标识号 Task Complete Duration Start Finish 前置任务 2020年3月 2020年4月 2020年5月 2020年6月 2020年7月 2020年8月 2020年9月

Percent 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20
1 SCHEDULLE_BOYACA TANKS "6 CCT + 1 DAW - 0301 0% 190 days 2020/2/19 2020/9/26
2 LOI confirmation 100% 1 day 2020/2/19 2020/2/19
3 Signed contract -abi 0% 1 day 2020/3/25 2020/3/26 22SS-30 days
4 Civil ready for site construction-abi 0% 1 day 2020/6/13 2020/6/13 43SS-2 days
5 Civil ready for tank location-abi 0% 1 day 2020/2/19 2020/2/19
6 PREPARATION IN LEHUI WORKSHOP 0% 174 days 2020/2/20 2020/9/9
7 6 CCT 4000hl + 1 DAW 0% 130 days 2020/2/20 2020/7/20
8 Design and confirmation 0% 8 days 2020/2/20 2020/2/28
9 Drawing design 0% 6 days 2020/2/20 2020/2/26 2
10 Drawing confirmation 0% 3 days 2020/2/27 2020/2/29 9
11 Drawing dispatch (ERP+WPS+ITP) 0% 7 days 2020/3/2 2020/3/9 10
12 Procument 0% 70 days 2020/2/27 2020/5/18
13 Main materials 0% 10 days 2020/2/27 2020/3/9 9
14 Piping 0% 30 days 2020/3/10 2020/4/13 11
15 Fittings 0% 60 days 2020/3/10 2020/5/18 11
16 Manufacturing 0% 54 days 2020/2/27 2020/4/29
17 Vessel manufacturing 0% 48 days 2020/2/27 2020/4/22 9
18 Factory Acceptance Test 0% 3 days 2020/4/23 2020/4/25 17
19 Package and cleaning before shipping 0% 3 days 2020/4/27 2020/4/29 18
20 Transportation 0% 114 days 2020/4/30 2020/9/9
21 1st batch(6 CCTs in pieces) 0% 53 days 2020/4/30 2020/6/30
22 FOB China port 0% 2 days 2020/4/30 2020/5/1 19
23 CIF 0% 45 days 2020/5/2 2020/6/23 22
24 Custom clearance(by customer) 0% 3 days 2020/6/24 2020/6/26 23
25 DAP site 0% 3 days 2020/6/27 2020/6/30 24
26 2nd batch(PIR) 0% 53 days 2020/5/20 2020/7/20
27 FOB China port 0% 2 days 2020/5/20 2020/5/21
28 CIF 0% 45 days 2020/5/22 2020/7/13 27
29 Custom clearance(by customer) 0% 3 days 2020/7/14 2020/7/16 28
30 DAP site 0% 3 days 2020/7/17 2020/7/20 29
31 3rd batch(1 DAW in whole part) 0% 53 days 2020/7/10 2020/9/9
32 FOB China port 0% 2 days 2020/7/10 2020/7/11
33 CIF 0% 45 days 2020/7/13 2020/9/2 32
34 Custom clearance(by customer) 0% 3 days 2020/9/3 2020/9/5 33
35 DAP site 0% 3 days 2020/9/7 2020/9/9 34
36 4th batch(steel structure) 0% 53 days 2020/5/20 2020/7/20
37 FOB China port 0% 2 days 2020/5/20 2020/5/21
38 CIF 0% 45 days 2020/5/22 2020/7/13 37
39 Custom clearance(by customer) 0% 3 days 2020/7/14 2020/7/16 38
40 DAP site 0% 3 days 2020/7/17 2020/7/20 39
41 MECHANICAL ASSEMBLY ON SITE 0% 89 days 2020/6/16 2020/9/26
42 Mobilization / Preparing the Assembly Area 0% 10 days 2020/6/16 2020/6/26
43 Mobilization / Preparing the Assembly Area 0% 10 days 2020/6/16 2020/6/26 25SS-10 days
44 TANKS 6 CCT 4000 HL - Boyaca 0% 62 days 2020/7/1 2020/9/10
45 Assemble cones 0% 6 days 2020/7/1 2020/7/7 25
46 Assemble dish head 0% 6 days 2020/7/11 2020/7/17 45 LEHUI
47 Assemble shells 0% 25 days 2020/7/18 2020/8/15 46
48 Erection 0% 3 days 2020/8/17 2020/8/19 47
49 Install steel structure 0% 2 days 2020/8/20 2020/8/21 48
50 Erect DAW 0% 1 day 2020/9/10 2020/9/10 35,30
51 HYDRO - TEST 0% 6 days 2020/8/22 2020/8/28
52 CCT TQ 001# 0% 1 day 2020/8/22 2020/8/22 49
53 CCT TQ 002# 0% 1 day 2020/8/24 2020/8/24 52
54 CCT TQ 003# 0% 1 day 2020/8/25 2020/8/25 53
55 CCT TQ 004# 0% 1 day 2020/8/26 2020/8/26 54
56 CCT TQ 005# 0% 1 day 2020/8/27 2020/8/27 55
57 CCT TQ 006# 0% 1 day 2020/8/28 2020/8/28 56
58 INSULATION 0% 26 days 2020/8/27 2020/9/25
59 CCT TQ 001# 0% 3 days 2020/8/27 2020/9/10 52FS+3 days
60 CCT TQ 002# 0% 3 days 2020/9/11 2020/9/14 59
61 CCT TQ 003# 0% 2 days 2020/9/15 2020/9/16 60
62 CCT TQ 004# 0% 3 days 2020/9/17 2020/9/19 61
63 CCT TQ 005# 0% 3 days 2020/9/21 2020/9/23 62
64 CCT TQ 006# 0% 2 days 2020/9/24 2020/9/25 63
65 HANDOVER TO ABI PIPING CONTRACTOR 0% 14 days 2020/9/11 2020/9/26
66 CCT TQ 001# 0% 1 day 2020/9/11 2020/9/11 59
67 CCT TQ 002# 0% 1 day 2020/9/15 2020/9/15 60
68 CCT TQ 003# 0% 1 day 2020/9/17 2020/9/17 61
69 CCT TQ 004# 0% 1 day 2020/9/21 2020/9/21 62
70 CCT TQ 005# 0% 1 day 2020/9/24 2020/9/24 63
71 CCT TQ 006# 0% 1 day 2020/9/26 2020/9/26 64