level. slotted to fit around the mounting bolts provide the most solid mounting
arrangement for later mounting of bearings.)
2. Tighten hold-down bolts on foundation.
For fans with independent pedestals: SET AND ALIGN FIGURE 8
HOUSING ON FOUNDATION:
1. If housing was shipped dismantled, lift bottom half of EQUAL DEFLECTION ON
EACH SIDE FOR DWDI FANS
housing onto foundation. To prevent damage to anchor bolts
while housing is being moved, place wooden blocks beside the
anchor bolts.
2. Use spreader bars as necessary to minimize distortion while
lifting housing. Lift housing from as many points as possible and
align over anchor bolts.
3. Once aligned over anchor bolts, lift housing one side at a
time, re-move the block, and carefully lower housing onto
foundation. Note that parts are match-marked to aid in assembly.
4. Place stainless shims (approximately the same thickness as
the grout) on each side of the anchor bolt. Shims should be
approximately 100mm wide and flush with the edge of the base
angle. See Figure 7.
For center supported housings, refer to “High Temperature”
D. ROTOR ASSEMBLY PREPARATION
section. Most Robinson heavy duty rotors are shipped with a shrink fit to
the shaft. Check the assembly drawing for proper rotor rotation.
FIGURE 7 SHIM PLACEMENT DETAIL Figure 9 is for reference only.

Back 0 1. Place rotor on floor, bracing into position

U-SHAPED STAINLESS SHIMS 2. Remove protective coatings (as applicable) from shaft and
MUST BE PLACED /”
hub. Inspect for rust, corrosion and nicks.
AT ALL ANCHOR BOLTS,
FOUR CORNERS, AND AT 3. Cleanup may be necessary. Crocus cloth or “Scotchbrite”
INTERMEDIATE POINTS may be used for cleanup of journal surface. (NEVER use emery
IF VISUAL DEFLECTION cloth on bearing journals.)
IS EVIDENT
FIGURE 9
STAINLESS SHIMS MUST BE FLUSH
TYPES OF CENTRIFUGAL FAN IMPELLERS
WITH BASE ANGLES

~ZTATI~N @jj @j @

C. SETTING AND ALIGNMENT OF BEARING PEDESTALS Back Back RADIAL BACKWARD AIRFOIL
BLADE INCLINED
1 . Use shims to put bearing pedestals in place at the proper
bearing centerline height.
2. Level the fixed (drive side) bearing using stainless shims
under the sole plate. Use of a surveyor’s transit is very helpful in
this operation. RADIAL BACKWARD FORWARD
TIP CURVED CURVED

Reprinted by permission from AMCA Publication 202 ‘Troubleshooting’

FIGURE 6
ROTOR ALIGNMENT/SHIMMING DETAIL

Back to Page 5 Back to Page 7 SHAFT

FIXED BEARIN LOATING BEARING MACHINED


J SURFACE

SET MOTOR LOW SHAFT WILL E X P A N D


FOR EXPANSI

SOLE PLATE

GROUT

8
Contents
E. SETTING OF INLET PIECES DODGE Plain and XC Bearings:
Split thrust collars are field mounted during installation. Refer
The inlet piece must be placed over the shaft end before
to specific instructions attached.
mounting the rotor assembly in the housing. See Figure 10. If
variable inlet vanes are provided, check for proper rotation. DODGE RT Bearings:
Inlet vanes in the half-closed position must prespin the air in the Thrust collars are either integral to the shaft or split for field
direction of rotor rotation. On a DWDI fan, one inlet vane mounting into pre-machined grove. Refer to specific instruc-
control is counter-clockwise, the other clockwise. They must tions attached.
not be installed reversed. Secure inlet vane controls to rotor for DODGE RXT Bearings:
lifting purposes. If vane center mechanism is allowed to rest on For special applications requiring extremely high bearing oil
shaft, damage may result. film stiffness, the Dodge RXT bearing may be used. This
bearing involves machined-in thrust surfaces on the shaft and
F. BEARING PREPARATION AND SETTING OF ROTOR ASSEMBLY special assembly and handling procedures. Refer to the separate
instruction manual (attached) if your fan is equipped with this
SLEEVE BEARINGS (Refer to DODGE instruction manual, type of bearing.
attached, if applicable for your fan.)
1. Remove bearing caps; clean with solvent. ANTI-FRICTION BEARINGS - SOLID PILLOW BLOCKS
(See bearing manufacturer's literature, attached.) Solid pillow
2. Coat with new oil and cover bearings with plastic to avoid
blocks are placed over shaft ends before putting rotor in place.
contamination.
Refer to assembly drawing for floating bearing and fixed
3. Clean shaft seals and oil rings bearing location. Note that two fixed bearings are used on some
4. Loosely bolt lower half of bearing into place, then cover to applications.
avoid contamination. ANTI-FRICTION (ROLLER) BEARINGS-ADAPTER MOUNT,
5. Sling rotor assembly in manner previously described. Rotor SPLIT PILLOW BLOCK (See bearing manufacturer’s literature,
assembly is to be placed above bearing journals and liner for attached.)
drive bearing fastened to shaft. Be sure to check for proper rotor 1. Cleaning of internal parts is not necessary since the
rotation before setting the assembly into the bearings. Lower corrosion preventative compound applied by the manufacturer
into housing with rotor assembly. See detailed bearing infor- is compatible with the Robinson recommended lubricants.
mation (inserted). Carefully inspect all internal parts since corrosion, if undis-
covered, can lead to mechanical problems.

FIGURE 10
TERMINOLOGY FOR CENTRIFUGAL FANS

-n r-- r FAN SCROLL

ps,An h BACKPLATE %EiF; SECTION

INLET BOX

// rlNL~T/SHdOUD CLEARANCE \ \\ SINGLE INLET FAN WITH INLET BOX

7 -
SPLITTER PLATE
SECTION

IMPELLER AND SHAFT


ASSEMBLY

BLADE PlTCH ANGLE

SECTION " A - A "


Reprinted by permission from AMCA Publication 802-82 establishing DOUBLE INLET FORM WITH INLET BOXES
performance using laboratory models.
9
Contents
2. Cover open pillow blocks and bearing parts which are H. SETTING AND ALIGNMENT OF BEARINGS.
exposed to the atmosphere with a clean cloth to prevent dust or The driver side bearing, floating bearing, and motor are all to be
moisture contamination. set level. Refer to Figure 6. Check to be sure the bearing seal has
3. Replace bearing internals in same order as removed from equal clearance to the shaft all around. See Figure 11. No
pillow block. grouting is to be done until all components are leveled and
aligned.
4. Sling rotor assembly as previously described, and lift into
place.
5. Prior to final alignment, replace bearing caps.
I. COUPLING INSTALLATION AND ALIGNMENT Back
NOTE:
6. Pay particular attention to bearing internal clearances
On completely assembled units with premounted motor and
before and after tightening.(Refer to Figure 21).
coupling, alignment must be rechecked after fan is secured onto
7. Locate floating bearing to allow for shaft axial expansion its permanent foundation. Adjustments regarding alignment
must be made and the coupling relubricated if necessary. Refer
LOCTITE ADHESIVE PROCEDURE to tag as shown in Figure 12.

This procedure is for use on all fans with setscrew mounting that The following is a general description of the installation of grid
operate at or above 2500 RPM. and gear couplings. For examples, refer to Figures 13, 14, and
15. All bearings, inlet vanes, etc. must be installed prior to
1. LOCTITE SAFETY SOLVENT: aligning couplings.
Spray Loctite Safety Solvent onto inner bearing race and to fan 1. Install each coupling half cover with 0-ring (if equipped) on
shaft to flush away oil, dirt, grease. Wipe clean using paper its shaft.
towel. Wait 5 minutes until solvent entirely evaporates.
2. See coupling manufacturer’s manual to determine which
2. CAUTION! LOCQUIC PRIMER N: Use this to speed up the direction long/short shank of coupling hub is to be located (if
set up time. Spray Locquic Primer N to the inner bearing race applicable).
only, not to the shaft. ALLOW PRIMER N TO ENTIRELY
EVAPORATE-THIS SHOULD TAKE APPROXIMATELY 5 3. Using a hot oil bath, electric heater, or oven, heat coupling
MINUTES AND IS VERY CRITICAL. hub to temperature of 300°F. being careful not to apply flame to
hub teeth.
3. NOTE: LOCTITE Adhesives will not set up at all on stainless
shafts unless Primer N is used.
Adhesive: Loctite RC/620–400°F–.015” gap maximum.

NOTICE
Apply the adhesive to the shaft and assemble bearing race to
shaft. Wipe off any excess adhesive which may have oozed out
from the applied area during assembly.
4. Tighten bearing set-screws to proper torque.
I ALTHOUGH THIS UNIT WAS CAREFULLY ALIGNED
AT OUR PLANT, IT IS POSSIBLE THAT MOVEMENT
5. ALLOW SHAFT ASSEMBLY TO ACHIEVE PARTIAL CURE:
15 MINUTES IF LOCQUIC PRIMER N WAS USED,
MAY TAKE PLACE DURING SHIPMENT OR DUE TO
18 HOURS IF NO PRIMER IS USED. FOUNDATIONS AND / OR MOUNTING.
IT IS ADVISED THAT THE ALIGNMENT BE RECHECKED
G. ROTOR AND HOUSING ALIGNMENT IN THE FIELD BEFORE START-UP.
Be sure that shaft centerline is the proper height for connection
to the driver.
Alignment details of rotor to inlet piece are included on the
Robinson assembly drawing. The assembly drawing gives a
4. Install coupling hub(s) on shaft. (Hub and shaft face should
dimension for the inlet piece to rotor and backplate to housing.
normally be flush).
Check this alignment before final tightening of pedestals, bearing
bolts and bearing locking devices. 5. Key couplings to shafts while hubs are at elevated
temperature.
6. Adjust the gap between coupling hub faces. See assembly
FIGURE 11 drawings for proper coupling gap.
7. If using a sleeve bearing motor, and the magnetic center of
the motor is not marked, equally divide the maximum play to
Back BLADE, I-- CASING determine the mechanical center, then align in this position. A
limited endfloat coupling must be used with sleeve bearing
motors. Refer to assembly drawing.
8. Check to insure that the faces of fan and driver couplings
are parallel using a tapered wedge, feeler gauges, dial indicator
or laser alignment. See Figure 20 for maximum allowable
angular and parallel misalignments.
INLET PIEC
WEB (OR BACKPLATE)
9. Align shafts until parallel. Repeat procedure at 90º intervals
SHAFT CENTERLINE, and recheck angular alignment and hub separation.
Suggested method of alignment: Using a dial indicator clamped
on one hub with the dial indicator button resting on the other
FOR HIGH TEMPERATURE FANS (ABOVE 250 F) hub, rotate hubs in unison and take indicator reading. (See
REFER TO ASSEMBLY DRAWING FOR SPECIAL
Figures 18 and 19). Repeat the procedure at the three remaining
INLET PIECE TO WHEEL FIT-UP REQUIREMENTS
90º intervals. Refer to Figure 20 for allowable tolerance.
1 CRITICAL RUNNING CLEARANCES NOTE: Laser alignment of couplings is also available; contact
Robinson Service Dept.

Contents 10
10. When using large turbines or motors as drivers, allow for J. INLET ALIGNMENT
driver expansion during operation: set driver side of the low by a 1. Install gasketing in housing split then install split portion of
few thousandths; this will bring coupling into alignment during housing.
operation.
2. Reposition inlet piece to give correct clearance. Inlet piece
General rule for initial alignment of large motor: Set driver low should be centered around inlet eye of the rotor, unless stated
0.001” per inch of motor shaft diameter. otherwise on assembly drawing.
Coupling misalignment may be a result of these factors, related 3. Tighten all remaining fasteners in foundation.
to installation of the drive unit:
4. Install shaft seals (if applicable).
a) rough or dirty surfaces between motor foot and base
b) short or tilted motor leg (soft foot condition). 5. Turn rotor to insure it runs freely.
c) angled or warped motor mounting plate. 6. It is often a good practice to butt inlet piece support blocks
d) dirty, bent, or oversized shims. against the inlet piece flange and tack weld them to the housing
e) too many shims, or shims with burrs. sides as a means of “fixing” the inlet piece location.
If any of these conditions present themselves in your applica- SEE DETAILED BEARING INSTALLATION INFORMATION
tion, it is essential that they be corrected to provide proper (ATTACHED) AND INSTALL BEARINGS.
alignment.
Once unit has been in operation and thermal expansion K. FAN DRIVERS (MOTORS. ENGINES, TURBINES)
complete, recheck coupling alignment, making adjustments if
(Fan drivers may be supplied by Robinson or by others.)
necessary.
STARTING TIME
11. Inspect gasket for tears or damage.
The starting time can be calculated as follows:
12. Install gasket between coupling halves. Coupling flanges
(WR²) (delta RPM)
should then be drawn together keeping gasket in line with bolt time =
holes. (307.2) (avail.torque)
13. Bolts, lockwashers, and nuts are now to be inserted and time (seconds)
tightened. delta RPM = change in speed (rev/min)
avail. torque = (motor torque capability)-(fan torque require-
14. Lubricate according to specifications as outlined in grease
ment) at all speeds from zero to normal operating
lubrication charts found in maintenance section.
speed (lb-ft)...see Figure 24
W R ² =fan rotor rotational moment of inertia (lb-ft²)
FlGURE 13
PREMATCHED/PREMARKED
FIGURE 16

EXPOSED BOLTS

FIGURE 13 KOP-FLEX SERIES ‘H’ GEAR COUPLING.


Mac-C®AND FAST®ARE REGISTERED TRADEMARKS OF KOP-FLEX, FIGURE 16 NON-LUBRICATED METAL DISK-TYPE COUPLING
INC.

FIGURE 17
FIGURE 14

Back

FlGURE 14 FALK “T10” STYLE STEELFLEX COUPLING


DRIVING FLANGE OUTER MEMBER INNER MEMBER RUBBER ELEMENTS

FIGURE 17 E X P L O D E D VlEW OF HOLSET PM COUPLING


FIGURE 15 OFTEN RECOMMENDED FOR VARIABLE SPEED DRIVEN UNITS
(INSPECT ELEMENTS ONCE/YEAR AND REPLACE IF NECESSARY)

TO INSPECT THE RUBBER ELEMENTS, UNBOLT THE COVER OF THE


COUPLING SO THAT THE FACES OF THE RUBBER BLOCKS CAN BE
SEEN. IT IS NOT NECESSARY TO REMOVE THE RUBBER ELEMENTS OF
THE COUPLING. THE RUBBER ELEMENT SHOULD BE REPLACED IF
ANY OF THE FOLLOWING ARE FOUND:
-DEEP CUTS, OVER 10% OF THE WIDTH OF THE RUBBER ELEMENT.
-RUBBER ELEMENTS WHICH ARE LOOSE IN THEIR CAVITIES.
-RUBBER ELEMENTS WITH CRACKED OR STICKY SURFACES.
LARGE AMOUNTS OF RUBBER DUST AND AN IMPRESSION OF THE
FIGURE 15 FAST® GEAR TYPE COUPLING COUPLING INNER MEMBER ON THE COVER ARE SIGNS OF EXCESSIVE
MISALIGNMENT.
MAX-C®AND FAST®ARE REGISTERED TRADEMARKS OF KOP-FLEX,INC
11
Contents
FIGURE 18 Back FIGURE 19 Back

I ,

GAP AND ANGULAR OFFSET ALIGNMENT


ALIGNMENT Align so that a straight edge rests squarely (or
Use a spacer bar equal in thickness to gap within the limits specified in Table 1) on both
specified in Table 1. Insert bar, as shown h u bs as s h o w n a b o v e and also at 90º inter-
a b o v e , t o same depth at 90º intervals and vals. Check with feelers.
measure clearance between bar and hub face
with feelers. Courtesy The Falk Corporation

Courtesy The Falk Corporation


Back MEASURE CLEARANCE WITH
FEELER GAGE HERE
\

FIGURE 20 ANGULAR MISALIGNMENT Back


HUB DIA OUTSIDE MAXIMUM ALLOWABLE ANGULAR MISALIGNMENT
Inches (Difference in inches between
Coupling hub gaps measured 180 apart,
Components, Inc., Link-Belt Bearing Division
LOAD ON BEARING
2 0.001
4 0.002
ADAPTER MOUNT SPHERICAL ROLLER INTERNAL CLEARANCE TOLERANCES AS
6 0.003
MEASURED WITH A FEELER GAGE BETWEEN THE ROLLING ELEMENT AND THE
8 0.004
10 0.005 OUTER RACEWAY.
12 0.006
14 0.007 Reduction in Min. Permissible
16 0.008 Final Clearance
18 0.009
20 0.010

Angular Misalignment Parallel Offset Misalignment

*Special increased clearance fit bearings supplied through Robinson Industries


PARALLEL OFFSET MISALIG N M E N T
FIGURE 22
SPEED PARALLEL OFFSET MISALIGNMENT
(RPM) (Maximum allowable total indicated runout)
APPLICATION DATA
NATIONAL ELECTRIC CODE REQUIREMENTS FOR 1 HP TO 200 HP MOTORS
3600 0.002 - 0.003
1800 0.004 - 0.005
1200 0.005 - 0.006
900 0.005 - 0.006
720 0.005 - 0.006

NOTES

1 ALIGN DRIVER TO THE FAN


2 DETERMINE IF THE DRIVER NEEDS TO BE SET LOW TO ALLOW FOR
THERMAL EXPANSION OF THE DRIVER. FOR ELECTRIC MOTORS A
GENERAL GUIDELINE IS TO ALLOW 0.001 IN. PER INCH OF MOTOR
SHAFT DIA.

I
T h e s e harts are for reference only. Detailed electrical requirements should be
determined by customer’s electrical engineer or electrical contractor.

12
Contents
Most single speed fans will achieve full operating speed in 25 STARTERS AND CONTROLS
seconds or less. Longer starting times can result in motor Full Voltage Starting (Across-the-Line) initially connects the
overheating. The following are typical causes of excessively motor directly to the power lines. The advantages of this
long starting time: method are its low cost, high starting torque, low maintenance,
1. Driver torque not adequate for fan rotor WR². and the fact that it may be used with any standard motor. Note
that the high starting torque and high starting current may
2. Low voltage, causing reduction in motor torque capability.
shock the driven fan equipment.
3. Partially open fan inlet damper, causing increase in fan
Auto Transformer Starting (Reduced Voltage) limits input
torque requirement.
voltage and reduces inrush current. Normally an adjustable
4. Low temperature (high density gas) causing increase in fan timer is provided for switching to full voltage after the motor has
torque requirement. partially accelerated. Note that motor output torque is reduced
5. Driver speed-torque curve not providing enough available by the square of the voltage reduction at the motor and,
torque when compared to fan torque requirement (especially on therefore, starting time is extended.
gasoline/diesel engine driver units). W ye Start/Delta Run allows starting at reduced phase voltage at
NOTE: Drivers are often sized for the operating horsepower at reduced load and inrush current. Starting voltage is full voltage
process temperatures and are incapable of starting the fan at divided by the square root of three. High transient currents are
cold conditions unless the inlet damper is fully closed through- possible at the transition from wye to delta. This is a non-
out the start-up. standard motor connection that must be specified at order time.

Starting switch gear, overload protection, and other electricals Note the full load amperage and the motor service factor as
are supplied by others unless specifically stated in the purchase listed on the motor name plate. Monitor the motor current and
order. DO NOT OPERATE THE MOTOR IN AN OVERCURRENT
CONDITION. In most cases the fan must be connected to the
MOTOR OVERCURRENT PROTECTION system ductwork and/or dampers closed to provide a system
The electric current during starting is typically 5 to 7 times the resistance before operating the fan.
motor full load current. Motor thermal overload protection is
ln general, on motors above 200 HP, do not restart more than
recommended to prevent burnout from misapplication or ex- once every 30 minutes. Detailed start-up limitations are available
cessive number of starts. Thermal overload protection must be from the motor manufacturer.
selected to allow high current for up to 25 seconds or more in
some cases when starting high-inertia fans. The National VARIABLE FREQUENCY AC APPLICATIONS
Electric Code allows dual element time delay fuses to be rated at To avoid torsional natural frequency problems, a special coupling
125% of the motor full-load current for all AC squirrel cage may be required. Operation below 30% of the motor normal
motors with full voltage, resistor, reactor, or auto-transformer speed at 60 Hz should be reviewed with the drive supplier.
starting under normal conditions. In cases where this rating is Variable frequency drives should be properly matched to the
insufficient for the starting current of the motor, the rating of the motor.
fuses may be increased up to a maximum of 140% of the motor
Belt drives are not recommended for variable speed applica-
full-load current. (Refer to Articles 430-31 through 430-34 of the
tions.
National Electric Code). See Figure 22.

FIGURE 23
FIGURE 24 Back
MAXIMUM INERTIA LIMITS AND ALLOWABLE ACCELERATION TIME
MOTOR TORQUE
PROTECTED . ENCLOSED CAPABILITY

FAN REQUIRED
‘TORQUE (WITH
DAMPER CLOSED)

PERCENT SPEED

TYPICAL SPEED/TORQUE CURVES

FIGURE 25 Back
O P T I O N A L A S S E M B L Y POSlTIONS

FLOOR MOUNTED

STANDARD F-1 STANDARD F-2

CONDUIT BOX LOCATIONS

Contents
13
SYNCHRONOUS MOTORS d. It will be necessary to readjust tensioning the first few hours
These drivers are designed to eliminate the slip that occurs in of operation after new v-belts have been installed.
induction speeds of 3600, 1800, 1200, 900 rpm, etc. They are e. Periodic inspection and alignment of the drive is recom-
rarely used in fan applications. High transient torque pulses are mended.
common with synchronous motors and can lead to coupling
and/or shaft failures. Refer to manufacturer’s instructions, attached, for further
information.
MOTOR BEARINGS
Refer to motor manual for motor bearing lubrication instruc-
tions. The recommended vibration alarm and shutdown limits M. BOLTED INLET BOX CONSTRUCTION Back
for the motor bearings are the same as the limits for the fan [Applies only to large fans shipped with separate inlet box/boxes].
bearings. Motor bearing loads must be adequate for rotor Bolt the inlet box(es) to casing before setting the assembly on
weight on Arrangement #4 and for belt pull on Arrangement #1 the foundation. Only after all installation and alignment pro-
and #9. Large horsepower motors are sometimes supplied with cedures are complete is welding of the Inlet box(es) to take
sleeve type bearings which allow axial shaft movement. In such place. Inlet box is to have continuous weld inside and stitch weld
cases a limited end-float coupling must be used. (Refer to outside. Housing brace bars and inlet box brace bars are to be
coupling section). Do not use a sleeve bearing motor on belt- welded together where they meet. Check that split bars on inlet
driven applications. box line up with respective split bars on housing. Refer to Figure 26.
OTHER NOTES:
N. GROUTING UNIT
-Conduit box location is important on Arrangement #1 and
Arrangement #9. F1 is standard; F2 non-standard. See Figure Following completion of installation and alignment, it is sug-
gested that a Robinson service man check the installation
25.
before any grouting is done. Robinson service fees are noted on
-Drive rotation must be specified to match required fan Schedule List #9100. After inspection, grouting may be com-
rotation. Note that fan rotation is “as viewed from the motor pleted. Robinson recommends the use of U.S. Grout 5-Star
end” and motor rotation is “as viewed from the end bell” Epoxy (mix A and B...add C aggregate). or Chockfast grouting
(opposite the shaft end). Gasoline and diesel engine rotation is systems.
“as viewed from the shaft end” and are available only in counter-
clockwise rotation. O. SPECIAL FEATURES
-On all belt driven fans the motor must be mounted on a slide DAMPERS
rail base for proper belt tension adjustment. Dampers are furnished in separate channel sections either
-Drivers mounted on concrete pedestals require an auxiliary structural or fabricated. It is best to close the damper when
steel base or soleplate. This mounting plate must be shimmed installing to prevent damage to the damper blades. Damper
(during alignment) prior to final grouting. blades and linkage are preset to give a tight fit between blades
when the damper is closed. Check the damper operation to
insure that all blades can operate without binding and can close
L. V-BELT DRIVE ALIGNMENT Back tightly. On double inlet fans, inlet box dampers are controlled
To insure proper alignment, tensioning, and long belt life from a common shaft, usually arranged for automatic control.
perform the following procedures:
Check all levers, linkage, and blade hardware to see that they
1. Check that motor and fan shafts are parallel. Shim motor if are secure. Mount dampers in place on inlet boxes and position
necessary. control shaft to housing according to assembly drawing.
2. Check for axial alignment of fan and motor sheaves. Information concerning damper bearing lubrication is shown in
3. Balanced sheaves of special materials are required above the table below. Frequency of lubrication per the following table
6500 ft/min. peripheral speed. is every 4 weeks. Refer to fan assembly for further information
concerning lubrication of damper bearings, if required.
4. Properly adjust tension of belts:
FORCE DEFLECTION METHOD
FIGURE 27
a. Move driver unit forward to allow for easy installation of Back
belts onto sheave.
b. Refer to manufacturer’s instructions for required force and
deflection values. i A +
c. Using a spring scale, apply a perpendicular force to any one
of the belts. Increase or reduce the centers as is necessary to
T-7 LOUVERED
DAMPER
obtain proper deflection.

FIGURE 26 BOLTED INLET BOX CONSTRUCTION


Back
HOUSING
BRACE BAR 7 HOUSING SIDE

FAN HOUSING

STUDS
4 INLET BOX SIDES

ARE FOR ALIGNMENT TO


CLOCKWISE ROTATION SHOWN
HOLD INLET BOX IN BRACE BAR (FROM DRlVEN END)
POSITION FOR FIELD WELDING

NOTE. In some cases, inlet boxes will be shipped separate from housing but INLET DAMPER MUST BE ORIENTED SO THAT
bolted to the housing in the field and welded, as shown, by others. Housing IT PRESPINS THE GAS STREAM IN THE
brace bars and inlet box brace bars are to be welded together where they meet. SAME DIRECTION AS IMPELLER ROTATION
Also check that split bars on box line up with respective split bars on casing
14
Contents
SHAFT/BEARING AMOUNT OF
FIGURE 29
SIZE (INCHES) GREASE (IN³)
Back
1/2–1 0.12
1-1/16–1-7/16 0.30
1-1/2–3/16 0.45
1-7/8–2-3/16 0.52
2-1/4–2-7/16 0.56
2-1/2–3 1.36
3-1/16–3-1/2 2.24
3-9/1 6–6 5.00

After installation manually operate the damper several times to RECOMMENDED PACKING SPLICE CUT
insure that nothing interferes with damper operation. Check
inlet damper operation for correct rotation relative to the fan.
Inlet dampers should spin the gas stream in the same direction SHAFT SEALS
as the fan rotor rotation when partially open. Refer to Figures 27 Standard shaft seals are made from compressed fibrous
and 28. materials that can expand and contract to compensate for
NOTE: vertical expansion of fan housing. Special shaft seals involving
Field installation of the tie rod, couplings and bearings is often carbon rings and/or mechanical seals for gas tight operation
required on double inlet fans. Be sure that the dampers are may require center-supported housing construction. See
synchronized throughout the full range of operation. Figures 30, 31, and 32 for examples. On high temperature fans,
On dirty gas streams, dust build-up may occur and hinder packing gland type shaft seals often include water-cooled
movement of the vanes. If the damper normally requires cavities to prevent overheating of the packing, as in Figure 34.
operation over a small range, and only occasionally is required See assembly drawing for your application.
to move to full open or full closed position, it is recommended General instructions for installation of packing gland seals:
that full open and full closed positions be reached daily for the 1. Clean the packing gland thoroughly. If old packing is being
purpose of sweeping accumulated dust from damper vane area. replaced make sure all old packing is removed. Check shaft for
DAMPER OPERATORS smoothness. Scored shafts should be repaired or replaced. See
If the operator was installed at the Robinson factory, the unit Figure 29.
should be ready for connection to utilities and can be put into 2. Install rings one at a time using split ring bushings or
operation after reviewing specific product instructions (at- packing tamper to be sure that each ring is seated properly
tached). If operator is to be field installed: before adding next ring.
1. Adjust operator to damper control arm linkage to allow free 3. Make sure that the joints are staggered 90º apart.
operation over the full 90º operating range. Cycle several times.
4. Turn shaft by hand to make sure that rings are free and not
2. Check damper blades (visually) to be sure they are fully installed too tightly.
closed and fully open when moved by the operator to the
5. Tighten packing gland until finger tight, then start equip-
indicated open position.
ment and carefully tighten the gland to reduce leakage. Make
3. On modulating systems, set-up an input signal to the sure that during this adjustment period the temperature of the
damper operator controller to insure that the operator output packing gland does not rise. An adjustment of approximately 1/8
responds correctly to variations in the input signal. turn at a time is maximum. Allow approximately 15 to 20
minutes between adjustments for the packing to adjust to its
FIGURE 28 Back new load. If, during this period, heating occurs, back off on the
gland and allow to run until packing gland cools. This process
could take several hours on a high temperature application.
6. In some cases a lantern ring, along with a purge tap, is
supplied with a packing gland seal. As an alternate, a purge tap
only may be supplied. Refer to the assembly drawing for
instructions as the tap may be for a gas purge, or, in some cases,
for lubrication, depending on instructions.
7. For replacement seal material information, please refer to
the fan assembly drawing or consult Robinson Industries.
HIGH TEMPERATURE FANS
HIGH TEMPERATURE DESIGN LIMITS
Observing the maximum operating temperature as noted on the
assembly drawing is essential for insuring satisfactory operating
life. Material yield strength as well as creep and rupture strength
properties drop off dramatically with only slight increase in
temperature. When designing furnaces, avoid a direct line-of-
sight from the heat source to the fan rotor. This radiant energy
can greatly increase the actual rotor operating temperature and
cause premature failure unless taken into consideration during
design stages.
All high temperature fans are furnished with temperature
FIGURE ILLUSTRATES INLET DAMPER
sensitive pellets that serve as a record of the highest temperature
P O S I T I O N I N G T O PRESPIN AIR IN SAME to which the rotor has been exposed.
DIRECTION AS THE IMPELLER ROTATION

Contents 15
TEMPERATURE RATE-OF-CHANGE HlGH TEMPERATURE EMERGENCY SHUTDOWN AND
AUXILIARY DRIVES (TURNING GEARS)
Maximum allowable heating or cooling rate for Robinson fan
equipment is 100º F./hour, unless otherwise specified. If desired, In the event of power failure or interruption in fan operation at
special designs are available to permit temperature changes in high temperatures, it is imperative that the fan be rotated by
excess of 100° F./hr. If temperature rate-of-change is exceeded. hand or other available means continuously until the gas
loosening of hub to shaft fit may occur, resulting in high temperature decreases to 200º F. or lower. Failure to do this
vibration, movement of the rotor on the shaft, impeller cracking, may result in permanent distortion of the shaft which in turn
etc. Thermal fatigue and premature rotor failure can result if would cause high vibration. An auxiliary drive (turning gear) is
extremely rapid changes in temperature occur desirable with large fans for slow rotation of the fan rotor during
shutdowns. The low RPM auxiliary drive also helps eliminate
extremely high vibration levels that can occur upon restarting.
FIGURE 30 GASKET SHAFT SEAL
Back Auxiliary drives are typically designed to maintain a minimum
speed (i.e. 40-60 RPM) as the fan slows down. They are
typically not intended for use in starting the fan rotor from a
dead stop.
HIGH TEMPERATURE CORROSION
PLATE Due to the presence of certain chemical compounds, special
alloys or special treatment of material exposed to high tempera-
tures may be required. Sulfidation and carburization are two
common examples which can occur. Evidences of such
problems include metal embrittlement, surface pitting, cor-
rosion of fillet weld material, etc. Contact the factory or advice
on combatting these problems.
CLEARANCES
Special clearance requirements may be necessary at inlet piece

iI
p\_ HOUSING OR INLET BOX to rotor fit-up area to allow for the vertical expansion of housing
and axial expansion of shaft. The fit-up will be non-symmetric
during initial ambient fit-up so that symmetry is achieved during
the designed high temperature operation.
HEAT FLINGERS

FlGURE 31 PACKlNG G L A N D
Heat flingers of aluminum (or other highly conductive material)
are often used on fans above 250° F. to reduce flow of heat
Back through the shaft to bearings. These are typically clamped onto
the shaft. Rotate the rotor and shaft assembly to be sure the heat
GASKET
flinger turns freely without contacting the guard.
i , ADJUSTING SLEEVE
BEARlNG BASE
Bearing base may be separated from fan housing on some high
temperature units. Check assembly drawing to see if shipping
angle bolts should be disconnected before the fan is put into
operation. Refer to Figure 33.
WATER COOLED SHAFT SEAL
A water packing gland may be used on higher temperature
applications. Insure that the specified water flow is maintained
(typically 1.0 gpm). Refer to shaft seal section for tightening
procedure.
p- HOUSING Other shaft cooling means may be necessary above 1300º F.
This may include air or water-cooling of the shaft. Refer to
assembly drawing and special equipment information if
applicable.
CENTER SUPPORTED HOUSINGS Back
FIGURE 32 PURGED PACKING GLAND
Center supported housings are sometimes provided on high
Back temperature fans with special shaft sealing requirements. By
supporting the fan housing near the shaft centerline, the
housing is free to expand radially in all directions about the
center without affecting shaft seal clearances. See Figures 35
ANTERN RING and 36. Robinson strongly recommends that factory field
service personnel be present during the installation of center
supported fan equipment.
SPECIAL INSTALLATION PROCEDURES FOR CENTER
SUPPORTED FAN HOUSINGS:
1. Refer to fan assembly drawing and center support arrange-
ment detail drawing identified with proper Robinson factory
ADJUSTING SLEEVE
order and customer number for the fan being assembled.
NOTE: ALL HOUSING SUPPORT PLATES TO BE AT SAME
HEIGHT AND LEVEL. INDEPENDENT BEARING PEDESTAL
HOUSING
AND MOTOR SOLE PLATES MAY BE AT DIFFERENT LEVELS
AS SHOWN ON DRAWINGS BUT ALSO MUST BE LEVEL.
Contents
16
FIGURE 33
Back to Page 13
VERTICAL EXPANSION OF CASING No grouting to be done until all components are leveled and
aligned. Refer to other installation procedures for specific
Back to Page 14 details on bearing, coupling, inlet piece, etc.
HEAT FLINGER__ I Al
2. Level and align housing support plates as shown on
__ INLET PIECE drawings using full length steel shims.
3. Install bottom half of fan housing to support plates, be sure
to install sliding pads. Tighten bolts to proper torque and check
AXIAL EXPANSION
outlet flange and inlet flange alignment to ducts. Check fan
TEMPORARY SHIPPING ANGLES_ _ I I
AFTER INSTALLATION, REMOVE
ML 1 1 t OF SHAFT

C E N T R I F U G A L IMPE LLE R
housing to be sure it is level with support plates.
4. Install independent bearing pedestal and motor soleplates.
1/4” SPACER AND LEAVE
|/ |
UNIT UNBOLTED DURING _____________ ____ ________ __________ | Level and align. Install bearing pedestals, level and align
pedestal unit with U-shaped shim at bolts between sole plate
OPERATION L: 1/4” SPACER ’ FAN HOUSING
and concrete. Form for grouting.
‘NOTE FINS ON HEAT FLINGER S H O U L D
FACE THE FAN HOUSING FOR OIL 5. If arrangement #1or #8 with fabricated bearing base or
LUBRICATED SYSTEMS. bearing/motor base, install base, level and align. Use U-shaped
FIGURE 33A
shim pack at each foundation bolt, form for grouting. If bearing
EXPANSION JOINTS & A N C H O R L O C A T I O N S base is used for one or more casing supports, this step must be
done before #3.
Back 0
DUCTWORK 6. Install center anchor plate.
STRUCTURAL ANCHOR
WITHIN 24” OF JOINT 7. Mount bottom half of bearing on to pedestal. Refer to
“Setting and alignment of bearing pedestals” for further installa-
EXPANSION JOINT
EXPANSION JOINT _ tion instructions.
EXPANSlON JOlNTS
WITHIN 24” OF J
Expansion joints are recommended on all fans with operating
temperatures up to 250º F.
Expansion joints are required/essential on all fans above 250º F.
and for fans mounted on vibration isolators/bases.
The expansion joints are to be mounted at the fan inlet and
outlet connections, drain pipes, and other connections to/from
the fan. They must have adequate lateral and longitudinal
FIGURE 34
WATER COOLED PACKING GLAND flexibility to allow for thermal expansion of the fan. The
expansion joints are to be structurally anchored so that no loads
Back will be transmitted from the duct work to the fan. The duct work
must be 100% supported by structural members other than the
PACKING - WATER OUT fan. See Figure 33A.
SHAFT
lNSULATION
-w A D J U S T I N G S L E E V E
FACTORY INSULATION
Factory insulation normally includes a double-walled housing
with a non-settling insulating material. A heavily braced inner
housing is a standard feature. Unless otherwise specified, the
housing is typically designed for an external surface tempera-

P
L
ture of 250º F. or less. Take appropriate precautions to avoid
burn injuries to personnel.
Typically, the housing can be disassembled and the rotor
(-- L WATER IN removed without disturbing the insulation. Refer to “MAIN-
TENANCE, Rotor and Shaft Removal”.
FIGURE 35 FAN INLETS
FIELD INSULATION
Field insulation is normally done “by others” over insulation
Back clips. Be sure that field mounted insulation does not restrict
movement of inlet/outlet expansion joints. The additional
weight of the insulation should be considered in sizing springs if
a spring isolation base is to be used. Leave adequate clearance
CENTER HEIGHT in the area around the shaft heat flinger for air circulation
INCREASES WITH cooling. Refer to Figure 33.
TEMPERATURE

CONCRETE FIGURE 37
SOUND OUTPUT THRU
STANDARD HOUSING OPEN OUTLET OF FAN

FIGURE 36
Back CASING IS FREE TO EXPAND
IN ALL DIRECTIONS
AROUND THE CENTERLINE

SILENCER 1 1

CENTER HEIGHT
DOES NOT CHANGE SPECIAL SLIDING
WITH TEMPERATUR SURFACES

SOUND OUTPUT
THRU SILENCER
CENTER SUPPORTED HOUSING

17
Contents
SPARK RESISTANT FANS couples or electrical resistance temperature detectors; this is an
Fans constructed for spark resistance are made to correspond option available to customers. TTEC and Thomas A. Edison
to specifications as outlined in AMCA Standard 401-66. Classi- type electrical resistance detectors or Leads and Northrup
fications are: thermo-couples are typical of the detectors available. Both
types are mounted by inserting the end of the probe through the
TYPE CONSTRUCTION tapped hole in the pillow block into the liner on sleevoil bearings
A All parts of fan in contact with the air or gas being handled or up to the outer race on anti-friction bearings. See "MAINTENANCE,
shall be made of non-ferrous material. Bearing Temperature Limits” for recommended bearing tempera-
ture alarm and shutdown limits. Robinson recommends spring
B The fans shall have an entirely non-ferrous rotor or loaded detectors. Monitors and wiring are normally supplied by
impeller and non-ferrous ring about the opening through others.
which the shaft passes.
SOUND CONSIDERATIONS
C The fans shall be so constructed that a shift of the rotor or
impeller will not permit two ferrous parts of the fans to rub Sound Power Level ratings shown are decibels referred to 10-¹²
or strike. W att and obtained in accordance with AMCA Standard 300.
Sound Power Level for each band and dBA are calculated per
NOTES: AMCA Standard 301. Levels shown do not include motor or
1. Bearings shall not be placed in the air or gas stream. auxiliary equipment. Refer to Figure 38 information on additive
2. The user shall electrically ground all fan parts. noise effect due to the fan motor or other equipment in the area.

ACCESS AND/OR INSPECTION DOORS Data is for use by a system acoustical design engineer for
evaluation of the fan singularly and within a system. Because of
Access and/or inspection doors are included on fan housings the infinite variations in system arrangements and the many
for inspection of the interior of the fan housing, rotor and shaft. factors which affect sound pressure levels, it is the designer’s
Access doors are to be opened only after the fan has been shut responsibility to properly apply this data based on his knowledge
down and has come to a complete stop. In no case should the of the system. Some guidelines for use of this data are: for
access doors be open unless the fan is at a complete stop and “NEAR FIELD” reported data to apply to ducted inlet and outlet
the driver electrically “locked out”. installations, any opening in the duct must be a minimum of 100
In the case of doors which are hinged to open vertically, it will be ft. away from the fan. Openings within this range are assumed to
necessary for the user to make provisions for safely opening emit a sound pressure equal to the fan Sound Power Level. This
and closing the door considering its weight. The weight will be also applies to untreated inlet and outlet expansion joints. Note
indicated on the door prior to shipment or shown on the that for ducted inlet/outlet the ductwork thicknesses must equal
assembly drawing. If the weight is not shown, obtain it from the the fan housing thickness to achieve the Sound Pressure Levels
factory. Some cases will require mechanical assistance to open noted.
doors.
All hinges and hinge pins are to be periodically checked and
lubricated to make certain that they are in satisfactory condition FIGURE 38
and not damaged or deteriorated. Periodic inspection of the CHART FOR COMBINING NOISE LEVELS
mounting and retaining components must be made to assure Back
that they are in first class condition.
ELASTOMERIC COATINGS (RUBBER, BUTYL, NEOPRENE,
ETC.)
Due to the corrosive nature of gases flowing through the fan,
elastomeric coatings may be used to protect the fan from
corrosion, premature aging, etc. These fans have special
considerations to be taken into account while fan is in operation
and prior to performing maintenance.
No welding is to be done on the outside of housings coated with
0 2 4 6 8 10 12 14 16 18
elastomeric materials. This would result in damage to the
DIFFERENCE IN DECIBELS BETWEEN
coating. Gas stream temperature limits must be strictly observed TWO LEVELS BEING ADDED
so as not to damage the coating. Some coatings, especially
natural rubber, are flammable, causing potentially hazardous
conditions if operating temperature is exceeded. Refer to
assembly drawing for maximum operating temperature.
Exposure to certain chemical agents in the process environment
could cause deterioration of coating. Exposure to gasoline,
cleaning fluids, abrasives, paints and other such materials FIGURE 39
FREE-FIELD SOUND DISTRIBUTION
should be avoided with many elastomers.
Elastomer coated fans warrant special care in handling to avoid Back ,,-----., v SILENCER
damage to surface. Spark testing should be used to detect holes
or imperfections in elastomer coating once every 6 months in
highly corrosive environments. Damaged areas should be
repaired using a patch kit with proper material, adhesive, and
curing conditions as prescribed by the original supplier of the
coating. Lw = Sound Power at
Accoustic Center
Should in-field balancing be necessary, consult with Robinson of Fan
Field Service Group for special techniques used on elastomeric THRU HOUSING
Lp¹ = Sound Pressure Level
coated fans. (NEAR FIELD)
TEMPERATURE DETECTORS Lp² = Sound Pressure Level
(Beyond NEAR FIELD)
It is recommended that bearings be equipped with thermo-

18
Contents
VIBRATION DETECTORS
CONCRETE
FIGURE 40 FAN STRUCTURE SUB-BASE
FILLED BY
It is strongly recommended that bearings be equipped with
seismic vibration detectors mounted on the bearing housing or
Back on the bearing pedestal. This is an option available to customers.
Accelerometer type devices mounted directly on the bearing are
recommended. Such units should have adjustable alarm and
shut down vibration set points and solid state electronics that
are reliable over a long period of time with a high degree of
accuracy.
The operation of these vibration pickups should be checked
FLOOR OR STRUCTURAL STEEL
monthly and calibrated at least once every 6 months. The use of
SPRING ISOLATION BASE these is highly recommended as operation at high vibration
levels may result in catastrophic failure with resultant damage to
equipment and injured personnel. Vibration monitors and wiring
NEAR FIELD - A hemispherical space where sound pressure are typically supplied by others.
waves from one radiating surface tend to interfere with waves
generated by other surfaces. NEAR FIELD boundary, distance PAINT
from radiating surface, is related to the wavelength of lowest Steel equipment will normally be supplied with one coat of red
frequency and overall size of source. oxide primer (suitable for acceptance of a wide range of
FREE FIELD - Area beyond near field, with no obstructions, customer finish coats) unless special paint is requested. No
where Sound Pressure Levels decay 6 dB for each doubling of paint will be applied to stainless steel or aluminum parts. Take
distance from near field. Effects of the room constant (for indoor care in the handling of painted parts to avoid scraping that could
installations), background noise levels, and directivity are not result in rusting. Painted steel parts that are to be stored more
considered. See Figure 39. than two months prior to being placed in service should be
stored indoors at reasonable levels of temperature and humidity.
The tolerance on Estimated Sound Power and Sound Pressure Refer to storage section.
Levels is typically +/-2 dBA plus the accuracy tolerance of the
measuring instrument.
VIBRATION ISOLATION
Vibration isolation bases reduce the transmission of vibrational
energy from a rotating fan to the structure on which it is III. O P E R A T I O N
mounted. Robinson recommends that all fans which must rest
on steel structures with stiffness < 1.0 x 10^7 Ibs/in. be mounted on
A . RECOMMENDED OPERATIONAL PARAMETERS
spring isolation bases. See Figure 40. BEARING VIBRATION LIMITS
Transmissibility (the degree of isolation, related to the pro- Alert supervision when any reading increases by more than 50%
portion of the disturbing force) is expressed as: in one week or if the levels exceed the alarm level as shown in the
1 attached vibration severity chart, Figure 41. Shutdown for
T=
(f/fn)² - 1 balancing and inspection may be required above this level.

where f is the fan operating speed, and fn is the spring base BEARING TEMPERATURE LIMITS Back
natural frequency. Transmissibilities of 5% should be targeted, TYPE BEARING ALARM SOUNDS SHUTDOWN
while transmissibilities which remain under 10% are normally
anti-friction 200º F. 220° F.
acceptable.
sleeve 180º F. 190º F.
Expansion joints should be fitted to the fan inlet and outlet.
Do not run bearings at excessive temperatures; it can result in
Refer to sections on duct design and high temperature fans for
premature failure.
more information on expansion joints.
COOLING WATER FLOW AND TEMPERATURE
PROCEDURE FOR FILLING CONCRETE INERTIA, VIBRATION
ISOLATION BASE: See assembly drawing for cooling water flow and temperature.
Water flowrate is important. Too little flow means over-
1. Position empty frame in place on tar paper or visqueen.
temperature operation. Too much flow can lead to higher
2. Fill with concrete to top flange. (Concrete by others.) lubricant viscosity and reduced film stiffness. Refer to assembly
3. After concrete has completely cured, mount fan securely to drawing for proper flow.
the inertia base with the base resting on a level surface.
PROCEDURE FOR LEVELING VIBRATION ISOLATION BASE: B. START-UP
(WITH OR WITHOUT CONCRETE) BEFORE STARTING FAN, COMPLETE THE FOLLOWING
1. Position fan/base unit in the desired position. LIST:

2. Raise unit to allow clearance for the spring elements. 1. Lock out the power source.

3. Install spring elements as shown on this drawing according 2. Check and tighten hold-down bolts.
to size and location. 3. Check and tighten rotor setscrews.
4. Loosen nuts on the horizontal restraints (one on each end) 4. Rotate rotor to see that it does not rub and maintains proper
to allow ¼" clearance between lock nuts and the steel housing. inlet piece/rotor clearances.
5. Tighten the spring elements adjusting nut, no more than 5. Check coupling and bearings for proper alignment.
one full turn at a time, working your way around the base, one
6. Check fan and ducts for any foreign material or dirt build-
spring at a time, until the unit lifts off spacer shims at both ends
of each spring. Remove spacer shims. up.
7. Secure all access doors.
6. Final leveling to be done as in Step #5, except only turn
adjusting nut ½ turn, before moving on to the next spring. 8. Check lubrication of bearings, couplings, drive unit, etc.
19
Contents
9. Secure and check safety guards for clearance. 15. During a run-in period make observations of bearings at
10. Bump start and check for proper rotation (after lube least once an hour. Higher bearing temperatures may result if
system is operating). bearings are over-lubricated.
16. Refer to Trouble-Shooting Guide for any unusual occur-
11. Close dampers for adequate system resistance to prevent
rences encountered during the run-in period. Only after any
drive unit from overloading. Insure dampers are closed by a
vibrations, misalignments, etc. have been corrected may the fan
visual check inside.
be restarted.
12. Supply water to water-cooled bearings as instructed.
NOTE:
13. Start the equipment according to recommendations of Be sure to lock out power source when making corrections to
drive unit and of starting equipment manufacturers. system operation.
14. Allow fan to reach full speed, then shut down. Make
immediate corrections if any vibrations or unusual sounds have
been detected.

FIGURE 41
GENERAL MACHINERY
VIBRATION SEVERlTY CHARTS Back
For use as a GUIDE in Judging vibration as a warning
of Impending trouble

NOTE 1 RIGID SUPPORT


The fundamental natural frequency of the
machine/support system is higher than the operating
speed
excellent — 0 to .10 in/sec
good - .11 to .25 in/sec
alarm - .26 to .50 in/sec
shutdown - > .50 in/sec

NOTE 2 FLEXIBLE SUPPORT


The fundamental natural frequency of the
machine/support system is lower than the operating
speed.
excellent — 0 to .15 in/sec
good - .16 to .40 in/sec
alarm - .41 to .75 in/sec
shutdown - > .75 in/sec

FIGURE 42

Back
PEAK STATIC PRESSURE

NORMAL (DESIGN)
OPERATION

RESISTANCE

ACFM

Contents 20
C. TROUBLE-SHOOTING

Back
TROUBLE-SHOOTING GUIDE

PROBLEM: CHECK FOR:


Vibration 1 Loose bolts in bearings and pedestals, or improper 10. Misaligned v-belt drive.
mounting. 11. Improper wheel rotation.
2. Defective bearings. 12. Operation near system critical speed.
3. Improper alignment of bearings and coupling. 13. Shaft bent or distorted during high-temperature
4. Out of balance fan wheel shutdown.
5. Loose setscrews holding wheel to shaft. 14. Defective motor
6. Weld cracking. 15. Resonant frequencies of structural steel
7. Improper fan wheel clearance to inlet piece(s). mounting.
8. Material build-up and/or wear on wheel. 16. Loose v-belts.
9. Insure expansion joints in ductwork are not fully 17. Beat frequency with other fans on common base
compressed. 18. Loose hub to shaft fit.

Duct Pulsation This often occurs when a centrifugal fan is operated on a system with high resistance. The fan is forced to operate far
below the normal or design volume. If the operating volume is lower than the value corresponding to the fan’s peak
static pressure, instability (surge) can occur. (Refer to Figure 42). Possible solutions include:
1. Increase operating volume (reduce system resistance).
2. Control volume with a radial inlet damper.
3. Add a “blow-down” valve on fan discharge to allow discharge of part of the gas stream to atmosphere.
4. Recirculate a portion of the gas stream back to the fan inlet.
5. Change to a special “surgeless” blower design. (Robinson Patent #4,708,593).

High Motor 1. Improper ventilation of cooling air to motor, (may be 4. High ambient temperature.
Temperature blocked by dirt). 5. Motor cooling fan is incorrect rotation for full cooling.
2. Input power problems, (especially low voltage).
3. High amperage.

Noise 1. Squealing v-belts, due to misalignment or improper 6. Rubbing of shaft seal, wheel to inlet piece, or wheel to
tensioning. housing.
2. Defective bearings, or bearing seal rubbing. 7. Heat flinger is contacting guard.
3. Misaligned bearing seal. 8. Coupling failure.
4. Misaligned housing shaft seal 9. Untreated expansion joints.
5. Foreign material in fan housing. 10. Ductwork is thinner than housing.

Poor Performance Incorrect fan rotation. 5. Prespin condition at fan outlet, add splitter plate to
Wheel is off-center; poor Inlet piece fit-up allows inlet box.
recirculation of air. 6. Inlet damper installed backwards (counter-rotation).
Fan drive sheaves selected for too low or too high 7. System resistance is excessive compared to design
RPM. requirements, (partially closed damper may be the
Poor duct design. Installation of elbow splitters or cause).
turning vanes could remedy problem. 8. Fan speed too low/high.
9. Density may be different than design density.

High Bearing 1. Defective bearings. 6. V-belts too tight or too loose.


Temperature 2. Over lubrication. 7. Improper location not enough room for free axial
3. Improper lubrication or contaminated lubricant. movement of floating bearing in its housing at elevated
4. Lack of lubrication, cooling fluid, or circulation. temperatures.
5. High ambient temperatures or direct exposure to 8. Low cooling water flow rate.
sunlight. 9. Heat flinger missing.

Excessive Starting 1. Motor improperly sized for fan wheel W R ² . 4 Temperature at Inlet is excessively low (high density).
Time 2. Inlet dampers not closed during start-up. 5. Low voltage at motor terminals.
3. Properly selected time-delay starter/fusing required, 6. Inadequate system resistance.
(many industrial fans take up to 20-25 seconds to
reach operating speed). See page 10.

NOTE: Do not exceed motor manufacturer’s specified number of starts per hour.

Contents 21
VIBRATION DIAGNOSTIC CHART D. MAINTENANCE
Probable Disturbing Dominant
Source Frequency Plane WATER SPRAY CLEANING SYSTEMS
The following are recommendations for use of water spray
Rubbing Subharmonic Radial Surging: aerodynamic
symptoms can occur at
cleaning systems:
reduced flow rate Inspect
w h e e l & inlet piece &
1. Use only drinking quality (city) water (40 psig required).
for possible contact.
shaft seal.
2. Requirements at fan inlet: 1 GPM/16000 CFM/each inlet
- FULL JET SPRAY.
Unbalance 1 x RPM Radial Field balance. Robinson
servicemen available. 3. Requirements at web and shroud: 1GPM/32000 CFM/each
Motor Problems 120 Hz All Peak disappears inlet - FULL JET SPRAY.
instantly when power to
motor i s cut off. 4. Initially, use water spray system intermittently to determine
Parallel Radial Most misalignments will the exact amount of time (and thus the amount of water)
(1x.2xRPM) be combination. Errors required for satisfactory cleaning.
Axial are most c o m m o n in the
Angular
(1x.2xRPM)
vertical plane Through 5. A periodic check of the rotor for erosion is mandatory.
use of laser alignment
Both Radial & devices, Robinson can 6. Piping from supply line to spray unit must include a manual
(1x.2xRPM) Axial check for alignment
accurately.
or automatic valve for shutoff and regulation; installation is to
be consistent with good piping practice.
Radial The presence of ½ X RPM
multiples of peaks are a sign of 7. Provide proper drainage from housing and inlet box(es)
1 x RPM. progressed mechanical
as high as looseness. Check for when using sprays. To drain inlet boxes, a vertical seal loop
10 x RPM loose bolts, bearing. below the drain point must be used to provide a height equal to
poor shimming, etc. the fan negative pressure.
Defective
Bearings. 8. Allow for approximately a 5% increase in horsepower when
1. Anti-friction EARLY Radial. Bandwidth broadens as sprays are in use.
STAGES:- except bearing degrades Check
30k-60k cpm higher axial for “bumping” or other BALANCING
depending on on thrust unusual sound in the
size & speed bearings bearings Also. look for Robinson field servicemen are recommended for performing
overheating (190º F and field balancing. Balance weights must be of the same material
LATE STAGES:
above). Check inner race
high 1x and as the rotor. Welding of balance weights should be done using
to shaft fit. loose
multiple
harmonics
attachment. Robinson approved field welding procedures for the type of
material involved.
2 Sleeve EARLY Radial High baseline energies
STAGES: below 1x, 2x, 3x RPM FIELD REPAIRS
sub-harmonics Look for poor babbitt to
housing fit, improper Fans for heavy duty operation require inspection to insure
LATE STAGES
will appear as
plunger screw torque continuity of operation. When an inspection reveals the
w o r n thrust collars.
mechanical
scoring, dirty lubricant.
presence of corrosion or erosion to fan components, it is
looseness (see
advisable to analyze the cause and take steps to provide
above)
replacements or repairs. Your local Robinson representative
Blade/Vane Pass (# of blades) Radial Aerodynamic related. can be of assistance in such cases and obtain factory recom-
Frequency x RPM
mendations that might be needed. Under no circumstances
Resonance Requires only Axial or Vibration amplitude varies should any welding be attempted on rotors except with specific
a small forcing Radial with time or temperature.
function to System shows extreme written welding recommendations from Robinson Industries.
excite its sensitivity to slight
natural amount of unbalance. LUBRICATION
frequency. Structure can be bump-
tested to determines its
BEARING LUBRICATION
natural
frequency.
Protective circuits should be set to alarm when bearing lubrica-
tion temperature exceeds the values shown in “MAINTENANCE
Belt Drive:
Bearing Temperature Limits”. Alert supervision if bearing
1. Mis-matched Many Radial- Check each belt for
worn or stretched multiples of especially. appropriate tension. temperatures change abruptly or if circulating oil flow rate is
(also applies to belt frequency. high in line Replace worn belts with less than the required flow (see bearing operating conditions).
adiustable sheave but 2x belt with belts. matching type.
frequency TYPICAL LUBRICATION SYSTEMS
usually
dominant. CIRCULATING OIL SYSTEMS
2. Eccentric &/or 1x (shaft Balancing Circulating oil systems are recommended for fans operating on
unbalanced speed) possible with washers
sheaves applied to taper lock bolts. critical equipment when downtime must be minimized. Such
systems provide a continuous flushing of filtered lubricant at
3. Drive belt or 1x (driver Axial Check sheave face controlled temperature and pressure which is very desirable for
sheave face speed) alignment (refer to “V-Belt maximizing the life of bearings. These systems are typically
misalignment Drive” section for
method). Confirm
furnished with redundant gear pumps that activate automatically
alignment with strobe to insure continuous lubrication. Local and/or remote moni-
light and belt excitation toring of lubricant level, temperature, flow rate, pressure, etc. is
techniques.
available. Piping for the lubricant return (from the bearing to the
4. Drive belt Belt Radial Adjust belt tension or belt
resonance resonance at length to eliminate
lubricant reservoir) should be large diameter (approximately
only particular problem. Belt stretch 1½” to 2”) and sloped at a minimum of ½ inch vertical per foot
operating natural frequency i s horizontal run. The flow to the bearing must be controlled (by
speeds. excited at particular
operating speed. Avoid
valves or an orifice) to prevent flooding the bearing housing.
these speeds. Maximum distance from the bearing housing to the lubricant
reservoir is 40 feet. The maximum height from the pumps to the
bearing housing is 10 feet. Oil heaters and tracing may be
supplied (by others) if low ambient temperatures are anticipated.

22
Contents
FIGURE 43 STATIC OIL LUBRICATION
FIGURE 45 AIR COOLING SYSTEM
Back
ER INLETS ?fli, /- SLEEVE BEARING
WATER
OUTLETS
OIL LEVEL
INDICATOR
TEMPERATURE
DETECTOR
TEEL BEARING
PEDESTAL

VIBRATION
DETECTOR
PRESSURE BLOWE AIR INLET
L

NOTE: “AIR PUSH” SYSTEM SHOWN. “PULL THROUGH” SYSTEM ALSO


AVAILABLE

FIGURE 44
OIL MIST LUBRICATION
OPTIONAL EXTERNALLY COOLED HEAT EXCHANGER

ANTI-FRICTION BEARING
Back
CIRCULATING OIL SYSTEM

VENTURI

t COMPRESSED
(BY OTHERS)
AIR

L OIL LUBRICANT PUMPS (2)


I I

STATIC OIL LUBRICATION


Static oil lubrication and oil mist lubrication provide other GREASES FOR FAN BEARINGS:
optional methods of lubrication. See Figures 43 and 44.
The recommended lubricant is Mobilith SHC 100 for fan
For oil lubrication use Mobil SHC 626 for most anti-friction
operating temperature below 300º F. Mobilith SHC 220 for fan
bearings. See fan assembly drawing for recommended oil
operating temperature above 300º F.
lubrication for sleeve type bearings.
Other acceptable lubricants are:
NOTE:
Texaco Premium RB #2 (or Texaco 1939 Premium RB)
During shutdowns in cold weather be sure to either drain or Mobilgrease 28
blow out all water from water cooled bearing liners. Freezing Amoco Rykon Premium Grease #2
will cause cracks in the bearing liner that lead to contamination Mobilgrease 532
of the lubricant with water. (Alternatively add an antifreeze to Shell Alvania Grease #2
the water to prevent freezing). Heat tracing of water lines may be Gulfcrown Grease #2
required.
The recommended schedule for greasing is clearly spelled out
SPECIAL INSTRUCTIONS FOR VERTICALLY MOUNTED FAN in the notes on the assembly drawing. You should determine
ASSEMBLIES: exactly how many pumps of your grease gun is equivalent to the
Whenever possible, each vertically mounted fan unit is test run volume of grease required. If the recommended lubrication
in the vertical position before leaving our plant. The bearings are schedule and type of grease is adhered to, you should have
equipped with seals for retaining the grease lubrication. These satisfactory life from the bearings. If substitute greases are used
bearings are described on the assembly drawing. (without our written approval) or the lubrication frequency is
haphazard, our experience shows that premature bearing failures
It has been our experience that vertically mounted units can
can result. Do not mix greases!
have bearing failures if they are not lubricated on strict
schedules. It will be necessary to lubricate bearings more COUPLING LUBRICATION
frequently with this arrangement than if the unit were mounted For applications with ambient temperatures below 150° F., use a
horizontally. If the lubrication frequency is inadequate, the grease as recommended below. For higher ambient tempera-
roller elements can become grease-starved and this will lead to tures, contact Robinson Industries, Inc. for specific recom-
a bearing failure. mendations. Greases listed below are in response to request for
The more frequent lube schedule may result in a somewhat specific recommendations. This list is not complete and is not
higher bearing operating temperature. This should not be a intended to restrict the use of equivalent lubricants manu-
significant problem as long as the ambient temperature near the factured by companies not listed, nor is it intended to exclude
bearing is less than 120º F. The consequences of the more improved lubricants developed since publication of this list.
frequent lubrication schedule are much less severe than the Relubrication every two months based on typical industrial
result of under lubrication in such applications. applications is recommended.

Contents 23
GREASES FOR COUPLINGS: INSPECTION
Amoco........................................Coupling Grease At least once every six months the fan should be shutdown for
Arco...........................................Litholine HEP #1 inspection. Carefully inspect all anchor bolts for tightness and
BP.................................................Energrease LS-EP #1 foundation/grouting for loosening or cracking. Repair any
Brooks........................................Klingfast 370 deficiencies. Check the rotor for wear - especially near the inlet
Chevron......................................Dura-lith #1 piece and along the center web plate. Any significant decrease
Citgo...........................................HEP #1 in thickness of structural parts (i.e. less than 90% of the original
Exxon.........................................Pen-o-led, EP material thickness) remaining should be reported. It may be
Gulf............................................Gulfmill EP-S necessary to repair these areas - contact the supplier.
Mobil...........................................Mobilux EP #1
Drain a sample of lubricant from the bearings. Any milkiness
Shell...........................................Alvania EP #1
may indicate the presence of water contamination. Remove the
Sohio..........................................Bearing Guard MK
top half of the bearing housing and inspect surface condition for
Texaco........................................Marfak #1
damage or scars. Be sure to reassemble using proper
Union..........................................Hi-Temp #2
procedure. Drain oil and change. (See bearing operating
Viscosity.....................................Viscor 1429 EP
instructions and assembly drawing for type of oil.)
For spacers with limited end float thrust plates and for floating
Check coupling bolts, bearing pedestal bolts, and bearing
shaft arrangements, each end must be separately lubricated. mounting bolts for tightness. Check mounting pad hole
clearance (on center supported housings) to be sure ample
clearance exists for expansion and that hold-down bolts are
properly torqued.

FIGURE 47

GREASE LUBRICATION SCHEDULES


(Typical for Ambient Temperature Horizontal Shaft Fans)
...Also refer to Assembly Drawing

APPROXIMATE GREASE RELUBRICATION SCHEDULE

PILLOW SPEED (R.P.M.) GREASE ADDED AT EACH INTERVAL (OUNCES)


BLOCK
NUMBER SHAFT ROLLER BALL
225/226 DIA. 900 1200 1800 3600 BEARINGS BEARINGS

09 1 7/16” 2140 1715 980 515 0.35 0.08


10 1 11/16” ix 2000 1600 900 460 0.37 0.10
11 1 15/16” 5 1880 1495 830 410 0.45 0 12
13 2 3/16” P 1670 1320 705 320 0.67 0.17
15 2 7/16” 1495 1170 600 0 72 0.21
16 2 11/16” i 1420 1105 550 0.83 0.24
17 2 15/16” 2 1345 1040 505 0 97 0.25
18 3 3/16” tf 1280 980 460 1.15 0 26
20 3 7/16” a 1155 875 380 1.49 0.39
22 3 15/16” 1045 775 300 1.91
24 4 3/16” F 940 680 2 24
26 4 7/16” d 845 595 2.65
28 4 15/16" ii 755 515 3.05
30 5 3/16” 9 670 440 3 54
32 5 7/16” 590 365 4 17
34 5 15/16” 515 295 4.79

NOTE: FOR MOST GREASE GUNS 25 PUMPS 1 OUNCE

Contents 24
ROTOR AND SHAFT REMOVAL Back IV. WARRANTY
1. Lockout the fan and damper drive systems electrically.
N O T E : CUSTOMER MUST CONFORM EXACTLY TO SPECI-
2. Disassemble the coupling using proper procedure FICATIONS AS OUTLINED IN WARRANTY. FAILURE TO DO
3. Unbolt and remove the inlet piece(s). SO VOIDS ROBINSON WARRANTY.
4. Locate the “pie-shaped” section of housing designated for
rotor and shaft removal (refer to assembly drawing). Remove all TERMS AND CONDITIONS OF SALE
necessary split and flange bolts. W e guarantee equipment against defects in materials and
5. Carefully remove pie-shaped portion of housing, exposing workmanship for a period of one year from date of shipment and
housing internals rotor and shaft. agree to replace defective parts f.o.b. our factory, free of
charge. However, our liability shall in no case exceed the price
6. Remove top half of bearing housings. Inspect liner and
paid for the goods furnished by us. In this regard, we will under
housing, then store in a clean, dry area.
no circumstances be liable for any consequential damages. In
SPARE PARTS LIST addition thereto, we shall not be liable for any back or other
Robinson recommends that the customer have the following charges on account of work performed on equipment furnished
spare parts on hand: rotor and shaft, one pair of bearings, one by us unless such charges are approved by the Home Office.
set of V-belts (or coupling). Refer to assembly drawing for Furthermore, the equipment is not guaranteed against abrasion,
specific sizes of parts. wear, or other failure due to operation under conditions which
are in excess of design limits. Any alterations to the product
PREDICTIVE MAINTENANCE sold by Robinson Industries, or the failure of the purchaser or
Routine vibration monitoring and trend analysis is recom- its successors to observe safety standards recommended by
mended. This allows early detection of problems so that Robinson Industries, in either the transportation, erection or
potentially hazardous operation or unscheduled shutdowns use of the product sold, will void any warranty made by
can be avoided. Contact Robinson for more information on this Robinson Industries. In the event any field work or erection is
service. required, the customer will remove all obstructions at his own
risk and cost. Outside manufactured items which are ordered
by the customer to be included with the equipment under this
order shall carry only the guarantee and warranty supplied by
that manufacturer and shall carry no guarantee or warranty,
expressed or implied of Robinson Industries, Inc.

Robinson Industries, Inc. Robinson Fans Service & Equipment


P.O. Box 100 P.O. Box 707
Zelienople, PA 16063 Trussville, AL 35173-0707
(412) 452-6121 (205) 655-8312
FAX 412-452-0388 FAX 205/655-8327

Robinson Fans West, Inc. Robinson Fans Florida, Inc.


P.O. Box 65806 P.O. Box 6260
Salt Lake City, UT 841650806 Lakeland, FL 33807-6260
(801) 972-3303 (813) 646-5270
FAX 801/972-3445 FAX 813/646-1712

Contents 25

You might also like