You are on page 1of 76

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/301975838

A Comparison of Bond Work Indices from Sepor and BICO Mills

Technical Report · May 2016

CITATIONS READS
0 536

4 authors, including:

Corby Anderson
Colorado School of Mines
461 PUBLICATIONS   986 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Recovery of Tin From Iron Ore Tailings View project

Recovery Of Critical Materials From Pyrometalllurgical Wastes View project

All content following this page was uploaded by Corby Anderson on 06 May 2016.

The user has requested enhancement of the downloaded file.


Colorado School of Mines

A Comparison of Bond Work Indices from

Sepor and BICO Mills

MME Senior Design Project Spring 2016

Elliot Britvec, Hanna Steadman, Nathanael Williams

05/02/2016

Submitted to: Dr. Corby Anderson


2

Executive Summary
The crushing and grinding circuit in mining is the most energy intensive process in a
mining project. Improvements in predicting the energy required to crush a given material, and
therefore the cost of comminution, would help to mitigate cost overruns in mining. The Bond
Work Test is an empirical way to predict this energy cost. Sepor has developed a mill that is
supposed to more accurately predict the Bond Work Index of any given material.

The new Sepor mill was tested against an older BICO mill with two reference materials,
one used by Dr. Husni Usman for his thesis and the other one was from JKTech in Australia and
was sent around the world to compare the Bond Work Indices. The Bond Work Test was run in
duplicate on each mill for each material. The Bond Work Indices from Dr. Usman’s material
were calculated to be, 13.39 kWh/mt and 14.87 kWh/mt for the BICO and Sepor mills
respectively. The Bond Work Indices for the Australian material were calculated to be 13.01
kWh/mt and 14.71 kWh/mt for the BICO and Sepor mills respectively.

A student-t test was calculated for each set of tests with a 95% confidence interval. The
data from Dr. Usman’s material suggested that there was no statistical difference between the
two mills, but the data from the Australian material suggested that there was. The data from the
Sepor mill was still lower than the world average, which was 15.39 kWh/mt, but was closer than
the BICO mill.

An economic analysis was conducted and it was found that the calculated Bond Work
Indices resulted in large discrepancies in capital and operating cost. The difference between the
values from the BICO and Sepor mills from the Australian material resulted in a $5.1 million
dollar difference in power operational costs for a year for 80,000 tonnes feed per day.

This underestimation of the BICO mill could have a disastrous effect on predicted costs
in mining projects. While the Sepor mill reported a value that was still lower than the world
average, it more accurately predicted the Bond Work Index than the BICO mill. It is
recommended that a larger test program be conducted in order to refine the averages of the two
machines and increase the certainty that the two machines produce a statistically different result.

______________________ _____________________ ____________________

Elliot Britvec Hanna Steadman Nathanael Williams


3

Table of Contents
Executive Summary ........................................................................................................................ 2
Figures and Tables .......................................................................................................................... 4
1.0 Introduction ............................................................................................................................... 5
2.0 Background ............................................................................................................................... 5
2.1 Bond Work Index .................................................................................................................. 5
2.2 Experimental Material ........................................................................................................... 8
2.3 Equipment ............................................................................................................................. 9
3.0 Scope ....................................................................................................................................... 11
4.0 Experimental Methods ............................................................................................................ 12
5.0 Results and Discussion ........................................................................................................... 15
5.1 Usman Aggregate ................................................................................................................ 15
5.2 Australian Material .............................................................................................................. 18
6.0 Economic Analysis ................................................................................................................. 21
7.0 Conclusion .............................................................................................................................. 26
Appendix A: Ball Charge Analysis............................................................................................... 27
Appendix B: Usman Material Feed Size Analysis ....................................................................... 29
Appendix C: Australian Material Feed Size Analysis .................................................................. 34
Appendix D: Husni Usman Material BICO Mill Tests ................................................................ 40
Appendix E: Husni Usman Material Sepor Mill Tests ................................................................. 43
Appendix F: Husni Usman Material BICO Mill Product Size Analysis ...................................... 46
Appendix G: Husni Usman Material Sepor Mill Product Size Analysis ...................................... 50
Appendix H: Statistical Analysis of Dr. Husni Usman’s Material ............................................... 54
Appendix I: Australian Material BICO Mill Tests ....................................................................... 55
Appendix J: Australian Material Sepor Mill Tests ....................................................................... 58
Appendix K: Australian Material BICO Mill Product Size Analysis ........................................... 61
Appendix L: Australian Material Sepor Mill Product Size Analysis ........................................... 64
Appendix M: Statistical Analysis of Australian Material ............................................................. 67
Appendix N: Economic Analysis.................................................................................................. 68
References ..................................................................................................................................... 74
4

Figures and Tables


Figure 1: A simple grinding circuit containing a ball mill. [1] ....................................................... 6
Figure 2: A graph depicting the top ten energy intensive processes and their energy
saving opportunities within the mining industry. [3] .................................................................... 7
Figure 3: The Jones splitter used to increment the samples of the crushed material. ..................... 9
Figure 4: A Ro-Tap used for size analysis of the feed, crushed and product materials.................. 9
Figure 5: The BICO ball mills used in the experiments. .............................................................. 10
Figure 6: The inside of the BICO ball mill, showing the protrusions that could act as lifters. .... 10
Figure 7: The Sepor ball mill used in the experiments. ................................................................ 11
Figure 8: The smooth inside of the Sepor ball mill. ..................................................................... 11
Figure 9: Annual operating cost summary for Morrison Copper/Gold Project based on processing
30,000 tonnes of feed per day. [13] .............................................................................................. 22
Figure 10: This graph shows a direct comparison between the different materials run on both the
BICO and Sepor mills and the operating costs estimated for a 20 tonnes of feed per day mill. .. 24

Table 1: The size and weight analysis of the BICO ball mill charge. .......................................... 12
Table 2: The size and weight analysis of the SEPOR ball mill charge......................................... 13
Table 3: The results of the feed size analysis for both materials. ................................................. 13
Table 4: The Bond Work Index data for Usman’s material using the BICO mill. ....................... 15
Table 5: The Bond Work Index data for Husni Usman’s material using the Sepor mill. ............. 16
Table 6: Summary of results for t-test assuming unequal variance. ............................................ 16
Table 7: The t-test for the two samples assuming equal variance. ............................................... 17
Table 8: The Bond Work Index data for the Australian material using the BICO mill. ............... 18
Table 9: The Bond Work Index data for the Australian material using the Sepor mill. ............... 19
Table 10: The summary of the results from the t-test of the two samples assuming equal
variance. ........................................................................................................................................ 19
Table 11: The summary of the results from the t-test of the two samples. ................................... 20
Table 12: The variation in a simple payback period in years with over or underestimates of
CAPEX and OPEX models. .......................................................................................................... 21
Table 13: The power operational cost for each of the test runs from the different mills based on
20, 5000, and 80000 tonnes of feed per day. ................................................................................ 23
Table 14: The capital cost estimates of ball mills for various size plant scales using the test
results from the BICO, Sepor and Round Robin. ......................................................................... 25
5

1.0 Introduction
The purpose of this investigation is to compare the BICO ball mill to the Sepor ball mill

in regards to the measurement of Bond Work Indices. Both ball mills serve the purpose of

measuring the energy required to grind a material to a particular size, usually a target of 150

microns, according to the empirical test based on Fred Bond’s Third Theory of Comminution.

Using this test procedure, a previously characterized aggregate material and a reference material

from a global test set were tested using the two ball mills to determine the Bond Work Index of

the materials. The results of these tests were then analyzed using statistical methods to

investigate any differences between the experimental results. These results were also analyzed

using economics to see how the accuracy of the Bond Work Index can affect the capital and

operating costs in a real world setting.

2.0 Background
2.1 Bond Work Index
The Bond Work Index is a measure of how much energy is required to grind a given

material down to a set size. This material property is useful in determining energy costs and

capital requirements for comminution circuits, namely the grinding portions such as the ball mill

featured in the simple flowsheet in Figure 1.


6

Figure 1: A simple grinding circuit containing a ball mill. [1]

According to a survey by EY, “Mining projects are showing an average budget overrun

of a staggering 62%.” [2] One of the main causes of this problem is inadequate planning. The

determination of the Bond Work Index is part of the planning stage and can greatly affect the

projected cost associated with a grinding circuit. As shown in Figure 2, the grinding stage in

mining is one of the most energy intensive and also is an area with the largest energy saving

opportunity. [3] An accurate Bond Work Index is essential for the proper design and estimation

of grinding requirements in comminution circuits.


7

Figure 2: A graph depicting the top ten energy intensive processes and their energy saving opportunities
within the mining industry. [3]

Improvements in the accuracy of the Bond Work Index value allow for more accurate

engineering design criteria for grinding circuits which will lead to reductions in cost overruns in

the construction of such circuits.

The Bond Grindability Test is a procedure that attempts to quantify the amount of energy

required to grind a particular material. Based off of Fred Bond’s Third Theory of Comminution,

the test procedure produces an index, in units of kWh/mt, which describes the amount of energy

required to grind rock from a theoretically infinite size down to 150 microns. [4] Using a smooth

ball mill and a specified ball charge distribution, the test’s empirical procedure attempts to

simulate a full-sized ball mill in a laboratory-scale test.

While the Bond Work Index and procedure have become a world standard for measuring

the energy required to grind material and designing grinding circuits, the test is highly empirical

and can vary significantly as a result. According to one study, the Bond Work Index measured by

three different mills that were side by side varied as low as 4.2% and up to 8.6%.[5] Even

variations within the distribution of the ball charge will result in differences between 2.9% and
8

6.9 %. [5] Even though there are difficulties in reproducing Bond Work Indices and there is

variability in the results, the quantity is one of the better measures of the energy required in a

grinding circuit and persists in engineering design.

The equation used to calculate the Bond Work Index is as follows:

44.5
𝑊𝑖 =
10 10
𝑃10.23 ∗ 𝐺𝑃𝑅 0.82 [( 0.5 ) − ( 0.5 )]
𝑃80 𝐹80

(1)

P1 is the 100% passing size of the product in microns, GPR is the average

grams/revolution of the last three cycles, P80 is the 80% passing size of the product in microns

and F80 is the 80% passing size of the feed material in microns.

2.2 Experimental Material


For this investigation, material from two different sources was used. The first set of

material was an aggregate used in a previous doctoral study by Dr. Husni Usman. During his

thesis, he measured the Bond Work Index of the material using the BICO mill used in this

investigation. Using a similar test procedure, Dr. Usman determined that the Bond Work Index

for the aggregate was 13.03 kWh/mt. [6] His material needed to be pre-crushed to >3.36mm.

In addition to this aggregate, material was secured from JKTech labs as a part of a global

investigation into the reproducibility of Bond Work Indices. This material was sent out to

various labs around the world in order to collect a wide set of data concerning the Bond Work

Index of the material. Upon the writing of this report, the full study had not been completed.

However, the preliminary results from the study were released in order to allow for comparison

with the data collected from this investigation.


9

2.3 Equipment
A roll crusher was used to crush Dr. Usman’s material to >3.36mm. Once the material

was crushed a Jones splitter was used to get representative samples. The Jones splitter was also

used later in the investigation to split the product material; it is shown in Figure 3. A Ro-Tap,

pictured in Figure 4, was used to separate the product material from the material that still needed

to be crushed. The Ro-Tap was also used to characterize the feed material and the product

material.

Figure 3: The Jones splitter used to increment the samples of the crushed material.

Figure 4: A Ro-Tap used for size analysis of the feed, crushed and product materials.
10

The Bond Work Index procedure calls for the use of a 30.5 cm x 30.5 cm smooth ball

mill, such that no part of the mill may act as a lifter, which would increase the energy imparted

on the ore. The BICO machine used in this experiment is shown in Figure 5. As shown in Figure

6, the barrel of the BICO is not particularly smooth and the seam along the back protrudes from

the surface. The Sepor machine used measures 30 cm by 30 cm and is shown in Figure 7. From

Figure 8, the Sepor machine has a much smoother barrel, ensuring that nothing no part of the

barrel acts as a lifter once the machine is closed.

Figure 5: The BICO ball mills used in the experiments.

Figure 6: The inside of the BICO ball mill, showing the protrusions that could act as lifters.
11

Figure 7: The Sepor ball mill used in the experiments.

Figure 8: The smooth inside of the Sepor ball mill.

3.0 Scope
As mentioned previously, the Bond Work Index is currently one of the most used factors

to determine the energy required for an ore to be ground to a set size and this factor is used in

many facets of grinding circuit design. Due to its importance in design, it is equally important

that the tools used to measure the value, the Bond ball mills, should adhere to the original

procedure as much as possible. The Sepor machine claims that it adheres more closely to the
12

ideal Bond procedure through the careful design of its mill and thus produces a more accurate

value for the Bond Work Index. In particular, it is suggested that the Sepor machine produces a

higher, but more accurate Bond Work Index, as it does not have any surfaces that may serve as

lifters. This investigation looks to compare the Bond Work Indices for two sets of material, the

aggregate from Dr. Usman’s thesis and the reference material from JKTech. By comparing the

values produced by the two machines, statistical tests, namely the Student t-test will be used in

order to determine if the indices produced are statistically different. Using the Bond Work

Indices found through these experiments, a capital and operating cost model will be built using

the values from the BICO and Sepor machines in order to highlight the economic implications of

any differences between the measured values.

4.0 Experimental Methods


The same testing methods were used for both materials on both of the mills. The original

Bond Procedure was followed as closely as possible. Unfortunately, the prescribed number of

balls and the total weight of the ball charge were unable to be met simultaneously, given the ball

charge that was provided. Professor Erik Spiller stated that the weight mattered the most in the

test, so the prescribed weight of 20.125 kg was obtained as closely as possible. [7] A size and

weight analysis of the two charges can be found in Tables 1 and 2(See Appendix A).

Table 1: The size and weight analysis of the BICO ball mill charge.

Size (in) Number of Balls Total Mass (kg)


1.45 39 8.794
1.17 64 7.16
1 10 0.668
0.75 68 2.436
0.61 91 1.495
Total Charge Mass (kg) 20.553
13

Table 2: The size and weight analysis of the SEPOR ball mill charge.

Size (in) Number of Balls Total Mass (kg)


1.45 39 8.795
1.17 64 7.162
1 10 0.668
0.75 68 2.434
0.61 91 1.494
Total Charge Mass (kg) 20.552

The material used by Dr. Usman needed to be crushed down to under 3.36 mm (<6 Tyler

Mesh) before the Bond Work Index test could be conducted. This was done by roll crushing in

stages and screening at the end of each stage to eliminate the material that was already under

3.36 mm. Once the material was under the prescribed size, the material was split using a Riffle

Type Jones Splitter. The material was run through several times to make sure that is was all

homogenous for testing. The material was split into 200-500 g increments. The Australian

material was already passing 3.36 mm, and had been pre-split, so this process was unnecessary

for this material.

Both materials’ weights of 700 cc needed to be determined for the test. This was done by

placing the material in a graduated cylinder and packing it down. A size analysis of the feed

material also needed to be run before the Bond Work Index test could be run. The 80% passing

size and the percent of the product in the feed needed to be found. Three size analyses were run

for each material (See Appendix B and C); the results can be seen in Table 3.

Table 3: The results of the feed size analysis for both materials.

Material Percent Product in Feed 80% Passing Size of Feed (µm)


Dr. Usman 12.80 1867
Australia 14.20 2759
14

The material was placed into the ball mill and run, initially, for 100 revolutions. The

material is then removed and placed into a Ro-Tap to separate the product, -100 Mesh, from the

remaining material. The oversized material is weighed and new material is added to match the

initial weight of the sample. This completes one cycle for the test. A spreadsheet of the data

needed for the test was tabulated so that the grams per revolution could be analyzed and the

number of revolutions required for the next cycle could be calculated. The full Bond Work Index

Test can take anywhere from 5-9 cycles. This process was done until closure was achieved.

There were two conditions for closure from the literature. The first was from Prof. Erik

Spiller and stated, “A reversal in the grams of undersize product per revolution; a reversal is a

trend of up/down/up (e.g. 1.89, 1.88, and 1.90) or down/up/down (e.g. 1.75, 1.71, 1.72) in the

last three cycles.” Also, there must be less than a three percent difference between the highest

and lowest values. [8] The condition for closure that we used was from a procedure from Phillips

Enterprises LLC. and stated, “The reversal value should be within 3% of the previous number.”

[9]

Once the test achieved closure a composite of the last three cycles’ products was formed

and weighed out to around 250 g. This was wet screened with 400 mesh then dried. The dried

sample was then Ro-Tapped to form a product size distribution to calculate the 80% passing size

of the product. This number was used in the final Bond Work Index Calculation.
15

5.0 Results and Discussion


5.1 Usman Aggregate
Following the previously described procedure, the Usman aggregate was tested in order

to determine its Bond Work Index using both mills (See Appendix D and E). The P80 of the

product was determined using polynomial plots (See Appendix F and G). The results of each test

can be seen in Tables 4 and 5.

Table 4: The Bond Work Index data for Usman’s material using the BICO mill.

Test P1 Grams/Revolution P80 F80 BWI (kW- BWI (kW-


Number (µm) (µm) (µm) hr/st) hr/mt)
1 149 1.848 118.8 1867 12.40 13.67
2 149 1.912 116.2 1867 11.88 13.10
Average 12.14 13.39
Standard Deviation 0.368 0.403

The values produced by the BICO for the Usman material compare well with the value

Dr. Usman reported in his thesis. The average difference between the measured Bond Work

Index and the Usman value is 0.35 kWh/mt, a difference of 2.7%. Any differences may have

been the result of using a difference charge distribution than the one used by Usman to determine

the Bond Work Index for the aggregate. This suggests relatively good reproducibility for the

testing procedure used in the experiment.

Table 5 below summarizes the test results using the Sepor mill. From the average value

for the Bond Work Index, the Sepor machine produced a value higher than that of the BICO mill

for the same material. The average value for the Sepor machine was 1.48 kWh/mt more, a

difference of 9.9%. As the ball charge was comparable between the BICO and the Sepor

machines and the procedure was the same for both machines, the difference between the two

values would appear to be the result of an inherent difference between the machines.
16

Table 5: The Bond Work Index data for Husni Usman’s material using the Sepor mill.

Test P1 Grams/Revolution P80 F80 BWI (kW- BWI (kW-


Number (µm) (µm) (µm) hr/st) hr/mt)
1 149 1.616 118 1867 13.79 15.20
2 149 1.636 112 1867 13.18 14.53
Average 13.49 14.87
Standard Deviation 0.431 0.474

While there is a difference between the two averages, one must ask if this difference is

statistically significant enough to confirm that the two averages are, in fact, different. In order to

test this, a Student t-test was performed, first assuming equal variances between the machines

and the second assuming unequal variances between the machines. The t-test was performed

using both assumptions concerning the variance of the populations as it was uncertain that the

variance of each of the machines was equal. However, considering the sample variances, it may

be suggested that they are relatively equal and, as a result, the t-test using equal variances may be

the more correct test.

Using the null hypothesis that the difference between the population mean for the BICO

and the population mean for the Sepor was zero, Table 6 was generated to summarize the t-test,

assuming a 95% confidence interval and unequal variances. (See Appendix H)

Table 6: Summary of results for t-test assuming unequal variance.

Calculated t-stat t-Critical P(T<=t) Low Error Bound High Error Bound
-3.347 4.303 0.07884 0.708 2.242

From this t statistic, it is not possible to reject the null hypothesis. As a result, it cannot be

said that the measures of the Bond Work Index are statistically different between the machines.
17

While it is not possible to reject the null hypothesis outright, bounds can be put on the range into

which the difference between the mean lies. Using the above t statistic and equation 2 below

[10], the difference between the means may range from 0.708 and 2.24 kWh/t.

𝑠12 𝑠2 2 𝑠12 𝑠2 2
x̅1 − x̅2 − 𝑡𝛼,𝑣 √ + ≤ 𝜇1 − 𝜇2 ≤ x̅1 − x̅2 + 𝑡𝛼,𝑣 √ +
2 𝑛1 𝑛2 2 𝑛1 𝑛2

(2)

Considering the same null hypothesis as previously described, Table 7 summarizes the t-

test for the Usman data assuming a 95% confidence interval and equal variances.

Table 7: The t-test for the two samples assuming equal variance.

Calculated t-stat t-Critical P(T<=t) Low Error Bound High Error Bound
-3.347 4.303 0.07884 0 3.37

Similarly to the t-test assuming equal variances, the t statistic from this test does not

allow for the rejection of the null hypothesis. However, using equation 3 [10] below, bounds may

be set on the differences between the means. The difference in means may statistically range

from 0 to 3.37 kWh/t.

1 1 1 1
x̅1 − x̅2 − 𝑡𝛼,𝑛+𝑛
𝑠 √
−2 𝑝
+ ≤ 𝜇1 − 𝜇2 ≤ x̅1 − x̅2 + 𝑡𝛼,𝑛 +𝑛 −2𝑠𝑝 √ +
2 1 2 𝑛1 𝑛2 2 1 2 𝑛1 𝑛2

(3)

Statistically, it cannot be said that there is a difference between the two data sets.

However, there is an apparent difference between the Bond Work Indices of these two Bond

mills. Such a difference could have significant effects on any future design based on them. More
18

data points using the two mills should be collected in order to better refine the respective

populations and ensure that the mills are statistically similar.

5.2 Australian Material


Following the procedure described previously, the Australian material was tested to

determine the Bond Work Index using both the BICO and Sepor mills (See Appendix I and J).

The P80 of the product was determined by a polynomial plot (See Appendix K and L). Table 8

below summarizes the test results from the Australian material measured using the BICO mill.

Table 8: The Bond Work Index data for the Australian material using the BICO mill.

Test P1 (µm) Grams/Revolution P80 (µm) F80 (µm)


BWI (kW- BWI (kW-
Number hr/st) hr/mt)
1 149 1.687 109.8 2759 12.01 13.24
2 149 1.778 111.2 2759 11.59 12.77
Average 11.8 13.01
Standard Deviation 0.297 0.332

When compared to the global average value of 15.44 kWh/mt for the Australian material,

the BICO produced a value 2.43 kWh/t less, a difference of 15.7%. This is a substantial

difference between the global averages but still sits just outside of one standard deviation from

the mean. The differences between these measures and the global mean may be due to

differences in laboratory procedure, the ball charges used, and differences between machines

around the globe.

Table 9 below summarizes the test data of the Australian material measured using the

Sepor mill.
19

Table 9: The Bond Work Index data for the Australian material using the Sepor mill.

Test P1 Grams/Revolution P80 F80 BWI (kW- BWI (kW-


Number (µm) (µm) (µm) hr/st) hr/mt)
1 149 1.413 102.6 2759 13.31 14.67
2 149 1.419 104.1 2759 13.38 14.75
Average 13.35 14.71
Standard Deviation 0.0495 0.0566

Comparing the average value of these tests to the global average, the Sepor machine is

much closer. In magnitude, the Sepor measurement is 0.73 kWh/mt less than the average, a

difference of 4.7%. As with the BICO differences between the global average and the Sepor

machine may be due to procedural differences, the ball charge distributions used, and the

machines employed to measure the Bond Work Index.

As with the Usman material, student t-tests were performed on the data in order to assess

the statistical difference between the two data sets. Using the null hypothesis that there is no

difference between the data sets, the t-tests were run assuming the same variance and non-equal

variances. Table 10 below summarizes the t-test assuming equal variances. (See Appendix M).

Table 10: The summary of the results from the t-test of the two samples assuming equal variance.

Calculated t-stat t-Critical P(T<=t) Low Error Bound High Error Bound
-7.298 4.303 0.0183 0.71 2.71

As the t statistic is larger than the critical value for the two-tail t-test, it can be said that the two

populations are statistically different. Based on this result, it can be said that the Sepor machine

produces a value that is higher than and statistically different from the BICO. As all other

variables were controlled as much as possible between tests in the two machines, this may

suggest that such a difference may be attributed to the machine itself. The higher value produced

by the Sepor machine may be the result of a lack of any surface that could act as a lifter. Without
20

any lifters, it would require more energy to grind the material to the same size as a machine that

did experience the advantage of lifters. Using equation 3 previously described, the bounds on the

difference in the means ranges from 0.71 to 2.71 kWh/mt between the machines.

Table 11 below summarizes a t-test assuming that the variances between the two

machines are not equal.

Table 11: The summary of the results from the t-test of the two samples.

Calculated t-stat t-Critical P(T<=t) Low Error Bound High Error Bound
-7.298 12.71 0.0867 0.84 2.58

Based on the assumption of unequal variances, the t statistic produced is not greater than the

critical value. As a result, it is not possible to reject the null hypothesis; it cannot be said that the

two data sets are statistically different. Using equation 2 previously described, bounds on the

difference in the means may be set, ranging from 0.84 to 2.58 kWh/mt.

In summary, this investigation must consider the differences between the machines both

qualitatively and quantitatively. Qualitatively, the Sepor machine attempts to hold to the ideal

Bond mill through its higher quality construction. The completely smooth barrel does not allow

for a lifter to be formed that would otherwise influence the energy required to grind the material.

The BICO machine, on the other hand, has design issues that deviate from the Bond procedure

and may produce a value that is inaccurate as a result. While machines such as the BICO have

been the standard models used in Bond Grindability Tests in the past, the values produced may

have deviated from values found in the field and values suggested by Bond’s Third Theory of

Comminution.

As to the quantitative analysis, the t-test of equal variance will be considered as the

differences between the sample variances were relatively small. Based on these test, the Usman
21

material does not suggest that there is a statistical difference between the two mills. However,

considering the Australian material, there is a statistically significant difference between the two

data sets. From this result, it may be said that the Sepor mill produces a statistically different and

higher value for the Bond Work Index. Such a difference has significant implications concerning

capital and operation cost models for grinding circuits.

6.0 Economic Analysis


Using the Bond Work Index and the calculated energy required to grind the material, an

economic evaluation can be done to determine capital (CAPEX) and operational (OPEX) costs.

Creating accurate CAPEX and OPEX models early in feasibility studies for projects can allow

for more accurate values for net present value, rate of returns and simple paybacks. (See

Appendix N)

Operating costs for concentrating are typically set about 13% too low which can greatly

affect the net present value, rate of returns and simple payback for the project. [11] For example,

a project with correct CAPEX and OPEX estimations, a simple payback period would be about 6

years. If the OPEX estimation for this project was low by 13%, Table 12 shows the payback

period gets pushed back to about 6 years and 10 months. [12]

Table 12: The variation in a simple payback period in years with over or underestimates of CAPEX and
OPEX models.

Simple Variation in CAPEX


Payback
(years) -20% -10% -5% 0% 5% 10% 20%
Variation in OPEX

-20% 3.76 4.36 4.75 5.00 5.25 5.50 6.00


-10% 4.18 4.89 5.16 5.43 5.71 5.98 6.52
-5% 4.55 5.11 5.40 5.68 5.97 6.25 6.82
0% 4.76 5.36 5.66 5.95 6.25 6.55 7.14
5% 5.00 5.63 5.94 6.25 6.57 6.88 7.50
10% 5.27 5.93 6.25 6.58 6.91 7.24 7.90
20% 5.89 6.63 6.99 7.36 7.73 8.10 8.71
22

OPEX models for mining related projects typically include costs from crushing, grinding

and floatation of the material. This is can be broken down into many categories such as, “process

labor”, “maintenance labor”, “process power, propane and fuel”, “supplies (operating and

maintenance)” and “general and administration.” [13] Figure 9 shows about 25% of the operating

costs are the power to run the machinery and of this, grinding is a substantial amount. This is

why there is a large focus on the Bond Work Index and the energy required to grind a specific

material to the required size.

$6,922,054 $3,727,000
$2,288,000 Process Labor
$2,389,000
Maintenance Labor

$12,459,000 Process Power, Propane,


Fuel
$32,524,000
Supplies (Operating and
Maint.)
Tailings

Figure 9: Annual operating cost summary for Morrison Copper/Gold Project based on processing 30,000
tonnes of feed per day. [13]

By using the calculated kWh/t values from the BWI, the cost of energy used per year can

be calculated for each of the tested mills and materials. Table 13 shows the estimated $/year

spent on power for a 20, 5000 and 80000 tonnes feed per day mills.
23

Table 13: The power operational cost for each of the test runs from the different mills based on 20, 5000,
and 80000 tonnes of feed per day.

20 tonnes feed 5000 tonnes 80000 tonnes


per day feed per day feed per day
kWh/mt $/yr $/yr $/yr
BICO Mill
Usman 1 13.67 $8,881 $2,220,350 $35,525,596
Usman 2 13.10 $8,511 $2,127,768 $34,044,280
Aus. 1 13.24 $8,602 $2,150,507 $34,408,112
Aus. 2 12.77 $8,297 $2,074,167 $33,186,676
Sepor Mill
Usman 1 15.20 $9,875 $2,468,860 $39,501,760
Usman 2 14.53 $9,440 $2,360,035 $37,760,564
Aus. 1 14.67 $9,531 $2,382,775 $38,124,396
Aus. 2 14.75 $9,583 $2,395,769 $38,332,300
Round Robin 15.39 $9,999 $2,499,721 $39,995,532

Figure 10 shows the direct comparison between the values of the BWI of the BICO and

the Sepor ball mills on a plant scale of producing 20 tonnes per day. On average, the BICO ball

mill had lower kWh/t values for each of the tests run on both Dr. Usman’s and the Australian

material. This leads to lower overall operating costs for the plant to grind the same material.

When comparing these values to the round robin average of test from around the world, both the

BICO and Sepor mills produced lower kWh/t values and hence, lower estimated operating costs.
24

$10,000
Power Operational Cost ($/year)

$9,500

Husni 1
$9,000
Husni 2
$8,500 Aus. 1
Aus. 2
$8,000

$7,500
BICO SEPOR

Figure 10: This graph shows a direct comparison between the different materials run on both the BICO
and Sepor mills and the operating costs estimated for a 20 tonnes of feed per day mill.

Companies often underestimate the CAPEX to compete for financing which leads to

lower bidding from contractors. [14] This explains the massive amounts of budget overruns at

the end of projects. By correctly estimating the CAPEX early in the feasibility studies, there is

less of a chance for going over budget later in the project.

A useful tool when predicting CAPEX values is the six-tenths rule. Approximate costs

can be obtained if the cost of a similar item of different size or capacity is known. [15] The

approximate cost of the equipment can be multiplied of a ratio of corresponding sizes (cfm, Hp,

ft2, etc.) and raised to the six-tenths. Six-tenths is an average size exponent for many different

process equipment. [16] For ball mills specifically, the exponent is .65 which was used in the

calculations for CAPEX with tons/hr being the corresponding size used in the ratio.

𝑆𝐵 0.6
𝐶𝐵 = 𝐶𝐴 ( )
𝑆𝐴

(4)
25

Where Cb is the approximate cost ($) of equipment having size Sb (cfm, Hp, ft2, etc.), Ca

is the known cost ($) of equipment having corresponding size Sa (same units as Sb) and Sb/Sa is

the ration known as the size factor, dimensionless [15].

The typical size for the Bond Ball Mills is about 0.3 m x 0.3 m. The cost for a BICO ball

mill is about $6900. [17] The Sepor ball mill costs about $9000 but includes an additional

charge, table and electronics. [18] Using the six-tenths rule, it was estimated that the average ball

mill cost for the round robin tests was about $7600.

By knowing the values for Bond Ball Mills, a ball mill for a larger plant scale can be

calculated by again using the six-tenths rule. Table 14 shows the estimated capital costs for a 20,

5000 and 80000 tonnes of feed per day mill with the BICO, Sepor and round robin tests. The

dimensions of the ball mill needed for the capacities were taken from Cost Mine and the costs

were extrapolated. [19] Because there is a dependence of kWh/t when using the six-tenths rule,

the BICO results showed the lowest cost estimate for the ball mills followed by Sepor and then

the round robin. These values differ by about a half million at the largest scale of plant which

would cause either over or under estimates of CAPEX depending on which value was chosen

during the feasibility study.

Table 14: The capital cost estimates of ball mills for various size plant scales using the test results from
the BICO, Sepor and Round Robin.

20 tonnes feed per 5000 tonnes feed per 80000 tonnes feed per
day day day
kWh/mt (diam. X $/ball mill (diam. X $/ball mill (diam. X $/ball mill
length) length) length)
BICO 13.01 0.8x1.4m $249,655 5x9m $3,660,112 7x12m $5,491,460
Sepor 14.71 0.8x1.4m $268,847 5x9m $3,941,485 7x12m $5,913,618
Round 15.39 0.8x1.4m $275,917 5x9m $4,045,138 7x12m $6,069,135
Robin
26

Overall, the results from the BICO ball mill tended to underestimate the values for both

CAPEX and OPEX while the Sepor ball mill and ball mill used during the round robin testing

were similar with overestimating the values. Under or over estimations of these values greatly

affect the overall project budget which is why it is so important to perform very precise

metallurgical tests such as the Bond Work Index.

7.0 Conclusion
The data from Dr. Usman’s material suggests that there is no statistical difference

between the BICO and Sepor mills using a 95% confidence interval, but there is a 10%

difference between the average values from each machine. This 10.0% increase from the BICO

to the Sepor will greatly increase the predicted required energy and, therefore, the cost of the

process.

The data from the Australian material suggests that there is a statistical difference

between the two machines. There is an 11.6% increase in the calculated value from the BICO

mill to the Sepor mill. The underestimation of the BICO mill could cost a mining company up to

$5.1 million in a year in power operational costs, assuming 80,000 tonnes of feed per day.

Many mining projects are having cost overruns and getting an accurate Bond Work Index

will help to mitigate this problem. The Sepor mill reports a higher value, which will help in not

underestimating the cost required for the mining project.


27

Appendix A: Ball Charge Analysis

Nominal Ball Average


Top Size Bottom Size Total
Size Weight Number
Weight
per Ball of Balls
(kg)
in. mm in. mm in. mm (g)
1.45 36.8 1.5 38.1 1.25 31.8 204.8 43 8.806
1.17 29.7 1.25 31.8 1 25.4 107.6 67 7.209
1 25.4 1 25.4 0.88 22.4 67.2 10 0.672
0.75 19.1 0.88 22.4 0.63 16 28.3 71 2.009
0.61 15.5 0.63 16 0.5 12.7 15.2 94 1.429
Total 285 20.125

This is the desired ball charge analysis, while below are the analyses of the ball charges that were used.
28

BICO Ball Charge

Size (in) Number of Balls Total Weight (kg)

1.45 39 8.794
1.17 64 7.16
1 10 0.668
0.75 68 2.436
0.61 91 1.495
Total 272 20.553

Sepor Ball Charge


Size (in) Number of Balls Total Mass (kg)
1.45 39 8.795
1.17 64 7.162
1 10 0.668
0.75 68 2.434
0.61 91 1.494
Total 272 20.552

.
29

Appendix B: Usman Material Feed Size Analysis

0
2 2.2 2.4 2.6 2.8 3 3.2 3.4
-0.1
A: log(% Passing) = 0.7436(ln(size)) - 2.55
R² = 0.9982
-0.2
B: log(% Passing) = 0.7375(ln(size)) - 2.4621
R² = 0.9979
-0.3
C: log( % Passing) = 0.6605(ln(size)) - 2.2729
R² = 0.9982
Log(% Passing)

-0.4
Test A
-0.5
Test B

-0.6 Test C

-0.7

-0.8

-0.9

-1
Log(Size) (µm)

The Gates-Schumman plot used to determine the F80 of Dr. Usman’s material.
30

0.5

0
Ln(-Ln(1-% Passing/100))

5 5.5 6 6.5 7 7.5 8

-0.5
Test A
Test B
-1 Test C
A: ln(-ln(1-% Passing/100)) = 0.9287(ln(size)) - 6.7884
R² = 0.9958
-1.5 B: ln(-ln(1-% Passing/100)) = 0.9841(ln(size)) - 6.9037
R² = 0.9932
C: ln(-ln(1-% Passing/100)) = 0.9268(ln(size)) - 6.594
-2 R² = 0.9873

-2.5
Ln(size) (µm)

The Roslin Rambler plot used in determining the F80 for Dr. Usman’s material
31

Test A
Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
Mesh
(µm) Retained Retained Retained Passing Feed
10 1700 99.2 29.6 29.6 70.4 11.2
16 1000 77.0 23.0 52.6 47.4
28 600 46.3 13.8 66.5 33.5
60 250 52.6 15.7 82.2 17.8
100 149 22.1 6.6 88.8 11.2
Pan 0 37.5 11.2 100.0 0.0
Total 334.7
Initial
336.5
Mass
32

Test B
Mesh Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
(µm) Retained Retained Retained Passing Feed
10 1700 71.9 18.9 18.9 81.1 13.3
16 1000 90.0 23.6 42.5 57.5
28 600 72.5 19 61.5 38.5
60 250 66.2 17.4 78.8 21.2
100 149 30.0 7.9 86.7 13.3
Pan 0 50.7 13.3 100.0 0.0
Total 381.3
Initial 382
Mass
33

Test C
Mesh Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
(µm) Retained Retained Retained Passing Feed
8 2380 55.8 11.2 11.2 88.8 13.9
10 1700 79.6 16.0 27.3 72.7
16 1000 107.4 21.6 48.9 51.1
28 600 67.5 13.6 62.5 37.5
60 250 80.3 16.2 78.7 21.3
100 149 36.5 7.4 86.1 13.9
Pan 0 69.0 13.9 100.0 0.0
Total 496.1
Initial 497.6
Mass
34

Appendix C: Australian Material Feed Size


Analysis

4.5

A: log(% Passing) = 0.5011log(Size) + 0.1619


4.3
R² = 0.9959
B: log(% Passing) = 0.5905log(Size) - 0.4251
4.1 R² = 0.9899
C: log(% Passing) = 0.5832log(Size) - 0.2785
3.9 R² = 0.9947
Log(% Passing)

3.7

3.5 Test B
Test C
3.3
Test A
3.1

2.9

2.7

2.5
5 5.5 6 6.5 7 7.5 8
Log(Size) (µm)

The Gates-Schumman plot used to determine the F80 of the Australian material.
35

0.5

0
5 5.5 6 6.5 7 7.5 8

A: ln(-ln(1-% Passing/100)) = 0.5993ln(Size) - 4.8785


Ln(-Ln(1-% Passing/100))

-0.5 R² = 0.9891

Test A
-1
Test B
Test C

-1.5 B: ln(-ln(1-% Passing/100)) = 0.7433ln(Size) - 5.7867


R² = 0.9719
C: ln(-ln(1-% Passing/100)) = 0.7568ln(Size) - 5.7436
R² = 0.9779
-2

-2.5
Ln(Size) (µm)

A Roslin Rambler plot used to determine the F80 of the Australian material.
36

80.0
A: % Passing = 0.023(Size) + 12.79
70.0 R² = 0.9932

B: % Passing = 0.0248(Size) + 10.58


60.0 R² = 0.9987
Cumulative Percent Passing

50.0 C: % Passing = 0.0264(Size) + 12.52


R² = 0.9977
Test A
40.0 Test B
Test C
30.0

20.0

10.0

0.0
0 500 1000 1500 2000 2500
Size (µm)

The linear plot used to determine the F80 of the Australian material.
37

Test A
Mesh Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
(µm) Retained Retained Retained Passing Feed
10 1680 156 49.3 49.3 50.7 14.7
16 1000 45.7 14.4 63.7 36.3
28 595 25.9 8.2 71.9 28.1
60 250 29.5 9.3 81.3 18.7
100 149 12.8 4.0 85.3 14.7
Pan 0 46.5 14.7 100.0 0.0
Total 316.4
Initial 316.9
Mass
38

Test B
Mesh Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
(µm) Retained Retained Retained Passing Feed
8 2380 84.2 29.8 29.8 70.2 13.4
9 2000 28.6 10.1 40.0 60.0
10 1680 24.7 8.8 48.7 51.3
16 1000 44.6 15.8 64.6 35.4
28 595 25.0 8.9 73.4 26.6
60 250 27.0 9.6 83.0 17.0
100 149 10.3 3.7 86.6 13.4
Pan 0 37.7 13.4 100.0 0.0
Total 282.1
Initial 284.3
Mass
39

Test C
Mesh Size Weight Percent Cumulative Percent Cumulative Percent Percent Product in
(µm) Retained Retained Retained Passing Feed
8 2380 106.7 25.5 25.5 74.5 14.7
9 2000 38.9 9.3 34.7 65.3
10 1680 35.3 8.4 43.2 56.8
16 1000 70.3 16.8 59.9 40.1
28 595 43.2 10.3 70.2 29.8
60 250 45.4 10.8 81.1 18.9
100 149 17.8 4.2 85.3 14.7
Pan 0 61.5 14.7 100.0 0.0
Total 419.1
Initial 421.1
Mass
40

Appendix D: Husni Usman Material BICO Mill


Tests
2.1

2.05

1.95
Grams/Revolution

1.9

1.85
Usman 1.1
1.8 Usman 1.2

1.75

1.7

1.65

1.6
2 3 4 5 6 7 8 9
Cycle Number

As the test reaches closure, the grams/revolution, when compared to the previous cycle, are close
to each other.
41

Usman 1.1
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1166.8 149.35 N/A N/A 149.4 N/A 333.4
1 270.7 34.65 100 896.1 257.1 2.225 333.4
2 276.7 35.42 134 890.1 264.4 1.705 333.4
3 361.5 46.27 175 805.3 340.3 1.682 333.4
4 377.4 48.31 171 789.4 352.8 1.784 333.4
5 397.5 50.88 160 769.3 379.2 2.055 333.4
6 321.3 41.13 138 845.5 306.9 1.933 333.4
7 337.7 43.23 151 829.1 320.3 1.832 333.4
8 351.5 44.99 158 815.3 337.7 1.848 333.4
42

Usman 1.2
Cycle Number New Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Feed (g) Feed (g) /Cycle (g) (g) Load (g)
0 1167 149.38 N/A N/A 149.4 N/A 333.4
1 209.8 26.85 100 957.2 194.8 1.679 333.4
2 360.9 46.2 183 806.1 349.9 1.664 333.4
3 380.5 48.7 173 786.5 353.9 1.768 333.4
4 378.4 48.44 161 788.6 362.7 1.952 333.4
5 341.2 43.67 146 825.8 331 1.968 333.4
6 341.8 43.75 147 825.2 325.3 1.912 333.4
43

Appendix E: Husni Usman Material Sepor Mill


Tests
1.7

1.65

1.6
Grams/Revolution

1.55
Usman 2.1
Usman 2.2
1.5

1.45

1.4
2 3 4 5 6 7
Cycle Number

Grams/revolution for each cycle, as the test closes the change in grams/revolution is minimal.
44

Usman 2.1
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1166.8 149.35 N/A N/A 149.4 N/A 333.4
1 228.5 29.25 100 938.3 197 1.678 333.4
2 322.8 41.32 181 844 300.2 1.428 333.4
3 396.3 50.73 205 770.5 365.1 1.537 333.4
4 380.1 48.65 184 786.7 346.9 1.622 333.4
5 363.4 46.52 176 803.4 337.8 1.659 333.4
6 350.5 44.86 173 816.3 324.3 1.616 333.4
45

Usman 2.2
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1167.1 149.39 N/A N/A 149.4 N/A 333.4
1 197.8 25.32 100 969.3 180.6 1.553 333.4
2 325.6 41.68 198 841.5 311.1 1.358 333.4
3 382.1 48.91 215 785 362.9 1.462 333.4
4 356.1 45.58 195 811 335.5 1.490 333.4
5 373.5 47.81 193 793.6 350.7 1.568 333.4
6 358.6 45.9 182 808.5 342.8 1.630 333.4
7 348.5 44.61 176 818.6 333.3 1.636 333.4
46

Appendix F: Husni Usman Material BICO Mill


Product Size Analysis
0.8
1.1: ln(-ln(1-% Passing/100)) = 1.281ln(size) - 5.666
0.6 R² = 0.9644

0.4 1.2: ln(-ln(% Passing/100)) = 1.317ln(size) - 5.891


R² = 0.9636
0.2
ln(-ln(1-% Passing/100))

0
3.5 3.7 3.9 4.1 4.3 4.5 4.7 4.9
-0.2
Usman 1.1
-0.4 Usman 1.2

-0.6

-0.8

-1

-1.2

-1.4
ln(size) (µm)

The Roslin Rambler plot used to determine the P80 of Dr. Usman’s material used in the BICO
mill.
47

90.0

1.1: % Passing = 0.6169(Size) + 6.007


80.0 R² = 0.9955

1.2: % Passing = 0.6047(Size) + 9.110


R² = 0.9974
70.0
% Passing

60.0
Usman 1.1
Usman 1.2
50.0

40.0

30.0
30 50 70 90 110 130
Size (µm)

The linear plot used to determine the P80 of Dr. Usman’s material from the BICO mill.
48

Usman 1.1
Mesh Size (µm) Weight Retained (g) % Retained Cumulative % Retained Cumulative % Passing
115 125 32.8 14.8 14.8 85.2
150 105 27.3 12.4 27.2 72.8
200 74 44.2 20.0 47.2 52.8
270 53 28.3 12.8 60.0 40.0
400 37 15.4 7.0 67.0 33.0
Pan 0 73.0 33.0 100.0 0.0
Total 221.0
49

Usman 1.2
Mesh Size (µm) Weight Retained (g) % Retained Cumulative % Retained Cumulative % Passing
115 125 41.2 16.4 16.4 83.6
150 105 31.3 12.4 28.8 71.2
200 74 52.0 20.7 49.5 50.5
270 53 34.1 13.6 63.1 36.9
400 37 15.3 6.1 69.1 30.9
Pan 0 77.6 30.9 100.0 0.0
Total 251.5
50

Appendix G: Husni Usman Material Sepor Mill


Product Size Analysis
1
2.1: ln(-ln(1-% Passing/100)) = 1.1352ln(size) - 4.9971
R² = 0.9581
2.2: ln(-ln(1-% Passing/100)) = 1.478ln(size) - 6.4912
0.5 R² = 0.9571
ln(-ln(1-% Passing/100))

0
3.5 3.7 3.9 4.1 4.3 4.5 4.7 4.9
Usman 2.1
Usman 2.2
-0.5

-1

-1.5
ln(size) (µm)

A Roslin Rambler plot used to determine the P80 of Dr. Usman’s material used in the Sepor mill.
51

100.0

90.0
2.1: % Passing = 0.5468(Size) + 15.09
R² = 0.9967
80.0 2.2: % Passing = 0.683(Size) + 3.468
R² = 0.9957

70.0
% Passing

Usman 2.1
60.0
Usman 2.2

50.0

40.0

30.0
30 50 70 90 110 130
Size (µm)

A linear plot used to determine the P80 of Dr. Usman’s material used in the Sepor mill.
52

Usman 2.1
Mesh Size (µm) Weight Retained (g) % Retained Cumulative % Retained Cumulative % Passing
115 125 38.7 15.9 15.9 84.1
150 105 27.8 11.4 27.4 72.6
200 74 44.6 18.4 45.8 54.2
270 53 26.8 11.0 56.8 43.2
400 37 15.5 6.4 63.2 36.8
Pan 0 89.4 36.8 100.0 0.0
Total 242.8
53

Usman 2.2
Mesh Size (µm) Weight Retained (g) % Retained Cumulative % Retained Cumulative % Passing
115 125 28.0 10.5 10.5 89.5
150 105 37.0 13.9 24.4 75.6
200 74 61.2 23.0 47.4 52.6
270 53 39.0 14.7 62.1 37.9
400 37 18.5 7.0 69.1 30.9
Pan 0 82.3 30.9 100.0 0.0
Total 266.0
54

Appendix H: Statistical Analysis of Dr. Husni


Usman’s Material
t-Test: Two-Sample Assuming Unequal
Variances

Variable Variable Error Bounds on Difference


1 2 in Means
Mean 12.14 13.48 Low High
Variance 0.134 0.185 0.642 2.03
Observations 2 2
Hypothesized Mean Difference 0
df 2
t Stat -3.347
P(T<=t) one-tail 0.0394
t Critical one-tail 2.920
P(T<=t) two-tail 0.0788
t Critical two-tail 4.303

t-Test: Two-Sample Assuming Equal


Variances

Variable Variable Error Bounds on Difference


1 2 in Means
Mean 12.14 13.48 Low High
Variance 0.134 0.185 -0.382 3.06
Observations 2 2
Pooled Variance 0.160
Hypothesized Mean Difference 0
df 2
t Stat -3.347
P(T<=t) one-tail 0.0394
t Critical one-tail 2.920
P(T<=t) two-tail 0.0788
t Critical two-tail 4.303
55

Appendix I: Australian Material BICO Mill Tests

1.750

1.650
Grams/Revolution

1.550
AUS 1.1
AUS 1.2
1.450

1.350

1.250
2 3 4 5 6 7 8 9
Cycle Number

A plot of the grams/revolution for each cycle, as the test nears the end the grams/revolution
stabilizes.
56

AUS 1.1
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1331.1 189.02 N/A N/A 189 N/A 380.3
1 302.4 42.94 100 1028.7 289.6 2.467 380.3
2 241.3 34.26 137 1089.8 222.7 1.378 380.3
3 410.2 58.25 251 920.9 399.1 1.357 380.3
4 424.1 60.22 237 907 417.6 1.506 380.3
5 405.1 57.52 213 926 396.2 1.594 380.3
6 405.3 57.55 203 925.8 393.7 1.660 380.3
7 396.9 56.36 194 934.2 384.4 1.687 380.3
8 375.8 53.36 192 955.3 361.8 1.606 380.3
57

AUS 1.2
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1331.3 189.04 N/A N/A 189 N/A 380.4
1 262 37.2 100 1069.3 247.1 2.099 380.4
2 253.7 36.03 164 1077.6 242.5 1.263 380.4
3 435.2 61.8 273 896.1 418.2 1.307 380.4
4 465.4 66.09 242 865.9 455.8 1.610 380.4
5 392.9 55.79 195 938.4 380.8 1.665 380.4
6 412 58.5 195 919.3 398.3 1.743 380.4
7 392.2 55.69 185 939.1 384 1.778 380.4
58

Appendix J: Australian Material Sepor Mill


Tests
1.500

1.450

1.400

1.350
Grams/Revolution

1.300

1.250
AUS 2.1
1.200 AUS 2.2

1.150

1.100

1.050

1.000
2 3 4 5 6 7 8
Cycle Number

A plot of the grams/revolution of each cycle, as the test nears its end the change in
grams/revolution is minimal.
59

AUS 2.1
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1329.3 188.76 N/A N/A 188.8 N/A 379.8
1 318.3 45.2 100 1011.0 304.5 2.593 379.8
2 217.9 30.94 129 1111.4 204.5 1.345 379.8
3 354.3 50.31 259 975.0 341.1 1.121 379.8
4 459.1 65.19 294 870.2 444.5 1.291 379.8
5 406.2 57.68 244 923.1 391.1 1.368 379.8
6 406.6 57.74 236 922.7 393.1 1.424 379.8
7 330.2 46.89 192 999.1 318.1 1.413 379.8
60

AUS 2.2
Cycle New Feed Product in Revolutions Oversize Product Grams/Revolution 250% Circulating
Number (g) Feed (g) /Cycle (g) (g) Load (g)
0 1331.6 189.09 N/A N/A 189.1 N/A 380.5
1 277.1 39.35 100 1054.5 264.3 2.250 380.5
2 232.2 32.97 152 1099.4 216.4 1.210 380.5
3 381 54.1 287 950.6 360.1 1.065 380.5
4 461.5 65.53 306 870.1 461.5 1.294 380.5
5 416.4 59.13 243 915.2 403.9 1.419 380.5
6 489.1 69.45 286 842.5 475.3 1.419 380.5
61

Appendix K: Australian Material BICO Mill


Product Size Analysis
95

AUS 1.1: y = 0.0002x2 + 0.5459x + 17.623


85 R² = 0.9986
Cummulative Passing (%)

75

65 AUS 1.1
AUS 1.2

55 AUS 1.2: y = 0.0003x2 + 0.5181x + 18.68


R² = 0.9993

45

35
30 50 70 90 110 130
Size (µm)

Linear plot used to determine the P80 of the Australian material from the BICO mill.
62

AUS1.1
Mesh Size (µm) Weight Retained % Retained Cumulative % Cumulative %
Retained Passing
115 125 31 11.1 11.1 88.9
150 105 29.7 10.7 21.8 78.2
200 74 52.8 18.9 40.7 59.3
270 53 36.7 13.2 53.9 46.1
400 37 20.5 7.4 61.2 38.8
Pan 0 108.1 38.8 100.0 0.0
Total 278.8
63

AUS 1.2
Mesh Size (µm) Weight Retained % Retained Cumulative % Cumulative %
Retained Passing
115 125 34.5 12.4 12.4 87.6
150 105 29.5 10.6 23.1 76.9
200 74 51.1 18.4 41.5 58.5
270 53 33.9 12.2 53.7 46.3
400 37 21.1 7.6 61.3 38.7
Pan 0 107.3 38.7 100.0 0.0
Total 277.4
64

Appendix L: Australian Material Sepor Mill


Product Size Analysis
95
AUS 2.1: y = -3E-05x2 + 0.6266x + 16.012
R² = 0.9995

85 AUS 2.2: y = 0.0003x2 + 0.5372x + 20.832


R² = 0.9986
Cummulative Passing (%)

75

65 AUS 2.1
AUS 2.2

55

45

35
30 50 70 90 110 130
Size (µm)

Linear plot used to determine the P80 of the Australian material from the Sepor mill.
65

AUS 2.1
Mesh Size (µm) Weight Retained % Retained Cumulative % Cumulative %
Retained Passing
115 125 17.6 6.6 6.6 93.4
150 105 30.4 11.3 17.9 82.1
200 74 54.1 20.2 38.1 61.9
270 53 35.5 13.2 51.3 48.7
400 37 24.8 9.2 60.5 39.5
Pan 0 105.9 39.5 100.0 0.0
Total 268.3
66

AUS 2.2
Mesh Size (µm) Weight Retained % Retained Cumulative % Cumulative %
Retained Passing
115 125 20.5 7.8 7.8 92.2
150 105 28.2 10.7 18.5 81.5
200 74 50.9 19.3 37.8 62.2
270 53 34.3 13.0 50.8 49.2
400 37 19.5 7.4 58.2 41.8
Pan 0 110 41.8 100.0 0.0
Total 263.4
Appendix M: Statistical Analysis of Australian
Material
t-Test: Two-Sample Assuming Unequal
Variances

Variable Variable Error Bounds on Difference


1 2 in Means
Mean 11.80 13.34 Low High
Variance 0.0877 0.00226 0.760 2.34
Observations 2 2
Hypothesized Mean Difference 0
df 1
t Stat -7.298
P(T<=t) one-tail 0.0433
t Critical one-tail 6.314
P(T<=t) two-tail 0.0867
t Critical two-tail 12.706

t-Test: Two-Sample Assuming Equal


Variances AUS

Variable Variable Error Bounds on Difference


1 2 in Means
Mean 11.80 13.34 Low High
Variance 0.0877 0.00226 0.635 2.46
Observations 2 2
Pooled Variance 0.0450
Hypothesized Mean Difference 0
df 2
t Stat -7.298
P(T<=t) one-tail 0.00913
t Critical one-tail 2.920
P(T<=t) two-tail 0.0183
t Critical two-tail 4.303
68

Appendix N: Economic Analysis


POWER
CONSUMPTION
Equipment Energy Consumption Cost Percentage
mWh/yr kWh/mt US$/yr
Primary Crushing 3,358 0.23 $402,960 1%
Conveying 6,132 0.42 $735,840 1%
Secondary Crushing 0 0.00 $0 0%
Tertiary Crushing 0 0.00 $0 0%
SAG Milling 89,644 6.14 $10,757,280 20%
Grinding 159,286 10.91 $19,114,320 35%
Collective Floatation 20,878 1.43 $2,505,360 5%
Regrinding 5,694 0.39 $683,280 1%
Selective Floatation 2,628 0.18 $315,360 1%
Tailings and Transport 26,426 1.81 $3,171,120 6%
Conc. Thickening 3,796 0.26 $455,520 1%
Filters Plant 2,336 0.16 $280,320 1%
Desalination Plant 28,470 1.95 $3,416,400 6%
Water Pumping System 102,054 6.99 $12,246,480 23%
30.87 $54,084,240 100%
450,702
*Based on 40,000
tons/day
69

COST SUMMARY
Operating Costs Cost Percentage
Supplies and Materials $ 6.88 81%
Labor $ 0.63 7%
Administration $ 0.22 3%
Sundry Items $ 0.77 9%
Total $ 8.50
Capital Costs Cost Percentage
Equipment $ 100,729,500.00 29%
Installation Labor $ 63,013,100.00 18%
Concrete $ 8,282,800.00 2%
Piping $ 25,031,700.00 7%
Structural Steel $ 9,009,600.00 3%
Instrumentation $ 6,189,400.00 2%
Insulation $ 3,215,700.00 1%
Electrical $ 12,882,900.00 4%
Coatings and Sealants $ 1,063,000.00 0%
Mill Building $ 7,040,300.00 2%
Tailings Embankment $ 61,399,100.00 18%
Engineering/Management $ 27,078,600.00 8%
Working Capital $ 19,736,900.00 6%
Total $ 344,672,600.00
Total $ 344,672,608.50
*Based on 40,000 tons/day

Example pulled from Cost Mine for a mill that has 40,000 tonnes of feed per day. [19]
Power Operational Costs
20 tonnes feed per 5000 tonnes feed per 40000 tonnes feed per day 80000 tonnes feed per day
day day
kWh/mt $/d $/yr $/d $/yr $/d $/yr $/d $/yr
BICO Mill
Usman 1 13.67 $ 24.33 $ 8,881 $ 6,083 $ 2,220,350 $ 48,665 $ 17,762,798 $ 97,330 $ 35,525,596
Usman 2 13.10 $ 23.32 $ 8,511 $ 5,830 $ 2,127,768 $ 46,636 $ 17,022,140 $ 93,272 $ 34,044,280
Aus. 1 13.24 $ 23.57 $ 8,602 $ 5,892 $ 2,150,507 $ 47,134 $ 17,204,056 $ 94,269 $ 34,408,112
Aus. 2 12.77 $ 22.73 $ 8,297 $ 5,683 $ 2,074,167 $ 45,461 $ 16,593,338 $ 90,922 $ 33,186,676

Sepor Mill
Usman 1 15.20 $ 27.06 $ 9,875 $ 6,764 $ 2,468,860 $ 54,112 $ 19,750,880 $ 108,224 $ 39,501,760
Usman 2 14.53 $ 25.86 $ 9,440 $ 6,466 $ 2,360,035 $ 51,727 $ 18,880,282 $ 103,454 $ 37,760,564
Aus. 1 14.67 $ 26.11 $ 9,531 $ 6,528 $ 2,382,775 $ 52,225 $ 19,062,198 $ 104,450 $ 38,124,396
Aus. 2 14.75 $ 26.26 $ 9,583 $ 6,564 $ 2,395,769 $ 52,510 $ 19,166,150 $ 105,020 $ 38,332,300

ROUND ROBIN
Average 15.39 $ 27.39 $ 9,999 $ 6,849 $ 2,499,721 $ 54,788 $ 19,997,766 $ 109,577 $ 39,995,532
71

CAPITAL COST OF BWI BALL MILLS


Model Average kWh/mt (diam. x length) Capital Cost Cost Relative to BICO

BICO 13.20 .3 x .3 m $6,902 100%


Sepor 14.79 .3 x .3 m $9,000 108%
Average 15.39 .3 x .3 m $7,628 111%
72

CAPITAL COST OF BALL MILLS

Plant Scale 20 tonnes feed per day 5,000 tonnes feed per day 40,000 tonnes feed per day 80,000 tonnes feed per
day
kWh/mt (diam. x $/ball (diam. x $/ball mill (diam. x $/ball mill (diam. x $/ball mill
length) mill length) length) length)
BICO
Usman 1 13.67 0.8 x 1.4 m $249,655 5x9m $3,660,112 6 x 10 m $4,412,702 7 x 12 m $5,491,460
Usman 2 13.10 0.8 x 1.4 m $249,655 5x9m $3,660,112 6 x 10 m $4,412,702 7 x 12 m $5,491,460
Aus. 1 13.24 0.8 x 1.4 m $249,655 5x9m $3,660,112 6 x 10 m $4,412,702 7 x 12 m $5,491,460
Aus. 2 12.77 0.8 x 1.4 m $249,655 5x9m $3,660,112 6 x 10 m $4,412,702 7 x 12 m $5,491,460

SEPOR
Usman 1 15.20 0.8 x 1.4 m $267,478 5x9m $3,921,418 6 x 10 m $4,727,738 7 x 12 m $5,883,511
Usman 2 14.53 0.8 x 1.4 m $267,478 5x9m $3,921,418 6 x 10 m $4,727,738 7 x 12 m $5,883,511
Aus. 1 14.67 0.8 x 1.4 m $267,478 5x9m $3,921,418 6 x 10 m $4,727,738 7 x 12 m $5,883,511
Aus. 2 14.75 0.8 x 1.4 m $267,478 5x9m $3,921,418 6 x 10 m $4,727,738 7 x 12 m $5,883,511

ROUND
ROBIN
Average 15.39 0.8 x 1.4 m $269,647 5x9m $3,953,211 6 x 10 m $4,766,067 7 x 12 m $5,931,211
SPECIFICATIONS Capital
Air Swept Ball Diam. x length HP Cost
Mills
air swept ball 1.8 x 2.3 m 150 $583,980
air swept ball 2.4 x 2.9 m 300 $874,800
air swept ball 2.7 x 3.0 m 400 $970,880

air swept ball 3.0 x 4.0 m 750 $1,166,600


air swept ball 3.5 x 4.4 m 950 $1,556,300
air swept ball 4.0 x 5.6 m 1450 $2,137,700
air swept ball 4.7 x 6.4 m 2500 $2,817,000

Cost Mine estimates for different dimension ball mills. [19]


74

References
[1] F.P. Van Der Meer and W. Maphosa, “High pressure grinding moving ahead in copper, iron,

and gold processing,” in Journal of the South African Institute of Mining and Metallurgy. Vol.

112 n. 7 Jul. 2012

http://www.scielo.org.za/scielo.php?script=sci_arttext&pid=S0038-223X2012000700008

[2] “Opportunities to Enhance Capital Productivity,” Ernest & Young, London, UK, 2015.

http://www.ey.com/Publication/vwLUAssets/EY-opportunities-to-enhance-capital-

productivity/$FILE/EY-opportunities-to-enhance-capital-productivity.pdf

[3] “Mining Industry Energy Bandwidth Study,” BCS, Incorporated, Laurel, MD, 2007.

http://energy.gov/sites/prod/files/2013/11/f4/mining_bandwidth.pdf

[4] “Crushing and Grinding Theory A New Industrial Frontier,” Allis-Chalmer, Milwaukee, WI,

1953.

[5] E. Kaya, P. C. Fletcher and P. Thompson, “Reproducibility of Bond Work Index with

Different Standard Ball Mills,” Phelps Dodge, Safford, AZ and Dawson Metallurgical Lab, Inc.

Salt Lake City, UT., 2002.

[6] H. Usman, “Measuring the Efficiency of the Tumbling Mill as a Function of Lifter

Configurations and Operating Parameters,” Ph.D. dissertation, Dept. Mining Eng., Colorado

School of Mines, Golden, CO.

[7] E. Spiller, private communication, Mar, 2016.

[8] “Standard Bond Ball Mill Grindability Test,” Colorado School of Mines, Golden, CO, May,

1999.

[9] “Bond Ball Mill Grindability Test Procedure,” Phillips Enterprises LLC., Golden, CO, 2016.
75

[10] D.C. Montgomery, “Inferences about Process Quality,” in Introduction to Statistical Quality

Control,” 7th ed. Hoboken, NJ: Wiley, 2013, ch. 4, sec. 4.2, pp. 139-141.

[11] R.L. Bullook, “Accuracy of feasibility study evaluations would improve accountability,”

Jackling Lecture in Mining Engineering, April 2011, Vol. 63, No. 4, SME, pp. 78-85.

[12] “Sensitivity Analysis for Mineral Processing Projects”, PEC Consulting, Saint Louis, MO,

2015.

[13] R. Anguelov, “Operating Cost Estimate (OPEX),” Project Feasibility Study, February 2009,

Vol. 4, pp. 2-34.

[14] R. L. Bullock, “Mine Feasibility Studies Need Improving!” Missouri University of Science

and Technology, MO, 2013.

[15] R. W. Whitesides, “Process Equipment Cost Estimating by Ratio and Proportion”, PDH

Course G127, [Online]. Available: www.PDHonline.org.

[16] C.G. Anderson, “Engineering Design and Cost Analysis”, Colorado School of Mines,

Golden, CO, 2016.

[17] “Ball Mill”, BICO Braun International, [Online]. Available:

http://www.bicoinc.com/ballMill.html.

[18] D. Willis, private communication, Apr. 2016.

[19] J. B. Leinart, “Mining Cost Service”, Cost Mine, Spokane Valley, WA, 2015.

View publication stats

You might also like