You are on page 1of 7

4164 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO.

6, NOVEMBER/DECEMBER 2014

Evaluating Generator Circuit Breakers Short-Circuit


Duty Using IEEE C37.010 and C37.013
Ketut Dartawan, Member, IEEE, and Conrad St. Pierre

Abstract—This paper describes a procedure for calculating


generator circuit breaker duty. Currently, commercially available
software products help in determining the duty for a general-
purpose circuit breaker. However, further calculations are needed
to determine the duty for a special-purpose generator circuit
breaker. IEEE Std C37.010-1999 provides the calculation proce-
dure for general-purpose circuit breakers. In order to evaluate a
special-purpose generator circuit breaker, this paper will expand
the steps and methodology used in IEEE C37.010-1999 by pre-
senting a procedure and detailed calculations for finding a duty
multiplication factor based on the test X/R ratio of generator
circuit breakers given in IEEE C37.013-1997 (Standard for AC
High-Voltage Generator Circuit Breakers Rated on a Symmetrical
Current Basis). This way, engineers can still make a generator
circuit breaker assessment although generator circuit breaker
evaluation module is not included in many commercial short-cir-
cuit programs.
Index Terms—AC generators, circuit breakers, IEC Standards, Fig. 1. DC component at contact parting time (CPT) for General-Purpose
IEEE Standards, interrupters, synchronous generators. and Generator Rated Circuit Breakers. (Notes: DC component in percentage
is based on the peak value of a symmetrical three-phase current. The circuit
breaker CPT includes 0.5 cycle, or 8.33 ms, protective relay time).
I. I NTRODUCTION
to differ from the method given in IEEE C37.010-1999 in

T HE ANSI/IEEE Standard that specifies a symmetrical


current basis for testing, rating, and application of circuit
breakers was first issued in 1964. The standard represented
section 6.3.2. In the latter standard, separate R and X network
reductions are used in the calculation of the dc component
current. Both IEEE C37.010-1999 and IEC-60909 [12] indicate
a change from using the total current as a basis for circuit that the X/R ratio taken from the complex math jX/R ratio is
breaker ratings to a new symmetrical current basis. It is now not conservative for the calculation of the dc component.
approaching 50 years since total current basis circuit breakers The circuit breaker duty analysis will require examination
were last manufactured and the standard has evolved further. of both the circuit breaker’s peak current (closed and latched)
The most recent circuit breaker application guide is and interrupting time duties. This paper discusses several ap-
IEEE C37.010-1999 [11]. This guide focuses on the application proaches that have different levels of conservatism for the peak
of symmetrically rated circuit breakers, specifically general- and interrupting time calculations based on IEEE C37.010 and
purpose circuit breakers that are tested at a lower X/R ratio C37.013.
than generator circuit breakers. However, a stand-alone appli-
cation guide specifically for the application of generator rated
II. S YMMETRICAL AND A SYMMETRICAL R ATINGS OF THE
circuit breakers is not available. Some application information
C IRCUIT B REAKERS AND M ULTIPLICATION FACTOR
is provided in the Annex of IEEE C37.13-1997 [13], but in this
paper, the method for determining the fault X/R ratio appears Fig. 1 gives the amount of dc that is included in the circuit
breaker design for the general-purpose and generator rated
Manuscript received January 30, 2012; revised April 26, 2013, March 6,
circuit breakers. The faster the circuit breaker opens, the more
2014, and April 2, 2014; accepted April 27, 2014. Date of publication May 6, dc is included for the same symmetrical current rating. The
2014; date of current version November 18, 2014. Paper 2012-CSC-023.R3, generator circuit breaker has a greater dc component because
presented at the 2012 IEEE/IAS Industrial and Commercial Power Systems
Technical Conference, Louisville, KY, USA, May 20–24, and approved for
the fault current from the generator is likely to have a long dc
publication in the IEEE T RANSACTIONS ON I NDUSTRY A PPLICATIONS by decay rate (high X/R ratio).
the Codes and Standards Committee of the IEEE Industry Applications Society. The application of IEEE C37.010-1999 for generator circuit
K. Dartawan is with Pterra Consulting, Albany, NY 12205 USA (e-mail:
KetutDartawan@Pterra.us). breakers requires an understanding of Figs. 8–10, which present
C. St. Pierre is with Electric Power Consultants, LLC, Schenectady, NY multiplication factors for symmetrically rated circuit breakers.
12303 USA (e-mail: Conrad@capital.net). The curves provided in IEEE C37.010-1999. Figs. 8–10 have
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. their basis on the total current (ac and dc) fault curves
Digital Object Identifier 10.1109/TIA.2014.2322132 given in Annex A, in Figs. A.5 and A.9. The basis for the
0093-9994 © 2014 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
DARTAWAN AND PIERRE: EVALUATING CIRCUIT BREAKERS DUTY USING IEEE C37.010 AND C37.013 4165

TABLE I
C IRCUIT B REAKER R EQUIRED A SYMMETRICAL C APABILITY FOR
G ENERAL -P URPOSE AND G ENERATOR R ATED C IRCUIT B REAKERS

multiplication factors is the total symmetrically rated curves


with an adjustment multiplier, i.e., the “S-factor,” where
ISYM MF = ITOTAL MF/S-factor.
The S-factor is the ratio of total current to symmetrical
current. The S-factor is not included in IEEE C37.010-1999,
but it is in IEEE C37.010-1979 [16] in Fig. 4. Fig. 2. Remote three-phase multiplication factors for generator rated circuit
breakers.
A general-purpose circuit breaker is tested based on the fault
current X/R ratio of 17. The resulting interrupting rating is TABLE II
given in symmetrical amperes, but the circuit breaker has the M ULTIPLICATION FACTORS FOR T OTAL FAULT C URRENT H AVING
B OTH AC AND DC C OMPONENTS (R EFERENCE C37.010-1999,
capability to interrupt fault currents that have a dc compo- F IG . A.9. CPT IN C YCLES )
nent associated with fault X/R ratio of 17 or less. The ratio
of total current to symmetrical current at an X/R of 17 is
given in Table I and is a function of the circuit breaker CPT.
For an ANSI/IEEE rated high-voltage circuit breaker, a half-
cycle (8.33 ms) protective relay time is included in the CPT.
When the symmetrical multiplier curves were developed for
IEEE C37.010-1979, a test X/R ratio of 15- and 4-cycle
CPT was applied. The resulting total current is 1.034 times
the symmetrical current, subsequently rounded to 1.0. Table I
includes the S-factor for generator rated circuit breakers.
Fig. 2 provides a set of multiplication factor curves for
generator rated circuit breakers at 60 Hz following the same
procedure as used in IEEE C37.010-1979 between symmetrical
and total current basis circuit breakers.
The total asymmetrical current is determined from

ITOT = (Iacsym )2 + (Idc )2 . (1)

Taking Iacsym as 1.0 PU, composition is not known; thus, the development of similar
√ X/R √ 2πf t multiplying curves is done by using data read from the Fig. A.9
Idc = 2 × ε− tc ; tc = = 2 × ε− X/R
t
; thus Idc curves. Dividing any of the total fault currents in Table II
2πf
(2) by the generator circuit breaker S-factor of Table I yields a
multiplication factor of less than 1.0 for all values in Table I.
where Therefore, for a system where all the current is from a local
t time (in seconds); generator without any impedance between the generator and the
tc time constant (in seconds); fault, the multiplication factor is set equal to 1.0.
f frequency (in hertz).
For an X/R ratio = 17, tc = 0.045 s, and for X/R = 50,
III. E XAMPLE
tc = 0.133 s.
Fig. A.9 of IEEE C37.010-1999 has the multiplication fac- The example of a typical combined cycle generating station
tors for currents that have both ac and dc decrements (not stated is shown in Fig. 3. The combustion and steam turbine genera-
in IEEE C37.010-1999 as having ac decay, but it is the same tors (identified as “CTG” and “STG” in the figure) share a com-
as Fig. A.9 in C37.010-1979). The origin of the amount of ac mon transformer, but each generator is required to have its own
decay given in the curve is not based on equation, and its exact circuit breaker. The data for the station are given in Table III.
4166 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 6, NOVEMBER/DECEMBER 2014

Fig. 3. Sample combined cycle one-line diagram.


Fig. 5. Impedance diagram on a 100-MVA base for the example in Fig. 3.

TABLE III
DATA FOR THE E XAMPLE IN F IG. 3 less than the generator reactance, the resistance component of
voltage has been neglected.
IEC equation

Vinternal = 1 + Xdv × sin [ar cos(P F )] . (3)

Detailed equation

Vinternal = (1 + Xdv × sin [ar cos(P F )])2 + (X  × PF )2
dv

(4)

X dv
generator impedance modifier = . (5)
VINTERNAL

The IEC equation gives the internal voltage of the STG


as 1.12960 PU V, whereas the detailed equation gives
1.142741 PU V. With some commercial software using the
internal machine voltage as 1.0 PU V, the generator impedance
is modified to obtain the same terminal fault current as if the
higher internal voltage is used. For example, the STG has an

Xdv = 21.6% and would be modified by the internal voltage as

Xdv /VINTERNAL = 21.6/1.142741 = 18.9%. Fig. 5 gives the
impedance diagram of the system on a 100-MVA base.

IV. P ROCEDURE
Using the system diagram in Fig. 3, a three-phase fault is
placed at location A–B with all connections active. Then, a fault
is placed at A with the STG out of service. This will give the
fault point X/R ratio of the system for the current flowing from
the transformer. Finally, a fault is placed at location B with the
transformer out of service; this will give the fault point X/R of
the STG plus any bus duct/cable current following the circuit
breaker from the STG.
Using IEEE C37.010 procedures, a fault at location A or B
on Fig. 3 gives the total system symmetrical fault of 114.59 kA
with an IEEE X/R ratio = 80.61. In Fig. 3, the symmetrical
fault current for the first half-cycle and instantaneously cleared
Fig. 4. Vector diagram for generator internal voltage calculation for STG. interrupting time is the same since the IEEE C37.010 suggested
that generator impedance is the same for both times.
In the upcoming analysis, to provide some conservatism, The symmetrical fault current from the STG is 39.71 kA at
the voltage behind the subtransient reactance will be used −89.560 (X/R = 130.2) and 74.88 kA at −88.830 (X/R =
(see Fig. 4). This is a deviation from 1.0 PU driving voltage 48.96) from the transformer. The current via the transformer
suggested in IEEE C37.010 and is similar to the effect of the has two components: 35.14-kA contribution from the CTG and
generator impedance modifier used in IEC 60909. To calculate 39.75 kA from the 400-kV system. The fault point IEEE X/R
this per-unit internal voltage for the generator at rated load, ratio from the STG is 130.3 when the transformer is out of
the approximate equation from IEC 60909 or a more detailed service, and the IEEE X/R for the current via the transformer
equation can be used. With the generator resistance being much is 53.99 when the STG is out of service. The IEEE X/R ratio
DARTAWAN AND PIERRE: EVALUATING CIRCUIT BREAKERS DUTY USING IEEE C37.010 AND C37.013 4167

for the current via the transformer is 53.99, as compared with terrupting time duties. We look at several approaches, each
the complex jX/R ratio of 48.96. having a different level of conservatism for the interrupting time
If an auxiliary station were connected to location B, then calculations.
its protective device would be evaluated with the 114.59-kA
symmetrical current and an X/R ratio of 80.61. The limiting
circuit breaker duty for circuit breaker STG would be either the A. Peak Current Calculation
current from the transformer for fault location A or the current The peak current is associated with the first half-cycle and
from the generator for fault location B. While the current from is approximated by (6) or (7). Since the peak actually occurs
the transformer is greater than the current via the STG, the duty before the half-cycle, using the time as 0.5 cycle would result
for both conditions should be evaluated since the STG current in a small error. To correct for this error, a fictitious time of τ is
has a higher X/R ratio and could result in the duty current used, as shown in the IEEE Violet Book (6) and IEC-60909 (7)
being greater than the transformer current. √  
IEEE Violet Book → IP K = 2IacRMS 1 + ε− X/R
2πτ
Circuit breakers that are classified as generator rated circuit (6)
breakers have several ratings that are different than general-
X/R
purpose circuit breakers. The two key ratings, as far as this τ = 0.49 − 0.1 × ε− 3

paper is concerned, are the “close and latch” rating and the √  
IEC-60909 → IP K = 2IacRMS 1.02 + 0.98ε− X/R . (7)
3
test X/R ratio. A general-purpose circuit breaker has a peak
current “close and latch” rating of 2.6 times the interrupting,
and its interrupting rating is based on the fault current X/R From STG
ratio of 17 (45-ms dc decay rate). The generator rated circuit
τ = 0.49 − 0.1 × ε− 3 = 0.49
130.2
breaker has a peak current “close and latch” rating of 2.74 times
the interrupting, and its interrupting rating is based on the fault √  2π×0.49

current X/R ratio of 50 (133-ms dc decay rate). IP K = 2 × 39.71 1 + ε− 130.2 = 111.0 kA.
For circuit breaker duty calculations, it is important to obtain
the system X/R that represents the dc decay. In IEEE C37.010- From transformer
1999, section 6.3.2 provides a method to determine the fault
τ = 0.49 − 0.1 × ε− 3 = 0.49
53.99

point X/R that is more representative of the dc decay rate. Us-


√  
ing the jX/R ratio from the complex impedance reduction does 2π×0.49
IP K = 2 × 74.88 1 + ε− 53.99 = 205.9 kA.
not provide a ratio that would yield conservative calculation of
the asymmetrical or peak fault current; this statement is also
mentioned in [1]. These calculations were made assuming that the generator
The purpose of performing the three sets of faults at voltage is at 100% rated voltage. For this condition, fault duty
locations A and B is to obtain the fault point IEEE X/R ratio is below the circuit breaker peak rating of 220-kA peak, and
of each branch current flow, which generally could not be ob- since the fault current via the transformer is greater than the
tained from commercial software programs unless the software fault current from STG, it is used to evaluate the duty of the
provides a line-end fault calculation. IEEE C37.010 states that circuit breaker. However, since the generator has the capability
“the bus fault point X/R ratio is to be used for circuit breaker to operate continuously at 105% of nameplate voltage, this
duty calculation.” Using the bus fault point X/R ratio for a condition results in fault current via the transformer being
multi-circuit-breaker bus makes sense because the difference 1.05 ∗ 205.9 = 216.2 kA or 98.3% of the generator circuit
between the total system symmetrical fault current and the breaker rating.
symmetrical fault current used for individual circuit breaker
duties is small. For a system, as shown in Fig. 3, the total B. Interrupting Time Current Calculation
system fault current is much different than the actual fault
current in the generator circuit breaker. For this system and The STG circuit breaker has a CPT of 2.4 cycles with a
with all elements in service, for a fault at point A or B, the protective relay time of 0.5 cycles (8.33 ms). Since both circuit
IEEE bus fault point X/R ratio is 80.61. Using the 80.61 breakers are subject to a fault current with an IEEE X/R
X/R ratio for the generator current, which has an X/R ratio ratio greater than 50, a duty multiplier is required. The duty
of 130.3, would yield a nonconservative duty, whereas for the multiplier can be determined from Fig. 2 or calculated using
transformer current with an X/R ratio of 53.99, the result could (1) and (2).
be overly conservative. Section 6.3 of IEEE C37.010 allows the From Fig. 2 with 2.4-cycle CPT, the multiplier for the current
more rigorous method to be used. Using the IEEE fault point via the generator is 1.12 and via the transformer is 1.01. This
X/R ratio as proposed by individually removing the branch on is a conservative approach since Fig. 2 considers dc decay only
each side of the generator circuit breaker is rigorous. and does not include ac decay. In real life, generally, the fault
current contribution from generator would have ac decay. Thus,
using Fig. 2, the interrupting time duty would be
V. A NALYSIS
from STG, IacRMS ∗ multiplier = 39.71 ∗ 1.12 = 44.48 kA
Circuit breaker duty analysis requires examination of both
the circuit breaker’s peak current (close and latch) and in- from transformer, 74.88 ∗ 1.01 = 75.63 kA.
4168 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 6, NOVEMBER/DECEMBER 2014

The duty multiplier can be also calculated from (1) and (2). gives 40.214 kA plus the 35.14 kA from the CTG gives a total of
First, the circuit breaker interrupting rating capability (includ- 75.355 kA. Allowing for 5% high voltage, the total duty current
ing ac and dc) at the circuit breaker test X/R ratio of 50 at would be 79.12 kA or 98.9% of the circuit breaker rating. In
40 ms needs to be determined. Second, calculate the current this case, this decrease in rating to duty is small (from 99.4%
via STG and transformer if the fault X/R ratio is greater to 98.9%) and would be greater if the IEEE X/R ratio of the
than 50. The duty multiplier is the value from the second step current from the transformer was greater.
divided by the value from the first step. If the fault point X/R
ratio is less than 50 (circuit breaker test X/R ratio), the duty
C. Calculations Using IEEE C37.013-1997
multiplier (other than 1.0) is not required, and the symmetrical
interrupting current can be compared to the circuit breaker’s Generally, the generator transformer impedance and source
interrupting rating directly. impedance are less than the generator impedance; thus, the cur-
Circuit breaker interrupting rating capability (including ac rent via transformer is used for circuit breaker duty evaluation.
and dc, or ITOT ) can be calculated from (1) and (2) as follows: In rare cases where the current from the generator dictates the
√ circuit breaker duty, the refinement in the current from the gen-
Idc = 2 × ε− 50 = 1.046
377∗0.04

 erator can be based on the generator parameters. An example of


IOT = (1)2 + (1.046)2 = 1.447. this is given in IEEE C37.013-1997, Annex section A.3.
The expression for the ac decay with the currents in per unit
Current via STG on the generator base is

Idc = 2 × ε− 130.2 = 1.2595
377∗0.04
−t −t
    
 IGEN = (IG −IG )×ε Td +(IG −IG−SS )×ε Td +IG−SS
ITOT = (1)2 +(1.2595)2 = 1.608 1 1

IG =  = = 4.6296
1.608 X dv 0.216
duty multiplier = = 1.111
1.447  1 1
IG =  = = 3.4014
interrupting duty current = IacRMS × 1.111 X dv 0.294
1 1
= 39.71 ∗ 1.11 = 44.13 kA. IG−SS = = = 0.5089. (8)
Xdv 1.965
Current via transformer Equation (8) would be used to calculate the peak current

Idc = 2 × ε− 53.99 = 1.0696
377∗0.04
and the interrupting time current. As indicated in (6), the peak
 current occurs closer to 0.49 cycles rather than 0.5 cycles. Using
ITOT = (1)2 +(1.0696)2 = 1.464 0.49 cycles (8.2 ms) in (8) gives
1.464
duty multiplier = = 1.0117 IGEN = (4.63 − 3.4) × ε−0.0082/0.033 + (3.4 − 0.51)
1.447
interrupting duty current = IacRMS × 1.0117 × ε−0.0082/0.419 + 0.51
= 74.88 ∗ 1.0117 = 75.76 kA. IGEN = 0.959 + 2.834 + 0.51 = 4.3033 PU.

All interrupting duty currents determined using Fig. 2 and Adjusting for the generator internal voltage rather than
(1) and (2) are less than the circuit breaker rating. Allowing for 1.0 PU V that was used in (8) has the generator PU A at
105% operating voltage, the circuit breaker interrupting current 4.3033 ∗ 1.14274 = 4.9176 PU A. The generator symmetrical
is at 99.4% of the circuit breaker rating. If this system were fault current at the circuit breaker CPT allowing a 105%
in the design stage, a larger margin between the duty and the generator voltage is 1.05 ∗ 4.9176 ∗ 7.506 = 38.76 kA (note,
circuit breaker rating would be warranted. STG-rated amps is 7506 from Table III). Using (6), correcting
For discussion purposes, let us assume that the interrupting the symmetrical current for the generator X/R ratio of 130.2
time current is slightly greater than the circuit breaker rating and τ = 0.49, gives the generator circuit breaker close and
and a further refinement in the calculation is desired. For latch duty for the current from the STG as 38.76 ∗ 2.7953 =
example, [2] uses graduated curves where the fault current 108.34 kA.
via the transformer could be treated as a composite of a The interrupting time calculation using the 40 ms CPT of the
decaying ac component and a nondecaying component. The circuit breaker in (8) gives
graduated curves given in [2] are widely used in software
IGEN = (4.63 − 3.4) × ε−0.04/0.033 + (3.4 − 0.51)
programs for industrial and commercial systems. Note that the
IEEE C37.010-1999 has curves for the current either being with × ε−0.04/0.419 + 0.5089
no ac decay or having ac decay from nearby generators. As IGEN = 0.365 + 2.629 + 0.51 = 3.504 PU.
given above, the current via the transformer has two compo-
nents: 35.14 kA from the CTG and 39.75 kA from the 400-kV Adjusting for the generator internal voltage rather than 1.0
system. It was shown earlier that the total current with decay PU V that was used in (8) has the generator PU A at 3.504 ∗
would not have any duty multiplier other than 1.0. This leaves 1.14274 = 4.0036 PUA. The generator symmetrical fault cur-
the multiplier to be applied only to the current component from rent at the circuit breaker CPT allowing a 105% generator
the 400-kV system. Using the 1.0117 multiplier on 39.75 kA voltage is 1.05 ∗ 3.504 ∗ 7.506 = 27.62 kA (note, STG-rated
DARTAWAN AND PIERRE: EVALUATING CIRCUIT BREAKERS DUTY USING IEEE C37.010 AND C37.013 4169

TABLE IV 2) For the conservative calculation, this paper develops a


C OMPARISON OF STG C IRCUIT B REAKER D UTY AT 1.0 PU VOLTAGE
curve to obtain multiplication factor for interrupting time
calculation of generator circuit breaker, as shown in
Fig. 2. The curve considers dc decay and does not include
ac decay.
3) The generator circuit breaker’s close and latch and inter-
rupting ratings are based on X/R ratio of 50 rather than
17 of the general-purpose circuit breaker.
amps is 7506 in Table III). Correcting the symmetrical current
4) In the sample presented in this paper, the current from the
for the generator X/R ratio gives the generator circuit breaker
step-up transformer dictates the duty current for generator
duty for the current from the generator as 27.62 ∗ 1.111 =
circuit breaker.
30.68 kA. In addition, 1.111 is the multiplier factor from the
5) The generator current of 1/X − dv results in a conser-
interrupting duty for the STG current (refer to Section V-B,
vative generator fault current at the close and latch and
Interrupting Time Current Calculation).
interrupting times.
As noted, while these calculations were made in the PU
6) For an existing system where circuit breaker duties are
generator current at the half-cycle time, using IEEE genera-
to be determined, including bus duct/cable between the
tor impedance would have 1/X  dv = 1/0.216 = 4.63 PU A,
generator and the step-up transformer in the short-circuit
whereas using the generator impedance modifier from
model, would have an effect on lowering the fault point
IEC 60909 would have 1/X  dv = 1/0.189 = 5.29 PU A.
X/R ratio and the total fault currents.
Using the detailed equation (8) to calculate the fault current at
the half-cycle time, the IEC generator impedance modifier (5) The IEEE working group P62271-37-013 is working on re-
appears to be overly conservative for a nondetailed fault cal- vising C37.013-1997, and the procedure given in this paper
culation. Using the unmodified generator impedance per IEEE may differ from those of the working group final procedures.
calculations generally will be conservative if the generator time This paper covers generators in industrial plants that are on a
constant T  d is less than approximately 0.045 s for nondetailed common bus with the plant loads.
calculations.
Table IV provides a comparison of the STG circuit breaker ACKNOWLEDGMENT
duty using the conservative and detailed calculations for gener-
ator circuit breaker duty evaluation. The peak current calcula- The authors would like to thank C. Davis of Easy Power and
tion is compared directly to the peak current rating of the circuit R. Austria of Pterra Consulting for their contributions, as well
breaker, and similarly, the interrupting current is compared to as anonymous IEEE reviewers for their comments and review
the symmetrical rating of the circuit breaker. of this paper.
The discussion places emphasis on the high fault point
X/R ratio (higher than 50) that would require duty multi- R EFERENCES
plier calculation for generator circuit breaker evaluation. On [1] K. Dartawan and C. St. Pierre, “Proposed methods to determine fault point
installed systems in which the circuit breakers are at or over X/R ratio for breaker evaluation,” IEEE Trans. Ind. Appl., vol. 40, no. 4,
the circuit breaker rating, including the bus duct/cable between pp. 941–949, July/Aug. 2004.
[2] W. C. Huening, Jr., “Interpretation of new American National Standard
the generator and the step-up transformer in the short-circuit for power circuit breaker application,” IEEE Trans. Ind. Gen. Appl.,
model can have a positive effect on lowering the fault point vol. IGA-5, no. 5, pp. 501–523, Sep/Oct. 1969.
X/R ratio and the total fault currents. Even short lengths are [3] G. D. Gregory, “North American and IEC standards for circuit breakers,”
IEEE Ind. Appl. Mag., vol. 7, no. 1, pp. 64–71, Jan./Feb. 2001.
important because of their low X/R ratios. While symmetrical [4] B. Kulicke and H.-H. Schramm, “Application Of vacuum circuit-breaker
fault current is not significantly reduced, the total fault currents to clear faults with delayed current zeros,” IEEE Tran. Power Del., vol. 3,
could significantly reduce due to reduction in the multiplication no. 4, pp. 1714–1723, Oct. 1988.
[5] E. M. Ruoss and P. L. Kolarik, “A new IEEE/ANSI standard for generator
factor (the lower the fault point X/R ratio, the lower the circuit breakers,” IEEE Trans. Power Del., vol. 10, no. 2, pp. 811–816,
multiplication factor and the total fault current). Apr. 1995.
[6] I. M. Canay, D. Braun, and G. S. Koppl, “Delayed current zero due to
out-of-phase synchronizing,” IEEE Tran. Energy Convers., vol. 13, no. 2,
pp. 811–816, Jun. 1998.
VI. C ONCLUSION [7] R. E. Owen and W. A. Lewis, “Asymmetry characteristics of progressive
short circuits on large synchronous generators,” IEEE Trans. Power App.
This paper has shown that the procedures in IEEE C37.010 Syst., vol. PAS-90, no. 2, pp. 587–596, 1971.
can be used to evaluate generator circuit breakers that have a [8] A. Eidinger, “Interruption of high asymmetric short-circuit currents hav-
higher test X/R ratio than the general-purpose circuit breakers. ing long delayed zeros—An acute problem for generator breakers,” IEEE
Trans. Power App. Syst., vol. PAS-91, no. 4, pp. 1725–1731, 1972.
This paper gives both a conservative and a detailed approach to [9] R. P. P. Smeets and W. A. van der Linden, “The testing of SF6 generator
the circuit breaker duty evaluation. The procedure discusses the circuit-breakers,” IEEE Trans. Power Del., vol. 13, no. 4, pp. 1188–1193,
following. Oct. 1998.
[10] K. Chanda, R. Parthasarathi, and S. Holla, “Estimation of short circuit
1) The IEEE fault point X/R ratio can be determined for capability of generator circuit breaker for a generator fed fault,” in Proc.
the branch currents on each side of the generator circuit IEEE/PES Trans. Distrib. Conf. Expo, Latin Amer., 2008, pp. 1–4.
[11] Application Guide for AC High-Voltage Circuit Breakers Rated on a
breaker. This is done by having the equipment on each Symmetrical Current Basis, ANSI/IEEE Std. C37.010-1999 (R2005),
side of the circuit breaker being inactive in turn. 2000.
4170 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 6, NOVEMBER/DECEMBER 2014

[12] International Standard Short-Circuit Current Calculation in Three-Phase Conrad St. Pierre received the B.S.E.E. degree
a.c. Systems, IEC Std. 60909-02001, Jul. 2001. from The University of Maine, Orono, ME, USA,
[13] IEEE Standard for AC High Voltage Generator Circuit Breakers Rated on in 1965 and the M.S. degree from Union College,
a Symmetrical Current Basis, IEEE Std. C37.013-1997, 1997. Schenectady, NY, USA, in 1983.
[14] IEEE Standard for AC High Voltage Generator Circuit Breakers Rated He is currently the President of Electric Power
on a Symmetrical Current Basis Amendment 1: Supplement for Use With Consultants, LLC, Schenectady, where he provides
Generators Rated 10-100 MVA, IEEE Std. C37.013a-2007 (Amendment analytical studies for industrial clients. He has writ-
to IEEE Std C37.013-1997), 2007. ten numerous IEEE papers and magazine articles and
[15] IEEE Recommended Practice for Calculating Short-Circuit Currents published a book, A Practical Guide to Short-Circuit
in Industrial and Commercial Power Systems, IEEE Std 551—(Violet Calculations, and coauthored a book titled Industrial
Book), 2006, Chapter 2. Power System Grounding Design Handbook.
[16] Application Guide for AC High-Voltage Circuit Breakers Rated on a Mr. St. Pierre has been a senior member of several subcommittees, and he
Symmetrical Current Basis, ANSI/IEEE Std. C37.010-1979, 1979. was the Chairman of the Violet Book Working Group that deals with short-
[17] IEC Standard for High-Voltage Switchgear and Controlgear, circuit calculations. He was also a member of the U.S. National Committee of
IEC Std. 62271-100, 2008. the International Electrotechnical Commission Technical Advisory Group for
[18] C. St. Pierre, A Practical Guide to Short-Circuit Calculations, TC73/WG1 and WG2 concerning short-circuit currents and calculation method.
(self-published book), Jul. 2001, ch. 3.
[19] W. D. Stevenson, Elements of Power System Analysis, 3rd ed. New York,
NY, USA: McGraw-Hill, 1975.
[20] D. Beeman, Industrial Power Systems Handbook. New York, NY, USA:
McGraw-Hill, 1955.
[21] , Westinghouse Transmission and Distribution Book. New Delhi, India:
Oxford & IBH, 1950, ch. 11.

Ketut Dartawan (M’00) received the B.Sc. degree


from Sepuluh Nopember Institute of Technology,
Indonesia.
He is currently the Managing Principal and a
Founding Member of Pterra Consulting, Albany, NY,
USA. He was previously a Senior Consultant with
Power Technologies, Inc., Schenectady, NY, USA,
and a Senior Engineer with Freeport McMoRan,
Phoenix, AZ, USA, one of the largest copper and
gold mining companies in the world. He has 15 years
of experience in power system studies, distribution
networks, transmission congestion contracts, course instruction, and software
development. He directed and participated in numerous analytical studies
on electrical transmission and distribution. He has managed and conducted
more than 100 system impact, citing, generator deliverability, and transmission
studies in the USA and other countries involving proposed wind farms, steam
and fossil-fired generation, nuclear upgrades, and ac and HVdc transmission
lines, ranging in potential power capability from 20 to 1200 MW.

You might also like