DOC: D-3-01-09-01-01
Revision-1
5
PRE COMMISSIONING TEST - EOT CRANE & SHOCK RECORDER
I. EOT CRANE
Load Test to be conducted on EOT Crane as per IS 3177:1999 (Reaffirmed 2004) “Indian Standard:
Code of Practice for Electric Overhead Cranes and Gantry Cranes other than steel work cranes “
Note: Above test to be conducted before starting installation of GIS bays in GIS hall
Shock Recorders are to be provided in all the critical compartments during transportation like Circuit
Breaker, Voltage Transformers etc. After receipt of compartments at site, shock recorder data needs to
be downloaded preferably at site in presence of POWERGRID representative and analysis of the data
needs to be submitted before start of erection activities. Incase of violation of limit for the shocks in
any of the three directions, internal inspection of the compartment needs to be carried out so as to
decided rectification measures based on the findings.
6
PRE COMMISSIONING CHECKS ON SF6 GAS
I. Quality Checks on SF6 Gas
Bay Details: D04 BUSCOUPLER Ambient Temperature: 28 ̊C
Reference Drawing Number:
Kit Details
Make: MBW S.No:13-1016 Model: MBW 973-SF6 Calibration Validity date: 18-SEP-2018
Permissible limit: Moisture Content (200 ppmv), Dew point (- 36 deg C) & Purity (99 %)
Note:
a) Dew point of SF6 gas to be measured after at least 120 hours of gas filling
b) Gas pressure reading to be monitored and recorded by the executing agency after every two
weeks till energisation for identification of leakage in gas compartment if any and rectification.
c) Gas quality test to be done only by using testing kit which has the pump back facility so that
after measurement of gas quality, SF6 gas is not wasted and sent back to GIS compartment.
7
II. Checks on SF6 Density Monitor
B0.2 (R) 647034-09 600 611 608.2 600 611 604.2 530 542 539.4
B0.2 (Y) 647034-014 600 609 607.0 600 610 604.2 530 541 540.6
B0.2 (B) 647034-004 600 609 600.4 600 609 600.1 530 538 532.0
8
III. SF6 Leakage test
Bay Details: D04 BUSCOUPLER
9
I. General Details
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Bay Name: D04 BUSCOUPLER LOA No:BUSCOUPLER
Make: ABB CHINA Year of Manufacturer: 2017
Equipment Designation: D04 – Q0 Type: ELK -SP14
Sr. No: 501916739 – D04 – Q0 Rated Breaking Capacity (kA): 50 Ka
Rating: 3150 A Control Voltage (DC): 220 V
Operating Voltage: 245Kv Date of Erection:
Date of Receipt at Site: Date of Energisation:
Spring
Hydraulic
Hydro-Spring √
i. Hydraulic/Hydro-Spring System
a) Accumulator
R Ø YØ BØ
Make ABB
SD10104-
210005313986/02
SD10104-
210005313988/02
SD10104-
Serial number 210005313988/03
Type HMB-4.2
Year of
2017
manufacture
b) Pump details
10
Make Volt
Type Hp/ Kw
11
a) Operation checks
Date of Hydraulic Oil filling _____________________
1 Pre-filling pressure of N2 in
accumulator ( bar / deg. C)
12
__________ make/break
Oil pressure drop during operations and pump running time in seconds : -
Sl.N
Description Site Test Value
o
Note: Pump MCB to be kept OFF in order to record drop in pressure after O/C/ CO
operation. Subsequently switch ON MCB to record normalisation time.
13
ii) Spring Operating System
Sl no Amperes
Type Hp/kw
Setting (thermal
Year of Manufacture overload)
R- Ø Y- Ø B- Ø
Details Factor
Factory Site Factory Site y Site
Circuit Typ
Reference Make e
timer
d). Charging of spring of Circuit Breaker manually - Not Possible
Sl Operational Check
No Circuit Reference
Local Remote
C Closing Circuit OK OK
D Anti-hunting Feature OK OK
15
V. Operating Time ( In mille-seconds )
Close OCO
(Max Closing Trip Close Open
Tripping Coil
Phase (Ø) 150ms) Coil (OK/NOT OK)
Current
Current
Trip – I Trip - II Trip - I Trip – II Trip - I Trip - II Trip – I Trip - II
R-Ø main
51.0 2.3 15.3 15.2 2.3 2.4 23.1 23.1 OK OK
contact
R-Ø PIR
Y-Ø main
51.2 2.3 15.3 15.4 2.3 2.3 23.9 24.2 OK OK
contact
Y-Ø PIR
B-Ø main
50.3 2.3 15.2 15.3 2.3 2.3 23.6 23.0 OK OK
contact
B-Ø PIR
Auxiliary
56.850 29.150 29.200
contact a
Auxiliary
20.800 13.900 13.275
contact b
Permissible limits
Open 25 ms 25 ms 35 ms 40 ms
16
VI. IR Value of Control Circuit(using 500 volt megger)
Make of Kit:
Date of Calibration:
CAUTION: Isolate necessary dc for trip coil I and trip coil II, closing coil before meggaring.
Counter Put √
Type Mark
ELECTRICA
L √
MECHANIC
AL (Reading to be recorded before
energisation)
Reading Date
Sl. No Phase
open Close open Close
17
A R-Ø 33 33
B Y-Ø 34 34
C B-Ø 35 33
R
Y
B
IX.
DDetails are attached in this report
Note- 2.5 Sec for CBs with Auto Reclose Function & 0.5 Sec for CBs without Auto Reclose
Function.
18
XI. Final Documentation Review
Yes No
19
Organization: (Erection Agency) (POWERGRID Site (POWERGRID
Representative) Members:
(Wherever 1.
Applicable) 2.
3.
4.
I. General Details
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS ,
SABOUR
Bay Name: E04 T1 & T2 BUSCOUPLER LOA : BUSCOUPLER
Make: GUANGDONG Rating: 800-1600-3000/1A
Sr. No:
T1 T2
R-Ø: GD17/220040 R-Ø: GD17/220032 Type: LMGB1-220
Y-Ø: GD17/220040 Y-Ø: GD17/220032
B-Ø: GD17/220040 B-Ø: GD17/220032
Year of Manufacturer: Date of Receipt at site:
R-Ø: 2017 R-Ø: 2017
Y-Ø: 2017 Y-Ø: 2017
B-Ø: 2017 B-Ø: 2017
Date of Erection: Date of Energisation:
20
Core Ratio Class KVp/Burden Imag ( at VK) Protection / Metering
Winding I –T1 800-1600- PS 800-1600-
<50-25-13.3 mA Protection
3000/1A Rct<4-8-15 Ω 3000 V
Winding II –T1 800-1600- PS 800-1600-
<50-25-13.3 mA Protection
3000/1A Rct<4-8-15 Ω 3000 V
Winding III –T2 800-1600- 0.2 S
VA: 20-20-40 FS: 5 Metering
3000/1A
Winding IV –T2 800-1600- PS 800-1600-
<50-25-13.3 mA Protection
3000/1A Rct<4-8-15 Ω 3000 V
Winding V –T2 800-1600- PS 800-1600-
<50-25-13.3 mA Protection
3000/1A Rct<4-8-15 Ω 3000 V
Remark
Sl. Status
Description
No Record
Yes No Deficiencies, If
Any
1 Equipment is cleaned and free from dust / dirt foreign materials etc. √
All the cable identification tags provided and all cores are provided
√
7 with identification ferrules in CT sec box and LCC panel.
Check secondary cables are properly routed and dressed with proper
√
8 support/ trays and unused holes at cable entry are sealed.
Ensure unused secondary cores, if any, has been shorted and earthed
√
11 in LCC panel.
Check star point has been formed properly and grounded at relay
√
12 panel end only.
21
14 Check direction of primary (P1/ P2) w.r.t. Bus/ line on erection √
b.
Phase
Between Unit
RØ YØ BØ
T2 – CORE3 , CORE 4 , CORE 5
Secondary Core III –
MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
Earth
Secondary Core IV –
MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
Earth
Secondary Core V –
MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
Earth
Core III – Core IV MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
Core III – Core V MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
Core IV – Core V MΩ ≥1 GΩ ≥1 GΩ ≥1 GΩ
22
V. Measurement of Secondary Winding Resistance (In Ohm)
23
1S1 (+VE) 1S4 (-VE) OK OK OK
2S1 (+VE) 2S2 (-VE) OK OK OK
CORE II 2S1 (+VE) 2S3(-VE) OK OK OK
2S1 (+VE) 2S4 (-VE) OK OK OK
3S1 (+VE) 3S2(-VE) OK OK OK
CORE III 3S1 (+VE) 3S3(-VE) OK OK OK
3S1 (+VE) 3S4(-VE) OK OK OK
4S1 (+VE) 4S2(-VE) OK OK OK
CORE IV 4S1 (+VE) 4S3(-VE) OK OK OK
4S1 (+VE) 4S4(-VE) OK OK OK
5S1 (+VE) 5S2(-VE) OK OK OK
CORE V 5S1 (+VE) 5S3(-VE) OK OK OK
5S1 (+VE) 5S4(-VE) OK OK OK
R Phase
24
CORE II 3000 1.0 3000 -0.004
(2S1 - 2S4)
CORE III 3000 1.0001 3000 0.014
(3S1 - 3S4)
CORE IV 3000 0.999 3000 0.080
(4S1 - 4S4)
CORE V 3000 0.9995 3000 0.029
(5S1 - 5S4)
*Primary current to be injected as per the continuous current rating of maintenance Earth switch
(specified by manufacturer)
Incase CT ratio test has been performed by CT Analyzer, direct ratio & error to be filled
NOTE: %Error Values Are Filled By as per CT Analyzer Shown Results Only.
Y Phase
25
(4S1 - 4S4)
CORE V 3000 0.9995 3000 -0.046
(5S1 - 5S4)
Incase CT ratio test has been performed by CT Analyzer, direct ratio & error to be filled
NOTE: %Error Values Are Filled By as per CT Analyzer Shown Results Only.
B Phase
26
CORE IV 3000 0.999 3000 -0.104
(4S1 - 4S4)
CORE V 3000 0.9995 3000 -0.053
(5S1 - 5S4)
Incase CT ratio test has been performed by CT Analyzer, direct ratio & error to be filled
NOTE: %Error Values Are Filled By as per CT Analyzer Shown Results Only.
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
Y Phase
27
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
B Phase
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
Knee Point Voltage (KVp) = 2000 Volt
R Phase
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
Y Phase
28
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
B Phase
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
Knee Point Voltage (KVp) = 3500 Volt
R Phase
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
Y Phase
29
Note: Magnetizing current to be tested for adopted tap (as per approved schematic)
B Phase
Note: Magnetizing current to be tested for adopted tap (as per approved schematic
ii. Document regarding spares equipment, O&M manuals etc available at site
for O&M purpose
Yes No
iii. After modification, if any, “As built Drawings” are available at site
Yes No
30
Designation: Designation: Designation: Designation:
Representative) Members:
(Wherever 1.
Applicable) 2.
3.
4.
I. GENERAL DETAILS
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Feeder name: D04-Q61 BUSCOUPLER LOA No. :BUSCOUPLER
Make: ABB CHINA Type: ELK-DE0
Sr. No: 501916739-D04-Q61 Operating Voltage rating: 245kV
Control Voltage: 231.5 DC Current Carrying capacity: 3150 A
Year of Manufacture: 2017 Date of Receipt at site:
Date of Erection: Date of Energisation :
SL.N STATUS
REMARK / RECORD
DESCRIPTION
YES NO DEFICIENCIES, IF ANY
O
1 Equipment is free from dirt/dust foreign materials etc. √
Equipment is free from all visible defects on physical √
2
Inspection
All nuts and bolts are tightened correctly as per specified √
3
Torque
Equipment erection is complete in all respect as per √
4
instruction Manual (attach remaining activities, if any)
5 Auxiliary contacts and relays have been cleaned √
31
and free from rust / damage
Functional checking of auxiliary contacts for √
6
indications and interlocks
7 Earth switch connected to earth firmly NA
Make
Type
Volt
Amperes
Hp/ Kw
O/L setting
(Thermal Over
load)
V.
INSULATION RESISTANCE MEASUREMENT
Date of calibration :
Ambient temperature :
Using 500 volt megger measure resistance between the winding of motor and earth
SL.
BETWEEN PHASE
NO
R Ø YØ B Ø
1 Winding to Earth
32
VI. OPERATIONAL CHECKS
MOTOR CURRENT
ISOLATOR R–Ø Y–Ø B–Ø
OPERATION Factory Site
CLOSE 0.20 A 0.487 A
OPEN 1.20 A 0.468 A
OPERATION PHASE
UNIT
R-Ø Y–Ø B–Ø
Sec 1.90
OPENING TIME
Sec 1.72
CLOSING TIME
33
VII. FINAL DOCUMENTATION REVIEW
34
Designation: Designation: Designation: Designation:
I. GENERAL DETAILS
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Feeder name: D04-Q1 LOA No. :BUSCOUPLER
BUSCOUPLER
Make: ABB CHINA Type: ELK-DE0
Sr. No: 501916739-D04-Q1 Operating Voltage rating: 245Kv
Control Voltage: 231.5V DC Current Carrying capacity: 3150 A
Year of Manufacture: 2017 Date of Receipt at site:
Date of Erection: Date of Energisation :
SL.N STATUS
REMARK / RECORD
DESCRIPTION
YES NO DEFICIENCIES, IF ANY
O
1 Equipment is free from dirt/dust foreign materials etc. √
Equipment is free from all visible defects on physical √
2
Inspection
All nuts and bolts are tightened correctly as per specified √
3
Torque
Equipment erection is complete in all respect as per √
4
instruction Manual (attach remaining activities, if any)
35
Auxiliary contacts and relays have been cleaned √
5
and free from rust / damage
Functional checking of auxiliary contacts for √
6
indications and interlocks
√
7 Earth switch connected to earth firmly
√
8 Earth switch link grounding point marked clearly
Make
Type
Volt
Amperes
Hp/ Kw
O/L setting
(Thermal Over
load)
36
Date of calibration :
Ambient temperature :
Using 500 volt megger measure resistance between the winding of motor and earth
SL.
BETWEEN PHASE
NO
R Ø YØ B Ø
1 Winding to Earth
V. OPERATIONAL CHECKS
i. Operate the isolator, earth switch and record the motor current
MOTOR CURRENT
OPERATIO ISOLATOR EARTH SWITCH
N R–Ø Y–Ø B–Ø R–Ø Y–Ø B–Ø
Factory Site Factory Site
CLOSE 0.20 A 0.482 A 0.20 A 0.374 A
OPEN 0.20 A 0.449 A 0.20 A 0.420 A
37
TIME
CLOSING TIME Sec 1.81 1.80
38
iii. After modification, if any, “As built Drawings” are available at
Site Yes No
√
I. GENERAL DETAILS
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS ,SABOUR
Feeder name: D04-Q2 LOA No. : BUSCOUPLER
BUSCOUPLER
Make: ABB CHINA Type: ELK-DE0
Sr. No: 501916739-D04-Q2 Operating Voltage rating: 245Kv
Control Voltage: 231.5V DC Current Carrying capacity: 3150 A
Year of Manufacture: 2015 Date of Receipt at site:
Date of Erection: Date of Energisation :
39
II. PRE-COMMISSIONING CHECKS
SL.N STATUS
REMARK / RECORD
DESCRIPTION
YES NO DEFICIENCIES, IF ANY
O
1 Equipment is free from dirt/dust foreign materials etc. √
Equipment is free from all visible defects on physical √
2
Inspection
All nuts and bolts are tightened correctly as per specified √
3
Torque
Equipment erection is complete in all respect as per √
4
instruction Manual (attach remaining activities, if any)
Auxiliary contacts and relays have been cleaned √
5
and free from rust / damage
Functional checking of auxiliary contacts for √
6
indications and interlocks
√
7 Earth switch connected to earth firmly
√
8 Earth switch link grounding point marked clearly
Make
Type
Volt
Amperes
Hp/ Kw
O/L setting
(Thermal Over
load)
40
IV. INSULATION RESISTANCE MEASUREMENT
Date of calibration :
Ambient temperature :
Using 500 volt megger measure resistance between the winding of motor and earth
SL.
BETWEEN PHASE
NO
R Ø YØ B Ø
1 Winding to Earth
V. OPERATIONAL CHECKS
i. Operate the isolator, earth switch and record the motor current
MOTOR CURRENT
OPERATIO ISOLATOR EARTH SWITCH
N R–Ø Y–Ø B–Ø R–Ø Y–Ø B–Ø
Factory Site Factory Site
CLOSE 0.30 A 0.380 A 0.30 A 0.407 A
OPEN 0.30 A 0.442 A 0.30 A 0.370 A
41
OPEN OK OK
42
i. Final documents of Pre- Commissioning checks reviewed and Yes No
approved
√
I. GENERAL DETAILS
43
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Feeder name: D04-Q15 LOA No. :BUSCOUPLER
BUSCOUPLER
Make: ABB CHINA Type: ELK-ES0
Sr. No: 501140634-D04-Q15 Operating Voltage rating: 245 Kv
Control Voltage: 231.5 VDC Current Carrying capacity: -
Year of Manufacture: 2015 Date of Receipt at site:
Date of Erection: Date of Energisation :
SL.N STATUS
REMARK / RECORD
DESCRIPTION
YES NO DEFICIENCIES, IF ANY
O
1 Equipment is free from dirt/dust foreign materials etc. √
Equipment is free from all visible defects on physical √
2
Inspection
All nuts and bolts are tightened correctly as per specified √
3
Torque
Equipment erection is complete in all respect as per √
4
instruction Manual (attach remaining activities, if any)
Auxiliary contacts and relays have been cleaned √
5
and free from rust / damage
Functional checking of auxiliary contacts for √
6
indications and interlocks
√
7 Earth switch connected to earth firmly
√
8 Earth switch link grounding point marked clearly
44
R–Ø Y–Ø B–Ø
Make
Type
Volt
Amperes
Hp/ Kw
O/L setting
(Thermal Over
load)
Date of calibration :
Ambient temperature :
Using 500 volt megger measure resistance between the winding of motor and earth
SL.
BETWEEN PHASE
NO
R Ø YØ B Ø
1 Winding to Earth
V. OPERATIONAL CHECKS
MOTOR CURRENT
EARTH SWITCH R–Ø Y–Ø B–Ø
OPERATION Factory Site
CLOSE 0.80 A 0.298 A
OPEN 2.30 A 0.550 A
45
EARTH SWITCH CONTROL PANEL
OPERATION LOCAL REMOTE
CLOSE
OK OK
OPEN OK OK
OPERATION PHASE
UNIT
R–Ø Y-Ø B–Ø
Sec 1.21
OPENING TIME
Sec 1.40
CLOSING TIME
46
i. Final documents of Pre- Commissioning checks reviewed Yes No
and approved
√
47
I. Contact Resistance Measurement
Contact Resistance Measurement to be conducted for whole GIS by injecting 100 A current or more.
Typical Configuration for performing Contact Resistance Measurement for reference SLD (Double Main
Bus Scheme) attached as Annexure – I have been shown in the table.
a. For Double Main Bus Scheme, Sample SLD for reference attached as Annexure - III
48
Bay Details Equipment Operation SCADA LCC Panel Status Indicator
Details Indication Lamp At Equipment
Close OK OK OK
Q1/ISO
Open OK OK OK
Close OK OK OK
Q2/ISO
Open OK OK OK
Close OK OK OK
Q51/ES
Open OK OK OK
Close OK OK OK
D04 Q52/ES
Open OK OK OK
Close OK OK OK
Q61/ISO
Open OK OK OK
Close OK OK OK
Q62/ISO
Open OK OK OK
Close OK OK OK
Q15/ES
Open OK OK OK
Close OK OK OK
Q25/ES
Open OK OK OK
Close OK OK OK
Q0/CB
Open OK OK OK
49
III. Alarms & Annunciation Check
50
B5 Compartment Zone Trip 31 - 32 OK OK
51
Disconnector Q1 Blocked Mode
52
VI. Earth Resistance Measurement
Earth Resistance needs to be measured for Outdoor Yard (at each voltage level) and each Bay in GIS
Hall.
*Details Attached in this report.
I. General Details
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Bay Name: D04-T15 BUS#1 LOA No: BUS#1
Make: SIEYUAN Primary Voltage Rating: 220000/√3 V
Secondary Voltage Rating: Secondary Voltage Burden:
Winding - I: 110/√3 V Winding - I: 50 VA
Winding - II: 110/√3 V Winding - II: 50 VA
Winding - IIII: 110/√3 V Winding - IIII: 50 VA
Sr. No: Type: JSQXFH-220
R- Ø: 2217917
Y- Ø: 2217917 Class : 3P/3P/0.2
B- Ø: 2217917
Year of Manufacturer: Date of Receipt at site:
R-Ø: 2015
Y-Ø: 2015
B-Ø: 2015
Date of Erection: Date of Energisation:
Status of Impact Recorder : OK/Not OK (If Not OK case may be referred to manufacturer for
inspection)
53
III. Pre Commissioning Checks
Status Remarks
Sl. Record
Description
No N Deficiencies,
YES O If Any
54
IV. Continuity of Winding
i. Between terminals 1a – 1n
Yes No
55
Secondary Core – I to Earth MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Secondary Core – II to Earth MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Secondary Core - III to Earth MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Core – I to Core – II MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Core - I to Core – III MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Core – II to Core – III MΩ ≥1GΩ ≥1GΩ ≥1GΩ
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
1500 V 1a – 1 n 0.76
R 1500 V 2a – 2 n 0.76
1500 V 3a – 3 n 0.76
y 1500V 1a – 1 n 0.76
1500V 2a – 2 n 0.76
56
1500V 3a – 3 n 0.76
1500V 1a – 1 n 0.76
B 1500V 2a – 2 n 0.76
1500V 3a – 3 n 0.76
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
2500V 1a – 1 n 1.26
R 2500V 2a – 2 n 1.26
2500V 3a – 3 n 1.27
2500V 1a – 1 n 1.26
y 2500V 2a – 2 n 1.26
2500V 3a – 3 n 1.26
2500V 1a – 1 n 1.26
B 2500V 2a – 2 n 1.26
2500V 3a – 3 n 1.26
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
4000V 1a – 1 n 2.0
R 4000V 2a – 2 n 2.0
4000V 3a – 3 n 2.0
4000V 1a – 1 n 2.03
y 4000V 2a – 2 n 2.03
4000V 3a – 3 n 2.04
B 4000V 1a – 1 n 2.02
4000V 2a – 2 n 2.03
57
4000V 3a – 3 n 2.03
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
4500V 1a – 1 n 2.31
R 4500V 2a – 2 n 2.30
4500V 3a – 3 n 2.30
4500V 1a – 1 n 2.27
y 4500V 2a – 2 n 2.28
4500V 3a – 3 n 2.29
4500V 1a – 1 n 2.28
B 4500V 2a – 2 n 2.28
4500V 3a – 3 n 2.28
ii. Document regarding spares equipment, O&M manuals etc available at site
for O&M purpose
Yes No
iii. After modification, if any, “As built Drawings” are available at site
Yes No
58
Signature: Signature: Signature: Signature:
Representative) Members:
(Wherever 1.
Applicable) 2.
3.
4.
I. General Details
DETAILS
Region: Sub-Station: 220/132/33kV NEW GIS , SABOUR
Bay Name: D04-T25 BUSPT#2 LOA No:
Make: SIEYUAN Primary Voltage Rating: 220000/√3 V
Secondary Voltage Rating: Secondary Voltage Burden:
Winding - I: 110/√3 V Winding - I: 50 VA
Winding - II: 110/√3 V Winding - II: 50 VA
Winding - IIII: 110/√3 V Winding - IIII: 50 VA
Sr. No: Type: JSQXFH-132
R- Ø: 22171918
Y- Ø: 22171918 Class : 3P/3P/0.2
B- Ø: 22171918
59
Year of Manufacturer: Date of Receipt at site:
R-Ø: 2015
Y-Ø: 2015
B-Ø: 2015
Date of Erection: Date of Energisation:
Status of Impact Recorder : OK/Not OK (If Not OK case may be referred to manufacturer for
inspection)
Status Remarks
Sl. Record
Description
No Deficiencies
YES NO , If Any
60
Labelling and identification marking is available on GIS
√
6 enclosure.
√
iii. Between terminals 3a – 1n
Yes No
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
1500 V 1a – 1 n 0.76
1500 V 2a – 2 n 0.76
62
R 1500 V 3a – 3 n 0.76
1500V 1a – 1 n 0.76
y 1500V 2a – 2 n 0.76
1500V 3a – 3 n 0.76
1500V 1a – 1 n 0.76
B 1500V 2a – 2 n 0.76
1500V 3a – 3 n 0.76
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
2500V 1a – 1 n 1.26
R 2500V 2a – 2 n 1.27
2500V 3a – 3 n 1.27
2500V 1a – 1 n 1.26
y 2500V 2a – 2 n 1.27
2500V 3a – 3 n 1.26
2500V 1a – 1 n 1.26
B 2500V 2a – 2 n 1.26
2500V 3a – 3 n 1.26
63
Measured
Voltage Between
Value
4000V 1a – 1 n 2.0
R 4000V 2a – 2 n 2.0
4000V 3a – 3 n 2.02
4000V 1a – 1 n 2.03
y 4000V 2a – 2 n 2.03
4000V 3a – 3 n 2.02
4000V 1a – 1 n 2.02
B 4000V 2a – 2 n 2.01
4000V 3a – 3 n 2.01
Secondary Voltage
Phase Primary
Measured
Voltage Between
Value
4500V 1a – 1 n 2.30
R 4500V 2a – 2 n 2.30
4500V 3a – 3 n 2.30
4500V 1a – 1 n 2.28
y 4500V 2a – 2 n 2.28
4500V 3a – 3 n 2.28
4500V 1a – 1 n 2.28
B 4500V 2a – 2 n 2.28
4500V 3a – 3 n 2.29
64
VI. Final Documentation Review
ii. Document regarding spares equipment, O&M manuals etc available at site
for O&M purpose
Yes No
iii. After modification, if any, “As built Drawings” are available at site
Yes No
65
Name: Name: Name: Name:
Representative) Members:
(Wherever 1.
Applicable) 2.
3.
4.
66
FORMAT FOR RECORD OF MAJOR FAILURES OF EQUIPMENT AND COMPONENTS DURING
PRE-COMMISSIONING STAGE
In order to have complete information of problems observed during pre-commissioning stage for
assessment of quality of product and erection workmanship, record of major problems is required
to be maintained. This helps in identifying the critical area vulnerable/ prone to failure and
analysing the same to avert the same in future during O&M stage with the help of manufacture/
supplier. The record of major problems observed during erection and pre-commissioning stage to
be maintained in the format given below and to be signed by contractor, manufacturer &
POWERGRID. The problems including GIS mechanical assembly parts, motor drives & drive
mechanism, SF6 gas leakage, Density monitor and contacts, items rejected due to transport
/storage damage, failures observed during HV test with details of location and reason found after
opening the compartment, detection of partial discharge during HV test , improper contact
resistance, CB, Isolator, CT, VT improper test values, indication and interlocks etc may be
recorded.
1.
Signature