You are on page 1of 13

Fabrication Activities (MSL PIPING)

Joint Inspect Signature Inspect Signature


Dwg. Spool No Fit up Date Weld Date
No Date Date
APT DCPL HZL APT DCPL HZL
Erection Activities (MSL PIPING)
Inspect of Signature Signature
Fit up Weld Inspect
S No Dwg. Spool No fit up joint
Date APT DCPL HZL Date Date APT
Date
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
Signature
DCPL HZL
SCHDULE FO
S Activities Drawing No. SHEET Size
No. NO (Inch)
SKS to FF Pipe Rack Area ( Column No C7 to C21 & F9 to F13)

Fabrication & Erection of HP pipe line with welding and


1 supports. 6"

3-HZL-DCPL-ISO-HP-01 01 & 02

Loop and Steam Trap with valve Fabrication & Erection of HP


2 pipe line (Sht -01 of 02 & 02 of 02) with supports and welding 6", 4", 1"
up to ground level.
SKS Building at EL 25.9 to EL 6.5

Fabrication & Erection of HP pipe line with supports and


3 3-HZL-DCPL-ISO-HP-01 02 of 02 4"
welding.

FF Building at EL 11.0 up to EL 6.5

4 Fabrication & Erection of HP pipe line along with steam trap, 3-HZL-DCPL-ISO-HP-01 02 of 02 6"
valve with welding and supports.
TG Building and New pipe rack area

Fabrication & Erection of HP pipe line (Separator Tank Steam


5 outlet to TG Inlet) piping supports and welding. 6"

Fabrication & Erection of New Pipe Rack Structural 3-HZL-DCPL-ISO-HP-01 01 of 01

Fabrication & Erection of HP Steam line to Separator Tank


6 6"
and Axiliary Steam line with supports and welding.

Steam vent line (Warmp up line) to atmosphere with valve


7 2"
and support
FOR LP STEAM (INJECTION) TO TG

Fabrication & Erection of LP Steam line from Existing line


8 connected to TG Injection , valve , Steam trap and NRV with 3-HZL-DCPL-ISO-LPS-01 01 of 01 6"
support and welding.

Fabrication & Erection of Dump Steam line to condenser, 6", 8",


9 3-HZL-DCPL-ISO-DS-01 01 of 01
valve, safety valve with supports and welding. 10", 12"

10 Fabrication & Erection of Steam blowing piping arrengement

11 Radiography Test
12 Hydro Test
13 Insulation & Cladding work

14 Steam blowing activity


SCHDULE FOR MS PIPE LINE
Runing Total no During Start Finish Work status
Mrt of Joints (Day)
Fabrication Weld Joint Support
72mtr. Line laying &
Erection and 6nos
joint fit-up complete fabrication
170 42 18 2/5/2020 ### under
progress

fabrication under
22, 44, 8 22, 22, 68 9 ### ###
progress

45 42 13 ### ### 30mtr. Completed not started

76 32 19 ### ### under progress not started

20 20 3 ### ### 12mtr. Completed

### ###

15 joints
40 34 5 3/1/2020 3/5/2020 24mtr. Completed not started
completed

12 15 3 3/6/2020 3/8/2020 not started

50 34 6 ### 3/3/2020

6, 10, 4 , 11, 12, 8,


9 3/4/2020 ###
12 8

4 3/9/2020 ###

2 ### ###
2 ### ###
13 ### ###

01-04-2020 to
continuous
s Remarks

Erection
72mtr. Line laying &
Erection and 6nos
joint fit-up complete.
Work under progress

fabrication under
progress

under progress

not started

Flow
Elements
fiting after
Steam
blowing

not started

Flow
Elements
fiting after
Steam
blowing
After steam
blowing
connect to
Turbine Inlet
SCHDULE FOR MS PIPE LINE

S No. Activities Drawing No. SHEET NO Size (Inch) Runing Mrt Total no of During (Day) Start Finish Work status
Joints
SKS to FF Pipe Rack Area ( Column No C7 to C21 & F9 to F13) Fabrication Erection
6" piping
6" piping 60mtr
1 Fabrication & Erection of HP pipe line with welding and 6" 170 42 18 2/5/2020 2/21/2020 60mtr with 6 with 6 butt joint
supports. butt joint
copmt copmt
3-HZL-DCPL-
01 & 02
ISO-HP-01
Loop and Steam Trap with valve Fabrication & Erection of HP
2 pipe line (Sht -01 of 02 & 02 of 02) with supports and welding 6", 4", 1" 22, 44, 8 22, 22, 68 9 2/20/2020 2/29/2020
up to ground level.
SKS Building at EL 25.9 to EL 6.5
Fabrication & Erection of HP pipe line with supports and 3-HZL-DCPL-
3 02 of 02 4" 45 42 13 2/12/2020 2/25/2020
welding. ISO-HP-01
FF Building at EL 11.0 up to EL 6.5
Fabrication & Erection of HP pipe line along with steam trap, 3-HZL-DCPL-
4 02 of 02 6" 76 32 19 2/22/2020 3/10/2020
valve with welding and supports. ISO-HP-01
TG Building and New pipe rack area
Fabrication & Erection of HP pipe line (Separator Tank Steam
5 6" 20 20 3 3/11/2020 3/13/2020
outlet to TG Inlet) piping supports and welding.
Fabrication & Erection of New Pipe Rack Structural 3/11/2020 1/15/2020
3-HZL-DCPL-
Fabrication & Erection of HP Steam line to Separator Tank 01 of 01
6 ISO-HP-01 6" 40 34 5 3/1/2020 3/5/2020
and Axiliary Steam line with supports and welding.

Steam vent line (Warmp up line) to atmosphere with valve


7 2" 12 15 3 3/6/2020 3/8/2020
and support
Fabrication & Erection of LP pipe line, valve , Steam trap and 3-HZL-DCPL-
8 01 of 01 6" 50 34 6 2/26/2020 3/3/2020
NRV with support and welding. ISO-LPS-01

Fabrication & Erection of Dump Steam line to condenser, 3-HZL-DCPL-


9 01 of 01 6", 8", 10", 12" 6, 10, 4 , 12 11, 12, 8, 8 9 3/4/2020 3/12/2020
valve, safety valve with supports and welding. ISO-DS-01

10 Fabrication & Erection of Steam blowing piping arrengement 4 3/9/2020 3/12/2020

11 Radiography Test 2 3/13/2020 3/15/2020


12 Hydro Test 2 3/16/2020 3/18/2020
13 Insulation & Cladding work 13 3/19/2020 3/31/2020

14 Steam blowing activity 01-04-2020 to continuous


Remarks

Flow Elements fiting


after Steam blowing

Flow Elements fiting


after Steam blowing

After steam blowing


connect to Turbine
Inlet
SCHDULE FOR MS PIPE LINE
Piping line No/Name: Raw Water Piping
Contractor Name: JMD
Comments:
FILED Activity (Piping Pre-fabrication & Start Finish Remarks
S No Erection)
1 Sandblasting and painting work ### ### Completed
2 inside cleaning of pipeline ### ### Completed
3 Edge prepare , Fit-up & Erection of pipe line
Pipeline align/elevation check ### Continue under progress

4 All butt joints check ### Continue under progress


5 Positioning all structure supports & ‘U’ clamp as
per site ### Continue under progress

6 Dye penetrant Test 1/5/2020 Continue under progress


7 Hydro testing ### 3/30/2020
8 All observation to be corrected as per condition ###
Continue

You might also like