Professional Documents
Culture Documents
Technical Brochure
D. KHOMARLOU CA R. FERNANDEZ AU
L. RASMUSSEN DK S. LÁZARO ALONSO ES
P. BENNETT UK T. LECOMTE FR
C. WINTER DE
Copyright © 2018
“All rights to this Technical Brochure are retained by CIGRE. It is strictly prohibited to reproduce or provide this publication in any
form or by any means to any third party. Only CIGRE Collective Members companies are allowed to store their copy on their
internal intranet or other company network provided access is restricted to their own employees. No part of this publication may
be reproduced or utilized without permission from CIGRE”.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility, as to the
accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the maximum extent permitted
by law”.
ISBN : 978-2-85873-448-1
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Executive summary
Objective
This Technical Brochure is aimed to produce practical guidelines according to the experience of different
power utilities in the design and deployment of high voltage line optical cables and their further
maintenance, with examples and best practice cases.
The document, which is focused on Optical Ground Wires (OPGW) and on Optical Phase Conductors
(OPPC), is the result of a Joint Working Group which combines the two areas of knowledge involved in
optical cables associated to overhead transmission lines:
Information systems and Telecommunication (D2)
Overhead lines (B2)
Value
This document provides in a clear way to experts and non-experts a complete and updated view of both
OPGW and OPPC cables’ practical knowledge and lifecycle.
Main topics
The main topics covered in the document (Technology Overview, Design, Deployment & Commissioning,
Maintenance and Survey) are summarized as follows:
Technology Overview
Various types of fibre optic cable have been developed over the last 30 years in order to meet the needs
of utilities. These include metallic cables such as OPGW (Optical Ground Wire), OPPC (Optical Phase
Conductor) and MASS (Metallic Aerial Self Supporting). In addition there are dielectric cables such as
ADSS (All Dielectric Self Supporting), wrap and other optically attached cables.
OPGW and OPPC of various constructions serve as a direct replacements for the conductor or ground
wire, with the addition of fibres contained within tubes or other guides.
An overview of the technology behind fibre optic transmission is also included as well as a comparison
of the various types fibre optic cable solutions deployed by different utilities.
Design
The document illustrates how the need for an OPGW/OPPC cable is initiated and processed. An OPGW
or OPPC project is initiated by a need, and becomes a joint planning effort between the utility different
departments and areas of expertise. The Design chapter also shapes an example of the project workflow
for an OPGW or an OPPC from both, the utility and the supplier’s perspective.
An overview of the configuration for existing cables designs and their updates is also presented in the
document. The designs can be varied as the expectations can depend on local or particular country
adaptations. In general, optical, electrical, mechanical and environmental design characteristics must
be considered in order to satisfy the necessary requirements for functionality and reliability.
In order to verify that the cable is able to meet the functional and reliability requirements, industry
standards are introduced. They establish minimum criteria that must be met for an OPGW cable design
to be qualified and accepted for use. The standards may cover various stages within an OPGW project,
for example Type Testing, Routine, Factory Acceptance Testing or Commission Testing.
Other involved parties necessities, such as fibre costumers may also be considered in this design phase.
3
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Maintenance
The maintenance chapter describes where the technology stands today. The maintenance process is
divided into; Preventive/Routine Maintenance, Corrective Maintenance, Emergency repair and Predictive
Maintenance. Lessons learned are also presented.
The document highlights the importance of the handover from project to maintenance process. It is
also addressing the impacts of the total cost over the lifespan.
Network Monitoring is essential for maintenance and the principle for Remote Monitoring Systems along
with other methods to monitor the status of the optical network are described.
A process for Telecommunications Restoring in an event of the need for an emergency repair is
described along with different methods to restore fibre communication.
The chapter also provides three maintenance case studies.
Survey
The document also includes the feedback of a survey which was sent out to gather information around
the world in order to learn how different companies from different countries design, deploy and maintain
OPGW/OPPC technologies.
4
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Contents
Executive summary .................................................................................................. 3
5
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
3. Design............................................................................................................. 57
3.1 Introduction .............................................................................................................................................. 57
3.2 Project considerations ............................................................................................................................ 58
3.3 Project workflow: purchaser or utility ................................................................................................... 59
3.4 Project workflow: supplier ...................................................................................................................... 61
3.5 Cable system design considerations..................................................................................................... 63
3.5.1 Optical design features ...................................................................................................................... 64
3.5.2 Electrical design considerations......................................................................................................... 64
3.5.3 Mechanical design considerations ..................................................................................................... 65
3.5.4 OPGW/OPPC reel dimensions and length considerations ................................................................ 65
3.5.5 Environmental design considerations ................................................................................................ 67
3.6 Standards and country adaptations....................................................................................................... 67
3.7 Type tests ................................................................................................................................................. 69
3.7.1 Cable type tests ................................................................................................................................. 69
3.7.2 Hardware/accessory type tests .......................................................................................................... 75
3.8 Splicing and interface with third parties................................................................................................ 78
5. Maintenance ................................................................................................... 99
5.1 Introduction .............................................................................................................................................. 99
5.2 Handover to maintenance process ........................................................................................................ 99
5.3 Maintenance process ............................................................................................................................ 100
5.3.1 Preventive/ routine maintenance ..................................................................................................... 100
5.3.2 Corrective maintenance ................................................................................................................... 101
5.3.3 Emergency repair ............................................................................................................................ 101
5.3.4 Predictive maintenance ................................................................................................................... 102
5.4 Maintenance – common faults ............................................................................................................. 102
5.4.1 Introduction ...................................................................................................................................... 102
5.4.2 Lightning strikes ............................................................................................................................... 102
5.4.2.1 Incident – direct lightning strikes ...................................................................................................... 102
5.4.2.2 Correction ........................................................................................................................................ 103
6
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
7
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
8
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
9
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Tables
Table 2.1 Accessories Design Characteristics ................................................................................ 30
Table 2.2 Accessories used throughout OPGW Lifecycle ................................................................ 31
Table 2.3 Equivalence table ........................................................................................................ 48
Table 2.4 MFD of different types of SM Fibres [B36] ..................................................................... 50
Table 2.5 Optical single-mode Connectors [B36] .......................................................................... 52
Table 3.1 Cable Design Characteristics ....................................................................................... 63
Table 3.2 Sample Reel Length Schedule – Steel Reel (for Illustrative Purposes Only) ....................... 66
Table 3.3 Top Three Reference Standards Used for OPGW ........................................................... 68
Table 3.4 Examples of Type Tests for Cables .............................................................................. 70
Table 3.5 Required Type Tests - Survey Results ........................................................................... 72
Table 3.6 Sample Comparison of Procedure & Acceptance Criteria Between International Standards 73
Table 3.7: Simplified Analysis of “Similar Design” ......................................................................... 75
Table 3.8 Examples of Type Tests for Accessories/Hardware – Tension Clamps / Dead-end Clamps . 76
Table 3.9 Examples of Type Tests for Accessories/Hardware – Suspension Clamps ........................ 77
Table 3.10 Examples of Type Tests for Accessories/Hardware – Bolted & Miscellaneous Clamps ...... 77
Table 4.1 Diameter of stringing blocks ........................................................................................ 84
App Table A.1 Definition of general terms used in this TB ........................................................... 127
App Table A.2 Definition of technical terms used in this TB ......................................................... 127
10
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Equations
Equation 2.1 ............................................................................................................................. 40
Equation 2.2 ............................................................................................................................. 42
Equation 2.3 ............................................................................................................................. 43
Equation 2.4 ............................................................................................................................. 43
Equation 2.5 ............................................................................................................................. 49
Equation 3.1 Ovality Calculation................................................................................................. 78
Equation 4.1 ............................................................................................................................. 88
11
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
13
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Additionally this document attempts to describe best practices that may lead to improve processes and
in general to anyone who is interested in this specific OHL cables technology.
1.2 Objectives
This JWG has focused on the following objectives:
Produce Practical Guidelines for;
o The design, project, deployment, commissioning and maintenance of Optical
Ground Wires (OPGW) and Optical Phase Conductors (OPPC).
Develop The Lifecycle of OPGW and OPPC technologies.
Gather OPGW/OPPC experience from different utilities/companies around the world.
o Distribute a survey to obtain information and feedback on the technologies.
Increase the theoretical and practical knowledge of OPGW/OPPC cables and their associated
optical fibres.
Update CIGRE information
o Update the existing CIGRE information on the topic.
Introduce New Fibre Applications
o Fibre optic based sensors.
This TB is aimed to be a guide, including examples and best practices from different experts around the
world. Its intention is to be as general and inclusive as possible, it must not be read as a normative
standard and its information must not be assumed as the unique solution.
14
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
15
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
set out some considerations and experiences for maximizing business opportunities by the use of a
telecommunications network using optical fibres, New opportunities for optical fibre technology in power
utilities [B5].
16
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
operational applications of the EPUs. This included quality requirements, architectural aspects, related
organizational, management and management issues across different types of companies.
1.5 Survey
One of the major goals of this TB is to gather information around the world in order to learn how
different companies from different countries design, deploy and maintain OPGW/OPPC technologies.
For this reason, a survey was compiled and distributed throughout CIGRE.
The survey consisted of more than 60 questions and a second questionnaire containing five additional
questions was distributed at a later date.
Questions were divided into four main sections, which have a direct correspondence with the chapters
of the TB:
1. Technology Overview (11 questions from the first survey + 5 questions from the second
survey, all linked to chapters 1 and 2 of this TB).
2. Design (13 questions directly related to chapter 3 of this TB).
3. Deployment and Commissioning (21 questions linked with chapter 4).
4. Maintenance (16 questions which correspond to chapter 5).
The most significant results of the survey are utilised throughout the TB. The full set of results are
contained in APPENDIX C.
3% 2%
24%
37%
34%
Making a deeper analysis of the participation of the different countries, we can observe in Figure 1.2
that the number of answers from the different countries has not been uniform. For example, we have
received nine answers from Japan, whereas we have received one answer of different countries like
South Africa or France.
This fact needed to be taken into account when analysing the information and the results have been
weighted according to the grade of participation
17
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
A total of 87% of the answers are from people working at utilities. Whereas around 8% of the answers
are from contractors. The survey questions were not utility biased, they were designed in a format that
suited both utilities and contractors.
18
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
2. Technology overview
2.1 Introduction
Various types of fibre optic cable have been developed over the last 30 years in order to meet the needs
of utilities. These include metallic cables such as OPGW (Optical Ground Wire), OPPC (Optical Phase
Conductor) and MASS (Metallic Aerial Self Supporting). In addition there are dielectric cables such as
ADSS (All Dielectric Self Supporting), wrap and other optically attached cables.
OPGW and OPPC serve as a direct replacements for the conductor or ground wire, with the addition of
fibres contained within tubes or other guides. Various different constructions of cable have been
developed and details of these are given within this section.
ADSS, All-Dielectric Self-Supporting, is an additional cable that is added to the structure alongside the
existing conductors. Wrapped and lashed cables are attached to the existing conductor. The mechanical
strength to support the optical cable is provided by the conductor to which it is attached.
An overview of each of these options is given within this chapter along with greater detail for
OPGW/OPPC and their associated fittings and splice boxes. An overview of the technology behind fibre
optic transmission is also given at the end of the chapter.
A comparison of the various types fibre optic cable solutions deployed by different utilities is provided
in Figure 2.1: . This graph plots the quantity of different types of fibre optic cables distributed by
different utilities on their own network. According to the results of the survey, 30% companies have
more than 5000 km of OPGW installed on their network. 77% of the OPGW installed on networks is over
20 years old and 80% of companies plan to install OPGW in the next five years. These figures emphasis
the continued popularity of OPGW technology and the solutions it can provide for EPUs.
Figure 2.1: Number of utilities plotted by cable optic type and quantity installed
19
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
In the early 80’s in North America there were several cases of conductor manufacturers joining forces
with fibre optic cable manufacturers to develop OPGW. Notable examples are Ericsson with Reynolds
Metals, Phillips Cable Canada (a BICC subsidiary) with Fitel (Furukawa Electric Japan), Sumitomo with
Alcan, Kaiser Aluminium & Chemical Corporation with Siecor (Siemens – Corning) and Alcoa with
Fujikura. In Europe, apart from BICC, other large cable manufactures took on the development of OPGW
included Pirelli (now Prysmian) and AEG.
The earliest designs of OPGW used aluminium pipe protecting tight buffered fibres, before the
introduction of gel filled buffer tube (loose tube) designs. In the mid 1980’s the first alternative to
aluminium pipe designs were introduced to the market. These so called “second generation” designs
were based on tight buffer or loose buffer tubes being placed into helically twisted aluminium slotted
core for protection. The earliest recorded OPGW installation among respondents to the survey was in
1980. The choice of designs on the market did not change further until the introduction of stainless
steel tube technology in the 1990’s facilitated the use of OPGW for higher fibre count requirements and
resulting designs were more compact cable structures.
The first recorded installation of OPPC is widely held to be a short installation carried out using BICC
cable on the Isle of Man in 1994 on the 33kV lines of the Manx Electricity Authority. The first large scale
use of optical insulators was in 1996 when FOCAS Inc. supplied IXC Communications, Austin, Texas
several hundred miles of OPGW which was insulated in sections by the use of 40kV optical insulators.
20
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
21
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Wrapped Cable –A cable which is helically installed with specialised machinery onto an existing ground
wire or phase conductor and containing optical fibres for telecommunications purposes. When installed
on the phase conductor, the cable is passed through an optical insulator to transition from phase potential
to ground potential for access purposes.
Lashed Cable – A cable which is longitudinally installed onto an existing ground wire and then held in
place by one or two wires or tapes wound helically over the lash cable and the ground wire bundle, or
clipped at regular intervals to the ground wire. An example of lashed cable installation is shown in Figure
2.8 below. Note: This product is no longer available for HV Transmission lines.
22
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The optical fibres in the core are typically in one or more Polybutylene Terephthalate (PBT) buffer tubes
i.e. a “loose tube” construction.
The main benefit of the standard loose tube design is that the fibre management is very similar to a
standard underground fibre optic cable, with one or more PBT (Polybutylene terephthalate) buffer tubes
each containing from 6 to 48 fibres. Typical fibre counts for this design are 12 to 144 fibres. The main
23
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
disadvantage of this design is that the large cross-section of the aluminium pipe and fibre optic core
can lead to a significant diameter increase when compared to the ground wire it is replacing. For new
construction projects, the structures can be designed to accommodate a slightly larger OPGW.
Additionally, as the optical core is in the centre of the cable, the cable may only need one single layer
of aluminium and aluminium clad steel wires. For these so called “single layer” designs that may not be
torsionally balanced, they may need to be installed with Anti-Rotational Devices (ARD) to avoid excessive
rotation of the OPGW during installation. It is recommended to refer to supplier’s specified installation
instructions for best installation practices related to their design.
In a Stranded Tube design, the most common position for the stainless steel tube is in the first stranded
layer of the cable. In this position the helical path of the tube provides improved optical performance
under tensile loading. Additionally it is covered by a second layer of wires which offer protection against
lightning strikes and forms a protective cage under compressive forces.
24
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The alternating layers of wires in the OPGW create a more torsionally balanced cable which will reduce
the tendency to rotate during installation and may therefore normally be installed without ARDs. It is
still recommended to refer to supplier’s specified installation instructions for best installation practices
related to their design.
For higher fibre counts more than one stainless steel tube can be used. In this way higher fibre counts
of up to 432 fibres are achievable.
In a Central Tube design, the stainless steel tube can either be protected by a single or dual layer of
wires, or by an aluminium pipe in addition to a layer of wire stranding. In these Central Tube designs,
up to 96 fibres can be packaged into a very small, dense and lightweight package.
If a single layer of wires is employed, an ARD may be needed during the installation of these cable
designs. Again, refer to supplier’s specified installation instructions for best installation practices related
to their design.
General Benefits of Stainless Steel Tube Designs:
In general, a more compact design when retrofitting a conventional ground wire.
High fibre density: Allows for higher fibre counts in a small cross sectional area.
May not require Anti Rotational Device:
o In a multi-layer design, the layers of wire are helically stranded in opposite
directions, so when a tensile force is applied – the associated torque of each layer
“cancels” each other out – so the cable will not spin when being installed.
o A perfect cancellation is quasi impossible, rotational torque depends on type of
wire, size, number and radius from centre.
25
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The design is characterised by its extreme crush resistance and easy fibre management. For single layer
designs the cable requires the use of ARDs during installation.
Customer’s specifications have evolved over time, and customers have transitioned to other types of
OPGW style cables depending on their fibre count or splice preparation requirements. Due to a limited
baseload of customers, the design type was discontinued and is no longer commercially available.
Similar product evolution occurs in different areas of technology all of the time.
Other, unique OPGW design families, such as the spiral spacer OPGW, have been discontinued as well.
General Benefits of Slotted Core and Spacer Tube Designs:
26
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
OPPC presents many challenges for EPUs. It should be considered as a last resort application. It can
be considered when one or more of the following situations exist:
Some of the challenges posed by OPPC installations can be attributed to the following characteristics:
Aluminium content of OPPC cable is generally higher than conventional phase conductor in
order to compensate for lower thermal limit (lower than conventional phase conductor) as
well as presence of a steel tube -containing the optical unit - replacing original Al wires.
Steel content of OPPC cable is higher as opposed to conventional phase conductor in order
to control elongation.
Higher Aluminium and steel content of OPPC cables lead to larger diameter and heavier
weight which in turn requires stronger structures (or reinforcement in case of retrofit).
The conventional phase conductor and OPPC have different impedances which may lead to
electrical phase unbalance in three phase system.
OPPC diameter is larger in size compared to OPGW, therefore the drum length will be
shorter. This leads to more splices (and splice losses) and more deadends.
There will be a need to have structures that can support deadend loads.
Greater complexity of insulation and handling of metallic tube will result in higher costs in
installations.
Jointing of drum ends and fibre splicing must be completed at a height. This increases the
risks to the safety of the installers. It also increases the risks of damaging the OPPC.
When OPPC cables are installed at high voltage level there are some differences in construction and
methods of installations, as described below.
27
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
OPPC is a technology which has been used in medium and high voltage lines up to 225 kV.
From a construction point of view, it is important that an OPPC closely matches the standard conductor
with regard to DC resistance. As high voltage (HV) lines normally use three phase systems it is essential
that this system is in balance. Generally diameter and weight of OPPC is closely matched with
conventional conductors so no tower reinforcement is necessary.
Due to the fact that the OPPC is energised at the system voltage, an extra consideration must be made
where jointing of the fibres is made or where the fibres are separated from the electrical network; i.e.
at the ends of the system.
The following additional components are required for an OPPC system to overcome these issues:
Joint boxes for optical connection of the fibres that can be mounted at the system voltage. It
should be noted that these joint boxes can be either;
28
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
29
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
According to the survey, the majority (90%) consider the design of the hardware and procedures from
the point of view of the fitting compatibility at the beginning of the design process.
For the purposes of this TB, hardware/accessories are considered fittings that are permanently in direct
contact with the cable:
Tension Fitting.
Suspension Fitting.
Earthing Fittings.
Bolted Clamps.
E.g. Downlead clamps used to fasten the OPGW to structure members on its path down
to the splice box.
Vibration Protection Fittings.
Vibration Dampers.
Marker Fittings.
e. g. Aircraft warning markers, birdflight diverters.
Repair Rods.
Repair damaged OPGW. Rods are capable of restoring the electrical conductivity and
mechanical strength of OPGW.
Splice Boxes.
Hardware/accessories needed to connect tension and suspension fittings with the attachment points at
the supports, e. g. links, shackles, turnbuckles, may be part of the OPGW package. These fittings are
no different to links for conventional ground wires.
In any case, the interface with the supporting structures should be clearly defined. Among other
information this may be:
Diameter of holes of attachment plates,
(select size of connecting bolts)
Thickness of attachment plates,
(select width of clevis-type links)
Orientation of attachment plates,
(along or across line direction, horizontal or vertical, to decide if straight or twisted links
are needed)
The mechanical requirements for tension and suspension fittings with regard to strength follow the
same rules as that which apply for conventional ground wires. They are governed by line parameters,
e.g. ruling span, weight span, wind span, and climatic conditions (design wind and ice loads). Design
30
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
needs to take into account safety factors required by the applicable design or safety code. Special load
cases may need to be considered (e.g. differential loads on suspension clamps due to uneven icing, or
similar).
Regarding electrical requirements, short-time fault currents for which the OPGW is designed need to be
taken into consideration for tension and suspension fittings as well as for the connecting links. Grounding
connections between OPGW and structure members may be used to shunt suspension and tension
fittings to prevent them from taking the full short-time current. Usually these grounding connections
should have at least the same short-time current rating as the OPGW. When dedicated grounding
connections are used the downlead clamps can be expected to take only a minor share of short-time
currents so that they can be designed only for their mechanical purpose, i.e. secure fastening of the
OPGW to tower members.
Further to mechanical and electrical requirements, compatibility with the OPGW so as to warrant the
mechanical integrity and the optical performance of the telecommunication module is paramount.
Application Examples
Installation of OPGW Kellem grips, anti-rotation device (ARD)
Installation of OPGW in Live Line
Cradle block
Conditions
Tension fittings, suspension fittings,
Permanent Installation of OPGW
downlead clamps
Long Term Performance Damper
Associated Hardware Splice box
31
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
32
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
33
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 2.17 Bolted Clamp: Example of a Downlead Clamp courtesy of Prysmian Group Brochure [B18]
34
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
35
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
36
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 2.21: Splice/Joint Box & Excess OPGW Loop Storage [B26] [B30]
37
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The insulator units can be either ‘assembled on-site’ or ‘pre-assembled’ by the manufacture. Installation
of the insulator unit is generally conducted at height. This imposes an increased risk factor on the
installation integrity and health and safety of the installation technicians.
The pre-assembled units have fibre optic cables embedded in the unit. The sealant material used to
protect the fibre optic cables should be of such material that it will not degrade over time and will
function under normal operational conditions of the OPPC system. There are two splice boxes located
at the top and bottom of the insulator unit. These splice boxes are fitted with splice cassettes for splicing
of OPPC via the already embedded fibre optic cables. This type of arrangement reduces the risk of fibre
damage when conducting a termination. The unit can also be electrically tested by the supplier before
installation.
The ‘assembled on-site’ insulator unit requires the fibres to be stripped back from the optical fibre cable
tail and ‘threaded’ through the unit and then spliced. The installer then pumps the insulator unit with a
sealant material. This task is completed at a height which further increases the risk of faults occurring
during this type of assembly.
A bypass arrangement is required for the insulator unit to ensure that there is no increase in resistance
in the electrical connection.
The design of the arcing horns and the position/location on the insulator units shall ensure that the
insulators unit (including optical fibres), associated hardware fittings, joint box, and phase conductor
are adequately protected in the event of surges.
Other specific accessories for OPPC are;
Tension assembly (tension towers, dead-end towers and line gate at power station) i.e. shackle,
ball eye, insulator, socket eye, thimble, helical dead-end, protection rod.
38
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Single-mode fibres are primarily used in OPGW cables, because multi-mode fibres are typically limited
to around 5-6 km (depending on the transmitter and receiver) and OPGW cables tend to have longer
deployments.
Single-mode fibres with core diameter around 9 μm only allow a single path for optical propagation
whereas multi-mode fibres with core diameter of 50 μm or higher allows the propagation of the light
following several trajectories inside the core.
2.6.1 Attenuation
Signal attenuation is one of the major distance limiting factors in long haul optical communication
systems. The main causes of signal power loss are absorption of light by the impurities of the fibre
material and scattering of light by non-uniformities of the fibre.
2.6.1.1 Intrinsic Losses
Intrinsic losses are uniform over the length of a fibre. The additional losses, for example, irregularities
of the core/cladding interface or chemical impurities may not be smoothly distributed.
Figure 2.26 shows the propagation losses of silica fibres in function of the transmission wavelength.
Recent developments situate the lower losses threshold in ≈ 0.16 dB/km around 1550 nm. Either side
of this value, the attenuation increases resulting in greater losses at 1310 nm and 1625nm. If the fibre
contains hydroxyl (OH) ions, additional peaks at 1390 nm and 1240 nm are found in the loss spectrum.
39
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The signal power ܲ, at ܮkilometres of the transmitter end and with launched power ܲை in a fibre with
an attenuation coefficient of ߙ in dB/km can be calculated by the following expression:
ఈ
ܲ ൌ ܲை ͳͲሺିଵሻ
Equation 2.1
Bend losses become more noticeable at higher wavelengths. For example, bend losses are more visible
at 1550nm wavelength when compared to 1310nm wavelength.
1625nm wavelength is also used to inspect bending losses (micro bending) on the fibre by means of
analysing the variation between this wavelength and others (i.e.1550nm).
The wavelength dependence is often strongly oscillatory due to interference with light reflected at the
cladding/coating boundary, and/or at the outer coating surface. The increasing bend losses at longer
wavelengths often limit the usable wavelength range of a single-mode fibre. Figure 2.27 illustrates
the measured bending losses at two wavelengths in a G.652D compatible fibre.
The deformations in the core-cladding interface caused by induced pressure over the fibre also produces
loses by micro-bending of the fibre. This is caused due to the use of inappropriate fittings which stresses
the optical fibres inside the cable. It is also caused by the use of inappropriate filling gel inside the loose
tubes.
40
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
2.6.2 Dispersion
Dispersion causes broadening of light pulses as they travel through the optical fibre. Modal dispersion,
chromatic dispersion and polarization mode dispersion are the main forms of dispersion which need
carefully consideration in an optical communications system design.
41
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
ߜ ܥൌ ܹܤݔܮݔܦ
Equation 2.2
Where, ܦis the chromatic dispersion coefficient, which is specific for the transmission fibre and
wavelength, ܮis the transmission distance, ܹܤis the spectral width of the transmission signal in
nanometres.
All fibre manufacturers publish the values of ܦat several wavelengths, i.e. 1300nm, 1400nm, 1550nm,
etc. Assuming that the real value of ܦis constant near the central wavelengths and ܹܤis much smaller
than ܦthe previous equation estimates the broadening with enough precision.
The diverse possibilities of combining the effects of the Waveguide and Chromatic dispersions have
generated a certain number of fibre types which are standardized by the Regulatory Bodies such as
ITU-T, IEC and TIA.
42
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Unlike other forms of dispersion, PMD is completely stochastic and methods of compensation can be
complex and costly. Currently most high-speed transmission systems are based on Continuous Wave
Modulation Transmission Systems, the PMD apparently has no effect on the actual transmission rates
of this technology.
The amount of pulse spreading related to the difference in speeds of modes is known as Differential
Group Delay (DGD) and is measured in picoseconds.
Pulse broadening due to PMD is given by the following equation:
Equation 2.3
In which ߜெ represents the broadening time in picoseconds, ܦெ is the PMD coefficient and ܮis the
length of the line.
The maximum available bandwidth ݓܤ, can be calculated considering:
ͳ
ݓܤൌ ߜݔெ
ͶͲ
Equation 2.4
43
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The Kerr effect is explained in terms of refractive index variations. Essentially, the refractive index of
the silica is not a constant. Chromatic dispersion appears because the refractive index is wavelength
dependent. In addition, the refractive index is a function of the instantaneous power travelling in the
fibre and function of the electric field inside the fibre. This last effect is the principle of the modern high
voltage meters.
From the electromagnetic propagation, we know that in a media different to that of a vacuum, the wave
travelling speed is ቀ ቁ.
ఌೝ
In optical terms, the speed of an optical wave travelling inside a certain media is ቀ ቁ.
ୖୣ୰ୟୡ୲୧୴ୣ୍୬ୢୣ୶
If the refractive index varies with the instantaneous power is easy to imagine that a certain degree of
wave distortion will appear.
The aspects of the Kerr distortion and the Stimulated Brillouin Scattering (SBS) arises when the launched
power into the fibre approaches its saturation point.
Those phenomena are discussed in more detail in APPENDIX D.
44
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
45
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The ITU-T have divided this bandwidth in sub-bands and Channelized (CWDM, Coarse Wavelength
Division Multiplexer). After the year 2000, the process to manufacture the fibre improves and the water
absorption peak at 1390 nm becomes negligible allowing the full bandwidth transmission and
superseding the transmission window concept.
Considering its intrinsic properties, ITU-T classifies the fibres in several recommendations included in
the G series (see Figure 2.32).
46
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
There is a significant difference in PMD value between the two types. PMD for G.652C fibre is 0.5 ps/˿
km, whereas for G.652D fibres it is less than or equal to 0.2 ps/˿km.
To avoid mismatching of pairs and reducing attenuation losses between the different types of fibres and
interlinking old optical networks with new, G.652C match with G.652A and G.652D match with G.652B.
2.7.2 ITU-T G.653 Dispersion Shifted Fibre
These fibres are designed to utilize the low attenuation window of 1550nm by minimizing the dispersion
value in the 1550nm area. At the time the purpose of this design was beneficial, but it generated
considerable non-linear effects near to the zero dispersion point limiting its application to a single
wavelength operation.
These types of fibres are no longer available on the market.
2.7.3 ITU-T G.654 Cut-off Shifted Fibre
This fibre is also known as low attenuation fibre. Some manufacturers achieve extremely low attenuation
at 1550nm for this type of fibre.
Mainly used in applications which demand low attenuation like those in submarine cables and terrestrial
ultra-long haul optical networks.
Low attenuation at 1550nm region, 0.15–0.16 dB/km, makes this fibre suitable for very long spans
without repeaters. This low attenuation is achieved using a largest effective core area of 11–12 μm, in
single mode fibres. In addition, this large effective area allows for the use of more launch power without
increasing the nonlinear effects.
The amount of chromatic dispersion in this type of fibre is very large and should be compensated.
2.7.4 ITU-T G.655 Non-zero Dispersion Shifted Fibre
The G.655 compliant family of fibres are an evolution of the G.652 pursuing a better performance in
the 1450nm to 1600nm region. These are wide band transmission supporting fibres which can be
manufactured with positive or negative Dispersion Coefficient (D). This allows the possibility to chain
reels with +D and –D self-compensating the chromatic dispersion.
ITU-T specifies G.655 variants from A to E. Models A and B are obsolete. C, D and E variants offers low
dispersion coefficient, wide bandwidth suitable for DWDM. The allowed variation of the chromatic
dispersion and PMD parameters are stricter in E subtype allowing for a better calculation of the link
parameters.
2.7.5 ITU-T G.656 Low Slope Dispersion Non-Zero Dispersion shifted fibre
This is another type non-zero dispersion shifted fibre, which has a low dispersion slope. This guarantees
the DWDM performance in wide wavelength range.
The second order and nonlinear distortions are considerable high compared with the G.655 fibres. In
consequence, the deployment of the G.656 type of fibres should be considered carefully in long span
lines.
2.7.6 ITU-T G.657A Compliant Bend Insensitive fibre
G.657 fibres are the new comers in the market and are very popular in the Fibre To The Home (FTTH)
market. As the name indicates, the bend insensitive fibres are suitable for applications where multiple
bends will be present.
Insensitivity to bends makes them suitable for installation at home and office environment. G.657A is
specifically designed to be compatible with G.652 D fibres. Nevertheless, splicing interconnectivity with
the whole existing range of G.652 fibres is possible for the G.657A fibres.
As they are back compatible with G.652D fibre it is a very attractive alternative for OPGW and OPPC
installation. It has the potential to reduce the probability of micro bends occurring and allow for easier
management of the fibre in the splice boxes.
47
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Note
Normally the manufacturers supersede the normalized characteristics. Some fibre models may comply
several standards at the same time.
This becomes important in long lines, more than 100km, in which, for engineering calculation, the
use of the values guaranteed by the manufacturer is recommended instead of the standardized values
Non-Zero Dispersion
B4 G.655 TIA-492E000 / TIA-
Shifted Fibre
492EA00
Bend-Insensitive Fibre G.657
48
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
A key component of performing a high quality splice is the ability to make a very precise and sharp
cutting of the core glass at the point of splice. Care should be taken to use reliable and a well-maintained
cleaver (blade cutters) for this purpose.
Planning the development of a Fibre Network is necessary to pay attention to the uniformity of the
different fibre types. Splicing single mode with multi mode fibres is not possible. Different types of single
more fibres have splicing incompatibility and this may increase the splicing attenuation losses up to
unacceptable levels.
The main parameter to be considered is the Modal Field Diameter (MFD), which is a wavelength (廗)
dependent parameter and lower than the physical core diameter.
Splicing fibres with different MFD adds an extra attenuation (ܽ) given by the expression:
ͳܦܨܯ
ܽ ൌ ʹͲ ݃ܮሺ ሻ
ʹܦܨܯ
Equation 2.5
Or in graphical mode
An increase in attenuation at a splice will also increase the reflectance levels. This increase in reflectance
may affect the signal quality received by the transmitter and/or it may damage the transmitter.
49
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Flat types includes Flat, PC and UPC which are position insensitive. The Angled termination, APC, sends
the reflected power outside the fibre minimizing the reflected power in the fibre. Their reflectance values
are indicated in Figure 2.35.
50
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The degree of polishing is colour coded on the connector body. For single mode fibres the most common
are PC polishing with a blue connector body and APC with a green connector body.
There is a variety of single mode optical connectors on the market, the most popular can be divided in
two groups:
x Heavy Duty Connectors with a ferrule diameter of 2.5 mm that are ST, FC, SC and others.
x High Density Connectors with a ferrule diameter of 1.25 mm such are LC, MU and others.
According to the survey, the main connectors used by EPUs are the following:
APC/SC 4
SC 16
FC 12
LC 11
0 2 4 6 8 10 12 14 16 18
51
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The main characteristics of these connector plus additional connectors are summarised below in Table
2.5:
Table 2.5 Optical single-mode Connectors [B36]
Type Ferral Polish Standard Attenuation Figure Comments
Size. Type
FC 2.5mm PC APC IEC 61754-13 0.15dB Popular in distribution panels
TIA-568.A 0.45dB Requires space for screw /
unscrew
Position dependent
Suitable for long term
connections
SC 2.5 mm PC APC IEC 61754-4 0.15dB Push-Pull squared socket
TIA 604-3 0.25dB Suitable for high density panels
0.45dB Plastic case
Popular in distribution panels
MT-RJ Special PC APC IEC 61754-18 0.20dB Dual fibre in a RJ-34 sized
0.45dB socket
Access Point in office
environment
Male and Female Plugs &
Sockets
NOTES:
52
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
In some cases an EPUs may only be chartered to provide electricity and the use of their fibre network
is strictly for internal operation in support of a utility’s SCADA and Teleprotection networks. Land use
easements may also limit their optical network to be used for internal purposes only.
Joint venture agreements with an external partner may pose other challenges, such as excessive
penalties for unplanned downtime, which may hamper their fibre network’s profitability or
disproportionately consume a utility’s technical resources.
Other utilities have formed partnerships with external partners to generate additional revenue or offset
construction and operating costs of a fibre network. In these types of joint venture agreements, a clear
delineation of each party’s responsibilities and expectations should be lined out, whether an external
party is leasing dark fibre or utilizing DWDM on existing fibres.
Fibre swaps, leases (per fibre and per km), and wave division multiplexing are all popular methods to
monetize their existing network.
An emerging trend in some global markets is the utility offering broadband services to their retail
customers in a fibre to the home offering. Using their existing power and optical infrastructure, a power
utility may be well positioned to provide this service, especially in rural areas where traditional internet
service providers may not choose to invest.
53
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
POWER POWER
[Watt] [dBm]
1W +30
+20
+10
Optical emitters power range
1mW 0
-10
-20
1μW -30
-40
-50
Figure 2.37 represents the available range, in dB, of a fibre optics link. In this figure the blue area
represents the transmission power of the diverse emitters available on the market. This area reflects
the performance of the actual emitters and the next comers. There are some physical constrains which
limits the launched power to the fibre.
The red line represents the limit of the sensitivity of the receivers. This line is a composite function of
the minimum photon power which is able to change the state of an electron and, consequently be
detected and the thermal noise, detector and fibre, which masks the real received signal. The actual
receivers, discarding for unpractical the cryogenic ones, are close to this limit.
54
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
With distributed sensors, these parameters are measured along the line and often plotted with a trace.
Typical distributed sensors are DTS (Distributed Temperature Sensing) which are generally based on
Raman scattering or DSTS (Distributed Strain and Temperature Sensing) which are based on Brillouin
scattering.
Raman-based DTS is more suited towards temperature monitoring and are limited in range. In DSTS
systems, however, analysis of the Brillouin frequency shift versus the optical pulse return time provides
insight into the physical properties such as temperature and strain changes at any location on the fibre.
The ability to monitor the strain or temperature change (absolute or relative) experienced by individual
fibres over the entire length of the cable (up to 70 km) - down to 1 m spatial resolution - provides
valuable information on the dynamic response of the cable to environmental factors.
Consequently, the use of Brillouin or Raman- based DTS or DSTS on aerially-installed fibre cable would
allow such cables to serve as long (many kilometres), highly sensitive, strain and temperature gauges
with accurate spatial resolution.
Vibrations can also be detected in a distributed way by using Acoustic Monitoring Systems.
Temperature and strain can also be measured locally with Bragg fibres. In this scenario special fibre
sections have to be spliced in the specific spots to be measured and the fibre is often used as a
communication medium to backhaul sensor measurements.
Monitoring the condition of the line for temperature and straining changes using such systems is very
common throughout EPUs. The survey results demonstrated that 83% utilised the fibre optic cable as
a sensor using a DTS or another system. 80% of these systems were using Brillouin DTS technology.
55
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
56
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
3. Design
3.1 Introduction
The design workflow of an OPGW or OPPC line involves various stages and several stakeholders. One
of the first stages is to determine whether to deploy OPGW or OPPC for the fibre optic link. Figure 3.1
illustrates a typical decision tree.
Once the type of cable is selected, the project begins. Project stages may include design, procurement,
testing, installation, deployment and commissioning, and maintenance. Stakeholders may include the
manufacturer or supplier, purchaser (e.g. utility, contractor), or installer.
The following section on design outlines the high level project considerations. The approach to this
workflow, from the purchaser or utility’s point of view, followed by the supplier’s point of view is
explored.
After the project workflow, cable system design considerations, including optical, electrical, mechanical
and environmental considerations, are discussed. The industry’s attempt to regulate these
considerations, through standards, country adaptations and Type Testing is investigated.
Finally, the chapter looks at splicing and interfacing with third parties.
Figure 3.1 represents a typical decision tree to determine whether to deploy OPGW or OPPC for the
fibre optic link. This decision tree is for illustration purposes only, and does not represent all available
options.
57
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Telecommunication Design: Fibre count, type and characteristics; splice identification and
location for maintenance; location of optical amplifier if applicable; documenting as-built
documents.
Procurement: Prepare commercial package including technical specs to solicit bids for supply of
cable.
This sequence of activities is partially illustrated in the “Project Workflow – Utility Point of View” shown
in Section 3.3 below.
The project closure will document in-service completion, as-built condition and acceptance by
stakeholders.
58
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
A sample of a complete workflow for an OPGW from a utility’s point of view, from design to installation
to commissioning, is shown in Figure 3.2.
The illustrative workflow demonstrates the coordination between the various teams and stakeholders
including Asset Management, Telecoms, Lines, Installation Contractor, Network Operations and the
OPGW Supplier.
Figure 3.2 represents a typical workflow for an OPGW for illustration purposes only, and does not
represent the workflow for all utilities.
59
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 3.2 Project Workflow for an OPGW: Utility (for Illustrative Purposes Only)
60
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 3.3 represents a typical workflow for an OPGW for illustration purposes only, and does not
represent the workflow for all suppliers.
The supplier must first review the design requirements outlined in the RFQ. Highlights from this review
process are described below. The relative importance of each requirement may shift from project to
project. Typically the number of fibres is the most critical consideration as it will determine the size and
number of optical units, followed by the mechanical and electrical requirements, which will dictate the
steel and aluminium combination for the design. Special situations will also shape the design process
(e.g. high corrosive environments with only aluminium surface contact or greasing; high lightning
intensity will shape the minimum wire size on the outer layer). A detailed review of each design
consideration is described in Section 2.4.
1. Operational considerations must be reviewed to determine the requirements for the project.
The following list outlines the highlights from the illustrative workflow shown in Figure 3.3.
a. Optical: Refer to Sections 2.6 and 2.7 for details on fibre optics technology and types
of fibre, respectively.
i. Type of fibre (e.g. as per ITU-T G series, IEC 60793)
ii. Optical parameters (e.g. attenuation, dispersion)
iii. Fibre configuration (e.g. tubes, fibre colour, fibre bundles)
iv. Number of fibres
b. Mechanical performance:
i. Minimum breaking strength
ii. Sag restrictions
c. Electrical performance:
i. Short circuit current capacity
2. Environmental:
a. High corrosion sites
b. Lightning arc intensity
3. Installation:
a. Maximum manufacturable length
b. Reel dimensions
Each supplier will typically validate its conceptual design through Type Testing, before launching the
product in the market.
61
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 3.3 Project Workflow for an OPGW: Supplier (for Illustrative Purposes Only)
62
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Note:
1. Acronyms defined in APPENDIX A.
63
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
64
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
65
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The drawback in using the maximum length of reels is limited access locations should there be an issue
with a fibre span or possibly an entire reel. Testing of reels prior to installation becomes more important
in this case; with some utilities testing all reels prior to installation. OPGW spans are allowed to stay in
traveller for short duration according to supplier specification, thus additional lines crew (or aerial
resources) are required to tension and clip the cables in at every tower with suspension and dead-ends
as required.
Within the maximum length limitation, the following factors are considered when defining the cut length:
i) No in-span splice box or splicing
ii) Preferably terminating on an anchor structure
iii) Identifying pulling site from an installation planning point of view
iv) Accessibility of splicing location from an installation and a maintenance point of view
v) Location of repeaters: access and power supply
3.5.4.3 Design Constraints
From a purchaser’s perspective, OPGW/OPPC cables are ordered by users in defined cut lengths for
several reasons:
i) In-span splicing is not practical and normally forbidden by utilities.
ii) Diverse section lengths dictated on a project-by project basis.
iii) To manage the cost of OPGW/OPPC cables, want to minimize scrap (left-over from
hypothetical standard length on reel).
From an economical point of view, manufacturers prefer a range of lengths so they can concatenate
and optimize manufacturing of short and long lengths of raw material by assigning a mix-and-match of
inventory with the aim of minimizing the scrap.
3.5.4.4 Illustrative Example
Maximum reel lengths prescribed for a particular puller/tensioner weight and dimension limitation are
shown in Table 3.2 below. This table is meant to be informative and should not be used for actual
installations. Suppliers can provide information for their particular installation.
Table 3.2 Sample Reel Length Schedule – Steel Reel (for Illustrative Purposes Only)
Table 3.2 represents sample reel length schedule for illustration purposes only, and is not meant to
be a prescriptive example.
66
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Commission Testing, or Site Acceptance Testing: Generally used to verify that the optical characteristics
of the fibre in the delivered product meet the order requirements. In addition, Commission Testing may
be used to ensure that the optical fibres have not been damaged during shipment or installation. Each
utility may have different testing requirements at different stages of the procurement process for
Commission Testing. Acceptance criteria may be based on industry standards, or may be defined by
67
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The three most common standards identified in the survey are shown in Table 3.3.
Individual countries may adapt these international industry standards, in whole or in part. Specialized
conditions relevant to local authorities may be added to address local technical challenges. For example:
Canadian Standards Association (CSA) are based on international standards such as IEC or
ASTM, with “Canadian Deviations” added to address cold weather applications.
Japanese Industrial Standards (JIS) are based on international standards such as IEC, but some
of the items that are not specified in the international standards are added into the standards
of JIS.
IEEE Institute of Electrical IEEE 1138 Standard for Testing and Performance for Optical
and Electronics Ground Wire (OPGW) for Use on Electric Utility
Engineers Power Lines
IEC International IEC 60794-1-2 Optical fibre cables - Part 1-2: Generic specification
Electrotechnical - Cross reference table for optical cable test
Commission procedures (See Note below)
ITU-T International ITU-T G.652 Series G: Transmission systems and media, digital
Telecommunication systems and networks. Transmission media
ITU-T G.654
Union - characteristics – Optical fibre cables –
Telecommunications ITU-T G.655 Characteristics of a single-mode optical fibre and
cable
ITU-T G.656
NOTE:
IEC 60794-1-2:2013 applies to optical fibre cables for use with telecommunication equipment and devices
employing similar techniques, and to cables having a combination of both optical fibres and electrical
conductors. The second edition of IEC 60794-1-2:2003 is separated into five (5) parts:
IEC 60794-1-2 Cross reference table,
IEC 60794-1-20 General and definitions,
IEC 60794-1-21 Mechanical tests,
IEC 60794-1-22 Environmental tests,
IEC 60794-1-23 Cable elements tests and
IEC 60794-1-24 Electrical tests.
68
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Other ASTM
7% 8%
TIA/EIA ASTM
10% IEEE IEEE
23%
IEC
ITU
ITU
26% TIA/EIA
Other
IEC
26%
A utility may develop their own internal specification for the design, procurement and testing of OPGW
cables. These internal specifications may reference internationally published guidelines or standards.
Guidelines offer generic details and identify parameters that must be agreed upon, and are not
prescriptive. Standards typically offer specific details, and prescribe values and acceptance criteria.
Table 3.4 highlights these two industry standards. Upon successful completion of these Type Tests,
the cable is qualified and considered suitable for use in the intended application. IEEE 1138-2009
categorizes the tests as “mandatory” (M) or “conditional” (C). IEC 60794-4-10 lists the mandatory tests
for OPGW.
According to the survey, for the overall tests, international and own company standards are the more
accepted ones. Only 15% do not require Type Test for OPGW/OPPC cables.
69
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
70
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
* Test not included in list of Type Tests. C = Conditional Test M = Mandatory Test
71
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Chromatic Dispersion 6 20
OTDR 2 28
Bleeding & Evaporation 5 16
Kink on Tubing 5 15
Kink on Complete Cable 9 13
Abrasion 6 14
Repeated Bending 9 16
Fiber Cut-off 5 24
Cable Cut-off Wavelength 8 18
Salt Spray 11 16
Temperature Cycle 3 27
Seepage of Flooding 12 13
Water Ingress 6 26
Lightning 6 25
Short Circuit 4 28
Galloping 1314
Aeolian 6 26
Twist 5 27
Bend 6 24
Impact 11 16
Crush 5 25
Sheave 4 28
DC Resistance 4 27
Ultimat Tensile 4 29
Strain Margin 5 25
Stress-Strain/Fiber-Strain 2 31
Tensile/Stress-Strain 3 30
Creep Test 5 28
Dimensions 0 31
0 5 10 15 20 25 30 35
No Yes
Typically a supplier will submit a Test Report, detailing the results of a Type Test Program. These test
reports will reference various industry standards or guidelines.
It should be noted that there are differences between international standards when it comes to
procedure and/or acceptance criteria. These differences are a result of the diverse background of the
individuals making up the committees who maintain the standards. The unique experiences of the
members will shape the industry standards.
A simple comparison of some differences between four tests is shown in Table 3.6. Although not all
the differences would be considered significant, it is good practice for the purchaser to be familiar with
these differences in order to qualify an OPGW best suited for their particular application. It should also
be noted that Table 3.6 is a snapshot of high level differences; please refer to the individual standard
for the complete test details and acceptance criteria.
72
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Table 3.6 Sample Comparison of Procedure & Acceptance Criteria Between International Standards
Lightning After simulated lightning arc strike, After simulated lightning arc strike,
Arc Test OPGW remaining strength is measured OPGW remaining strength is calculated
(cable tensioned to failure). (based on unbroken wires).
Residual strength (measured) Residual strength (calculated)
> 75% RTS > 75% RTS
Optical acceptance: permanent increase Optical acceptance: permanent or
in optical attenuation < 0.05 dB/fibre at temporary increase in optical attenuation
nominally 1550 nm for SMF < 0.2 dB or 0.2 dB/km of test fibre at
nominally 1550 nm wavelength for SMF
Five short-circuit pulses applied
Maximum temperature measured inside Three short-circuit pulses applied
optical unit < 180oC, higher temperatures
may be allowed if agreed upon between
manufacturer and end user. Maximum temperature measured inside
optical unit < 200oC
Maximum temperature of any metallic
Short component < manufacturer’s specified
Circuit Test value. Standard notes: due to potential Maximum temperature of any metallic
loss of tensile strength of cable when component : not specified
temperatures > 220oC, a tensile strength
test is recommended to verify it meets
the RTS after the Short Circuit Test. Optical acceptance: permanent increase
Optical acceptance: permanent increase in optical attenuation < 0.2 dB at
in optical attenuation < 0.05 dB/fibre at nominally 1550 nm wavelength for SMF
nominally 1550 nm for SMF
Sheave Number of Cycles = 15 Number of Cycles = 20
Test
Test Angle = 30o ± 2o Test Angle = 45o ± 15o
Maximum Ovality = 10% Maximum Ovality = 20%
Optical acceptance: permanent increase Optical acceptance: permanent or
in optical attenuation < 0.1 dB/test fibre temporary increase in optical attenuation
km at nominally 1550 nm for SMF < 0.2 dB or 0.2 dB/km of test fibre at
nominally 1550 nm wavelength for SMF
Aeolian Minimum 100 Million Cycles Minimum 10 Million Cycles
Vibration
Maximum Ovality = not specified Maximum Ovality = 20%
Test
Optical acceptance: permanent or Optical acceptance: permanent or
temporary increase in optical attenuation temporary increase in optical attenuation
< 0.2 dB/test fibre km at nominally 1550 < 0.2 dB or 0.2 dB/km of test fibre at
nm for SMF nominally 1550 nm wavelength for SMF
As demonstrated in Table 3.6, the optical performance acceptance criteria may differ between various
international standards. It is important to note whether the criteria are based on a temporary and/or
permanent change; and whether the signal is being monitored on as per fibre or per test fibre kilometre
basis.
Temporary changes are typically specified for tests simulating “in-service” conditions; whereas
permanent changes are typically specified for all tests. All of this information should be clarified between
73
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
the manufacturer and purchaser at the time of contract, and clearly described in the Type Test Report.
Although the standards define minimum optical performance requirements based on standardized test
protocol, an individual purchaser may have more stringent or specialized requirements for their system.
Because Type Tests are not necessarily designed to simulate the “exact” application, specialized test
protocol or acceptance criteria may be warranted to ensure a suitable OPGW/OPPC design for a
purchaser’s application.
The IEC 60794-1 Generic Specification series for Optical Fibre Cables lists other tests that would be
considered “conditional” for OPGW/OPPC – these may be added to a Type Test Program at the discretion
of the purchaser. There are many other tests that may be added to a Type Test Program, such as
individual wire tests, fibre tests, etc. Again, these tests may be required to qualify a given OPGW/OPPC
at the discretion of the purchaser, depending on the specific application.
Generic industry guidelines do not specify detailed test procedures or acceptance criteria. In these
cases, the guideline may point to another “detail specification”. When a generic specification is called
out, it is good practice to compare to international standards that prescribe set-up and procedure, and
acceptance criteria. For example: IEC 60794-4-10 does not include a Crush Test as part of an
OPGW/OPPC Type Test Program. However, a supplier may complete this test in accordance with
Method E3 of IEC 60794-1-21:2015 Optical fibre cables – Part 1-21: Generic specification – Basic optical
cable test procedures – Mechanical test methods. Because IEC 60794-1-21 is a generic specification,
the specific details of the test set-up, procedure and acceptance criteria, should be agreed upon between
the supplier and the purchaser.
In some cases, a supplier may supply a cable for a new project, using an OPGW/OPPC that underwent
a Type Test Program for a previous project. In this scenario, tests may be waived if in the opinion of
the purchaser, the OPGW/OPPC are of “similar design” and therefore may not require a full Type Test
Program. There is no strict definition of “similar design”, and some engineering judgement may be
required. Typically the definition of similar design should be agreed upon between the supplier and the
purchaser. Almost two thirds of survey respondents do not accept type test reports on a cable of similar
design.
There is no widely accepted definition of similar design. Typically it is understood that any changes that
may affect the performance characteristics would mean that two OPGW designs are not similar.
When deciding whether two designs are similar, there are two high level approaches:
A purchaser may mandate that retesting is required with any changes to cable design or
manufacturing process (e.g. manufacturing plant, manufacturing process, etc.).
A purchaser may perform an analysis of the differences to determine whether two designs
qualify as similar. If the designs are found to be relatively similar, it is possible that only
one or two Type Tests may be warranted, in order to provide confidence that the differences
will not affect the performance. A simplified analysis of this process is included in Table
3.7. This example is not intended to be an exhaustive analysis, but is meant for illustrative
purposes.
74
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Identify the Differences Qualify How the Changes Consider Whether Changes
May Affect Performance Can be Verified
Lighter design, with smaller Smaller ACS wires with thinner Salt Spray Corrosion Test
diameter ACS and AA wires aluminium cladding may have
lower corrosion resistance
Smaller AA wires may reduce Short Circuit Test
short circuit capability
Smaller ACS & AA wires may Lightning Arc Test
increase susceptibility to
lightning arc damage
Different manufacturing Welding process may affect Sheave Test
process for aluminium tube bending resistance as OPGW
installed
The concept of “similar design” may also be important when it comes to hardware compatibility. Refer
to Sections 2.5 and 3.7.2 for discussion on hardware compatibility.
There are several industry standards that prescribe a list of tests on hardware/accessories: IEEE and
IEC. IEEE 1591.1 “Standard for Testing and Performance of Hardware for Optical Ground Wire (OPGW)”
specifically deals with hardware/accessories designed to be used on fibre optic cables. In comparison,
IEC 61284 “Overhead lines – Requirements and tests for fittings” is not specifically written for fibre optic
cables, however the same requirements and tests for fittings for ground wires and phase conductors
may apply for hardware/accessories for fibre optic cables.
In addition, compatibility of fittings with the fibre optic cable has to be proven. Several of the tests
listed in IEEE 1591.1 would be considered “system” or “compatibility tests”, because they are designed
to test the “OPGW system”, which consists of the fibre optic cable and the associated
hardware/accessories for the particular application.
Highlight these two industry standards. Not all of the tests listed in these standards are considered
mandatory, and typically the final list of Type Tests should be agreed upon between the purchaser and
supplier.
75
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Table 3.8 Examples of Type Tests for Accessories/Hardware – Tension Clamps / Dead-end Clamps
IEEE 1591.1-
2012 IEC 61284-
Standard for 2009
Test on Testing and Overhead
No. Hardware/ Test Intent / Objective Performance of lines –
Accessories Hardware for Requirements
Optical and tests for
Ground Wire fittings
(OPGW)
Mechanical
Verify the manufacturer’s strength
1 Damage and * 11.5.2
rating of the hardware.
Failure Load Test
Magnetic Losses Ascertain the magnetic losses of the
2 * 12
Test hardware.
Simulate performance under sagging
3 Tensile Test 5.5.2.1.1 11.5.1
tensile load conditions.
Subject cable and hardware to Aeolian
Aeolian Vibration vibrations that can fatigue metal
4 5.5.2.3.2 *
Test components of the cable and/or
hardware at attachment locations.
76
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Table 3.10 Examples of Type Tests for Accessories/Hardware – Bolted & Miscellaneous Clamps
IEEE 1591.1-
2012 IEC 61284-
Standard for 2009
Test on Testing and Overhead
No. Hardware/ Test Intent / Objective Performance of lines –
Accessories Hardware for Requirements
Optical and tests for
Ground Wire fittings
(OPGW)
Verify that the cable is not damaged
Clamp Bolt
17 when hardware torqued to supplier’s 5.5.4 11.4.5 or 11.5.4
Tightening Test
recommended value.
Corona and RIV: Determine RIV and
corona performance of fittings. Test
Corona and RIV,
does not address permissible RI limits
Damper Fatigue,
18 or specified corona extinction voltages 5.5.4 to 5.5.7 14
Crush, Corrosion,
or gradients which are set by
etc.
regulations or utility practice.
Others: As above
77
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Acceptance criteria for the above tests may include mechanical performance and/or optical performance
requirements.
For example, after the “Clamp Bolt Tightening Test” or “Turning Angle Test”, the fibre optic cable is
dismantled and the cable and optical unit are inspected for ovalization. The ovality of the cable or
optical unit(s) shall be calculated after the test using the following calculation:
Ovality shall be less than the admissible ovality specified by the cable manufacturer.
Figure 3.5 and Figure 3.6 represent typical layouts for splicing and interfacing between utilities and
third parties for illustration purposes only, and do not represent the layout for all utilities.
78
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
OPGW
Typical
Splice Tower
Customer Interface
Cabinet
Figure 3.5 Splicing and Interfacing Between Utility and Third Parties (Illustrative Purposes Only)
Fiber Fiber
Cable Cable
Customer Interface
Cabinet
12 Fiber Stub
Cable
Splice Tower
Figure 3.6 Splicing and Interfacing Between Utility and Third Parties (Illustrative Purposes Only)
79
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
80
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
81
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
All necessary works can be done by the EPUs internal resources or their own approved contractors or a
third party Customer in co-operation with an appointed contractor. Permission to commence work must
be received in writing by the appropriate authorizes before works can begin.
Once approval has been obtained, the work place must first be made safe. All working crews must be
briefed in relation to the work-place environment and site specific training must be implemented.
Usually this place of work is the part of power line, where an OPGW/OPPC is going to be deployed, and
it is called a section. The section length can vary (see Section 3.5.4) and depends on engineering
documentation. As a result of that all crossings must be secured and safe access/egress to the working
area must be arranged.
4.2.2 Deployment
Once all the preparation works have been completed and all local safety guidelines have been adhered
to the deployment of the OPGW/OPPC section on the new built line or an existing line as its
refurbishment can commence.
Deployment can be performed during power line outage or using in a technique called “in the vicinity
of live parts” if live line installation work is required. For further details regarding this installation
techniques please see Section 4.3.
Deployment performance operates at its optimum when special consideration is provided to the
requirements described below:
4.2.2.1 Installation Equipment
The specialized equipment and tools must be located appropriately on sites. The puller at one end and
the tensioner together with the reel stand at the other end must be located in a suitable location.
The distance between the fore mentioned machines and the first tower (both ends) is usually three
times as much as the tower height on which the end-blocks are suspended (Figure 4.7 and Figure 4.8).
Typical ratio 3:1 (distance to the tower: tower height) is useful guideline for the crew working on-site
and it comes from the strength calculations completed in the past. This calculation must comply with
the tower series it is been installed on as there are different types of towers installed by EPUs throughout
their network. Installation practice in this matter can vary among EPUs as the towers strength also can
be different.
A ratio of 2:1, is also used but must be proven by calculation. Natural terrain or technique (in the vicinity
of live parts) sometimes does not practically allow for the distance mentioned above and therefore the
lower ratio is the only option. In such cases additional mechanical calculation of the towers strength is
required. Additional design considerations are also required as construction equipment must be clear of
vegetation, arrangements for access/egress and placement of ground mats and grounding rods of
appropriate size.
The tensioner and the puller must be placed aligned with the power line axis (the conductors) although,
for the most cases, the deviation angle max. 30q is still acceptable (Figure 4.1)
In addition to grounding system, a tarp is used and gravel of appropriate granularity is placed on the
ground, so that accidental oil leaks are contained. All equipment is placed on the ground must be
installed in a mechanically and electrically safe and secure manner. The gravel pads are removed after
completion of OPGW pull and vegetation is allowed to recover.
82
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The Puller
The puller must be equipped with a tension control system and an automatic disconnection in case of
over tension on the cable. Normal practice is to check the puller according to the accuracy of tension
measurement.
The Tensioner
According to Manufacturer’s Manuals [B23] a typical requirement for the tensioner is to have a bull-
wheel sheave with a diameter more than 70 times the cable diameter or 1200mm, whichever is smaller.
Some manuals provides requirements with a small difference in the diameter. It is always recommended
to follow the specific manufacturer's manual.
The wheels must be in such condition that they do not have any burrs or cavities which may damage
the cable. The running-grooves must be adapted in size to the cable diameter. For best performance
they can be coated with neoprene or similar material.
Tensioning should be readily controllable and capable of maintaining constant and even operation.
To prevent the OPGW/OPPC from birdcaging the correct orientation for entry and exit of the cable must
be respected. For right hand lay (Z), the cable must enter the brake on the left and exit on the right
(Figure 4.2). For left hand lay (S), the cable must enter on the right and exit on the left.
83
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Location Φ [mm]
The first and the last tower when deflection angle ≤ 120q ≥ 800
(the beginning and the end of line section)
Tension towers ≥ 600
Suspension towers ≥ 450
In case of where angles are greater than 45q, a special arrangement must be applied. This arrangement
is called a dual-block system and it is used to increase the bending radius during the installation of the
OPGW/OPPC.
Stringing speed
The speed of stringing at the beginning is around 5m/min till the OPGW/OPPC cable reach the first
tower. Once it passes the first tower, the speed can be raised up to 30m/min. The maximum speed of
stringing can vary, depending on the topology of the power lines, angles and the types of the towers,
but should be no more than 40m/min. Some of the manufacture manuals allow an increase of speed
up to 60m/min. This must be approved by the manufacturer on a case by case basis.
Bending Radius
The minimum permissible bending radius is 20 times the cable diameter unless other described in the
manufacturer’s manual.
84
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
According to the survey, the minimum radius of the drums and pulleys is cable dependent and the
companies usually follow the cable manufacturer recommendations.
Anti-Rotation Devices
When installing a single layer OPGW/OPPC cable, it must be performed with use an Anti-Rotation
Devices (ARD) (anti-torque system). It is necessary to compensate for the inherent effect of torque of
the OPGW/OPPC cable. [B24] The weight of the ARD placed at the pulling head of OPGW/OPPC
cable, has to be high enough to prevent OPGW/OPPC cable rotation. Installation of such a device
on a single layer OPGW/OPPC is normally mandatory in manufacturer's manuals.
The minimum values recommended for each counterweight are as follows:
spans ≤300 m Æ 12 kg
spans >700 m Æ 20 kg
OPGW/OPPC is supplied and installed in Engineered Lengths with the jointing locations pre-determined
at tension tower structures. The placement of the joint module (Termination Stack or In-Line type) on
the tension tower structure is determined by the structure type, jumper profile, etc.
The requirement to strictly observe the manufacturer’s instructions for stripping and prepping into the
joint closure is paramount for optical and electrical reliability in service.
Extreme care must be taken when stripping out the fibre cores as no ‘slack’ can be made available in
the conductor for rework in the event of core breakage.
The prepping and splicing of OPPC requires that the operation is successfully completed in a single
attempt. Unlike OPGW no excess slack is available for re-work. It is vitally important therefore that every
care is taken to ensure that each operation is ‘Right First Time’.
85
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
It is strongly recommended that the prepping and splicing of OPPC is undertaken from a fixed platform
structure so as to best guarantee completion of the work. This is not always possible due time and cost
constraints and therefore the task must be completed using a portable hoist. The use of a portable hoist
increases the risk of a failed installation and might not be practical due to access issues. The picture
below in Figure 4.4 shows the erection of scaffolding at an OPPC joint location in a bog area, the
materials were delivered via helicopter due to access restrictions. This is not a standard procedure.
Each fibre core on the drum must be examined using an OTDR at wavelength 1550nm to determine full
continuity over the drum length. The drum battens should not be removed. Testing should be completed
via the exposed tail end. Discrepancies are to be verified and immediately notified to the relevant parties
prior to stringing.
86
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Wind and gusting can cause difficulty in keeping cores secure and undamaged during the splicing
operation and may also ‘blow’ the fusion arc leading to failed or out of limits splices. Again, suitable
measures must be taken to protectively orient or shelter the splicing area during set-up preparations.
OPPC Jumper must be profiled by the Linesman. It is marked for stripping by the OPPC fibre
technician and the Linesman. Note: This stage is only applicable for OPPC.
Prepare splicing equipment and work area.
As per manufacturer specifications, strip conductor to the predetermined mark to reveal the
transport tube.
Note: Extreme caution is required during following stages to prevent damage to the fibre cores.
Cut the transportation/transition tube using the manufacturer’s bespoke cutter tool. Remove
the tube to reveal fibre cores.
Securely tie off/clamp the conductor prior to splicing the fibre cores.
Prepare the splice closure as per manufacturer’s instructions.
Clean, strip, cleave and fusion-splice fibre cores. Protect and store fibre cores correctly in
raceway tray.
All fibre cores in the conductor are to be spliced through end-to-end, except where otherwise
specified by a “Breakout Joint Schedule”. No fibre core is to be left ‘Stumped’ in any aerial
joint. Open circuit cores or Faulty/Out of Limits splicing is not acceptable. Random/Cross
splicing is not acceptable.
Splicing must achieve the companies specified standards set out below.
Seal the closure entry points as per the manufacturer’s instructions. Assemble the closure
and seal to specified torque settings and fix to line/structure. The Linesman must check
Electrical & Mechanical compliances of OPPC connections. Note: This stage is only applicable
for OPPC.
87
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Perform bi-directional OTDR tests from remote bare ends at both 1310nm and 1550nm
wavelengths on all fibre cores.
Verify OTDR results following completion of splicing, sealing of the joint closure and prior to
the team dismounting from the splicing position at the structure.
Any re-splicing or re-dressing must be undertaken immediately and re-tested in situ.
Splice losses must be equal to or better than 0.05dB average per splice. Average is to be
calculated as:
ݏݏܮ݀݁ݎݑݏܽ݁ܯ݈ܽݑݐܿܣሺܤݐܣሻ ݏݏܮ݀݁ݎݑݏܽ݁ܯ݈ܽݑݐܿܣሺܣݐܤሻ
൬ ൰
ʹ
Equation 4.1
Test results and calculated averages at both 1310nm and 1550nm for each fibre core must be
recorded.
It is recommended that a digital photo record is taken of each joint module and sub-assemblies
to clearly demonstrating compliance with manufacturer’s instructions. Figure 4.6 shows
completed straight through OPPC canister joint.
Submissions are required both for individual joints and for the entire optical link.
All cores must be spliced through to give full end to end connectivity within the limits specified. No
deviations are acceptable.
88
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Pilot-Rope Method
Power line De-energized
Existing power lines to be refurbished by OPGW/OPPC
In case of installation on an existing power line, the tension stringing method is the most effective.
The work can be done only when required conditions are met. A specific value can vary depending on
country (according to local Health & Safety Legislation) and can be described as:
Storm and lightning - Not closer than e.g. 10km.
Wind - Not stronger than e.g. 10m/s.
NO rain, snow, hail, drizzle, hoarfrost.
NO ice on the tower construction, wires.
NO temperature below e.g. -10 ºC.
No temperature more e.g. 40 ºC.
89
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Using the tensioner and the puller, the existing ground wire is kept under tension. In this way, during
the stringing process, the ground wire is kept far away from contacting the phase conductors (Figure
4.7). The tension in the ground wire also allows to pass over energized circuits, railways or major road
crossings without contacting them. Nevertheless, all crossing must be secured against uncontrolled fall
down.
The tensioner and the puller shall have the ability to regulate tension on the wire and pulling speed
during wire installation. Furthermore these devices shall have a hydraulic brake, which automatically
stops the puller and tensioner when the tension set point is exceeded or if the wire breaks.
As mentioned above, in case of OPPC installation, the stringing method above is also possible. This
method for OPPC can be straightforward when replacing an existing OPPC (Figure 4.8) as there is no
need to link all wires to create a section as this already exists.
90
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
First of all, tension level must be under control constantly and with very accurate value. This is to
maintain the required clearance distance between the ground wire and phase conductors. Accurate
values must come from the necessary calculations.
Secondly, the proper location of the tensioner with reel winder and the puller (Figure 4.9.) and aspects
such us equipotential stand, distance to the first and last tower, in line with the power line, etc.
Special arrangements must be provided to prevent against potential failure i.e. brake the wire. Another
concern, but not the last, is the requirement for special equipment (clothes, tools, etc.) and work
procedures during worktime.
91
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
4.3.2 Protection
In spans with crossings (i.e. rail road, public road, electrical power line, telecommunication line), when
replacing an existing wire there is a need to provide extra protection against uncontrolled falling down.
There are many protection methods currently in use, a few of these methods are described below:
92
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Parallel Arrangement
To place the rope as a barrier between phases, the system of ropes and hanging carriages is used. To
deploy the whole system accurately a remote controlled robot is in use, see Figure 4.13. The process
starts from the first tower to the second in the span where additional security needs to be implemented.
Once replacement of the ground wire is completed with the new OPGW the whole process starts again
in reverse direction.
93
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Diagonal Arrangement
In comparison to parallel, the only difference is the configuration of the link protective rope between the
phases see Figure 4.14.
Figure 4.14 Diagonal arrangement [B25] and [B26]
94
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Stakeholder’s and third party supervision, check to ensure the installation works is consistent with the
design documentation. Supervisors must access to the site at any time, provided that adequate notice
period is provided to the person in charge of the work.
Depending on the local standards, the quantity of checks varies. Usually, a percentage comes from local
national standards, industry standard or other accepted standards.
The most frequent check are:
Sag checking – at 1 or 2 spans per a OPGW/OPPC section using survey techniques. This is
done during installation by the independent surveyor (according to installation sag/tension
table) to ensure that deployment and sagging has been performed correctly.
Sometimes additional sag checking after 2-3 months of installation is completed. The value
of sag must be compared to maintenance sag/tension table.
Dampers location and quantity – 10% to 100% of total quantity.
Splice box and an extra stock localization – 100% of total quantity.
Fibre infrastructure at the substation and in telecommunication room– 100%. In case of
underground route a fibre-cable must be installed as per local specifications. As-built route
map must be prepared.
The angle of wire bend – all angles must be no less than described in manufacturer’s
instructions for particular type of the OPGW/OPPC.
An extra check, but not always necessary, can include checking the refurbished earthling
system on each tower station. Resistance measurements and their results must be
confirmed and recorded in writing.
95
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
4.5 Commisioning
Pre-Commissioning
During the deployment stages the installer must pay attention particular attention to the following:
Proper location of the tensioner with the reel of OPGW/OPPC as well as the puller location.
Tension force used while replacement and final installation (max approved tension force
not to be exceeded).
Sag checking – at 1 or 2 spans per a OPGW/OPPC section using survey techniques. This is
done during installation by the independent surveyor (according to installation sag/tension
table) to be sure that deployment and sagging has been performed correctly.
Dampers position and quantity – 100% of total quantity.
Splice box and an extra stock location – 100% of total quantity.
Fibre infrastructure at the substation and in telecommunication room– 100%. In case of
underground route a fibre-cable must be installed as per local specifications. As-built route
map must be prepared.
The size/diameter of the puller, the tensioner and the blocks.
96
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
All necessary measurements and details must be documented. These records are required to prepare
commissioning papers and for future record. In the event of fault they will be required during the
investigation process.
All documentation of completed works must to be provided and recorded in writing and usually in digital
version as well.
Commissioning
Commissioning process starts with:
Physical check of 100% of works.
As-built documentation – must take into consideration all changes of original design
documentation and implemented into the project. Including all acceptance documentation.
Measurement protocols –this can consist of:
OTDR and attenuation. Optional PMD and CD.
Sag and tension value.
Dampers localization and quantity.
Resistance of earthing system on each tower (an option),
All of tests must be completed and approved by the associated engineer before acceptance.
According to the survey the main commissioning tests which are completed after installation process
are: OTDR, power meters, attenuation profile, PMD and CD and these are done contractor in 83% of
cases.
The process of checking for commissioning documentation can be gradual. It can be commence during
the installation process or can start just after the completion of installation stage.
The following items must be completed before the final commissioning:
Physical check of works – depends on standards and practice but usually 10-100%,
As-built documentation – 100%,
Measurement protocols – 100%;
In case of some defects a notice to eliminate them must be issued. The Contractor/Installer is obligated
to fix all of these defects in the shortest possible time. Once all defects are rectified the commissioning
process starts again.
After successful checking and completion all documentation the final commissioning results can be
accepted and officially signed off by the relevant parties.
97
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
98
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
5. Maintenance
5.1 Introduction
Telecommunications systems are essential elements of modern electrical grid management network
infrastructure. Fibre is the carrier of modern telecommunication networks. Critical power system
protection and control as well as commercial traffic is carried on the fibre optic networks built/owned
or in some instances leased/operated by utilities. Fibre breaks can result in loss of protection and control
channels and forced outages on multiple high voltage lines thereby compromising power system
reliability. The high reliability requirements associated with this traffic combined with geographic
diversity of the network highlight the need for well-defined maintenance practices.
The fibre network needs to be supervised to avoid disturbances and unplanned outages. There must
also be an organization to do predictive and corrective maintenance as well as prepared plans for
emergency repair.
Many electric utility owners with fibre networks lease their fibres to telecom operators. This places an
additional set of demands on the network owner. Commercial telecom operators usually have systems
with higher bandwidths and low tolerances for outages. They often require planned outages to take
place at nights and/or at weekends to avoid disturbing their customers. This does not correlate well to
normal, safe work procedures in place at most electrical grids. Further the higher bandwidths required
might cause the telecom operator to demand a higher optical quality than the utility owner needs for
their own network. It should be understood that at all times within a utility, the needs of the grid
electrical network and associated protections are given much higher priority than the telecom network.
A challenge with OPGW and OPPC maintenance is that the technology is relatively new and there is little
experience documenting lifetime limitations. Survey responders raised the highest levels of interest in
the maintenance section compared to all other sections of the TB.
Even though the first OPGW installations are from the seventies the technology has developed over the
years and to date standard methods have not been in service time long enough to validate lifetime
expectancy. The OPGW cannot be expected to have a longer life time than a standard Overhead Ground
Wire placed in the same environment. Problems seen so far from the results of the survey can be related
to errors in design, manufacturing, installation or external impact. The majority maintenance work on
OPGW attempts to correct errors produced at different stages in the design/installation process.
There are ongoing technical studies presented to validate lifetime performance against design targets.
This is an exhaustive undertake because of the various OPGW construction (loose buffer tube vs tight
buffer tube, spacer vs metallic tube, central vs stranded tube, fibre congestion and sensitivity etc.). It
is also difficult to determine whether or not the OPGW has experienced the expected operational and
environmental conditions.
The OPGW/OPPC network is deployed on the EPUs overhead infrastructure and most repairs will be
done between towers or between splice boxes. These repairs will need to be coordinated with power
system operators and require an outage on the power network. As a result, the MTTR (Mean Time To
Repair) will be longer compared to MTTR for underground cables. On the other hand, MTBF (Mean Time
Between Failures) is also significantly longer, allowing for a more reliable overall system. These factors
must be taken in consideration when negotiating SLAs (Service Level Agreements) with third party
customers as well as when giving SLAs to internal functions within the utility.
For OPGW/OPPC maintenance there has to be a clear division of responsibilities and an understanding
within the EPUs departments, mainly for line maintenance and telecommunications maintenance. 56%
of respondents to the survey state that OPGW/OPPC maintenance is carried out by the HV Line
Department. There should also be an agreement on the threshold values at which maintenance of the
asset will be triggered. The threshold value depends - among other things - on the nature of the
anomaly, age of the asset, remaining lifespan and availability of outages. For example, an asset with
five to ten years remaining until end of lifespan may be maintained to function during the remaining
lifespan rather than adapting to as new maintenance standard.
99
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
It is imperative that the maintenance department is involved in the design phase of a project. This
ensures maintenance friendly installations e.g. more unified installations which among other things
reduce the number of items needed in stock, number of routines and need for education.
The total cost over the lifespan of an asset could be lower if maintenance is taken into consideration at
the design phase. A slightly higher installation cost could lead to significantly lower costs for
maintenance, therefore giving a lower total lifecycle cost.
The official handover to maintenance should follow the commissioning of the assets at the end of the
project. In this scheme, maintenance group accepts the delivery and takes over the responsibility for
the asset from the project.
There should be a handover meeting with a pre-set agenda and protocol where the specific parts for
the built asset are reviewed. The handover should include a formal document detailing the maintenance
responsibilities, where maintenance accepts the delivery and then takes over responsibility of the asset.
The handover document must include references to as built documentation, type tests, FAT, vibration
studies, warranties, maintenance plans, stock lists, etc.
100
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The inspections of OPGW and OPPC should be part of line maintenance inspections. These should be
integrated in the overall power line inspection procedures. Specific instructions on how to inspect
OPGW/OPPC should be given to line maintenance crews.
A program of Detailed Helicopter Inspection (DHI) which combines power line and OPGW or OPPC
inspection would reveal issues as broken strands on OPGW/OPPC or issues with attachment
hardware/accessories. DHI programs are expensive, but provide valuable design and operations data.
Additional information can be given when using infrared, heat-sensing cameras as well as standard
video and still image cameras mounted on Gyro-stabilized platforms underneath the helicopter providing
clear, high-resolution, recordings which are downloaded after every run. An operator controls the
camera for best views.
The use of drones - with much lower operating costs – to conduct DHI programs are being investigated
by EPRI and a number of EPUs. The development of this technology is continuously improving. The
stability of the drone images, their ability to gather the same amount of data with various camera
systems are issues being addressed. National laws may limit the use of drones.
101
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The process of failure investigation often involves several groups within a utility corporation which can
prove to be challenging. There are several competing considerations such as minimizing further damage,
speedy restoration of power system, resource/crew planning and expedited material procurement. The
most important factor shall be public and crew safety.
102
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
5.4.2.2 Correction
The standard solution to broken strands is to repair with repair rods as seen in Section 2.5.7. The repair
rods should have the same lay direction as the original cable for maximum effectiveness. For example,
if the OPGW with broken strand is left-lay, the armour rods used for repair should also have left-lay.
Breaking of the OPGW strands usually don’t affect the fibre strands in the central core, but can in rare
cases affect fibres in a stranded stainless steel tube cable. For some central tube designs, the use of
repair rods is not recommended.
If an excessive number of the cables strands are broken, repair using armour rods may not restore
cable strength to an acceptable percentage of Ultimate Tensile Strength (UTS).
Replacement of the damaged section is then necessary. If only a few spans are changed, additional
splice boxes must be installed. The overall system optical budget must be taken into consideration
when adding new splice boxes.
103
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
5.4.3.2 Correction
To avoid grounding issues in the future a proper shunt should be installed. This bonds the OPGW directly
to the tower as seen in Figure 5.6 below.
104
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 5.5 Same type of tower and fitting with shunt for better grounding [B31]
Galloping is oscillations up to 3Hz with amplitudes up to 10 meters. The damages caused by galloping
can be considerable on hardware and OPGW/OPPC. The stockbridge dampers in Figure 5.7 below were
damaged due to galloping.
105
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
5.4.4.2 Correction
Galloping on OPGW/OPPC can be suppressed by modifying the aerodynamics along the OPGW/OPPC
with alternating profiles. One solution is to install air flow spoilers (see Figure 5.8) in 25% of the span
length, in two groups around the quarter and three quarter points in the spans.
Figure 5.8 Air flow spoiler installed on OPGW to reduce galloping [B31]
106
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The increased impact comes from wind induced vibration and ice loads on the accessories. It is possible
to re-enforce the OPGW locally with armour rods in the clamping area. However, this will increase the
weight and surface area of the material.
Temporary loads and stress are induced on OPGW/OPPC when a cable car is used in the assembly of
bird diverters and marker balls or when servicing OPPC splice boxes and/or insulators.
The increased influence comes from the cable cars wheel diameter in combination with the weight of
the unit. This results in bending stress which could be critical to the OPGW/OPPC.
OPGW/OPPC manufacturer must be contacted to verify if the specific OPGW/OPPC can handle a cable
car.
107
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
108
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Figure 5.11 Splice box before recoiling (top) and after recoiling (bottom) [B32]
Figure 5.12 Splice box were tubes are bent due to pistoning [B30]
A temporary resolution is to allow fibre bundles to have room to move freely inside the splice box. The
permanent resolution however, may be harder to achieve. It involves re-terminating the cables inside
109
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
the splice box, this time with the strength member (or Kevlar) tied off. In extreme cases, the strength
member is too far inside the cable and replacement of several spans may be necessary.
Figure 5.13 below shows the same splice box after the tubes are rerouted to avoid excess bends.
Figure 5.13 The same splice box after the tubes are rerouted to avoid bends [B30]
110
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
111
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
ROTU ROTU
Private Corporate
WAN Network
Remote
Clients
Internet
Figure 5.14 Schematic example of Automatic remote monitoring system for optical cables
In the event of fibre break or higher than expected losses, automatic alarming will allow NOC operators
to isolate fault location and direct crews quickly – this is often a time-consuming first step in any
restoration. MTTR is therefore reduced significantly.
Fibre monitoring system also acts as a central, archival repository of fibre records and measurement
results, a valuable tool in asset management planning (identify asset demographics), engineering
(design parameters and records), operations (preventative and on-going/routine maintenance) and in
any dynamic/historical failure analysis.
112
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
In summary, a Remote Fibre Monitoring System has the following overall advantages:
Auto Optical Time Domain Reflectometer (OTDR) Geographical fault location for reduced MTTR;
Powerful remote real-time surveillance tool for the health and performance of fibre network
over time and over various atmospheric conditions, thus providing end of life indicators.
Predictive capability for fibre cable and related assembly failures – thus leading to planned
proactive repairs before they become forced outages.
Faster, less expensive and more efficient test & measurement tool that replaces preventive
maintenance, and the need for aerial cable helicopter inspections.
A marketable value-added service for commercial customers resulting in added revenue.
Immediate access to a central fibre optic information and trend data depository.
Immediate access to the most current and up-to-date test records.
Quick response by staff with limited training possible.
Centralized and up-to-date access to spare fibre cable and material records.
Two CIGRE documents which provide more in-depth details on automatic remote monitoring systems
for optical cables are:
D2_112_ Optical Network monitoring system of “Red Eléctrica de España”, 2012 [B39].
D2-01 A07 Optical Cable Management System for 500kV HVAC Networks, 2011 [B40].
113
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
1 3 4 5
NOC 2nd Line Feedback to
Fault reported to Emergency repair
Troubleshooting customer
NOC team
Rerouting Contract issues
NO NO
NO TEMP
NO 7
Considerations of
NO cost for temporary
repair
2
External
Netowner
External 8 6
Netowner Maintenace dep. Permanent repair
9
Closure of case
In the event that optical communication needs to be restored quickly, a key factor is the establishment
of the exact coordinates where the fault is.
Once the location (map coordinates) is established, there must be established procedures for the type
of cables involved as follows:
Wrap cable.
ADSS.
Duct cable.
OPGW, ready for emergency installation.
Cooperation between electrical and telecommunications NOC is essential in an emergency
repair/restoration situation.
The situation of an emergency fault with no possibilities for an electrical outage is complicated but easier
to handle if prepared.
For OPGW if the splice boxes are accessible a temporary connection can be made between splice boxes,
either by wrap cable, ADSS, tactical cable or other sufficiently hardened temporary fibre cables laid on
the ground.
Quite often with a short outage and some planning a permanent solution can be made relatively quick.
This reduces the overall workload and avoids first making a temporary solution and later a permanent
one.
For OPPC there are no methods for live line restoration.
114
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Temporary Cable
Another method is to install a temporary cable between two splice boxes. The cable could be overhead
(ADSS), a cable directly laid on the ground or a combination of both. The cable must be all-dielectric
and hardened so as not to get damaged easily. Problems with cables directly laid on the ground are
crossing roads, railways and rivers etc.
Prepared drums with cables in ducts or a stronger cable for installation without ducts are also a feasible
repair option. The IEC 60794-3-70:2016: “Outdoor cables for rapid/ multiple deployment” standard
could be used for specifying temporary ruggedized fibre cable for an emergency restoration kit.
A temporary ruggedized fibre cable should be capable of being deployed on the ground, on temporary
towers or tree canopies to restore services. The cable must have high crush resistance so that it is not
damaged when impacted by vehicles when crossing roads etc. The jacket must be made of tough
material and have chemical resistance according to the environment where it is installed. Cable
manufacturers produce a ruggedized, small diameter cable of small fibre count (sometimes called
restoration cable or tactical cable) specifically designed for this purpose.
115
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
ADSS could also be used, ADSS is a cable type for overhead installations which should be tensioned to
a high torsion strength provided by the manufacture. ADSS can be mounted in towers and poles etc. In
extreme situations, the ruggedized fibre cable or ADSS can be dropped and installed from a helicopter
flying slowly at low altitude. Even if not intended ADSS cable, (which has rigid jacket and good crush
resistance), can be placed on the ground (or preferably in ducts) to act as a temporary cable. Temporary
cables could be recovered for reuse but the cost for recovering might be higher than ordering new
material.
5.8.1 Storage
Material in the spare parts supply may never be needed. Nevertheless, when they are required they
must work without disturbances. The storage area as well as the material must therefore be chosen
with this in consideration. The material has to be packed in such a way that it is not affected by the
climate conditions of the storage.
According to the survey pull just 50% have their own stock in stores of those who do have it, 60% have
special storage requirement.
Cable drums are of importance. If wooden drums are stored in non-ideal conditions the wood can rot
and the drum can be very hard to manage, it might collapse during handling or stringing. To avoid this
steel drums are preferred instead of wooden drums for long time storage of OPGW/OPPC.
Any cables stored should be capped at both ends.
116
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
5.8.2.1 OPGW/OPPC
The variety of types of OPGW/OPPC needed in stock depends on the number of different types of
OPGW/OPPC installed in the network.
Replacing a cable with a cable of the exact same type is straight forward exchange and should not give
any additional problems. If the cable is replaced with a new one with other physical data, new
calculations must be carried out where the suspension and tensile forces in the towers are calculated.
Towers might need additional support, sag must be calculated to ensure proper distance to other phase
conductors and different type of fittings might be needed.
If the installed OPGW/OPPCs are no longer in production there has to be a substitute in the storage.
Calculations of sag and tension and engineering of fittings to attach the preferred design to the towers
can be done in advance. The number of cables needed in storage would decrease and fewer
constructions/designs could be used to fill the needs of supplies for the whole network. Additional
disturbances in the event of an emergency repair when not replacing an exact same cable type could
also be avoided.
The longest installed length should serve as a minimum length for drums in storage. However if there
is a huge variety of installed lengths in the network it could be beneficial to have different lengths in
storage. E.g. longest installed length is 5.5km, but many installed lengths are around 3.3km. Then it
could be useful to have both 6km drums and 4km drums. The 6km drum to handle the longest lengths
in the network and the 4km drum would be easier to handle in an emergency situation. If the terrain is
problematic it might be difficult to handle large drum lengths of OPGW/OPPC due to their size and
weight. Transportation for stringing equipment for these drums is also a consideration when selecting
a suitable drum size.
5.8.2.2 Fittings
Since the fitting usually consists of a number of different parts the easiest way to handle the fittings is
by set packing. The sets should be packed so that for each type of tower there should be a complete
set for a given cable type. If there are variations for example in the interface connection to the tower,
parts for all combinations should be included in the sets.
5.8.2.3 Clamps
There should be clamps to secure the cable to the tower when lead down from the top of the tower to
the splice box. The clamps could be considered as part of fittings.
5.8.2.4 Splice Boxes
Splice boxes with splicing hardware and accessories for one splice should be stored as a kit. This should
include, splice box, splice cassettes, sleeves, and materials required to attach the splice box securely to
the tower and the cable.
5.8.2.5 Special Tools
Any special tools required which are recommended by the OPGW/OPPC manufacture should be stored,
maintained and ready to use for emergency repairs.
5.8.2.6 Summary
A full inventory of all materials installed on the network is essential to completing repair work in as an
efficient means as possible. It is preferred if the whole network is built with the same type of
OPGW/OPPC and all of the towers are similar, but this is rarely the case in the real world. New varieties
come with developments of the technology over time. It is important to adapt to these changes.
117
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
In order to restore service, response crew installed insulation and attached a heating wire to the OPGW.
The heating wire was connected to an electric generator. The external heating wire warmed the first
118
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
10 meters of OPGW from splice box (in the access loop). The attenuation losses were reduced and the
link was restored on a temporary basis.
Within less than a week, a permanent fix was planned, high voltage power and communications outage
permits were secured through the NOC.
Two mid span cuts were made and four spans of OPGW were replaced with new OPGW in such a way
as to remove the affected splice box.
The fibre section from tower deadend facing East of the splice box and from splice box to deadend
assembly facing West were sent to manufacturer.
Testing and final dissection showed that the central core of the cable was crushed in one location
allowing water ingress into the core, see Figure 5.19 below.
Figure 5.19 Broken Aluminium Core as a result of improper installation practices [B30]
Another cut on the Aluminium core was caused by ice pressure. Dissection of the sample and detailed
site photographs taken earlier that summer showed that the original crushed core and subsequent tear
was the result of improper installation of a temporary ground stirrup clamp which was actually left on
119
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
the cable. A demonstration showed how this improper installation could deform and cut a tear in the
core. A failure analysis report was produced.
The above example is a case where a permanent fix (replacement of four spans) had to be carried out
before a failure analysis was complete. In this case, the temporary fix with an electrical wire heater
required a gasoline generator on 24/7 basis with crews on standby to fuel the generator every 6 hours.
A patrol of the line (90km) showed the same grounding stirrup still installed on the cable in several
other locations which were then removed during a maintenance plan.
It was concluded that the reason for this fault was due to the incorrect installation of grounding clamps
for the OPGW.
During the original installation of the this power line, two ground wires were installed. Both ground
wires where connected to ground with clamps and shunts at each tower.
When one of the ground wires was subsequently replaced with OPGW for some reason no shunts were
installed on the OPGW.
Differences in potential caused induced power/current to flow through the fitting, this induced heat,
causing the fibres to break in the fitting.
120
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
First task involved the installation of a shunt on the tower and all other towers to prevent any more
fibres from breaking. An further inspection in all towers was conducted to verify that no other defects
were present.
Finally the damaged OPGW section was replaced. In this case there were available fibres on the route
and the work could be carried out with no impact to the network.
During the inspection of the Termination Unit and connecting fibre cable, it was noted that the unit had
been mounted incorrectly, such that insufficient mechanical support was provided to the unit by the
attached dropper arrangement, see
Figure 5.21. This promoted a pivoting motion of the Termination Unit leading to attrition of the fibre
cable at its union with the unit.
It was concluded that the incorrect rotation mounting of the Termination Unit and the associated
arrangement of the dropper conductor led directly to the fibre failure through in-service pivoting of the
unit causing attrition of the lead-in fibre cable.
121
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Suitable measures must be taken to keep moisture (mist, rain etc.) out of the splicing area during set-
up preparations. Wind and gusting can cause difficulty in keeping cores secure and undamaged during
the splicing operation and may also ‘blow’ the fusion arc leading to failed or out of limits splices. Again,
suitable measures must be taken to protectively orient or shelter the splicing area during set-up
preparations. Splicing must not take place if these measures cannot be applied within any relevant
safety constraints.
Temporary Repair
Due to the adverse weather conditions experienced at the time of the fault there was an increased risk
of damaging the OPPC fibre cores during re-orientation of the Termination Unit. This damage cannot
be rectified without conductor re-stringing adjustment. To complete an effective repair in a safe and
suitable environment, at the time, would require the installation of scaffolding. This would significantly
increase the line/voltage outage time to complete the repair. This increased repair time was not feasible
due to high energy demands on the network.
The level of risk required to restore the system to its original state was deemed too high. An additional
solution was required as a temporary measure.
A short term solution was implement with the use of an existing widely used technology, Phase To
Ground (PTG), see Figure 5.22.
This solution was completed in short period of time (hours). The phase to ground was connected into
the additional port on the ‘live’ side of the OPPC termination unit. Splicing was completed in a mobile
122
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
elevated working platform. All critical services were restored and the system operated with no issues
for a period of 6 months until a full repair on the Termination Unit was completed.
123
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
12
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
6. Conclusion
This TB is a thorough overview on OPGW encompassing its project management, its designs, its testing,
its installations and its maintenance since its creation in the early 1980s. As a whole, the industry has
coincided into common project approaches, into a general rally around metallic tube with a high count
of fibres of new generations of improved telecommunications transmission performance, into standard
construction practices and into mitigative actions in maintenance.
The full scope is validated from the analysis of the survey included in the TB.
Nevertheless, the subject is not exhausted and has seen continuous lessons learned and new ventures
in topics such as OPPC, DTS and DSTS. One further topic of recent interest because of product 30-year
history of deployment is the assessment of its reliability and if the actual performance meets the design
predictions. This latest topic remains the complex subject of future studies because of the variety of
the conceptual configurations that were deployed.
125
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
126
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Acronym Phrase
JWG Joint Working Group
SC Study Committee
SME Subject Matter Expert
TB Technical Brochure
WG Working Group
Acronym Phrase
AA Aluminium Alloy
ACS Aluminium Clad Steel
AACSR All-Aluminium Conductor Steel-Reinforced
ACSR Aluminium Conductor Steel-Reinforced
ARD Anti-Rotation Device
CWDM Coarse Wavelength Division Multiplexer
DAP Designated Access Panel
DC Direct Current
FFH Factory Formed Helical Rods
FO Fibre Optic
HAES Helically Attached Elastomer Suspension
HV High Voltage
ITP Inspection and Test Plan
MASS Metallic Aerial Self-Supporting
MDL Maximum Design Load
MFD Mode Field Diameter
MRDT Maximum Rated Design Tension
NOC Network Operation Centre
NZDSF Non-Zero Dispersion Shifted Fibre
OHL Overhead Line
OPAC Optical Attached Cable
OPGW Optical Ground Wire
OPPC Optical Phase Conductor
OTDR Optical Time Domain Reflectometer
Plastic Buffer Tube or
PBT
Polybutylene Terephthalate
PFR Preformed Helical Rods
PMD Polarization Mode Dispersion
PTG Phase To Ground
RFQ Request for Quotation
RTS Rated Tensile Strength
SBS Stimulated Brillouin Scattering
SMF / SM single-mode Fibre
SRS Stimulated Raman Scattering
TIA Telecommunications Industry Association
127
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Acronym Phrase
TSO Transmission System Operator
UTS Ultimate Tensile Strength
128
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
129
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
130
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The results of the survey are plotted throughout this appendix with different graphs. The different
sections in this appendix follow the same structure as in the survey questionnaires.
The following considerations must be taken into account:
- Many assumptions have been made in order to summarize all the open text answers. For
example:
o In question #1.3, the answers have been grouped into four different groups but open
answers, like “to 22 up to 500kV”, have been considered in each of the different groups
made. This way the final graphic expresses the results in a more realistic way.
o In question #2.2, a second graphs has been made to show better the different ‘yes’
answers studding the “Other Collaboration” text box.
o In questions #3.18, a summary of some of the received answers has been made in
order to show the main ideas of the different responses.
- Not all the respondents have answered all the questions, so some percentages are relative only
to those who answered affirmatively or who answered something.
- “Unanswered” questions were omitted.
131
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
PARTICIPATION (Continental)
3%2%
24%
37%
34%
0 2 4 6 8 10
132
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
15
11 11
10
10 9
6
5 5 5
5 4 4
3
2 2 2
1 1
0 0 0
0
OPGW OPPC ADSS Wrapped Lashed Other FOC Underground
Cable Cables
30% 29%
19%
22%
22 ≥ X < 132 132 ≥ X < 220 220 ≥ X < 400 400 ≥ X < 765
133
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
27%
37%
36%
14 16
12
10
8
6
4
2 4
2
0
134
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
20%
80%
Yes No
20
21
15
10
5 8
3
0
20 22
15
10
5
3 0
0
135
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q1.9] Do you use DTS or other systems using FO cable as sensors in OHL?
17%
83%
Yes No
25%
42%
33%
Raman
20%
Brillouin
80%
Brillouin Raman
136
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q1.10] What are the types of fibre optic systems in your utility?
30
19
20
9
10 4
[Q1.11] Do you lease dark fibre and/or telecommunications services on your fibre?
36%
64%
Yes No
137
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q2.2] If there is collaboration between Telecommunications & HV Lines Departments, how is these
collaborations?
9%
24%
67%
138
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q2.3] Cable Design: what is the area of knowledge of your OPGW/OPPC specialists?
20
10
28%
72%
Yes No
26%
32%
25%
139
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
38%
62%
Yes No
[Q2.5] Demarcation Points: how do you determine the demarcation between two optical networks?
10%
3%
8%
37%
42%
Splice Box ODF Physical Border Geographical Border Other Demarcation Points
10
5
2
Central Tube Central Alum Central Stainless Stainless Hexacore Slotted Core "Other"
140
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
34%
66%
[Q2.8] If any part of the project is fixed by a superior (e.g. Government, Standards, etc.), please specify
which standard.
0 5 10 15 20 25
141
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
0 2 4 6 8 10 12 14 16
TIA/EIA-455-81 4
TIA/EIA-455-41 4
TIA/EIA-455-3 4
ITU-T G.652 20
0 5 10 15 20 25
[Q2.9] At what stage is hardware and fitting compatibility considered during design process?
The majority (90%) consider the design of the hardware and procedures from the point of view of the
fitting compatibility from the beginning of the design process.
This part in a lot of cases is checking during the initial tendering process as part of the product technical
qualification process and the vendor approval process.
Only a few take this into account during the testing and only one, consider it and the end of the design
of the cable.
142
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
32%
68%
Yes No
Own Company Standards International Standards Manufacturer Standards Other tests conforming to
85%
Yes No
143
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q2.13] Does your company require Type Tests for OPGW/OPPC cables?
85%
Yes No
No Yes
144
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.2] Does your company have field specialists for inspecting & supervising the deployment of the
cable or the supervision is external?
38%
62%
Internal External
90%
Yes No
145
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.3.1] If “Yes”, do you require FAT of the 100% of the reels, or do you require other inspection rates?
18
17
17
16
10
146
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
43%
57%
Yes No
[Q3.5] Does your company have any number or list of certified factories or manufacturers that are
preferred?
25%
75%
Yes No
147
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.6] Does your company use a Procedures Guide for mounting and installation of OPGW?
95%
Yes No
10 8
[Q3.7] Does your company supervise the mounting and installation tasks of the OPGW/OPPC?
95%
Yes No
148
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
30
25
20 18
15
10 7
5
0
[Q3.8] Does your company have specialists for the fibre optic splicing tasks?
43%
57%
Yes No
149
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.9] If your company subcontracts the FO splicing, do your contractors have to pass a specific training
course?
35%
65%
Yes No
[Q3.10] Does your company have instruments and adequate tools in order to do a precise optical fibre
splicing as well as measurement tasks?
23%
77%
Yes No
150
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
100%
Yes No
35
29
30
25
20
20
15 12
9
10
5 1
0
17%
83%
Utility Contractor
151
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.12] For splicing tasks as well as for the fibre optic cable testing, does your company have its own…
20
15
10
4
5
23%
77%
Yes No
152
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
24%
76%
Yes No
[Q3.14.1] What is the maximum length? And [Q3.14.2] What limits this length?
According to the answers normal lengths go between 4,000m - 6,000m, going from 2,000m to almost
10,000m but it depends a lot on the criteria of each company, on the limitations of handling and
transport due to the weight and size.
The main limitation for the maximum length of the drums is the weight and size of the reel and cable
that can be handled both in the manufacturing, transport and installation phases.
Other limitations are marked by the overhead power lines itself: type of towers, access to towers,
distance between towers, and location of splice boxes or simply mechanical issues
153
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
50% 50%
Yes No
[Q3.15.1] If you store your own stock, do you have special storage requirements?
40%
60%
Yes No
154
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q3.16] Does the hardware manufacturer contribute during the deployment, installation and
commissioning of the OPGW?
32%
68%
Yes No
[Q3.17] Do you have specific packaging requirements for the cable (additional to international
standards)?
46%
54%
Yes No
155
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
The mechanical tension used to install OPGW is usually according not to exceed a certain percentage
of the cables rated breaking, some examples of responses are:
- Paying-out tension is less than 20 % of UTS of OPGW
- 20-30% RTS (Rate Tensile Strength)
- 10% of UTS up to 1000 kg,
- 14% cable breaking load
- Within a band of 15 % either side of the UTS
- It is under 20% of ultimate tensile strength.
Other companies follows manufactures recommendations but in general, the exact amount depends on
the OPGW cable type and the chosen criterias, i.e:
- Line type tension:
o OPGW 60m2 7.8kN(800kgf)
o OPGW 80m2 9.8kN(1000kgf)
o OPGW 90m2 9.8kN(1000kgf)
o OPGW 170m2 10.8kN(1100kgf)
- And maximum stringing tension of OPGW installation is 10% UTS
95%
Yes No
156
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
According to the answers this information is cable dependent and the companies usually follow the
cable manufacturer recommendations.
Some criteria are:
- Sheave diameters are generally based on IEEE 524 recommendation of 40 x D where D is
outside diameter of OPGW.
- Minimum radius of the pulleys; more than 225 mm or more than 20 times of OPGW diameter.
- Depends on cable diameter. Basically 70 x diameter.
- 30 x diameter of cable.
Some examples are:
- Minimum radius of the drum is 500mm and minimum radius of the pulley is 225mm.
- Minimum winding diameter is 1000mm. Minimum diameter of pulley is 450mm.
- Drums 2200 mm diameter, pulley 120° radius
- 800 mm drum and 300 mm pulleys
- 1200 mm for the drums and 800 or 600 mm for the pulleys depending on first/last pulley of the
section or not
- drums: 450 mm, pulleys: 175 mm depends on transmission tower type
157
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
C.4. Maintenance
[Q4.1] Does your company have preventative maintenance or only corrective/reactive maintenance?
39%
61%
[Q4.2] Does your company have a predictive maintenance program (condition-based maintenance)?
42%
58%
Yes No
37%
63%
Yes No
158
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
10
”Other” answers:
15
10
10
159
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q4.7] What drives the decision to perform preventative maintenance vs. corrective (reactive)
maintenance?
20
15
15 12
10 7
5
20
15
10
10
160
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q4.9] Does your company have an Automatic Remote Monitoring System to remotely check your optical
cables?
45%
55%
Yes No
[Q4.10] Does your Network Operation Center (NOC) monitor your fiber optic cables?
49% 51%
Yes No
[Q4.11] What are the main maintenance issues with your OPGW/OPPC cables?
The main causes of breakdown or maintenance activities have to do with weather conditions or
environmental issues: corrosion, damage by vibration, wind or ice issues, lightning, falling trees, etc.
Other are relationed to improper installation:
- of the juction boxes: fibres creeping into splice box, rainwater infiltration,
etc.
- of the fittings or dampers.
161
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[Q4.12] What are the main faults your OPGW/OPPC cables suffer?
- Faults and/or cable breaking due to mechanical types like falls infraestructure or aerial
accidents;
- Faults due to installation errors like optical fiber disconnection into splice boxes, water leaking
into cable, etc.
- Faults due to weather condictions like lightning, corrosion, snow, rain, etc.
The main consecuences of this fault are damages over the surface of the cables (like some brand
disconnection or even break off, corrosion, etc) or attenuation losses in the links.
Some examples of concrete answer are:
- Deformation of an aluminium pipe struck by the lighting causes the pressure to the fiber core
and consequently the loss of signal occurs.
- Melting or breaking down of steel core caused by lightning.
- The faults is caused by the freezing of the water that is soaked into the slotted core of the
OPGW. The fibre core is pressed by the expansion of the frozen water and consequently the
loss of signal is caused by the bending of the fiber.
- Increase in attenuation caused by compressing the fiber due to frozen or corroded aluminum
pipe.
- Strand disconnection or break off. Water leaking into cable. Installation errors.
[Q4.13] Do you have Service Line Agreements (SLA) with third parties?
38%
62%
Yes No
162
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
15
10
Local International
36%
64%
Yes No
163
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
C.5. Survey 2
[S2-Q1] What construction Type was the 1st OPGW/OPPC Installation in your network?
0 2 4 6 8 10 12 14 16
[S2-Q2] Please select the legacy and current characteristics of the fibre optic used in your OPGW/OPPC
network
LEGACY CURRENT
164
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[S2-Q2.1] Why were these characteristics selected? i.e. legacy, national standard, etc.
16% 11%
5%
21%
47%
29%
71%
Loose_Tube_Buffer Tight_Tube_Buffer
165
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
[S2-Q4] What type of fibre optic connectors do you use in your network?
APC/SC 4
SC 16
FC 12
LC 11
0 2 4 6 8 10 12 14 16 18
12%
49% 24%
15%
166
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
In where v is the propagating speed, c the speed of the light in the vacuum and n the RI.
When we inject a laser pulse in a single-mode optical fibre, the propagation mode is TEM or quasi TEM
because the core diameter and its numerical aperture cuts other propagation modes. But this pulse trends
to propagate in all polarization modes, horizontal, vertical, inclined and circular.
In an isotropic media, the polarization mode is irrelevant because all of them propagates at same speed
and the wave-front of all polarization modes travels at the same speed. But what happens if the refractive
index becomes polarization dependent?
As a consequence of that, certain polarization modes will travel faster than others and its arrival time at
the detector will be not the same. This is the static PMD and its consequence is a pulse broadening. Its
causes can be found in symmetry or doping errors during the fibre manufacturing or manipulation
processes, deployment included.
In the real world and in terms to understand the propagation phenomena, we must consider that the
refractive index at every point inside the fibre depends on the polarization of the light, its power strength,
the temperature, the wavelength, the presence of external electric fields, its direction and other minor
parameters which are out of the purpose of this booklet.
To explain those complex phenomena, we need to apply superposition principle and examine the problem
from diverse points considering the RI properties only dependent of a few variables. In general, the
evolution of the optical wave inside the fibre will be the sum of those partial phenomena.
167
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Self-Phase Modulation
In the previous case we consider the Kerr effect due to the static optical power, which is the case of
Raman or ROPA pumping carriers.
Transmission of information implies carrier changes and now let’s analyse what is the evolution of the
RI when the optical power is changing. In that case the RI trends to increase when the amplitude of
the signal increases and decreases when the signal decreases. Increasing RI means low propagation
speed or phase delay while the opposite case means a phase advance.
This phase shifting can be considered as a Phase Modulation which broads the optical pulse.
Mathematically:
n(廡,I) = n0(廡)+n2I(t)
庣NL(t) = (2彃/ʎ)n2I(t)L
168
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Source: (4)
Fig. D.1 Instantaneous frequency variation vs. Pulse Power in Arbitrary Units
Self-Phase Modulation is an impairment related to the Pulse Amplitude Modulation which is the optical
modulation generally applied. However, the continuous wave modulations that the Industry starts to
apply now, looking for highest signalling speeds, overrides this phenomenon.
More promising is the technique which uses orthogonal polarization for the optical carriers eliminating the
FWM because its orthogonality. This technique will improve the FWM but the system becomes more
sensitive to the PMD.
169
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Fig. D.3 The Induced Phase Shift in fibre optics with Transverse Electrical Field
Some Authors have described, also, a certain degree of Faraday’s rotation measured using a polarized
light. This becomes relevant with the recent transmission systems which uses coherent detectors.
In AC power lines, this effect has lower importance than the DC lines because the electric and magnetic
fields are periodical and its effect is self-cancelled. In DC power lines both electrical, magnetic fields are
constant along the power line, and this effect should be considered.
In general, the presence of external electric field will be noted as an increment of the PMD more
important in DC lines.
on the positive side, the effect of electric field over optical devices is appreciable in fibre optics but is
more intense in some crystals like Lithium Niobate. This effect is applied in a complete dielectric voltage
sensor that his working principle is illustrated in the next figure:
170
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Source: (4)
Fig. D.5 SBS effect in a fibre when the launched power changes from +30 to +32.5 dBm
SBS introduces the most stringent power limit for the amplification and the passive propagation of
narrow-band optical signals in fibres. In order to avoid the Brillouin threshold, it is possible to increase
the bandwidth of the light beyond the Brillouin gain bandwidth, reduce the fibre length, concatenate
fibres with slightly different Brillouin shift, or, in high-power active fibre devices, exploit the longitudinally
varying temperature.
171
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
Source: (10)
Fig.D.6 Back reflection versus output power for three fibres with launched power up to
+27 dBm
Actually, the SBS effect is used in distributed sensors that uses the fibre itself. For silica fibres, the
Brillouin frequency shift is in the order of 10 to 20 GHz with the bandwidth up to 50 MHz and is a linear
function of the fibre temperature:
߭ ሺܶሻ ൌ ߭ ்ܥሺܶ െ ܶ ሻ
Where CT is the Frequency-Temperature coefficient and ưB0 is the Brillouin frequency shift at reference
temperature T0
Source: (4)
Figure D.7 The Raman gain in function of the pumping frequency offset
172
Design, deployment and maintenance of optical cables associated to overhead HV transmission lines
From engineering point of view, both SBS and SRS have the impairments and useful characteristics
resumed in the next table:
SBS SRS
• Suitable for applications where a single • Large Bandwidth allows its use as Telecom
wavelength is present in each direction signals amplifier
• Phonons propagates only in the same • Optical phonons propagate in both directions, the
direction of the pumping wavelength gain is effective in both directions
PROS • Excellent performance as a distributed • The frequency shift allows the filter separation of
temperature sensor the pumping wavelength
• High Peak Gain around 90 dB (Phonon Gain) • Gain Peak around 60 dB with some bandwidth
• High reflected power allows its use as a laser • Suitable for large bandwidth signal distributed
resonator amplifier
Appendix D References:
(1) Z. Liu, G. Ferrier, X. Bao, X. Zeng, Q. Yu, A. Kim. Brillouin Scattering Based Distributed Fibre
Optic Temperature Sensing for Fire Detection
(2) AN 4091, Corning Glass, Inc. Explanation of the Sources of Variation in Optical Fibre Effective
Group Index of Refraction Values.
(3) O.V. Butova,*, K.M. Golanta, A.L. Tomashuka, M.J.N. van Stralenb, A.H.E. Breuls. Refractive
index dispersion of doped silica for fibre optics
(4) Dr. Rüdiger Paschotta. Encyclopaedia of Laser Physics & Technology.
(5) L. de la Cruz-May, E. B. Mejía, O. Benavides, J. Vásquez Jiménez, J. Castro-Chacón and M. May-
Alarcón. Novel Technique for Obtaining the Raman Gain Efficiency of Silica Fibres
(6) G. Ravet, M. Wuilpart, J.-C. Froidure, P. Mégret, M. Blondel. Measurement of the distributed
Raman Gain spectrum in single-mode optical fibres.
(7) Q. Lin and Govind P. Agrawal. Raman response function for silica fibres.
(8) S Mauger, L Bergé and S Skupin. Self-focusing versus stimulated Brillouin scattering of laser
pulses in fused silica.
(9) G. Ronald Hadley and Arlee V. Smith. Self-focusing in High-Power Optical Fibres.
(10) Moshe Tur, Eran Herman, Alexander Kozhekin, and Yochay Danziger. Stimulated
Brillouin Scattering in High-Order Mode Fibres Employed in Dispersion Management Modules.
(11) Avner Peleg, Michael Chertkov, and Ildar Gabitov. Inelastic interchannel collisions of
pulses in optical fibres in the presence of third-order dispersion.
173