Section 1100 (Roadworks Overall Requirements)
Section 1100 (Roadworks Overall Requirements)
Page No.
1101 HORIZONTAL ALIGNMENTS, SURFACE LEVELS AND 11-1
SURFACE REGULARITY OF PAVEMENT COURSES
1102 ADVERSE WEATHER WORKING 11-4
1103 USE OF SURFACES BY CONSTRUCTIONAL TRAFFIC 11-5
1104 CARE OF WORKS 11-5
1105 MEASUREMENT AND PAYMENT 11-6
SECTION 1100-ROADWORKS OVERALL REQUIREMENTS
(2) Tolerances
If tolerances given in Table 11.1 for level and straight edge are not in
agreement, in that case the tolerances given for straight edge shall
prevail.
The tolerances for level and surface regularity as given in Table 11.1
shall be applicable only for New construction, Re-construction and
Rehabilitation works. These shall be not applicable in case of
resealing by surface dressing/sand seal/ slurry seal in existing paved
surfaces.
(e) Shoulders
The difference between road level measured at the centre line of the
road and that of the bottom of the side drain measured perpendicular to
the centre line of the road shall not deviate form the specified in the
drawing by ± 25 mm.
Where any tolerances in Sub-clause 1101 (2) are exceed, the Contractor
shall assess the full extent of the area which is out of tolerances and shall
make good the surface of the pavement course, earthworks or formation in
the manner described below.
(a) Earthworks
Where the depth of a side drain is less than that specified, the side
drain shall be excavated to the specified depth and grade. Where the
depth of a side drain is more than the specified depth, the side drain
shall be backfilled with suitable material compacted to a dry density of
at least 95% of MDD (Heavy compaction) up to the specified depth or
the extra excavated depth shall be made good by the same material of
lining of the drain as directed by the Engineer.
(b) Subgrades
Where the levels and or widths are out of tolerances, the full depth of
the layer shall be reworked to the Specification. The area to be treated
shall be as determined by the Engineer necessary for compliance with
the Specification.
Where the results of the construction control tests are less than
specified the full depth of the layer in the area representing the test
shall be reworked to the Specification. However, if needed, more tests
shall be conducted to ascertain the extent of the area required to be
reworked.
For bituminous bases the material of the full depth of the layer shall be
replaced with fresh approved material laid and compacted to
specification. Any area so treated shall be at least 5 m long and the
full width of the paving laid in one operation.
The Contractor shall be deemed to have allowed in his general rates and
prices for the cost of complying with the requirements of Clause 1101.
Not withstanding the provisions of Sub-clauses 1101 (2) and 1101 (3)
measurement and payment for earthworks and pavement works shall be
made on the basis of the net-cross Section ordered by the Engineer or as
shown on the Drawing. No additional payment shall be made for any
variation. If the executed work is within the limit of tolerance, but is less
than the specified on drawing or ordered by the Engineer, the payment shall
be made for actual quantity executed, if the executed work is more, the
payment shall be made for as shown on the drawing or ordered by the
Engineer.
(3) while the air temperature is rising, work may be performed at the
temperatures of;
(4) When the air temperature is falling, works must be stopped as soon as
temperature reaches 6 degree Celsius regardless of wind velocity. It shall
not be resumed until the temperature is definitely rising.
(5) When strong wind is blowing and this is likely to interfere with the proper
execution of the work, no surfacing, especially spraying of binder shall be
done.
(6) Concrete shall not be placed during falling temperatures when the ambient
falls below 7 degree Celsius or during rising temperatures when the ambient
temperature is below 3 degree Celsius. The temperature of the placed
concrete shall not be allowed to fall below 5 degree Celsius until the
concrete has thoroughly hardened. When necessary, concrete ingredients
shall be heated before mixing but cement shall not be heated.
When the ambient air temperature exceeds 40 degree Celsius during the
concreting operation, the Contractor shall take measures to control the
temperature of the ingredients. Such measures shall include spraying the
aggregates stockpile with water to promote cooling down by evaporation
and, where feasible, shading of stockpiles and the area where concreting is
carried out, reducing time between mixing and placing, and restricting
concreting as far as possible to early morning and late evenings. Curing
shall commence after placing of the concrete in order to prevent excessive
loss of moisture.
(2) The wheels and track of plant moving over various pavement
courses shall be kept free of deleterious materials.
The general obligations for “Care of the Works” shall inter-alia include the
following:
(1) Material shall not be spread on a layer that is wet and may damage it
during compaction of subsequent layer or when opened to traffic.
When material is spread out on the road, it shall, be given a good cross-fall
and a light compaction on the surface with a steel-tyre roller, in order to
facilitate run-off during rainy weather.
No measurement and payment shall be made for the works required under this
Clause. All costs in connection with the requirements specified herein shall be
deemed included in the rates and prices of the related items of works in the Bill of
Quantities.