Bangalore Water Supply & Sewerage Board Section 7 – Specifications

Contents
PART 2 .................................................................................................................................................... 2 
THE SITE ................................................................................................................................................ 2 
2.1  Location of the Sites ................................................................................................................ 2 
2.2  Access to the Sites ................................................................................................................... 2 
2.2.1  Kaggadasapura STP ................................................................................................................ 2 
2.3  Maintenance of the Site ........................................................................................................... 3 
2.4  Areas outside the Site .............................................................................................................. 3 
2.5  Road Works ............................................................................................................................. 3 
2.6  Maintenance of Existing Access Roads .................................................................................. 4 
2.7  Clearance of the Site................................................................................................................ 4 
2.8  Clearance and Reinstatement of the Site on Completion of the Works .................................. 5 
2.9  Access for the Employer and Engineer ................................................................................... 5 
2.10  Water Supply at Site ................................................................................................................ 5 
2.11  Toilets, Latrines, Washing Facilities, and Wastewater Disposal ............................................ 5 
2.12  Electricity for Contractor's Use on Site ................................................................................... 5 
2.13  Camp Facilities ........................................................................................................................ 6 
2.14  Compressed Air Use on Site.................................................................................................... 6 
2.15  Refuse Disposal on Site ........................................................................................................... 6 
2.16  Safety and Security on Site ..................................................................................................... 6 
2.17  First Aid and Life-saving Apparatus on Site ........................................................................... 7 
2.18  Electrical Safety on Site .......................................................................................................... 8 
2.19  Noise........................................................................................................................................ 8 
2.20  Warning and Safety Signs ....................................................................................................... 8 
2.21  Site Working Hours ................................................................................................................. 8 
2.22  Delivery to Site ........................................................................................................................ 8 
2.23  Protection from Weather and Storage ..................................................................................... 9 
2.24  Contract Signboards .............................................................................................................. 10 
2.25  Advertising ............................................................................................................................ 10 

Part 2: The Site 2-1 Bid Document


Bangalore Water Supply & Sewerage Board Section 7 – Specifications

PART 2

THE SITE
2.1 Location of the Sites

Details of the STP site location are shown in drawing

2.2 Access to the Sites

The Employer will afford to the Contractor access to and possession of the Site for carrying out the
Works. The Contractor shall be deemed to have inspected the STP Site including access before
submitting his Bid.

The Contractor shall ensure that all the plant components offered are of a size and weight or can be
divided into sections of a size and weight suitable for access to the place of installation.

The Contractor shall ensure that equipment used for installation purposes shall be able to gain access
and position for such purposes.

2.2.1 Kaggadasapura STP

The new plant is to be constructed within the Lake premises for which approach is available from CV
Raman Nagar Road. This road is suitable for heavy goods vehicles used.

The premises covers an area of Approx 2.5Acres,

Part 2: The Site 2-2 Bid Document