You are on page 1of 22

This document has been approved for use by agen-

cies of the Department of Defense and for listing in


the DoD Index of Specifications and Standards.

Standard Specification for


Cast-in-Place Nonreinforced
Concrete Pipe (ACI 346-90) (Reapproved 1997)
Reported by ACI Committee 346
Committee voting on proposed revisions to ACI 346/346R-81:

Gilbert G. Lynch, Chairman Curtiss W. Gilley, Secretary


Ernest R. Comstock Robert D. Gofonia
Leonard J. Erie, II Robert E. Leake, Jr.
Morgan Johnson William G. Reynolds

These specifications cover construction of cast-in-place nonreinforced 4.4-Admixtures


concrete pipe used for the conveyance of liquids such as irrigation water, 4.5-Bonding mortar
storm water, sewage, and industrial wastes. 4.6-Storage of materials
These specifications are a reference standard which the engineer or
architect may make applicable to any cast-in-place pipe project by citing Chapter 5-Pipe dimensions and tolerances,
them in the project specifications. Individual chapters or sections should p. 346-4
not be copied into project specifications since their meanings could be 5.l-Wall thickness
changed by taking them out of context. 5.2-Pipe diameter tolerances
The specifications need to be supplemented by designating or specifying 5.3-Offsets
individual project requirements. A list is provided indicating places in 5.4-Bearing plates
these specifications and items that may require specific treatment by the
specification writer.
Chapter 6-Concrete properties, p. 346-4
6.l-Strength
Keywords: admixtures: aggregates; air entrainment; cast-in-place pipes; compressive
6.2-Cement and water content
strength; concrete construction; concrete pipes; curing; finishing; formwork (con-
6.3-Air content
struction); joints (junctions); mixing; mix proportioning; patching; placing; repairs;
slump tests; specifications; temperature; tests; tolerances; vibration; water-cement
6.4-Slump
ratio. 6.5-Proportioning and mixing

CONTENTS Chapter 7-Concrete placement, p. 346-5


7.1-Method of placement
7.2-Construction joints
Instructions to the Specifier 7.3-Temperature
7.4-Finish
Chapter 1-General, p. 346-2
1.1-Scope Chapter 8-Curing, backfilling, and clean-up,
1.2- Reference specifications and testing methods p. 346-5
1.3-Conflicts 8.1-Curing and backfilling
1.4-Definitions 8.2-Clean-up

Chapter 2-Basis of acceptance, p. 346-3 Chapter 9-Testing, p. 346-6


2.1-General 9.1-Testing of materials
9.2-Testing services
Chapter 3-Trench, p. 346-3 9.3-Core tests
3.1-Excavation 9.4-Load test
3.2-Rock 9.5-Thickness tests
3.3-Unstable soils 9.6-Hydrostatic test
3.4-Precast pipe
3.5-Fill material
3.6-Wetting Adopted as a standard of the American Concrete Institute in May 1981 to supersede
3.7-Grade and alignment tolerance ACI 346-70, in accordance with the Institute’s standardization procedure. Revised by
expedited standardization procedure, effective May 1, 1990.

Copyright © 1990 American Concrete Institute. All rights reserved including rights
Chapter 4-Materials, p. 346-3 of reproduction and use in any form or by any means, including the making of copies
4.1-Cements by any photo process or by any electronic or mechanical device, printed or written or
oral, or recording for sound or visual reproduction or for use in any knowledge or
4.2-Aggregates retrieval system or device, unless permission in writing is obtained from the copyright
4.3-Water proprietors.

346-1
346-2 MANUAL OF CONCRETE PRACTICE

Instructions to the Specifier C 76-88 Specification for Reinforced Concrete Cul-


These general specifications are intended for use as a vert, Storm Drain, and Sewer Pipe
reference standard which may be made applicable to any C 94-89b Specification for Ready-Mixed Concrete
cast-in-place concrete pipe project by being cited in its C 109-87 Test for Compressive Strength of Hydraulic
project specifications. They are not ‘‘guide’’ specifications. Cement Mortars (Using 2 in. or 50 mm Cube
Individual chapters or sections should not be copied into Specimens)
project specifications since there is danger that taking them C 138-77 Test for Unit Weight, Yield, and Air Content
out of context may change their meanings. (Gravimetric) of Concrete
These specifications should be supplemented by desig- C 143-89a Test Method for Slump of Portland Cement
nating or specifying individual project requirements as fol- Concrete
lows: C 144-87 Specification for Aggregate for Masonry
Mortar
Section 3.1-Specify minimum acceptable soil condition in
C 150-86 Specification for Portland Cement
trench form and depth of cover over pipe.
C 171-69 Specification for Sheet Materials for Curing
Section 3.6-Specify any preirrigation or additional treat-
(1986) Concrete
ment of expansive soils if required.
C 172-71 Sampling Fresh Concrete
Section 4.1-Designate cement to be used or permitted if
(1977)
any other than those indicated in this section.
C 173-78 Test Method for Air Content of Freshly
Section 4.4-Designate admixtures to be used or permitted.
Mixed Concrete by the Volumetric Method
Section 8.1-Specify compaction of backfill where re-
C 191-77 Test for Time of Setting of Hydraulic Cement
quired.
by Vicat Needle (Including Tentative Revi-
Section 8.1.3-Specify color of pigmented curing com-
sion)
pound if required, such as white for hot weather use.
C 231-89a Test for Air Content of Freshly Mixed Con-
Section 8.2-Specify any special provisions for clean-up
crete by the Pressure Method
and disposal of excess earth.
C 260-86 Specification for Air-Entraining Admixtures
Section 9.4-Specify load test if required, including min-
for Concrete
imum acceptable criteria. Specification for Liquid Membrane-Forming
C 309-89
Section 9.6-Specify hydrostatic test if required, including
Compounds for Curing Concrete
the reaches of pipe line to be tested and the head to be
C 361-89 Specification for Reinforced Concrete Low-
used in the tests.*
Head Pressure Pipe
Additional explanatory information will be found in
C 403-88 Test for Time of Setting of Concrete Mix-
“Recommendations for Nonreinforced Cast-in-Place Con-
tures by Penetration Resistance
crete Pipe” by ACI Committee 346.
C 494-86 Standard Specification for Chemical Admix-
tures for Concrete
CHAPTER 1-GENERAL C 595-86 Specification for Blended Hydraulic Cements
1.1-Scope C 618-88 Specification for Fly Ash and Raw or Cal-
These specifications cover construction of cast-in-place cined Natural Pozzolan for Use as a Mineral
nonreinforced concrete pipe used for the conveyance of liq- Admixture in Portland Cement Concrete
uids such as irrigation water, storm water, sewage, and
industrial wastes. 1.3-Conflicts
In case of conflicts between referenced specifications and
1.2-Reference specifications and testing ACI 346, the specific requirements of ACI 346 shall govern.
methods
The Standards of the American Society for Testing and 1.4-Definitions
Materials† referred to in these specifications are listed be- The following terms are defined for general use in these
low with their serial designation, including the year of specifications:
adoption or revision, and are declared to be part of these Project specifications---Any individual specification
specifications the same as if fully set forth elsewhere herein. which employs ACI 346 by reference and which serves as
the instrument for making selections available under these
C 31-88 Making and Curing Concrete Test Specimens specifications and for specifying items not covered herein.
in the Field Project drawings---The drawings which accompany
C 33-86 Specification for Concrete Aggregates project specifications and complete the descriptive informa-
C 39-86 Test for Compressive Strength of Cylindrical tion for concrete construction work required or referred to in
Concrete Specimens the project specifications.
C 42-87 Obtaining and Testing Drilled Cores and Contractor---The individual, firm, or agency responsible
Sawed Beams of Concrete for construction.
Specifier---The individual, firm or agency preparing
project specifications and drawings and/or administering
*Maximum head recommended is 15 ft [44.83 kPa] above center line of pipe. See
Recommendations Section 1.1. work under project specifications and drawings for the pur-
†1916 Race St., Philadelphia, Pa. 19103. chaser.
SPECIFICATIONS FOR CAST-IN-PLACE PIPE 346-3

Purchaser-The individual, firm or agency issuing 3.4-Precast pipe


project specifications and drawings for whom the work is In lieu of the construction of cast-in-place concrete pipe,
constructed. the Contractor may at his option and expense substitute
Trench form-The vertical sides and semi-circular bot- precast concrete pipe conforming to ASTM C 76 or ASTM
tom of the trench shaped to provide full, firm and uniform C 361, the class to be correlated with the field requirements.
supports for the bottom 210 degrees of the pipe. The class of pipe, type of bedding, and joints shall be sub-
ject to the approval of the Specifier.
CHAPTER 2-BASIS OF ACCEPTANCE
3.5-Fill material
2.1-General
Where the pipe is to be constructed through fill material,
The acceptability of the pipe shall be determined by the such fill shall have stability in the zone of the trench form
results of the tests herein specified (unless otherwise re- equal to firm undisturbed earth in the area adjacent to the
quired in the contract documents) and by inspection to de- fill.
termine whether the pipe conforms to the project specifica-
tions. Any portion of the pipe failing to meet specification 3.6-Wetting
requirements shall be replaced, or repaired at the option of At the time of concrete placement, all soil adjacent to the
the Specifier, to meet the specifications at the expense of pipe shall be sufficiently wet that it does not absorb water
the Contractor. from the concrete nor expand upon additional wetting, and
the trench shall be stable and completely free of protrusions,
CHAPTER 3-TRENCH mud, debris, and standing water.
3.1-Excavation
3.7-Grade and alignment tolerance
The trench shall be excavated to lines and grades estab-
Departure from and return to established grade shall not
lished by the Specifier. The trench shall be shaped to form
exceed 1 in. per 10 lineal ft (25 mm per 3 m) and the
the bottom outside of the pipe and shall be graded and
maximum departure shall be limited to 1-1/2 in. (40 mm).
prepared to provide full, firm, and uniform support by un-
Departure from and return to established alignment shall not
disturbed earth, rock, or compacted fill over a minimum of
exceed 2 in. per 10 lineal ft (50 mm per 3 m) and the
the bottom 210 deg of the outside of the pipe, hereinafter
maximum departure shall be limited to 4 in. (100 mm).
referred to as the “trench form.” When the soil around the
trench form must be over-excavated and then backfilled and
CHAPTER 4-MATERIALS
compacted, trenching shall be performed to produce the
4.1-Cements
above-mentioned stable trench form. Trench shoring shall
Unless otherwise permitted or required, cement shall be
comply with OSHA and local government trench shoring
Type I, conforming to the requirements of ASTM C 150 or
requirements.
Types IS or IP, conforming to the requirements of ASTM C
595. Different types of these different cements shall not be
3.2-Rock used interchangeably in the same element or portion of the
Where boulders or other large rock particles are encoun- work.
tered, they shall be removed to at least 6 in. (150 mm)
below the grade of the bottom of the pipe. The grade shall 4.2-Aggregates
be reconstituted by filling voids with approved material, The aggregates used for concrete or mortar shall conform
such as sand, pea gravel, crushed rock, cohesive soil, or to the requirements of ASTM C 38, except that aggregates
other material approved by the Specifier to provide a failing to meet these specifications but which have been
smooth, firm foundation for placing the pipe. shown by special test or actual service to produce concrete
of specified strength and adequate durability may be used
3.3-Unstable soils where authorized by the Specifier. The nominal maximum
3.3.1 Noncohesive-- All unstable strata or lenses of loose coarse aggregate size shall be not more than 1/3 of minimum
sand, silt, or other noncohesive soils, below the contact line pipe wall thickness nor greater than 1-1/2 in. (40 mm).
of the concrete pipe and trench form, shall be stabilized by
approved methods or over-excavated and refilled in accor- 4.3-Water
dance with Section 3.3.3. Water used for making concrete and mortar shall be free
3.3.2 Cohesive soils-- When cohesive soil below the con- from injurious amounts of silt, organic matter, alkali, salts,
tact line of the concrete pipe and the trench form is unstable, and other impurities. Water is acceptable if mortar cubes
it shall be over-excavated and refilled as described in Sec- (ASTM C 109) made with that water have strengths equal to
tion 3.3.3 or stabilized by approved methods. at least 90 percent of companion cubes made with potable
3.3.3 Over-excavation and refill-- When this method is water, and if setting of cement paste (ASTM C 191) or of
adopted for stabilization, the trench shall be over-excavated concrete (ASTM C 403) is not adversely affected.
to such depths and widths as required, refilled with selected
cohesive soils, and compacted by acceptable methods to a 4.4-Admixtures
density that will provide stability for the trench form as If portland cement (ASTM C 150), portland blast furnace
described in Section 3.1. slag cement (ASTM C 595), or portland pozzolan cement
346-4 MANUAL OF CONCRETE PRACTICE

(ASTM C 595) is used, an air-entraining admixture shall be 5.3-Offsets


used in such amount as will produce concrete having an air Offsets at form laps and horizontal edges shall not exceed
l
content of 4 to 6 percent by volume of the concrete as /2 in. (13 mm) for pipe having inside diameter not greater
discharged from the mixer. Such air-entraining admixture than 42 in. (approximately 1.05 m); 3/4 in. (19 mm) for pipe
may be interground or blended with the cement as specified having inside diameter greater than 42 in. but not greater
in ASTM C 150 or C 595 or may be added to the concrete than 72 in. (approximately 1.8 m); and 1 in. (25 mm) for
as an admixture. However, pozzolans or other admixtures pipe having inside diameter greater than 72 in. (1.8 m).
as indicated below may be used with or in lieu of the air-
entraining admixture with the approval of the Specifier. All 5.4-Bearing plates
admixtures shall conform to the appropriate ASTM speci- Bearing plates, boards, or other supports necessary for
fications indicated below. two-stage construction shall be removed, and any indenta-
4.4.1 Air-entraining admixtures-- ASTM C 260 tions exceeding 1/2 in. (13 mm) left in the concrete from
4.4.2 Chemical admixtures-- ASTM C 494 such plates shall be cleaned, moistened, filled with mortar,
4.4.3 Fly ash and other pozzolans-- ASTM C 618 trowelled, and cured.

4.5-Bonding mortar CHAPTER 6-CONCRETE PROPERTIES


Bonding mortar shall consist of two or more parts of 6.1-Strength
cement to three parts of sand, by bulk volume. Sand shall Unless otherwise designated in the project specifications,
conform to ASTM C 144. the strength of the concrete shall be at least 3000 psi (20.7
MPa), when the concrete is not exposed to severe and fre-
quent freezing and thawing or 4000 psi (27.6 MPa) when
4.6-Storage of materials the concrete is exposed to severe and frequent freezing and
4.6.1 Cement shall be stored in dry moisture resistant, thawing, as determined on the basis of 28 day compressive
bins, or silos which will provide protection from dampness strength tests. Strengths shall be considered satisfactory if
and contamination. To avoid long storage with accompany- the average of any five consecutive sets of strength tests of
ing reduction in strength-producing properties, shipments of the laboratory-cured specimens is equal to or greater than
cement shall be used in the order received on the job. the specified strength, and if not more than 20 percent of the
4.6.2 Aggregate stockpiles shall be arranged and used in strength tests have values less than the specified strength.
a manner to avoid excessive segregation or contamination The pipe represented by unsatisfactory strength tests on cyl-
with other materials or other sizes of aggregates. To insure inders shall be further tested either by coring or by load
that this condition is met, tests for determining conformance testing at the Contractor’s option as specified in Sections
to requirements for cleanness and grading shall be per- 9.3 and 9.4. Any pipe failing these tests shall be replaced or
formed on samples secured from the aggregates at the point repaired at the option of the Specifier, at the Contractor’s
of batching. Sand shall be allowed to drain until it has expense.
reached a stable moisture content such that there is now
visible separation of water from aggregate at the time of 6.2-Cement and water content
batching. All concrete shall have a water-cement ratio not exceed-
4.6.3 Admixtures shall be stored in such a manner as to ing 0.53 by weight, including free surface moisture on ag-
avoid contamination, evaporation, or damage. For those gregates.
used in the form of suspensions or unstable solutions, suit-
able agitating equipment shall be provided to assure uni- 6.3-Air content
form distribution of the ingredients. Liquid admixtures shall All concrete shall contain 4 to 6 percent entrained air, as
be protected from freezing and from temperatures which specified in Section 4.4.
could adversely affect their characteristics.
6.4-Slump
CHAPTER 5-PIPE DIMENSIONS AND Slump of concrete shall be determined in accordance with
TOLERANCES ASTM C 143. Slump shall be the minimum required for
5.1-Wall thickness satisfactory placement of the concrete by the equipment
used by the Contractor.
The minimum wall thickness of cast-in-place pipe at any
point shall be 1/12 of the nominal internal diameter of the 6.5-Proportioning and mixing
pipe plus 1/2 in. (13 mm), but in no case less than 2 in. (50 Concrete shall be ready-mixed concrete meeting the re-
mm). quirements of ASTM C 94, or shall be job-mixed concrete
as described below. All concrete shall be mixed until there
5.2-Pipe diameter tolerances is a uniform distribution of the materials and shall be dis-
The internal diameter of the pipe at any point shall not be charged completely before the mixer is recharged. For job-
less than 95 percent of the nominal diameter, and the av- mixed concrete, mixing shall be done in a batch mixer of a
erage of any four measurements of the internal diameter type approved by the Specifier. The mixer shall be rotated
made at 45 deg intervals shall not be less than the nominal at a speed recommended by the manufacturer. Mixing shall
diameter. be continued for at least 1-1/2 min after all materials are in
SPEClFlCATlONS FOR CAST-IN-PLACE PIPE 346-5

the drum, for drum capacity not more than 3 yd3, (2.3 m3) 7.4-Finish
plus 1/4 min for each additional cubic yard of capacity. Except for the form offsets, the interior surface of the
pipe shall be equivalent to or better than a wood float finish.
CHAPTER 7-CONCRETE PLACEMENT All extraneous concrete shall be removed from the interior
surface.
7.1-Method of placement
The pipe shall be constructed in one placement, by either
CHAPTER 8-CURING, BACKFILLING,
the one or two stage method. The concrete shall be vibrated,
AND CLEAN-UP
rammed, tamped, or worked with suitable compacting
8.1-Curing and backfilling
equipment until thoroughly consolidated.
The Contractor shall be responsible for proper curing of
the concrete and backfilling the trench to an even grade.
7.2-Construction joints Curing shall be performed in such a manner as to prevent
When work is stopped at the end of a placement or for premature drying of the concrete. The Contractor shall use
any period that would permit initial set to take place, a one of the methods described in Section 8.1.1, 8.1.2, 8.1.3,
construction joint shall be formed. The ends of the pipe that or 8.1.4 and the method described in Section 8.1.5 for
are to be in butt contact shall be left in rough condition with curing the pipe. Final backfill shall be placed as specified in
a slope of approximately 45 deg. Before resuming, if the Section 8.1.1.
pipe diameter is 60 in. (1.5 m) or less, an excavation shall 8.1.1 A 3-in. (75-mm) layer of moist loose soil or sand
be made along the sides and bottom of the joint to permit may be carefully placed over the top of the pipe immedi-
casting of a concrete collar around the outside of the joint. ately after the pipe is cast. The backfill shall be materially
This collar shall have a minimum thickness of 1-1/4 times free of clods or rocks having a diameter greater than 2 in.
the wall thickness of the pipe and shall lap the entire joint by (50 mm), roots, or other deleterious foreign material. The
at least two times the wall thickness. Immediately before backfill shall be carefully placed over the top of the pipe to
resuming concrete placement the surfaces to be bonded prevent injury to the wet concrete. The thickness of the
shall be cleaned of all coatings, foreign materials, and loose backfill shall be increased to 6 in. (150 mm) after initial set
or defective concrete, thoroughly wetted, and coated with a of the concrete has occurred. The backfill shall be kept
layer of bonding mortar (Section 4.5) approximately 1/4 in. moist at all times until the pipe has been covered to a depth
(6 mm) thick. In lieu of the bonding mortar, neat cement of 12 in. (305 mm) or more. Final backfill, and compaction
paste may be thoroughly scrubbed onto the wet surface of where required, shall not be started until the pipe has de-
the previously placed concrete. veloped sufficient strength to support the loads to be im-
For a joint that may be used for connections to another posed and shall conform to local requirements and to project
pipe or structure, a joint shall be made by squaring off the specifications.
end of the pipe. An excavation shall be made along the sides 8.1.2 The exposed top portion of the pipe may be covered
and bottom of the cast-in-place pipe, for any diameter, to with wet burlap or other material of high moisture retentive
permit casting of a concrete collar as described above. properties immediately after the pipe is cast. The covering
The outside top of all joints shall be capped for the entire material shall be kept continuously moist until the place-
width of the pipe that is exposed, that is, between the earth ment of final backfill as described under Section 8.1.1.
walls of the excavated trench. This cap shall have a mini- Moisture retentive material may be removed or left in place
mum thickness equal to the wall thickness of the pipe and at the option of the Contractor.
shall lap the joint, both upstream and downstream from the 8.1.3 A pigmented membrane-curing compound con-
joint by at least twice the wall thickness of the pipe. A cap forming to ASTM C 309 may be applied to the exposed top
as described is required regardless of pipe size. surface immediately after the pipe is cast. The compound
shall be applied at the rate of not less than 1 gal. for each
7.3-Temperature 150 ft2 (1 liter for each 3.7 m2) of exposed concrete. The
The temperature of concrete when it is being discharged pipe shall then be covered with a minimum of 3 in. (75 mm)
from the mixer shall be not more than 90 F (32 C) and not of moist loose soil when the curing compound is sufficiently
less than 40 F (4 C) in moderate weather, or 50 F (10 C) in hard to resist damage from the fill. Final backfill shall be
weather during which the mean daily temperature drops placed as soon as the pipe attains suitable strength.
below 40 F (4 C). Whenever the mean daily temperature in 8.1.4 Polyethylene film complying with ASTM C 171,
the vicinity of the work site falls below 40 F (4 C) for more nominal thickness 0.0015 in. (0.038 mm), may be placed
than 1 day, the concrete shall be maintained at a tempera- on the exposed top surface of the pipe immediately after the
ture not lower than 50 F (10 C) for at least 48 hr after it is pipe is cast. The film shall be anchored in place with loose
placed. Concrete shall be protected against freezing tem- soil to assure continuous, adequate curing. The trench shall
peratures for an additional 48 hr immediately following the be completely backfilled as soon as the pipe attains suitable
48 hr of protection at 50 F (10 C). Where artificial heat is strength.
employed, special care shall be taken to prevent the con- 8.1.5 A humid atmosphere within the pipe as evidenced
crete from drying. The Contractor shall employ effective by condensation on the interior surface shall be maintained
means, such as precooling of aggregates and mixing water for at least 7 days following placement except for a maxi-
or placing at night, as necessary to maintain the placing mum period of 48 hr allowed for removing forms and mak-
temperature of the concrete below 90 F (32 C). ing repairs. To prevent air drafts which may dry the pipe
346-6 MANUAL OF CONCRETE PRACTICE

and to maintain a humid atmosphere inside the pipe, all and tested in accordance with ASTM C 42. The cores shall
openings into the pipeline shall be kept closed or covered have a length-to-diameter ratio of not less than 1. The Con-
except when and where work is actually in progress on the tractor shall take at least one core sample at locations se-
inside of the pipe. If necessary to promote high humidity, lected by the Specifier, for each set of two cylinders failing
the pipeline shall be partially filled with ponded water dur- to meet test requirements. The Contractor shall patch all
ing the curing period. core holes in a manner that will be as permanent and leak-
proof as the surrounding concrete.
8.2-Clean-up 9.3.2 Impact hammers, soniscopes, or other nondestruc-
The work area shall be restored to the same general con- tive testing devices may be used, if approved by the Spec-
dition that existed before the start of construction. ifier, to estimate relative strengths of various areas of the
structure as an aid in evaluating concrete in place or in
CHAPTER 9-TESTING determining locations of areas to be cored. Test results so
9.1-Testing of materials obtained, unless properly calibrated and correlated with
Routine testing of materials, of proposed mix propor- other test data, shall not be used as a basis for acceptance or
tions, and of resulting concrete for compliance with tech- rejection.
nical requirements of these specifications shall be the re-
sponsibility of the Purchaser and will be performed without 9.4-Load test
expense to the Contractor. Where specified, hydrostatic If the Contractor elects to make a load test under the
tests shall be performed by the Contractor according to Sec- provisions of Section 6.1, it shall be made without disturb-
tion 9.6. Other testing required because of changes in ma- ing the earth supporting the lower 210 deg of pipe. The load
terials or proportions of the mix requested by the Contrac- shall be applied to a 4-ft (1.2 m) length of pipe through a
tor, as well as any coring, load testing, or other extra testing “sandbox” in such manner that carefully placed sand in the
of concrete or other materials occasioned by their failure to sandbox forms a bedding over 1/4 the circumference of the
meet specification requirements, shall be at the Contractor’s pipe, measured at the center line of the crown. The sandbox
expense. The Contractor may retain at his expense a sepa- shall be made of metal or dressed timber so heavy as to
rate testing agency for his own information and guidance. avoid appreciable bending by the side pressure of the sand.
A strip of cloth or plastic film may be attached to the inside
9.2-Testing services of the sandbox on each side, along the lower edge, to pre-
The testing agency designated by the Purchaser shall per- vent the escape of sand between the sandbox and pipe. The
form the following tests which shall be used as the basis for depth of the bedding above the pipe at the thinnest point
accepting or rejecting the Contractor’s work. shall be 1/4 the inside diameter of the pipe. The sandbox
9.2.1 Test the Contractor’s proposed materials for com- shall not be allowed to come in contact with the pipe or
pliance with the specifications. sides of the trench. The sandbox shall be filled with sand
9.2.2 Review and test the Contractor’s proposed mix pro- which shall be clean and shall contain not less than five
portions. percent moisture and shall pass a 4.75 mm (No. 4) sieve.
9.2.3 Secure production samples of materials at plants on The upper surface of the sand shall be struck off level with
stockpiles prior to start of work and test for compliance with a straight edge and shall be covered with a rigid top bearing
specification and test throughout project as required by plate, the lower surface of which is a true plane, made of
specifications. heavy timbers or other rigid material capable of distributing
9.2.4 Secure at least one sample in accordance with the test load uniformly without appreciable bending. The
ASTM C 172 for each 50 yd3 (38 m3) of concrete used, but test load shall be applied to this bearing plate by piling
not less than one sample for each day’s work, nor less than weights directly on the bearing plate or by moving heavy
one sample for each section of pipe placed in a continuous equipment of predetermined weight onto the bearing plate.
operation. The bearing plate shall not be allowed to touch the sandbox.
9.2.5 Mold and cure two cylinders from each sample in The total load applied to the top of the pipe shall be at least
accordance with ASTM C 31. 125 percent of the maximum earth load to which the pipe
9.2.6 Test the two specimens at 28 days of curing in will be subjected, plus live load based on one 16,000 lbf (71
accordance with ASTM C 39. The 28-day test result shall kN) wheel load of AASHTO H-20-44 loading with an im-
be the average of the strengths of the two specimens, except pact factor of 2.0. The pipe shall be inspected prior to load
that if one specimen in a test manifests evidence of im- testing to catalog any existing longitudinal cracks; then the
proper sampling, molding, or testing, it shall be discarded pipe shall be reinspected after load testing to catalog any
and the strength of the remaining specimen used. additional longitudinal cracks.
9.2.7 Determine slump and air content of concrete in
accordance with ASTM Test Methods C 143 (slump) and C 9.5-Thickness tests
231, C 173, or C 138 (air content). Tests shall be performed The Contractor shall measure the thickness of the pipe at
no less frequently than the sampling frequency required by least every 200 lineal ft (60 m) with individual measure-
Section 9.2.4. ments staggered at points designated by the Purchaser.
Where thickness is not determined by probes through the
9.3-Core tests fresh concrete, small holes shall be drilled for the purpose.
9.3.1 If the Contractor elects to make core tests as pro- The Contractor shall patch all core holes in a manner that
vided in Section 6.1, cores shall be obtained from the pipe will be permanent and will not leak.
SPECIFICATIONS FOR CAST-IN-PLACE PIPE 346-7

9.6-Hydrostatic test
If a hydrostatic test is required by the Purchaser when for a minimum of 4 hours during which loss of water from
calling for bids, the test shall be made at any time after the the section under test shall be measured. Water less than 50
concrete has been allowed to harden for 28 days, or earlier F (10 C) in temperature shall not be used for this test.
if mutually agreed upon. The pipeline shall be filled with During the test period, the exfiltration rate shall not exceed
water to the head specified in the project specifications and 1000 gal. per in. of diameter per mile per 24 hour (926 liters
kept filled at least 48 hours. The line may be filled in one per 10 mm of diameter per km per 24 hour). If the line fails
length or between structures or bulkheads. If leaks are ev- the hydrostatic test, the Contractor shall drain the line, re-
ident, the line shall be drained and the leaks repaired, by pair imperfections as necessary to provide continuity in
and at the expense of the Contractor. Thereafter, with the structural and hydraulic integrity and retest the line as de-
line filled and under the specified head, there shall be a test scribed above.
This document has been approved for use by agen-
ACI 346R-90
cies of the Department of Defense and for listing in
the DoD Index of Specifications and Standards.

Recommendations for Cast-in-Place


Nonreinforced Concrete Pipe (Reapproved 1997)
Reported by ACI Committee 346
Donald L. Weesner, Chairman

Ernest R. Comstock Robert A. Midthun Pete W. Terre11


Earl R. Koller Noel A. Negley Carl R. Wilder
Frederick J. May William G. Reynolds Kenneth R. Wipff

The Committee voting on proposed revisions to ACI 346/346R-81:

Gilbert G. Lynch, Chairman Curtiss W. Gilley, Secretary


Ernest R. Comstock Robert D. Gofonia
Leonard J. Erie, II Robert E. Leake, Jr.
Morgan Johnson William G. Reynolds

This report presents a general view of present knowledge of cast-in-place 4.3-Concrete control and placement
concrete pipe, together with recommendations for design, construction, 4.4-Backfill and cleanup
and testing procedures. Construction specifications are contained in
“Specifications for Cast-in-Place Nonreinforced Concrete Pipe.”
Chapter 5-Safety and inspection, p. 346R-14
5.1-Safety
Keywords: admixtures; aggregates; air entrainment; backfilling; cast-in-place pipes; 5.2-Inspection
compressive strength; concrete construction; concrete pipes; curing; finishing; form-
work (construction); inspection; joints (junctions); load tests (structural); mixing; mix
proportioning; patching; placing: repairs; safety; slump tests; structural design; tem- Chapter 6-Equipment considerations, p. 346R-14
perature; tests; tolerances; vibration; water-cement ratio.
Chapter 7-References, p. 346R-15
CONTENTS
CHAPTER 1-INTRODUCTION
Chapter 1-Introduction, p. 346R-1 1.1-General description
1.1-General description
1.2-Methods of construction Cast-in-place pipe, as considered here, is an underground
continuous nonreinforced concrete conduit having no joints
or seams except as necessitated by construction require-
Chapter 2-Load carrying ability, p. 346R-6
2.1-General ments. It is intended for use to convey irrigation water,
2.2-Load tests storm water, sewage, or industrial waste under a maximum
2.3-Structural analysis internal operating head of 15 ft (45 kPa) and external loads
as subsequently discussed. Construction specifications are
Chapter 3-Design recommendations, p. 346R-9 contained in ACI 346.
3.1-Location requirements The pipe is cast in a previously excavated trench which
3.2-Hydraulic has a semicircular bottom and vertical or near-vertical side
3.3-Structural
walls. See Fig. 1.1 for typical section of cast-in-place con-
crete pipe. Concrete is usually delivered to the trench from
Chapter 4-Construction recommendation, transit-mix trucks.
p. 346R-11 The outside lower portion of the pipe is formed by the
4.1-General
4.2-Excavation
trench and the corresponding inside is formed by a
specially designed slipform commonly called a boat or
sled, or a more complex slipform machine. The inside of
ACI Committee Reports, Guides, Standard Practices, and Commen-
taries are intended for guidance in designing, planning executing, or
inspecting construction, and in preparing specifications. Reference to Copyright © 1990 American Concrete Institute. All rights reserved including rights
these documents shall not be made in the Project Documents. If items of reproduction and use in any form or by any means, including the making of copies
by any photo process, or by any electronic or mechanical device, printed, written, or
found in these documents are desired to be part of the Project oral, or recording for sound or visual reproduction or for use in any knowledge or
Documents they should he phrased in mandatory language and retrieval system or device, unless permission in writing is obtained from the copyright
proprietors.
incorporated into the Project Documents. The 1990 revisions consisted of minor changes throughout this document and the
addition of a new Chapter 6.

346R-1
346R-2 MANUAL OF CONCRETE PRACTICE

Fig. 1.1 - Typical Section; 12-120 in. (305-3050 mm)


cast-in-place concrete pipe.

the remainder of the pipe is formed either by metal forms


or a pneumatically inflated form. The finished bore of the
pipe is circular except for minor structural deformation and
surface imperfections, as allowed in Chapter 5 of the
specifications.
Cast-in-place pipe has been built in diameters of 12 to
120 in. (305 mm to 3050 mm) generally in 6 in. (150 mm) Fig. 1.2.1.1a - Single-stage process using metal
increments. Where the process requires access to the inside forms. Construction of 48 in. (1220 mm) diameter
for removal of metal forms, the smallest practical diameter storm water drain. Concrete from transit mixer dis-
is about 24 in. (610 mm). The inflatable. inner form, how- charges into hopper of machine where electrically
ever, can be removed from 12 in. (305 mm) pipe and has operated tampers move it downward around metal
been used successfully up to a diameter of 84 in. (2135 forms. Further consolidation is accomplished with
electric vibrators attached near base of mandrel.
mm).
Cast-in-place pipe has been used for agricultural purposes
in the San Joaquin Valley of California for more than 40
yrs. In recent years., this type of pipe has been used in other
states and countries and its application has been broadened
to include sanitary, storm, and industrial sewers.
Cast-in-place pipe has been used in sewers where the
earth till above the pipe exceeded 20 ft. (6.1 m). Sewers
and storm drains have been successfully installed under city
streets and highways carrying heavy traffic. Irrigation lines
are operating successfully under heavily traveled roads with
18 in. (455 mm) of cover. Structural computations and load
tests have demonstrated that such pipe can withstand loads
of 50 ft (15.2 m) or more of earth fill.1-5

1.2-Methods of construction
Two general categories of construction methods are dis-
cussed in this section:
• Two-stage construction by machine method.
Fig. 1.2.1.1b - Single-stage construction using metal
• Single-stage construction by machine methods. forms. Rear view of 84 in. (2135 mm) single-stage
Initially, cast-in-place pipelines were constructed entirely machine. Six ft (1.8 m) long aluminum forms are fed
by hand in two separate operations or “stages.” In the first into machine over rollers attached to the mandrel.
stage, the bottom half was placed and shaped by a semicir- Metal arch spreaders, used to support the forms, are
cular form or “boat.” In the second stage, semicircular shown leaning against the machine.
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE

Fig. 1.2.1.1c - Single-stage construction using metal


forms. Front view of 84 in. (2135 mm) diameter ma-
chine. Power unit and winch are mounted on front of
machine. Large metal forms are lowered into place
by machine mounted boom as concrete is fed into
the hopper.

metal forms were positioned on the previously placed invert


concrete and the upper half of the pipe completed. The
committee does not know of any recent use of this two-stage
process by hand methods.
Two-stage placement resulted in a longitudinal construc-
tion joint at about midheight of the pipe. This joint was
difficult to keep free of any material that sloughed off of the
sidewalls of the trench. It was necessary to place the upper
half while the lower half was still sufficiently plastic to
obtain satisfactory bonding of the two placements.
To eliminate the horizontal construction joint and to im-
prove on concrete placing and consolidation methods, ma-
chines were invented which could construct the entire pe-
riphery of the pipe in one operation or stage. This method
used metal forms for supporting the upper portion of the
pipe. Subsequently, another single placement method was
developed which is quite similar to that just described ex-
cept that it uses a dimensionally stable, pneumatically in-
flated inner form in lieu of metal forms.
There are many variations within the broad spectrum of
the foregoing categories, several of which are patented pro-
cesses. Nothing contained herein is intended to imply the
superiority or recommendation of any proprietary process Fig. 1.2.1.1e - Single-stage construction using metal
over any other, nor is the omission of any process or pro- forms. A 42 in. (1065 mm) machine installing storm
drain pipe. Metal forms are lined up at the side of
cedure intended to indicate that it is deficient in any the trench before manually lowering into machine.
manner. As pipe is formed the outside top is covered with
Two aspects of the construction operation are common to polyethylene to retain moisture and ensure proper
all cast-in-place construction methods: curing.
346R-4 MANUAL OF CONCRETE PRACTICE

1.2.1.1 Single-stage construction using metal forms-


The pipe casting machine consists of a steel sled and a
mandrel assembly supported by and attached to the sled by
hinges permitting it to adapt itself to the trench. The man-
drel assembly consists of the inside bottom and outside top
troweling skirts and hopper. An engine mounted on the
bottom front of the sled powers a generator and a winch.
The machine moves forward by a variable speed winch and
cable hooked to a deadman inside or outside the trench. A
separate machine is required for each pipe size.
As the machine moves forward, metal forms supporting
Fig. 1.2.1.2b - Single-stage construction using in- about 230 deg of the top inside of the pipe are inserted into
flatable form. Machine in trench with form being in- the front of the mandrel, hooked to the preceding form and
flated just prior to concrete placement. sprayed with oil. Metal struts are manually placed inside the
forms near each joint to hold the proper shape of the pipe
The trench has vertical or nearly vertical side-walls and a and support the weight of the concrete. Concrete is moved
semicircular bottom. from the hopper into the mandrel by tampers. Vibrators on
The upper portion of the pipe. is supported and formed by each side of the machine consolidate the concrete into a
an inside form. monolithic cast-in-place pipe. The speed of the tampers and
1.2.1 Single-stage construction by machine - The first the frequency of vibration can be independently controlled
known installation of machine-placed, monolithic, cast-in- to suit the consistency of the concrete being used.
place pipe was made in 1950 by a rancher on the Alves The metal forms are usually constructed of aluminum
Ranch near Woodland, Calif. The machine used for this alloy and are about 4 to 6 ft long (1.2 to 1.8 m). A fastening
installation served as the basis for the first patented cast- hook is provided at the top on one end and an eye on the
in-place concrete pipe machine. Other firms have developed other for hooking the forms together. The forms remain in
pipe making machines since the first was introduced. place until the concrete is strong enough for form removal,
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 546R-5

usually 4 to 6 hr. The supporting struts are removed and the prene coatings. They remain dimensionally stable under re-
inner form pulled forward into the trench which has been peated use and will withstand extensive wear.
excavated for the next placement. Usually this is done in Cast-in-place pipe has been made by this process in sizes
one withdrawal by using one of the pieces of equipment ranging from about 12 to 84 in. (305 to 2135 mm). This
available at the site. Sometimes, however, the forms are process is the only one which can be used to make pipe
separated inside the pipe and drawn forward in two or more
pulls. After the forms are withdrawn, they are unhooked,
stacked on the bank, and prepared for the next use. On
completion of a placement, the machine is thoroughly
cleaned and prepared for further use.
This process has been used to make pipe ranging in size
from 24 to 120 in. diameter (610 to 3050 mm) and larger
sizes are considered feasible.6-10
1.2.1.2 Single-stage construction using pneumatically
inflated inner forms. - With this method the pipe casting
machine is a one-piece steel sled and with an outside top
troweling skirt, two concrete hoppers, with tampers and
variable-speed vibrators. The machine is moved forward by
a truck-mounted variable speed winch. Power to the ma-
chine is supplied from a generator on the winch truck. Sep-
arate machines and forms are required for each pipe size.
The inner form of desired size and approximately 300 to
600 ft (91 to 183 m) in length is placed in the trench and
inflated to approximately 3 psi (0.02 MPa). As the machine
moves forward, the form is picked up on rollers and guided
into the barrel of the machine. Concrete from the forward
hopper is moved by tampers down to form the bottom half
of the pipe, while concrete from the rear hopper forms the
upper half. Vibrators move and consolidate the concrete
into a monolithic cast-in-place pipe. The outside top is
struck off smooth by the outside top troweling skirt.
When the concrete has cured sufficiently, normally in 3
to 4 hours, the inner form is partially deflated, pulled down
the trench and reinflated for the next section of pipe. Fig. 1.2.1.2d - Single-stage construction using in-
Meanwhile, the casting machine is removed from the flatable form. Front view of the machine sitting in
trench, thoroughly cleaned, and prepared for the next use. shipping stand. Partially inflated form being in-
The inflatable form was developed using specially woven spected for leaks can be seen in background through
the machine. Shipping stand is not attached to the
fabrics, coated with abrasion and chemical resistant neo- machine.

Fig. 1.2.1.2e - Single-stage construction using inflatable form. Rear view of the
machine in shipping stand with inflated form. Concrete is placed between solid
steel ring and inner form. Shipping stand is not attached to the machine.
346R-6 MANUAL OF CONCRETE PRACTICE

smaller than 24 in. diameter (610 mm) since it is not nec- cable and drum arrangement powered by a gasoline engine.
essary to enter the pipe to remove the inner form. 11 The cable extends forward and is anchored in the trench by
1.2.1.3 Evaluation of the single-stage method - Con- a deadman or other suitable anchorage. Adjustments can be
struction of cast-in-place pipe by the single stage machine made to the machine to permit varying the wall thickness.
method offers speed of construction and low manpower Concrete is placed in a hopper and flows around the pe-
requirements. Although a certain amount of concreting skill riphery of the trench bottom. Final finish is obtained by a
is required, no specially trained or highly skilled technicians semi-circular boat attached to the rear of the machine.
other than one or two key operators are required. Forms are The top half of the pipe is constructed by a second ma-
easily placed and oiled, and the entire operation is central- chine following closely behind the lower machine and at-
ized and controlled. For the process using metal forms, the tached to it by cables. Oiled forms are used to support and
invert can be inspected and imperfections eliminated at the form the upper half of the pipe. Wood bearing plates placed
time concrete is being placed. on the invert serve as a base for vertical wooden posts which
Some of the machines available are patented and their use support the top section metal forms. Spreader bars are in-
requires a rental or royalty payment to the patent holder. stalled horizontally across the pipe form at the approximate
The self-contained machines are heavy, but the weight is center line to prevent inward deformation of the otherwise
not beyond the handling capabilities of equipment normally unrestrained lower ends. One bearing plate, vertical post,
available on the job. and spreader bar is used for each form. The machine for
Since the machines depend on the previously excavated constructing the upper half of the pipe is placed in position
trench for line and grade, any irregularities, nonuniformity over the metal forms. It is supported by tubber-tired wheels
in firmness or density of the subgrade, or failure to remove in front and a shaping form in the rear, both adjustable to
debris or other loose material from the trench bottom ahead permit variation of the wall thickness. Concrete is placed in
of the machines, may cause them to deviate from desired a metal hopper on the form from which it flows to the void
grade and alignment. Therefore, it is necessary to maintain between the metal forms and the trench walls. Mechanical
close check on grade and alignment. steel tampers consolidate the concrete on each side. The
1.2.2 Two-stage construction by machine - This method outside top of the pipe is shuck off and smoothed by the top
is similar to the single stage construction using metal forms, of the machine.
except that two separate machines are used to perform the 1.2.3 Rate of production - Rate of production is usually
work. The lower half of the pipe is constructed by a trav- governed by factors other than the production capability of
eling slipform which is moved forward in the trench by a

Fig. 1.2.2b - Two-stage construction by machine.


Workman standing between the two pieces of pipe
making equipment has just placed metal semicircular
Fig. 1.2.2a - Two-stage construction by machine. form into position together with wooden spreader
Construction of 30 in. (760 mm) diameter pipe show- and bearing board for vertical strut; and is in posi-
ing the machine that places the top half of the con- tion to receive another metal form as the machine
crete pipe. moves forward in unison.
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 346R-7

the pipe making machines. In irrigation work the rate of against a steel box containing approximately 45 tons
advance is affected by the time required to remove the inner (approximately 41,000 kg) of sand and supported over the
forms, the nature of the soil such as a loose sandy soil or a pipe by sills and blocks. A hairline crack appeared at the
rocky or spongy foundation, length of trench excavated top and bottom of the pipe at 45,600 lbf (203 kN). This
ahead of concrete placement, and the condition of the crack opened to 0.01 in. (0.25 mm) when a total of 65,100
equipment. Rate of production in open country is usually in lbf (290 kN) was reached. When additional load was
the range of 400 to 700 ft (120 to 210 m) per day. However, applied, the cracks opened slightly and at 71,600 lbf (318
as much as 1700 ft (515 m) of 36 in. (910 mm) pipe were kN) a hairline crack appeared at the spring line on both
placed in one shift when all conditions were favorable. For sides. At this load cracks also began to appear in the soil
storm and sanitary sewers in city streets production progress adjacent to the sides of the pipe. When a total load of
is slowed by such obstacles as interference from under- 78,600 lbf (350 kN) was recorded, additional jacking
ground utilities, deep trenches, shoring problems, handling resulted only in the pipe sinking into the ground, but no
of trench excavation, control of traffic, and underground increase in the pressure reading. It was apparent that
water. Rate of progress under such conditions may be in the ultimate failure could not be reached under these
range of 150 to 250 ft (45 to 75 m) per day. conditions, so the test was stopped.
In 1969, static and dynamic load tests were applied to
CHAPTER 2-LOAD CARRYING ABILITY each of two locations of 96 in. (2440 mm) pipe installed in
2.1-General Dallas, Texas. Twenty-eight day compressive strengths
Most of the early nonreinforced cast-in-place concrete ranged from 4000 to 5000 psi (27.5 to 34.5 MPa). Howard
pipelines were used for conveying irrigation water where Needles Tammen and Bergendoff of Dallas coordinated the
earth loads were not an important consideration except at test program.
road crossings. Cover for such lines was usually in the In order to determine the stresses induced in the pipe
range of 2 to 3 ft (610 mm to 915 mm). As pipe making under test loads, a circumferential ring of 17 strain gages
processes improved, with corresponding increase in quality was attached to the inner and outer pipe faces at each lo-
of concrete, nonreinforced cast-in-place concrete pipe came cation. Deflectometers were installed at the horizontal and
into use for storm drains and sanitary sewers as well as for vertical diameters to measure the actual wall deflections of
irrigation lines crossing and parallel to paved roads carrying the pipe under load.
heavy traffic with cover of 24 in. (610 mm) or less. The For the initial static load test, a sandbox frame of dimen-
ability of such pipe to carry the heavy loads imposed on sions prescribed by ASTM C 76-57T was used. The box
them by deep earth fills and traffic loads has been demon- enclosed a 4 x 6 ft (1.22 x 1.83 m) area spanning one quar-
strated by load bearing tests conducted independently by ter of the pipe circumference. The box frame for the second
several agencies and by structural analyses also conducted static load test enclosed a 4 x 4 ft (1.22 x 1.22 m) area to
independently by a number of consulting engineers using concentrate the uniform load nearer the pipe crown.
different design methods. All such load tests and analyses Incremental loads to a maximum of 205,000 lbf (912 kN)
demonstrated conclusively that nonreinforced concrete were applied to the pipe through both the standard ASTM
pipelines could successfully sustain the external loads nor- and the narrow sandboxes at each of the test locations. Test
mally encountered in sanitary and storm sewers and irriga- gage readings increased quite uniformly as the increments
1,3,4,5,12,13
tion lines. of load were applied. The pipe exhibited slight vertical de-
formation under the load and this was accompanied by an
2.2-Load tests increase in horizontal diameter of lesser magnitude than the
From 1955 to 1958, load tests were conducted by the vertical deformation.
No-Joint Concrete Pipe Co., under the direction of E. C. Under the maximum test load of 205,000 lbf (912 kN) the
Fortier, consulting civil engineer, Fresno, California, on vertical deformation was only about 1/32 in. (less than 1 mm)
24, 30, and 60 in. (610, 760, and 1525 mm) pipe, and also with the narrow sandbox loading. The horizontal diameter.
on a simulated section of 120 in. (3050 mm) pipe. In Sep- increased by only about 1/64 in. (0.40 mm) under this load-
tember 1955 the Salt River Project, Phoenix, Arizona, con- ing.
ducted load tests on seven sections of 30 in. (760 mm) The unit pressure on the test area of the pipe was in
cast-in-place pipe excess of 11,000 lbf per sq ft (525 kPa). No visible evi-
In January 1961, Arizona Testing Laboratories in Phoe- dence of cracking or spalling occurred under this heavy
nix, Arizona, conducted load tests on an isolated 4 ft (1.2 loading.
m) section of 48 in. (1220 mm) cast-in-place pipe, con- A dynamic load test was conducted to investigate the pipe
structed using the inflatable form process. The purpose of response to impact loads which could occur with shallow
the test was to determine the load carrying capacity of 48 in. cover above the pipe. The action of dual wheel truck axles
(1220 mm) Fullerform pipe in a typical trench under normal was simulated by placing four wooden railroad ties across
field conditions. the pipe on about 12 in. (300 mm) of compacted earth fill at
The test procedure conformed to the sand-bearing the usual location of truck wheels, and dropping one of the
method of ASTM C 76-57T, except that the pipe was 16,000 lb (7250 kg) concrete blocks used for the static load
supported by natural soil and by the vertical sides of the tests on the ties, from increasing heights of 6 to 36 in. (150
trench in which the pipe was cast. The load was applied at to 915 mm) in 6 in. (150 mm) increments. Under the con-
a uniform rate of 8000 lbf (36 kN) per min by jacking dition of maximum impact, a vertical deformation of only
346R-8 MANUAL OF CONCRETE PRACTICE

about 1/16 in. (1.6 mm) was measured with a horizontal


Flexural
deformation of only about 1/32 in. (less than 1 mm). Again, Pipe size, fiber stress,
it is significant that no damage to the pipe occurred under in. (cm) (mm) psi (kg/cm2) (kPa)
this severe loading. 24 ( 61) ( 610) 143 (10.0) ( 986)
30 ( 76) ( 760) 255 (17.9) (1758)
36 ( 91) ( 915) 295 (20.7) (2034)
2.3-Structural analysis 42 (107) (1065) 334 (23.5) (2303)
Following the successful early load test, showing what 48 (122) (1220) 320 (22.5) (2206)
54 (137) (1370) 359 (25.0) (2475)
appeared to be unusually high supporting strength, it was 60 (152) (1525) 385 (27.1) (2655)
desired to determine if the test results could be substantiated 72 (183) (1830) 433 (30.4) (2985)
by structural design analysis. Such a study was undertaken
by Ernest C. Fortier of Fresno, Calif., in the fall of 1958.
He made calculations of outer fiber stresses in the concrete
shell for pipe sizes 24 to 72 in. (610 to 1830 mm) in diam-
eter for earth fills of 4, 10, 20, and 30 ft (1.2, 3.0, 6.1, and Since the ultimate flexural strength (or outer fiber stress
at rupture) is in excess of this for good concrete, it appears
9.1 m) above top of pipe and live load of AASHTO H-
that the values for fiber stress for the severe conditions cited
20-44. Subsequently, computations were made for a com-
above are conservative.16,17
bination of stresses due to external loads and internal hy-
drostatic head of 10 ft (29.9 kPa). Live load was for H- In 1960, Edib Kirdar of the Salt River Project in Arizona
20-44 loading with impact factor of 2. Fiber stresses were made a structural analysis similar to that made by Ernest
computed for sizes 24 to 72 in. (610 to 1830 mm) in diam- Fortier. The objective was to demonstrate by structural
eter and for earth fills of 2, 3, 4, 10, 20, and 30 ft (0.6, 0.9, analysis that cast-in-place nonreinforced concrete pipe in
1.2, 3.0, 6.1, and 9.1 m) plus live load and 10 ft (29.9 kPa) sizes 12 to 72 in. (305 to 1830 mm) could safely be installed
hydrostatic head. Earth loads were computed from the Mar- under or across any roadway in the area with a minimum of
ston formula assuming weight of soil to be 110 lbf per cu ft 2.0 ft (0.6 m) of compacted soil cover. The elastic arch
(1760 kgf/m 3), active and passive pressure K u = K'u = theory was used with assumptions similar to those used by
0.150 and Curve C to determine coefficients. Live loads Fortier. The report concludes that cast-in-place nonrein-
transmitted from the surface to the buried pipe were deter- forced concrete pipe is capable of withstanding loads in
mined in accordance with the procedure outlined in the excess of H-20 surface load with an impact factor of 2
transmitted through 2.0 ft (0.6 m) of compacted soil weigh-
publication by Thomas K. Breitfuss.14 Moments and thrusts
at the invert of the pipe were computed using coefficients ing 110 lb per cu ft (1760 kg/m3).1
In 1959, John P. Esvelt, structural engineer, Spokane,
developed by the elastic arch theory. These coefficients
were published by James M. Paris.15 Maximum fiber stress Wash., made an analysis of the load bearing strength of
cast-in-place nonreinforced concrete pipe known as “Ex-
at the invert was computed from the formula:
truda-Cast” pipe for R. A. Hanson Co. Inc., Palouse,
Washington.2 Extruda-Cast pipe is cast in a single opera-
tion. Esvelt states that his calculations were intended as a
theoretical determination of the load-bearing strength of
“Extruda-Cast” pipe of different sizes for comparison with
where f = stress in extreme fiber in psi; M = moment at load-bearing test results and for use in suggesting modifi-
invert in ft-lb per ft of pipe; T = thrust (direct stress) at cations in design of the pipe barrel to improve the strength
invert in lb per ft of pipe; and t = thickness of pipe shell in characteristics. His thought was that if a correlation is es-
inches. tablished between theoretically derived strengths and test
In metric units: results for a few sizes or loading conditions, the calculations
can proceed to the determination of pipe strengths for other
6M2 T sizes and/or cross sections. Fortier had much the same
t t thought in extending the calculations verified by load tests
where f is in kg/cm2; M is in kg-cm/cm of pipe; T is in of pipe 24 to 60 in. (610 to 1525 mm) in diameter to a
kg/cm of pipe; t is in cm. The vertical load was assumed to diameter of 120 in. (3050 mm). Load-carrying calculations
be uniformly distributed over the top 180 deg of pipe and for the 120 in. (3050 mm) section were verified by an actual
the vertical soil reaction on bottom 180 deg of pipe. The load bearing test (see Section 2.2).
uniform lateral load was assumed to be 33 percent of the For his analysis, Esvelt calculated bending moments in
vertical load and applied horizontally to a height from the accordance with PCA Bulletin IS 164 W.18 Soil reaction was
bottom of the pipe equal to 0.712 times the external diam- based on the bulb theory advanced by H. C. Olander in
eter. Moments and thrusts were computed for weight of USBR Engineering Monograph No. 6.19
pipe and weight of water and for thrust due to hydrostatic Earlier in 1959, load-bearing tests on a section of 30 in.
pressure head. (760 mm) Extruda-Cast pipe had been made by the Wash-
For the condition of 20 ft (6.1 m) of earth fill, live load ington Testing Laboratories, Inc., Spokane, Wash. Tests
for AASHTO H-20-44 with impact factor of 2 and hydro- were made with various conditions of side restraint and also
static head of 10 ft (29.9 kPa), the fiber stress was found to various types of loading, that is, single edge, sand bearing,
be: and uniform loading. 12,13
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 346R-9

TABLE 2.3 - Maximum safe depths of backfill


(Computed 1977, Edib Kirdar, Salt River Project, Phoenix, Arizona)

Maximum safe backfill depth to top of pipe


ft (m)

Pipe Safe load lbf Granular soil Saturated Sand and Saturated
size (no cohesion) top soil gravel clay
*W = 100 (1600) W = 100 (1760) W = 120 (1920) W = 130 (2080)
in. (mm) lbf/1in ft KN/m Ku = 0.1924 Ku = 0.150 Ku = 0.165 Ku = 0.110

24 610 5,800 ( 84) No limit No limit No limit No limit


30 760 7,200 (105) No limit No limit No limit No limit
36 915 8,500 (124) No limit No limit No limit No limit
42 1065 9,800 (142) No limit N o limit No limit 38 (11.6)
48 1220 11,000 (160) No limit No limit No limit 30 ( 9.1)
54 1370 12,200 (178) No limit No limit No limit 26 ( 7.9)
60 1525 13,300 (193) No limit 49 (14.9) 47 (14.3) 24 ( 7.3)
66 1675 14,300 (209) No limit 36 (11.0) 30 ( 9.1) 21 ( 6.4)
72 1830 15,500 (226) No limit 32 ( 9.8) 31 ( 9.4) 21 ( 6.4)
78 1980 17,000 (247) 45 (13.7) 32 ( 9.8) 24 ( 7.3) 20 ( 6.1)
84 2135 18,000 (262) 39 (11.9) 30 ( 9.1) 24 ( 7.3) 20 ( 6.1)
90 2285 19,000 (277) 33 (10.1) 28 ( 8.5) 23 ( 7.0) 20 ( 6.1)
96 2440 20,000 (290) 32 ( 9.8) 28 ( 8.5) 22 ( 6.7) 19 ( 5.8)
102 2590 21,500 (313) 32 ( 9.8) 26 ( 7.9) 21 ( 6.4) 19 ( 5.8)
108 2745 22,600 (329) 31 ( 9.4) 24 ( 7.3) 21 ( 6.4) 19 ( 5.8)
114 2895 23,700 (346) 30 ( 9.1) 24 ( 7.3) 21 ( 6.4) 18 ( 5.5)
120 3050 25,700 (375) 29 ( 8.8) 21 ( 6.4) 20 ( 6.1) 18 ( 5.5)

* W = lb per cu ft (kg/m3 )

On the basis of these several analyses and load tests, pipes and vents, present minimum interference to traffic and
Table 2.3 was prepared and expanded to show the maxi- to travel vision, particularly at intersections.
mum safe depths of backfill in vertical-sided trenches for For additional information on surveys for sanitary and
various sizes of cast-in-place pipe. storm sewers, refer to the ASCE Manual of Engineering
Practice, No. 37, entitled “Design and Construction of San-
CHAPTER 3-DESIGN RECOMMENDATlONS itary and Storm Sewers.”

3.1-Location requirements 3.2-Hydraulic


In general, the procedures and practices followed for the 3.2.1 Head - Cast-in-place pipe is intended for use under
location of cast-in-place lines are similar to those for other a maximum head of not more than 15 ft (4.6 m) above the
pipelines. Precautions to take for installation through fills, pipe center line, including the effects of pipe surges, water
in rock or unstable ground, and in areas where the ground hammer, or other pressure rise. Concrete with the specified
water is above the bottom of the pipe are discussed in Sec- compressive strength of 3000 psi (20.7 MPa) has sufficient
tion 4.2, Excavation. tensile strength to resist somewhat higher heads. Leakage
Right-of-way requirements for cast-in-place pipelines are from even minor defects increases with head. Conse-
similar to those for other types of pipelines. The right- quently, it has been found desirable to (1) keep the operat-
of-way should be wide enough for the trench, stockpile ing head as low as possible consistent with the topography,
material, a walkway on one side of the trench, and a 12 to not to exceed 15 ft (4.6 m), and (2) use check and control
14 ft (3.7 to 4.3 m) roadway for equipment on the other. structures to limit the operating head.
Curves in horizontal alignment can be negotiated with 3.2.2 Coefficient of friction - Actual field measurements
relative ease, but angular changes in direction should be to determine the coefficient of friction of cast-in-place pipe-
avoided. The minimum radius of curvature is in general lines are limited. The Salt River Project in cooperation with
controlled by the type of excavation equipment used. The the United States Bureau of Reclamation conducted a 3-year
following formula is recommended for minimum radius: series of tests to determine the value of n in Manning’s
formula. The details and test results are contained in their
R = 30D
“Report on Resistance Coefficient Tests, Cast-in-Place
where R = radius of curvature, and D = nominal internal Concrete Pipe,” Dec. 1966. See also Reference 20. The
pipe diameter, with R and D expressed in the same units. report states that, “A total of 281 tests were made on pipes
In irrigation work, cast-in-place pipelines are frequently ranging in size from 24 to 54 in. in diameter. The roughness
laid in existing irrigation channels. Such location has the coefficient n in Manning’s formula was calculated for each
advantage of holding additional right-of-way to a minimum. set of test measurements. The n values derived ranged from
Regardless of type of pipe used, it has been found advan- 0.008 to 0.018, but 241 of the tests, or 86 percent, had
tageous in public systems, such as for irrigation districts, to values of 0.013 or less. Only 26 tests, 9 percent, gave
locate irrigation lines outside of the road right-of-way. By values higher than 0.014, the recommended n factor.”
so doing, the large open-gate structures, as well as stand- The test results indicate that an n of 0.013 may be ac-
346R-10 MANUAL OF CONCRETE PRACTICE

ceptable, however, it is recommended that a value of 0.014 lowed, thus establishing the specified minimum wall thick-
be used for the design of cast-in-place pipelines which are to ness at 1/12 of the diameter plus 1/2 in. (13 mm).
be used for low head irrigation systems until more results To insure hydraulic performance in accordance with the
become available. In the design of sanitary sewers that carry design, the actual cross-sectional area should not be less
industrial waste or other matter of low viscosity, it is rec- than nominal and the internal diameter of the pipe at any
ommended that an n value of 0.015 or higher be used. In point should not be less than specified, usually 95 percent of
selecting an n value, the designer should consider the con- the nominal diameter. Deviations from nominal diameters
dition of the pipe surface and debris that may collect in the caused by unbalanced forces on the inner forms can be
pipeline after a period of operation rather than just the sur- overcome by slightly increasing the nominal diameter of the
face conditions immediately after construction. inner forms.
3.2.3 Protection against water hammer and surges - In
irrigation lines, water hammer and surges or other pressure
variations are especially troublesome and can cause exten- CHAPTER 4-CONSTRUCTION
sive damage to cast-in-place as well as precast pipelines. RECOMMENDATIONS
Pressure drops as well as pressure rises should be carefully 4.1-General
checked; negative pressure should not be permitted. Proper Cast-in-place pipe construction uses standard methods
design of standpipes, vents, checks, and control structures and equipment except for the concrete placing machine.
can virtually eliminate damage from pressure variation. It is Even the machine needs no highly specialized operating
especially important in irrigation lines to vent all high points personnel. Only a competent foreman and a well organized
and to avoid shutoff gates in a main line unless the pipeline 4 to 6-man crew who have experience in conventional
is protected by open structures or standpipes. In cross-sec- trenching, concreting, and backfilling methods are needed.
tional area, such structures or standpipes should be at least Such a crew can easily adapt to any special techniques
equal to that of the line pipe. required. Operations required for cast-in-place pipe con-
struction are discussed below.
3.3-Structural
3.3.1 Surcharge - The maximum surcharge load to 4.2-Excavation
which a pipe should be subjected is the HS-20 live load The trench should be neatly excavated with vertical sides
defined in the American Association of State Highway and and semicircular bottom. The width of the trench should be
Transportation Officials (AASHTO) Specifications. Many equal to the outside diameter of the pipe, so that the vertical
structural analyses have been made of this loading using a side walls and trench bottom serve as an outside form for
minimum cover of 2 ft (0.6 m). The resulting fiber stresses concrete placement. Side walls above the top of the pipe
are well within allowable conditions even when surcharge may be sloped if desired, or if necessary for stability.
loads are combined with all other probable loading condi- 4.2.1 Equipment - Commonly used types of excavation
tions. equipment are wheel-type and ladder-type trench excavators
3.3.2 Foundation - The foundation for the pipe should and backhoes, which should be fitted with rounded buckets
provide full, firm, uniform support throughout each contin- suitable for excavating a semicircular-bottomed trench. Se-
uous section. Most soils are capable of providing such sup- lection is largely a matter of personal preference or utiliza-
port without special precautions. The exceptional condi- tion of equipment already available. Line and grade are
tions are generally of three types: rock, soft or spongy maintained by measuring offsets, both horizontally and ver-
materials, and expansive clays. Because of the high cost of tically, from a previously established offset line. A simple
construction in rock and in soft or spongy soils, it may inverted L-shaped jig serves satisfactorily to determine
prove more economical to alter the alignment to avoid either whether the trenching equipment is following the prescribed
condition when large quantities are encountered. Cast-in- alignment and excavating to the proper grade. Some ma-
place pipe may be satisfactorily installed through any of chines are fitted with “feeler fingers” into which the offset
these conditions provided the appropriate special measures line wire must fit to maintain the desired alignment and
described in Section 4.2 are followed: grade. If the wire falls outside these fingers, appropriate
3.3.3 Pipe dimensions - Wall thicknesses for cast- adjustments must be made on the equipment before resump-
in-place pipe have been established more by custom than by tion of trenching operations. Other methods are used, but
design. In the early days of precast concrete pipe, manu- they are not as simple as the two mentioned above.
facturers of so-called “poured pipe,” in which concrete A common practice is to assign one piece of excavation
was spaded between vertical steel forms, used wall thick- equipment to each spread and to use it for other purposes
nesses of 1/12 of the internal diameter of the pipe plus 1 in. when not required for excavation. It may serve both as a
(25 mm). This practice seems to have been rather generally deadman to which the winch cable is attached to move the
adopted by the cast-in-place pipe constructors and has pipe casting machine forward and as a crane to lift the
proved adequate to meet the load and head conditions gen- machine into and out of the trench. A backhoe requires no
erally encountered. In recent years, technical studies and modifications to serve satisfactorily as a crane, but booms
load tests (see Section 2.2) also have demonstrated the ad- must be added to trenchers if they are to be used for this
equacy of the wall thicknesses in general use. purpose. Sometimes a separate mobile crane is provided.
To allow some leeway in casting concrete pipe, a de- Various types of equipment may be assigned to the work
crease of 1/2 in. (13 mm) in wall thickness is usually al- and each type has a number of different uses.
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 346R-11

4.2.2 Rate of advance - Normally the concrete placement of the trench which will serve as the outer form for at least
and form removal time exceed that for excavating the same the bottom 210 deg of the pipe (see Fig. 1.1). It should be
length of trench. Therefore, the rate of advance of the fin- excavated to the lines and grades established by the Spec-
ished pipe is generally controlled by the speed at which the ifier and should be prepared to provide full, firm, and uni-
machine can be moved and the time required to remove the form support of the pipe by undisturbed earth or compacted
inner forms. This accounts for the other uses of the exca- fill.
vation equipment previously discussed. It may prove pref- 4.2.6.1 Trench cleanup - The excavator normally digs a
erable for some projects to shift the excavators from one neat, clean trench suitable without further work for place-
location to another and keep them fully productive. In this ment of concrete. It will be necessary to remove from the
case, the number of excavators required would be deter- trench bottom any debris, foreign objects, or material from
mined by the output capabilities of the equipment and the side wall sloughing before starting concrete placement. The
time required to change locations. machine fits the trench so closely that occasionally, as it
4.2.3 Length of trench ahead of placement - The length moves forward, it scrapes the side walls and causes some
of trench to be excavated ahead of concrete placement, or sloughing. Care must be exercised to prevent this sloughed
excavation “headway,” is largely a matter of judgment. material from building up ahead of the machine and causing
Under normal circumstances the trench headway will be excessive departure from established grade. Where the
roughly equal to the amount of form to be withdrawn from metal inner form is used, excess material can be manually
the previous placement or the length of pipe to be placed removed ahead of the slipform. With either method of con-
during the following shift. Headway is often limited to pre- struction, small transverse ditches may be excavated across
vent drying of the trench walls and bottom against which the trench bottom to receive soil built up and pushed ahead
concrete is to be placed, because rapid absorption of the of the slipform.
water from the concrete can cause excessive cracking. Since 4.2.6.2 Trench moisture - Care should be taken to in-
dry trench walls can be moistened by sprinkling immedi- sure that at the time of concrete placement there is adequate
ately prior to concrete placement, this criterion is of sec- moisture in the trench form so that water is not drawn from
ondary importance. Construction should not be unnecessar- the freshly placed concrete. If the trench is too dry, all soil
ily restricted by arbitrary headway requirements, if in contact with the concrete should be moistened. However,
satisfactory alternatives can be agreed upon. The best rule the trench form must be free of water and mud at the time
to apply to headway is to keep excavation ahead of pipe of concrete placement.
fabrication by a distance sufficient to avoid interference 4.2.7 Rock and unstable materials - When it is necessary
with concrete placement. to install the pipe in rocky areas, the rock should be re-
4.2.4 Trench stability - From experience in a great vari- moved and replaced with suitable fill material compacted to
ety of soils, it appears that from a standpoint of trench proper density. The rock shall be removed to at least 6 in.
excavation most soils are suitable for installation of cast- (150 mm) below the grade of the bottom of the pipe. Areas
in-place pipe. With either a backhoe or a trencher, it usually left void by rock removal should be completely filled with
is possible to excavate trenches that are true, neat, and clean compacted material, then trenched for the pipe as though
with a minimum requirement for fine grading. Subsequent natural ground. If the rock below the pipe subgrade is frac-
sections deal with special treatments required in unstable tured or fragmented, or if it consists of large cobblestones or
soils. boulders, the replacement fill material should be carefully
In areas known to be excessively sandy, it is good prac- selected to insure that it is of such gradation that it will not
tice to excavate short test sections of trench with a small rig be moved downward by fluctuation of the water table. In no
to observe the action of the soil under actual trench condi- case should expansive soils be used for fill.
tions. A small backhoe mounted on a tractor has been found A procedure of over-excavation, backfill, compaction,
useful for this purpose. Some sandy soils show little or no and retrenching should be used where sloughing sand or soft
tendency to slough if moist. For other sandy soils, a slight or spongy conditions are encountered. Unstable trench
slope in the side walls may prevent excessive sloughing. If walls may be shored if necessary, but this will reduce the
these measures do not produce the required stability it is pipe production rate. When expansive clays are encoun-
necessary to replace the sand in the trench form with com- tered, they should be thoroughly moistened by ponding, to
pacted soil, as provided in Section 4.2.7, or substitute an- completely expand the soil, and the moisture maintained
other type of pipe. until the concrete is placed.
4.2.5 Prewetting - In areas where the soils are too hard 4.2.8 Groundwater control - Where the water table is
for efficient trenching or where additional moisture adds to above the grade line for the bottom of the pipe it is neces-
the trench stability, trench excavation may be simplified by sary to dewater the trench. In some cases, pumping from
prior wetting. Prewetting may be accomplished by either of sumps in the bottom of the trench will adequately control
two methods or a combination of both. One method is to the inflow. In other cases, it may be necessary to lower the
apply water just as though the land were being irrigated, by water table by pumping from wells located along both sides
either furrow, flood, or sprinkler irrigation. The second of the trench. Sometimes systems as elaborate as well points
method, often used in areas where large quantities of water may be required. Gravel or crushed rock may be used as a
are difficult to obtain, is to run water in a single ditch along French drain by over-excavation and placing to grade.
the center line of the pipe. Drain tile may be required in the gravel or crushed rock if
4.2.6 Trench form - The “trench form” is that portion large amounts of water are encountered. The gravel or
346R-12 MANUAL OF CONCRETE PRACTICE

crushed rock must be compacted to provide a satisfactory 4.3.3 Shrinkage and contraction - Satisfactory cast-in-
surface on which to place concrete. place concrete pipe is generally achieved without special
consideration of shrinkage and contraction. Ready-mixed
4.3-Concrete control and placement concrete or job-mixed concrete which is satisfactory in
The satisfactory performance of cast-in-place concrete other respects generally does not exhibit excessive cracking
pipelines requires concrete that is consistently watertight due to drying shrinkage and temperature contraction.
and durable, and has the necessary compressive strength. Any large cracks which do occur can be most easily
Such concrete may be readily obtained with proper attention patched with cement mortar within a few days after casting
to mix proportioning, with adequate testing to insure quality because bond is then most easily achieved. If epoxy mate-
control, and with proper placement and curing. Proportion- rials are used for patching, they appear to give best results
ing shall be according to ACI 211.1. if applied at a later time, preferably two weeks or more after
4.3.1 - Materials concrete is cast.
4.3.1.1 Portland cement - Portland cement should Occasionally, circumstances occur which produce an un-
meet the requirements of ASTM standard specifications for satisfactory amount of cracking or there will be a job where
portland cement, C 150. Where soils or waters contain it is desired to reduce leakage to an absolute minimum. In
150-1500 ppm of sulfates, Type II cement or a portland such cases, it is advisable to reduce cracking, drying shrink-
cement with a C3A content of not more than 8 percent age, and thermal contraction by some of the following
should be specified. For more than 1500 ppm of sulfates a practices:
Type V cement or a portland cement with not more than 5 • Reduce water content of the mix.
percent C3A should be specified, and the water-cement • Establish optimum curing practices to retain mixing
ratio should not exceed 0.50. Portland blast furnace slag water.
cement [ASTM C 595, Type IS (MS)] or portland pozzolan • Minimize temperature drop.
cement (ASTM C 595, Type IP) also may be used for such • Adjust mix proportions.
exposures. For such severe exposures (1500 ppm or more) • Use selected aggregates if economically feasible.
if none of those indicated is available, a cement with a C 3A Unit water content is least when the mix contains the least
content between 5 and 8 percent may be used with a amounts that are feasible of cement and sand, and the larg-
water-cement ratio not exceeding 0.45, or with a est practicable size of coarse aggregate. Water content
substitution by weight of pozzolan (ASTM C 618) for such should be reduced by using the lowest slump that can be
cement, not to exceed 25 percent by total weight of cement fully consolidated as the pipe concrete is placed. Use of air
plus pozzolan. Where aggregates are alkali-reactive a entrainment, well graded aggregate, water-reducing chem-
cement containing less than 0.60 percent alkalies should be ical admixtures, and fine materials when sands are deficient
specified. in fines also can reduce water requirement. Admixtures
4.3.1.2 Aggregates - Aggregates should meet the re- which increase shrinkage should be avoided. Proper mix
quirements of ASTM C 33. Gradation and maximum size of proportions using any or all of these ingredients must be
aggregates are important because of their effect on mix established by trial mixes. To minimize shrinkage cracks,
proportions, water requirement, workability, cohesiveness, early drying of the concrete from all surfaces must be pre-
and finishing characteristics of the concrete. In general, vented. Having adequate moisture in the trench form pre-
good workability, cohesiveness, and finishing characteris- vents drying from the lower part of the outer surface, and
tics can be obtained when 15 to 30 percent of the fine the curing practices, including moist backfill, prevent dry-
aggregate passes the No. 50 (300 µm) sieve and 3 to 7 ing of the upper part of the outer surface. Bulkheading and
percent passes the No. 100 (150 µm) sieve. Coarse aggre- the introduction of water in the invert will prevent drying of
gate should be graded up to the largest size used. This the inner surface.
reduces the amount of mortar used and can result in lower To minimize thermal shrinkage the concrete should be
cost, less temperature rise, and less drying shrinkage. mixed, placed, and cured at the lowest possible temperature
4.3.1.3 Admixtures - An air-entraining admixture, con- allowed in Section 7.3 of the specifications so that subse-
forming to ASTM C 260, should be used unless air-en- quent temperatures of the pipe in service will not be appre-
training portland cement is used. (See Specifications Sec- ciably lower than the highest of these initial temperatures.
tion 4.4.) Any other chemical admixture used should meet Low early temperatures can be attained by doing the work
the requirements of ASTM C 494. Fly ash or pozzolans, if in the coldest available weather above freezing, working
used, should meet the requirements of ASTM C 618. All during the cooler part of the day, and shading the trench to
admixtures should be used only in accordance with ACI keep surfaces against which concrete is to be placed as cool
212.1R/ACI 212.2R. as possible. Mixing and placing concrete at low tempera-
4.3.2 Slump - The contractor should be allowed to select tures can also be accomplished by substituting ice for part of
the slump of the concrete while maintaining the required the mixing water, keeping moisture low in aggregate to
water-cement ratio because of the considerable difference permit using more ice, and shading aggregate to reduce
in slump that may be required by different types of temperature of the aggregate the day it is used.
equipment. The required slump also may vary somewhat in Mixture proportions which achieve slow strength gain,
accordance with local project conditions. To help minimize combined with extended curing at low temperatures, are
shrinkage cracking, the lowest usable slump should be effective in reducing volume change cracking. High-early-
maintained. strength cement should be avoided unless early strength is
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 346R-13

essential. Where early service after construction is not re- (k) When crossing or digging near electrical lines, care
quired, some of the principles of mass concrete can be should be taken to avoid contact by equipment and person-
applied. For example, strength may be specified at 90 days nel.
instead of 28 days, thereby permitting the use of mixtures (l) Bracing or shoring should be provided where needed
with less heat of hydration, that is, mixtures containing less to protect workmen exposed to danger of moving ground
cement, cements with less heat of hydration (Type II rather and as required by applicable codes and regulations.
than Type I), or a combination of cement and pozzolan with (m) All utility companies or others who may have under-
less total heat of hydration. ground facilities in the area should be notified of the project
and given sufficient notice so that they can locate and mark
4.4-Backfill and clean-up their facilities prior to the beginning of excavation.
4.4.1 Agricultural installation - Where the pipe is used
for agricultural purposes and subject only to loads due to 5.2-Inspection
agricultural equipment, backfill should be uniformly placed During the construction of cast-in-place concrete pipe-
to the approximate density of the surrounding soil. A slight lines, the following procedures are recommended for in-
mounding over the trench may be desirable to compensate spectors:
for additional or subsequent settlement of the backfill. 5.2.1 - Check alignment and grade, to ensure that the
4.4.2 Urban installations - Where the pipe is installed in tolerances of Specifications Section 3.7 are adhered to.
a city street, the backfill should be placed and compacted in 5.2.2 - Check condition of trench, including just before
accordance with local requirements or as directed by the concrete placement, to ensure that the provisions of Spec-
engineer. ifications Sections 3.1 through 3.6, inclusive, are adhered
4.4.3 Clean-up - The work area should be restored to the to.
same general condition that existed before the start of con- 5.2.3 - Measure and record temperature of the concrete
struction. as specified in specification Section 7.3 and take slump tests
as necessary for control, as provided in Specifications Sec-
tions 6.4 and 9.2.7. Concrete with a slump higher than
CHAPTER 5-SAFETY AND INSPECTION required may produce pipe with a rough interior, reduce the
5.1-Safety compressive strength of the concrete, and increase shrink-
All applicable codes and regulations should be observed age.
including the following: 5.2.4 - Take at least two 6 x 12 in. (150 x 305 mm) test
(a) Safety helmets and glasses should be worn by all cylinders for the first 50 cu yd (38 m 3) and at least two
persons working in or around the pipe casting machine. 6 x 12 in. (150 x 305 mm) test cylinders for each additional
This also pertains to personnel who remove the forms from 50 cu yd (38 m3) or portions thereof for each day’s work.
inside the pipeline. Measure and record the slump of each concrete sample as
(b) Gloves should be worn by workers handling forms provided in specification Sections 9.2.4 and 9.2.5.
and concrete chutes. 5.2.5 - Check the dimensions of the cast-in-place pipe
(c) Ear plugs should be used where excessive noises may machine prior to its use. Monitor wall thickness where
injure hearing. possible around the periphery of the pipe as casting
(d) An air blower of sufficient size should be used to progresses.
adequately ventilate the pipeline while men are in the pipe 5.2.6 - Be sure that the freshly placed flow line area
to remove forms, and when repair work or inspection of below the metal forms is troweled if necessary to obtain a
pipeline is in progress. smooth finish.
(e) The pipe machine operator should not wear loose 5.2.7 - Where possible, inspect the interior of the pipe
clothing. from the inside of the machine frequently. Excessive boil
(f) Workers should not be permitted in the open excava- at the bottom of the metal forms will cause a horizontal
tion during the operation of the machine or when the winch ridge.
cable is in tension. 5.2.8 - Be sure that the top of the pipe is properly pro-
(g) The winch cable should be inspected prior to every tected to prevent rapid dehydration, as provided in specifi-
use for burrs or parted strands. If the cable is found dam- cations Sections 8.1.
aged, it should be replaced before further use. 5.2.9 - At the completion of each placement, close the
(h) The engine and fuel system should be inspected daily ends of the pipe with heavy canvas or equivalent to prevent
during use to ensure that no fuel or exhaust leakage is oc- drying of the fresh concrete, as provided in specifications
curring. Section 8.1.
(i) Proper methods and cables should be used to lift the 5.2.10 - Inspect the interior of the pipe as soon as the
pipe machine in and out of excavations. forms are removed. Check for voids, for form lap indenta-
(j) When crossing or digging near gas pipelines, care tion, interior pipe dimension and smoothness in the flowline
should be taken to prevent rupture of such lines. The gas area where troweling is required. Any necessary repairs to
may enter concrete pipelines and create a hazard. If pipe- the pipe should be made promptly.
lines are constructed in the vicinity of gas lines, a gas de- 5.2.11 - Stay close to the operation and remain alert. The
tector should be used to assure that there is no explosive gas success of the operation and the end result may depend on
in the line. how well the inspector does his job.
346R-14 MANUAL OF CONCRETE PRACTICE

CHAPTER 6-EQUIPMENT CONSIDERATIONS CHAPTER 7-REFERENCES


6.1-General 7.1-Specified and/or Recommended References
Anticipating problems and having a remedy on hand can
result in substantial cost savings. A common concert of The documents of the various standards-producing orga-
those installing cast-in-place pipe is that equipment might nizations referred to in this document are listed below with
fail during the concrete placement process. If the equipment their serial designation.
cannot be repaired quickly, the result may be the waste of American Concrete Institute
concrete that is on the job or in transit. Many times these 211.1-81 Standard Practice for Selecting Propor-
problems can be avoided by using good inspection and tions for Normal, Heavyweight and Mass
maintenance practices. Concrete
212.1R/212.2R Admixtures for Concrete and Guide for
Use of Admixtures in Concrete
6.2-Cleanliness 346-90 Standard Specification for Cast-in-Place
It is very important that equipment be cleaned immedi- Nonreinforced Concrete Pipe
ately after placement, before concrete hardens. Special at- ASTM
tention should be paid to the mandrel, tampers, and any C 33 Specification for Concrete Aggregate
other parts that come in contact with concrete during the C 76 Specification for Reinforced Concrete
operation. This is commonly done by removing the machine Culvert, Storm Drain, and Sewer Pipe
from the trench and washing it. C 150 Specification for Portland Cement
C 260 Specification for Air-Entrained Admix-
tures for Concrete
6.3-Inspection and maintenance C 494 Specification for Chemical Admixtures
Problems are often avoided by simply checking equipment for Concrete
prior to use. Inspection of the machine should include check- C 595 Specification for Blended Hydraulic Ce-
ing of rollers on the mandrel, mandrel seal, oilers, motors ments
and hoses. Power unit inspection should include oil, water, C 618 Specification for Fly Ash and Raw or Cal-
fan belts, battery, fuel, hydraulic fluid, winch and cable. cined Natural Pozzolan for Use as Min-
eral Admixture in Portland Cement Con-
crete
6.4-Metal forms The above publications may be obtained from the following
Excess concrete should be removed from forms immedi- organizations:
ately after stripping. This is commonly accomplished by
American Concrete Institute
hitting the form lightly with a spreader stick or other tool.
P.O. Box 19150
Forms should be checked for loose or broken hardware,
Detroit, MI 48219
bends, dents or tears prior to coating for reuse. This inspec-
tion should preclude use of forms that might jam in the American Society for Testing and Materials
machine or fail during concrete placement. It is very im- 1916 Race
portant that the forms be properly coated with a good form St. Philadelphia, PA 19103
release material, just prior to inserting in to the machine. A
program for keeping forms in proper curvature is also im- 7.2-References
portant in avoiding problems during placement and strip- 1. “Loads and Minimum Cover for Cast-in-Place Unreinforced Con-
ping operations. crete Pipe,” Salt River Project, Phoenix, 1960.
2. Esvelt, John P., “The Load-Bearing Strength of ‘Extruda-Cast’
Pipe,” R. A. Hanson, Company, Inc., Spokane, 1961.
3. “Sand Bearing Test on Field Installation of 54-in. No-Joint Pipe,”
6.6-Trenching equipment City of Phoenix, Arizona, 1962.
Inspection of bucket dimensions, wear and setting of 4. “Load Testing of No-Joint Cast-in-Place Concrete Pipe,” Public
bucket digging teeth should be made prior to and during Works Department, Division of Engineering, Phoenix, 1963.
5. Gabriel, L. H., “Load Testing of 72-in. Diameter No-Joint Cast-
excavation. This will help insure proper trench width and
in-Place Concrete Pipe with Shallow Cover,” Sacramento State College
eliminate two possible problems. A trench which is too Foundation, Mar. 13, 1964.
wide will cause excessive use of concrete and possible tip- 6. Shipley, H., “Cast-in-Place Pipe for Irrigation,” Western Construc-
ping of the machine. Worn teeth or a warped bucket result tion, V. 32, No. 11, Nov. 1957.
in a trench that is so narrow that the machine cannot move 7. Fortier, E. C., “Cast-in-Place Concrete Pipe Cuts Time and Costs,”
Civil Engineering - ASCE, V. 31, No. 12, Dec. 1961, pp. 65-67.
freely.
8. Campbell, T. C., “Cast-in-Place Drainage Pipe Proves to be the
Money Saving Way to Provide Drainage in Fast Urbanizing Sacramento
County,” The American City, V. 81, No. 12, Dec. 1966, pp. 100-102.
6.6-“Deadman” Anchor 9. Fortier, E. C., “Large Diameter Non-Reinforced Cast-in-Place Con-
No single type of “deadman” is always effective in ev- crete Pipe,” ACI JOURNAL , Proceedings V. 65, No. 7, July 1968, pp.
544-549.
ery type of soil. If a “deadman” begins to fail, a piece of
10. Darden, Wesley F., “Use of Cast-in-Place Concrete Pipe in Sac-
equipment on the job site may be used to secure the winch ramento County, California,” Department of Public Works, County of
cable so that concrete placement can be completed. Sacramento, 1969.
RECOMMENDATIONS FOR CAST-IN-PLACE PIPE 346R-15

11. Etheridge, David C., “Three-Element Forming Speeds Concrete ations in Testing Procedures,” Proceedings, ASTM, V. 57, 1957, pp.
Pipe Job,” Construction Methods and Equipment, V. 55, No. 12, Dec. 1122-1142.
1973, pp. 54-56. 18. “Analysis of Arches, Rigid Frames, and Sewer Sections,” Infor-
12. Marston, A., “The Theory of External Loads on Closed Conduits mation Sheet IS164W, Portland Cement Association, Skokie, 1942, 16 pp.
in the Light of the Latest Experiments,” Bulletin No. 96, Engineering 19. Olander, H. C., “Stress Analysis of Concrete Pipe,” Engineering
Experiment Station, Iowa State College, Ames, 1960. Monograph No. 6, U.S. Bureau of Reclamation, Denver, Oct. 1950, 13 pp.
13. Spangler, M. G., “Underground Conduits-An Appraisal of Mod- 20. Wilson, Thomas T., Jr., and Kirdar, Edib, “Manning for Cast-
ern Research,” Transactions, ASCE, V. 113, 1948, pp. 316-345; discus- in-Place Concrete Pipe,” Proceedings, ASCE, V. 95, HY3, May 1969,
sion, pp. 346-374. pp. 995-1007.
14. Breitfuss, Thomas K., “Loads and Supporting Strengths for Con- 21. “Guamuchil Project. Cast-in-Place Pipe. Evaluation Report and
Crete Pipe Lines,” American Concrete Pipe Association, Vienna, Va., Specification Review,” International Engineering Company, Inc., San
1957, 29 pp. Francisco, 1965.
15. Paris, James M., “Stress Coefficients for Large Horizontal Pipes,” 22. Corbin, V. Earl, “Cracking Patterns in Cast-in-Place Pipe,” Salt
Engineering News-Record, V. 87, No. 19, 1921, pp. 768-771. River Project in Cooperation With U.S. Department of the Interior, Bureau
16. Kesler, Clyde C., “Statistical Relation Between Cylinder, Modi- of Reclamation, Oct. 30, 1970.
fied Cube and Beam Strength of Plain Concrete,” Proceedings, ASTM, V. These proposed revisions were submitted to letter ballot of ACI Com-
54, 1954, pp. 1178-1186. mittee 346 and were approved in accordance with ACI balloting require-
17. “Studies of Flexural Strength of Concrete-Part 3: Effects of Vari- ments.

You might also like