Professional Documents
Culture Documents
Rev 4
Diesel Generator Site Installation Date 27-Nov-17
Method Statement
Pages 1 of 11
`
7.8 RISK ASSESSMENT
Risk Assessment Ref.: LRT-ALST-Y2-WMS-POW-GEN00-505160-A- Related Method Statement: Method Statement For Diesel Generator Site Installation
Residual
HAZARDS Original Risk CONTROL MEASURES the Convey Information
Risk
Manual work /
RISK
RISK
PPE
TRAINING
LIKELIHOOD
LIKELIHOOD
SEVERITY
carriageMachinery , track pulley
Illumination (night works)
Lifting operations, Noise
Hit by falling object
General Education
Legal requirement
Electrocution
Fall hazard
Trip / Falls
Hot work
Man
1 2 3 4 5 6 7 8 9 10 11
Fall from height collective controls to be in place where man can fall to depth
greater than 01 meter
Manual work /
RISK
RISK
PPE
TRAINING
LIKELIHOOD
LIKELIHOOD
SEVERITY
carriageMachinery , track pulley
Illumination (night works)
Lifting operations, Noise
Hit by falling object
General Education
Legal requirement
Electrocution
Fall hazard
Trip / Falls
Hot work
Man
Diesel Generator Installation
Ergonomics
1 2 3 4 5 6 7 8 9 10 11
Competent Lifting Supervisor, operator, Rigger man, lifting plan, 3rd party
certified tools and tackles
Cables are to be double insulated, industrial plug tops and sockets to be used
Manual work /
RISK
RISK
PPE
TRAINING
LIKELIHOOD
LIKELIHOOD
SEVERITY
carriageMachinery , track pulley
Illumination (night works)
Lifting operations, Noise
Hit by falling object
General Education
Legal requirement
Electrocution
Fall hazard
Trip / Falls
Hot work
Man
Diesel Generator Installation
Ergonomics
1 2 3 4 5 6 7 8 9 10 11
X X 3 3 9 Site Engineer, Supervisors and Safety Officers should monitor and control their 1 3 3 X X X X
workers
Supervisors and workers should check & inspect the tag of the power tools
Welders must have the CE/EN standard goggles, welding clothes, welding
respirator.
All welding equipment to be inspected by Main Contractor and must have valid
certificate and colour coded as per project requirements.
Sign board to be provided to warn others regarding the hot work activity.
Ensure that welding machine are inspected by competent authorized person &
tagged accordingly.
Appropriate DCP type fire extinguishers to be kept available in the hot work area
along with trained fire watcher.
Manual work /
RISK
RISK
PPE
TRAINING
LIKELIHOOD
LIKELIHOOD
SEVERITY
carriageMachinery , track pulley
Illumination (night works)
Lifting operations, Noise
Hit by falling object
General Education
Legal requirement
Electrocution
Fall hazard
Trip / Falls
Hot work
Man
Diesel Generator Installation
Ergonomics
1 2 3 4 5 6 7 8 9 10 11
Ensure appropriate exclusion zone and signage are provided around the
installation area.
Rev 4
Diesel Generator Site Installation Date 27-Nov-17
Method Statement
Pages 5 of 11
`
7.9 POTENTAIL HAZARD
This list may not identify all potential hazards present. Visit the job site to ensure all hazards are identified. If a potential hazard has no impact on the job, mark the box with "N/A" (Not Applicable.) If a potential hazard does have an impact on the job, tick
Potential Hazards the relevant box (es) with and implement appropriate control measures in the JSA.
WEATHER NOISE
HUMAN FACTORS
Have weather extremes been considered? Is there a need for hearing protection in the area?
Are personnel competent and confident to perform the task?
Is hearing PPE appropriate and in good condition? Will the work create higher noise levels?
Is fatigue an issue? Are procedures clear and understood?
ENVIRONMENTAL
WORKING ON ENERGY SYSTEMS/ENERGY ISOLATION CRANES & LIFTING EQUIPMENT
Have potential spill sources been identified?
Is there potential for contact with live electrical equipment? Will electrical isolation be Does the lifting activity require a lifting permit?
required? Has the need for drip trays, containment, spill blankets, absorption been Is a banks man overseeing all lifting activities?
considered?
Will mechanical isolation be required? Is all lifting equipment certified and colour coded
Has clean up after the job/housekeeping been considered?
Is the equipment to be worked on required to be drained, depressurized? Consider air, gas, Has lifting over live equipment been considered?
water, inert, oil, Hydrocarbons etc. Does job require waste disposal measures
Is the equipment in good condition (no oil leaks, etc.)?
Will equipment with stored energy (spring loaded, gravitational) have an impact on the job? Will job require hazardous waste collection and disposal
Does the equipment have a valid certificate
OCCUPATIONAL HEALTH CONFINED SPACE TOOLS & EQUIPMENT
Have health exposures been considered? (eg: Legionella) Does the work to be done require confined space entry? Will a generator, compressor or other mobile equipment be used?
Is a First Aider available Are relevant personnel trained in the entry requirements? Are machine guards in place? Are guards, safety rails, etc in good condition?
Welfare: drinking water, toilets, shaded areas Is there a stand-by person
Biological hazards: untreated sewage water, .. Is adequate rescue equipment required
Extreme temperatures
BARRIERS – TRAFFIC MANAGEMENT WORK AREA HAZARDOUS MATERIALS (COSHH)
Do barriers need to be erected to exclude non-authorized personnel or vehicles from an area Will confined space entry, hot work, other work be occurring nearby? Will hazardous substances be used? Have the MSDS's been checked? Have the health hazards of the
where potential hazards exist? Does work affect other contractors or members of the general public chemical been considered?
Is vehicular and pedestrian traffic segregated
Is signage/traffic management plan required?
Emergency Response: The JSA should consider egress routes, location of nearest first aid
mast and compression chamber, alarm, shutdown switch, fire equipment, etc.
LRT-ALST-Y2-WMS-POW-GEN00-505160-
Rev 4
Diesel Generator Site Installation Date 27-Nov-17
Method Statement
Pages 7 of 11
`
7.10 JOB SAFETY ANALYSIS
Gloves
Fall protection
Hearing protection
Lack of knowledge and training E/SC/O Personnel should wear the required Personal protective equipment (PPE) such as hardhat,
Misunderstanding of the area, time, weather eye protection, hand gloves, safety shoes.
Equipment Delivery and and other external conditions prior to delivery at Conduct formal training and familiarize the driver and store keeper the proper procedure
Handling site and guidelines (QA/QC) set down by before and after delivery of materials.
Safety induction prior to work/delivery commencement
For each hazard, indicate who is at risk: employees (E), sub-contractor employees (SC), Members of Public (P), Others (Specify) (O)
JOB SAFETY ANALYSIS PRE-TASK BRIEFING