Professional Documents
Culture Documents
Solution:
1) Capacity =?
Capacity = Total time available/Time require to process a batch
As there is only one worker in the whole process therefore total process time will be equal to
sum of all steps time because the only worker will complete each step in required time. So he
will move towards next step after completing previous step. He will process one batch in
1462 minutes which mean 7 Bunks beds in one week.
2. Capacity in beds per week of each step if one worker at each step.
Capacity (C) = Total time available (TTA) / Time require to process a batch (TRB)
Based on the above calculation step 7 naming “Polyurethane” is bottleneck because it has the
lowest capacity which is 24 bunk beds per week.
The overall capacity of the process is same as of the bottleneck which is 24 beds per week
because bottleneck is limiting the whole process to its capacity. Steps before Polyurethane
will process more but only 24 beds process in this step in a week because its overall capacity.
3. Capacity Utilization
1. Cut 58 20 20
×100=34 %
58
2. Plane 58 20 20
×100=34 %
58
3. Router 47 20 20
×100=42.5 %
47
4. Drill 78 20 20
×100=25.6 %
78
5. Sand 79 20 20
×100=25.3 %
79
6. Stain 152 20 20
×100=13.1%
152
7. Polyurethane 23 20 20
× 100=83.33 %
24
8. Kit assembly 60 20 20
×100=33.3 %
60
9. Cleating 160 20 20
×100=12.5 %
160
Table 3. Capacity Utilization
Capacity utilization will be higher at bottleneck because it has the lowest capacity and
demand cannot be exceed the lowest capacity. Demand must be less than or equal to the
bottleneck / overall capacity. Steps have higher capacity will have lower capacity utilization
because capacity of step is the denominator part of equation and nominator is same for each
step. When denominator increase result will decrease which mean it has inverse relation.
4. Capacity of each step if batch size is 8 beds per batch.
Capacity (C) = Total time available (TTA) / Time require to process a batch (TRB)
By increasing batch size from 4 to 8 capacity of step will increase because there is setup time
in process before each step and increasing batch size will not increase setup time and
production will increase. For example setup time for step one is 15 minutes irrespective of
batch size either it processing 4 beds or 8 beds it require 15 minutes. In case of 4 beds per
batch total time require for 8 beds is 165 + 165 = 330 minutes and in case of 8 beds per batch
time require for 8 units is 315 minutes which mean saving 15 minutes and decreasing
denominator which in result increase capacity. In case of step 8 and 9 batch does not impact
result because its setup time is zero.
Hence capacity increased from 24 to 47 beds per week. Now bottlenecks are
two step 3 and 7 both have capacity of 47 beds per week.
6. Throughput Time =?
I
T=
R
68 Bunks beds
Throughput Time= =3.4 weeks
Bunk Beds
20
week
hours
3.4 weeks ×40 =136 hours
week
One bed will take 3.4 weeks or 136 hours to complete the entire process because there are
total 68 bunk beds in the process and the demand of the process is to process only 20 beds per
week. Each bed has to wait for its turn and will process after the processing of all other beds
which are ahead from them. Mean each bed has to wait for other work in process inventory.
a) Throughput time can be reduced by increasing the throughput rate which is 20 beds
per week but the process have the capacity 24 beds per week.
68 beds hours
Throughput time= =2.83 weeks × 40 =113 hours
beds week
24
week
But for this demand must be created which will increase cost.
b) Another way to reduce throughput time is to decrease the work in process inventory.
Work in process inventory can be decrease by:
i. Hiring more workers which will also increase cost.
ii. It can be decrease by changing system from Progressive bundle system
(PBS) to Unit Production system (UPS) and also by changing
management philosophy from high work in process to low work in
process.
c) Throughput time consist of cycle time, inspection time, move time and queue time. So
by decreasing these times will reduce throughput time but this decision will be costly.
For example introducing automatic system for speed up the movement of WIP to
reduce time will cost extra. By reducing inspection time, you have to compromise the
quality of the product.
1st worker will process step 1 and 2 which is Cut and Plane.
2nd worker will process step 3 and 4 which is Router and Drill.
3rd worker will process step 5 and 6 which is sand and Stain.
5th worker will process step 8 and 9 which is Kit assembly and cleating.
Capacity
Note: Figures of require time of individual step is taken from calculation of answer 1 which is
in Table 1. Total Required Time
Maximum demand process can meet is 24 beds per week. Polyurethane is bottleneck and its
capacity is the process capacity. Each two steps sharing one worker except Polyurethane but
still its denominator is high as compare to other while nominator which is minutes per week
is same for each step. In any other options of workers allocation mean that Polyurethane will
share its one worker with other step which make its denominator higher than 405 which will
decrease its capacity therefore this allocation is the one which produce maximum output.
1st worker will process step 1 and 2 which is Cut and Plane.
2nd worker will process step 3, 4, 5 and 6 which is Router, Drill, Sand and Stain
4th worker will process step 8 and 9 which is Kit assembly and cleating.
Capacity
Note: Figures of require time of individual step is taken from calculation of answer 1 which is
in Table 1. Total Required Time
Based on above calculation the best allocation of 4 workers produce maximum 19 beds per
week. Any other combination of 4 worker allocation will produce less beds. For example if
Polyurethane share it one worker with sand and stain the denominator will be 405+121+63 =
589 which is greater than 508, nominator is same of every combination the issue is with
denominator. Another combination of cut, plane, Router and drill share 1 worker the
denominator will be 165+164+202+121 = 653 which also greater than 508. And the last
combination the Polyurethane share its one worker with Kit assembly and cleating the
denominator will be 405+60+160 = 625.
Hence the above combination will produce maximum beds per week.