You are on page 1of 17

GENES4/ANP2003, Sep.

15-19, 2003, Kyoto, JAPAN


Paper 1194

The Evolution and Future Development of the


High Temperature Gas Cooled Reactor
H. L. Brey*
Consultant to the Japan Atomic Energy Research Institute

This report chronologically traces the development of the high temperature gas cooled reactor
(HTGR) and includes an examination of current international research activities and plant designs.

The evolution of the HTGR as a safe, environmentally agreeable and efficient energy source for
the generation of electricity and for a broad range of high temperature industrial heat applications has
been on-going throughout the past four decades. This report depicts the development of the HTGR
through international plant designs and selected facilities from initial research to the present focus on
the modular gas turbine and high temperature heat applications such as the production of hydrogen 1,2).

This advanced nuclear heat process, with an average core outlet temperature approaching 950°C
and using ceramic coated fuel in a helium cooled, graphite matrix, provides a broad and unique set of
features and physical properties for scientific investigation as a major energy source for supporting the
needs of society well into the 21st century. This paper provides a review of current HTGR related R & D
activities including an overview of the HTTR and HTR-10 test reactors, status of GT-MHR and PBMR
plant development, the U.S. HTGR programme and a synopsis of the multi-national efforts of the EC and
Generation IV nuclear power technology program.

KEYWORDS: advanced reactor designs and development; gas cooled reactors

I. Introduction Interest in the HTGR has resulted in a wide array


of international research and development activities
including the multi-national efforts of the EC, Generation
The historical development of the HTGR is traced IV nuclear power technology and on-going R&D within
through individual plant designs and selected facilities the Member States associated with the IAEA.
from initial research and continuing through the design of
the modular steam cycle plant. This historical path, with A tabulation of the design characteristics of many
some discretionary latitude, can be divided into the of the HTGR plants, both past and future, is provided as
following four general areas: Appendix A at the end of this report.

• Early Gas Cooled Reactor (GCR) Development II. Historical Review of the HTGR
• HTGR Prototype Plants
• Demonstration Plants and Large Plant Designs 1. Early GCR Development
• Modular HTR Steam Cycle Plant Development
Gas-cooled reactor history effectively began with
Current and projected HTGR development the startup in November 1943 of the graphite-moderated,
activities that are anticipated to extend into the early air-cooled, 3.5-MW, X-10 reactor in Oak Ridge,
decades of the 21st century are divided into the following Tennessee. Commercial gas-cooled nuclear power began
three general areas: in 1953 when the United Kingdom decided to combine
plutonium production with electric power generation, and
• HTGR Powered Process Heat Applications work was started on the four-unit power station at Calder
• HTTR and HTR-10 Test Reactors Hall.
• Modular HTGR Gas Turbine Plant Development 1,2)
_______________________________________________ These first power reactors were graphite
* Corresponding author, Tel. +1-970-240-2791, E-mail: moderated with natural-uranium metal rods and cooled by
forced circulation of carbon dioxide at a pressure of 0.8
Larrybrey@AOL.com MPa and at an outlet temperature of 335°C. The U.K.'s
extensive commitment to GCR technology has included
construction of 26 Magnox reactors and 14 advanced gas- The Dragon reactor in the U.K. was the first
cooled reactors (AGRs), which deliver steam at the HTGR prototype. It began in 1959 as an international
modern conditions of 538°C and 16.5MPa. project of the European Organization for Economic
Cooperation and Development 5). The initial objective of
France's early interest in the GCR aided this project was to demonstrate the feasibility of the HTGR
development in the United Kingdom. In 1951, the 2-MW and to launch the development of a technology which had
research reactor at Saclay, which began operating with already begun at a low level in various national
nitrogen coolant and later switched to carbon dioxide, was laboratories. The Dragon Reactor Experiment first
the first gas-cooled reactor to use closed circuit, operated at power in July 1965 and reached its full-power
pressurized cooling. These experiments, coupled with the operation of 20MW(t) by April 1966. The reactor had a
experience of the air-cooled, open-circuit, G1 plutonium steel pressure vessel, graphite fuel elements with high-
production reactor, formed the basis for France's GCR enriched uranium-thorium carbide coated fuel particles,
program. Although similar to the U.K's program in coolant, and a helium coolant. Exit helium at 750°C was circulated
moderator, and fuel, the French program introduced the through primary heat exchangers and returned at 350°C
use of the prestressed concrete reactor vessel (PCRV), (electric power generation was not a feature of this
which the U. K. adopted for its later Magnox reactors and prototype).
all of its AGRS.
The reactor operated for long periods at full
The first nuclear power reactor in Japan, which power and demonstrated the successful operation of many
started commercial operation in July 1966, was the carbon components, e.g., the helium circuit purification system,
dioxide-cooled, 166MW(e) Tokai station located 80 miles the control rod drives, the fuel handling equipment, the
northeast of Tokyo. The plant design generally followed gas-bearing circulators, and the reactor fuel. As a test bed,
the design of the U.K's Magnox reactors; however, it provided much information on fuel and material
because of population concerns, its containment design irradiation tests and component tests under high-purity
provided a partial third barrier for a postulated release of helium conditions. The reactor operated until March 1976,
coolant by sealing after pressure decay. In 1969, the Japan at which time the project was terminated 6).
Atomic Energy Research Institute (JAERI) initiated
studies on the very high temperature gas-cooled reactor in Simultaneously with the initiation of the Dragon
recognition that a nuclear process heat source of 900°C or project, interest in Germany and the U.S. led to the 15
higher would find use in coal gasification and hydrogen MW(e) AVR at Julich, Germany, and the 40MW(e) HTGR
and methanol production 3). at Peach Bottom in the USA.

Development of the HTGR began in the 1950s to (2) The AVR


improve upon GCR performance. HTGRs utilize ceramic
fuel particles surrounded by coatings and dispersed in a In August 1959, the order was placed with the
graphite matrix, along with a graphite moderator. Either German partnership of BBC/Krupp for the construction of
prismatic graphite moderator blocks or spherical fuel an experimental nuclear power plant with a high
elements (pebbles) are employed. Helium is used as the temperature reactor of 46MW(t)/15 MW(e). Construction
coolant to permit an increase in the operating temperature, work on the plant at the KFA Nuclear Research Center in
and flows through coolant holes in the block type elements, Juelich began in 1961. Initial reactor criticality occurred in
or through the interstices present in the pebble bed core. August 1966, and on 17 December 1967 electricity was
HTGRs can operate at very high core outlet coolant supplied to the public supply grid for the first time. In
temperatures because of the use of an all ceramic core 4). February 1974, the mean gas outlet temperature, which
had initially been set at 850°C, was increased to 950°C.
2. HTGR Prototype Plants Operation of the AVR continued until December 1988. In
completing 21 years of service, the plant had accumulated
The initial HTGRs included the Dragon reactor more than 122,000 hours of operation with a 66.4% overall
experiment, the Arbeitsgemeinshaft Versuchsreaktor availability and had generated 1.67 billion kwhr of
(AVR) and Peach Bottom (No. 1). Common among these electricity 4).
plants were the utilization of steel vessels to contain the
primary system and the attainment of high core outlet The design of the AVR included a steel
temperatures culminating in the AVR achieving extended containment vessel and used particle fueled, graphite
operation at 950°C. spheres 6 cm. in diameter that traveled downward through
the core. Although the AVR initially included a core outlet
temperature of 850°C, this was subsequently raised to
(1) Dragon Reactor Experiment
950°C without decrease in plant performance.
level. These two features were to be dominant throughout
The AVR was the main fuel development tool for HTGR development of the 1970s and early 1980s.
the pebble bed concept, and it and supplementary Although the general focus of the HTGR plant designers
laboratory fuel testing became the major support of was on the development of large steam cycle units,
Germany’s position that an LWR-type containment barrier including the first significant design for a closed cycle gas
was not needed for future HTGRs 7). turbine plant, these designs did not materialize into the
commissioning of a nuclear plant. This was primarily
(3) Peach Bottom (No. 1) attributed to the nuclear industry being in a general state of
decline in those countries with national HTGR
Peach Bottom Unit 1 was the first prototype development programs.
HTGR in the U.S. The 40MW(e) plant, owned and
operated by the Philadelphia Electric Company, was built Performance of the THTR-300 and FSV in
as part of the U.S. Atomic Energy Commission Power validating reactor safety characteristics and the TRISO
Reactor Demonstration Program and the High coated fuel particle was very good. However, FSV was
Temperature Reactor Development Associates Program to beset with inconsistent operation and a corresponding low
demonstrate the feasibility of a high performance, helium capacity factor throughout its life. The THTR-300 also had
cooled, nuclear power plant. problems primarily associated with changing regulatory
requirements that contributed to delays that eventually
The reactor achieved initial criticality on March 3, ended up with a construction period of ~14 years.
1966, and the plant went into commercial operation in Corresponding financial concerns by the operating utilities
June 1967. It operated successfully with a gross capacity led to the premature shutdown of both these plants in the
factor of 74% and an overall availability of 88% (exclusive 1988-1989 time frame.
of planned shutdowns for R&D programs) from June 1967
until October 31, 1974, when it was shut down for (1) Fort St. Vrain (FSV)
decommissioning. Accumulated operation totaled 1,349
effective full-power days, for a total of 1,385,919 gross
electrical megawatt hours generated. The FSV HTGR was operated by Public Service
Company of Colorado as part of the U.S. Atomic Energy
Commission’s Advanced Reactor Demonstration Program.
Peach Bottom provided a valuable demonstration This plant was designed with several advanced features
of the high-temperature reactor concept by confirming the including; a.) A PCRV containing the entire primary
core physics calculations, verifying the design analysis coolant system, b.) A core of hexagonal, graphite block
methods, and providing a data base for further design fuel elements and reflectors with fuel in the form of
activities in the following areas: reactor core; mechanisms ceramic coated (TRISO) particles, c.) Once-through steam
in high-temperature helium; helium purification systems; generator modules producing 538°C superheated main and
and steam generator tube materials 6). reheat steam, and d.) Steam-turbine-driven axial helium
circulators. At its rated capacity, the FSV plant generated
3. HTGR Demonstration Plants 842MW(t) to achieve a net output of 330MW(e).

Early international development of the HTGR The steam cycle was essentially conventional,
focused on two basic core designs recognized specifically utilizing a standard reheat turbine, except that the steam
by their fuel element structure. The German core design flow was from the high-pressure turbine exhaust to the
has generally followed a core design incorporating helium circulator turbines before being reheated and
spherical fuel elements, whereas, beginning with Fort St. returned to the intermediate pressure turbine. The steam
Vrain (FSV), the U.S. core design included ceramic coated conditions were comparable to those of modern fossil fired
fuel particles imbedded within rods placed in large power plants.
hexagonal shaped graphite elements. The other major
HTGR designer during this period was Russia with their Initial electric power generation was achieved at
VG series of plant designs which incorporated the pebble FSV in December 1976, and 70% power was reached in
bed core. November 1977. Full-power operation was achieved in
November 19816). Although ~5.5 billion kwhr of
The HTGR plants that followed the successful electricity was generated at FSV, the plant operated at low
AVR and Peach Bottom included construction of FSV and availability primarily because of excessive downtime due
the Thorium High Temperature Reactor (THTR-300). A to problems with the water-lubricated bearings of the
major shift occurred with these plants including primary helium circulators. In spite of this low availability, the
systems enclosed within PCRVs rather then steel vessels, plant was a valuable technology test-bed, successfully
and accompanied by significant increases in plant power demonstrating the performance of several major systems,
including the reactor core with TRISO coated fuel particles the 1973 oil crisis and corresponding economic setback
in hexagonal graphite blocks, reactor internals, steam and collapse of the U.S. nuclear power market of 1975.
generators, fuel handling and helium purification 3). These plants incorporated cores of hexagonal graphite
blocks with TRISO coated fuel particles similar to FSV.
(2) Thorium High Temperature Reactor (THTR-300)
The German HTR-500 made considerable use of
The THTR-300 nuclear power plant included a the technology development for the THTR-300, with
steam cycle for the generation of electric power with a net simplifications and optimizations based on practical
output of 296MWe. The heat generated in the reactor core experiences with the THTR-300 4). This plant featured a
of the helium cooled, graphite moderated high temperature simple design with the primary system components located
reactor was transported via the helium gas coolant circuit within a single cavity PCRV, and included a pebble bed
(primary system) to the steam generators where it was reactor power level of 1,390MWt to produce 550MWe of
transferred to the steam-feedwater circuit (secondary electricity.
system) and then transported to the turbine generator. The
secondary system was cooled by means of a 180 m high The Russian HTGR development program
natural draught dry cooling tower 4). included the VG series of plants primarily developed at
OKBM in Nizhny Novgorod. Of these, the VG-400 design
incorporated a pebble bed reactor with a final power level
The THTR-300 power plant was sponsored by the of 1,060 MWt for co-generation applications of electricity
Federal Republic of Germany and Nordrhein Westfalen generation and process heat production for steam
(NRW). Construction of this 300MWe plant began in 1971, reforming of methane. The reactor was designed for a core
but primarily due to increasing licensing requirements, the helium outlet temperature of 950°C. During the
plant was not completed until 1984. This pebble bed preliminary phases of the design development both the
reactor plant was connected to the electrical grid of the pebble bed and prismatic fuel block variants of the core
utility Hochtemperatur-Kernkraftwerk GmbH (HKG) in were analyzed. As a result of the design and engineering
November 1985. analysis, the pebble bed core was chosen for further
development due to considerations of simplified fuel
In August 1989, the decision was made for the element manufacturing technology and possibility of full
permanent shutdown of the THTR-300. This action was scale testing in experimental reactors, utilization of a
not due to technical difficulties associated with the plant, simplified core refueling mechanism and the possibility of
but was the result of an application by HKG for early core refueling during on-load reactor operation. Also
decommissioning based on a projected short fall in funding considered was a gas turbine cycle/VG-400 reactor plant.
and contractual changes in the allocation of
decommissioning costs between the FRG, NRW and HKG (1) Early Gas Turbine HTGR Assessment
that would take effect upon the termination of the
demonstration phase in 1991. A promising approach for making good use of the
high temperature capability of the HTGR is to use the
Operation of the THTR-300 was successful in primary helium coolant to drive a gas turbine in a direct
validating the safety characteristics and control response of closed cycle arrangement. In the 1970s, this was
the pebble bed reactor, primary system thermodynamics extensively studied in the U.S., Germany, the U.K. and
and the good fission product retention of the fuel elements France. At that time, the concept was based on enclosing a
7)
. The plant operated over 16,000 hrs. and generated 2.891 large (2,000 to 3,000MWt) reactor core and the gas turbine
billion kwhr of electricity 8). power conversion system within a prestressed concrete
reactor vessel 24). One of the early gas turbine designs was
4. Large HTGR Steam Cycle Plant Designs 7) the HTGR-GT by General Atomic Co. This plant was
projected to have the potential for high plant efficiencies
The primary focus of international HTGR (40%) under dry cooling conditions and achievement of
designers in the 1970s and early 1980s was associated with even higher efficiencies (50%) when bottoming cycles
the development of large HTGR units. Continued interest were incorporated. An assessment of this plant was
in development of larger steam cycle HTGR plants subsequently conducted in ~ 1980 with the focal point for
included the German HTR-500, the Russian VG-400 and the assessment being the potential commercial HTGR-GT
the United States’ HTGR-Steam Cycle (SC) plants. plant of 2000 MW(t)/800MW(e) and an average core
outlet temperature of 850°C.
In the U.S., the focus in the early 1970s was on
HTGR-Steam Cycle designs of 770 to 1,160MWe. The principal findings of the assessment (in the
Contracts to General Atomic Co. from U.S. utilities early 1980s) were as follows: (1) the HTGR-GT is feasible,
included 10 plants that did not materialize due primarily to but with significantly greater development risk than that
associated with the HTGR-SC; (2) at the level of
performance corresponding to the reference design, no
incremental economic incentive can be identified for the
HTGR-GT to offset the increased development costs and
risk relative to those for the HTGR-SC (this was true over
the range of cooling options investigated); (3) the relative
economics of the HTGR-GT and HTGR-SC are not
significantly affected by dry cooling considerations; and
(4) although the reduced complexity of the cycle may
ultimately result in a reliability advantage for the HTGR-
GT, the value of that potential advantage could not be
quantified.

Although these (early 1980s) findings did not


provide the basis for the HTGR-GT as the preferred lead
commercial plant, the HTGR-GT continued to engender Fig. 1 Maximum accident core temperature depicted
interest from participating utilities. This interest stemmed chronologically for U.S. HTGR designs 3)
from the potential of the HTGR-GT for improved
efficiencies at high core outlet temperatures, the basic (1) HTR-MODULE 4)
simplicity of the gas turbine cycle (low maintenance, high
capacity factors), low water use requirements and The 80MW(e) HTR module (HTR-MODULE)
attractive co-generation characteristics 6). concept, developed by Siemens/Interatom, was the first
small, modular type HTGR concept to be proposed (Fig. 2).
In retrospect, this plant, although significantly Although initially developed in the early 1980s for
different in general configuration compared to the current industrial process heat applications, the passive safety
modular HTGR/gas turbine designs, its basic cycle has features of the side-by-side concept, coupled with the other
remained unaltered throughout these past twenty years. attractive characteristics of the modular concept, soon led
to the proposed electricity generation application. Work on
a generic, site independent safety assessment of the HTR
5. Modular HTGR Steam Cycle Plant Development module was initiated with the filing, in 1987, of the safety
analysis report in the State of Lower Saxony. The HTR
The overall good safety characteristics of all module safety concept is characterized by comprehensive
HTGRs are due to: the high heat capacity of the graphite protection of the environment by passive system
core; the high temperature capability of the core characteristics even under extreme, hypothetical accident
components; the chemical stability and inertness of the conditions.
fuel, coolant, and moderator; the high retention of fission
products by the fuel coatings; the single phase The safety features of the HTR module were
characteristics of helium coolant; and the inherent negative based on the design condition that, even in the case of
temperature coefficient of reactivity of the core. Fig. 1 failure of all active cooling systems and complete loss of
provides a graphic overview of maximum accident core coolant, the fuel element temperatures would remain
temperatures for U.S. HTGR designs. within limits such that there is virtually no release of
radioactive fission products from the fuel elements. Such a
The modular HTGR adds the unique condition guaranteed that the modular HTR power plant
characteristic of being able to cool the reactor entirely by would not cause any hazard to the environment either
passive heat transfer mechanisms following postulated during normal operation or in the case of an accident.
accidents without exceeding the failure temperature of the
coated particles. This characteristic has been achieved by A small core diameter (~3m) stems from the
deliberately decreasing the core power level and requirement for reactor shutdown from all operating
configuring the reactor so that natural heat removal conditions using only free falling control rods in reflector
processes can limit fuel temperatures to levels at which the borings. The requirement to keep the maximum fuel
release of fission products from the reactor system to the element temperature for all possible accidents inherently
environment is insignificant for postulated accidents. Even below 1600°C, a temperature at which all radioactive
for extreme accidents having very low probabilities of fission products are contained within the fuel elements,
occurrence, the cumulative fission product release at the leads directly to a mean power density of 3MW/m3. In
site boundary is estimated to be below those acceptable order to gain as much power as possible from the core, the
under defined protective action guidelines 7). core height was chosen as large as possible.
availability and capacity factors and potential close-in
siting required by industrial plants. The VGM modular
HTGR, with a power output of 200MW(t) and a
configuration very similar to the German HTR-MODULE
was selected as a low power pilot unit after considering
several different designs. The power required by large
industrial complexes would be reached by the use of
several such modules, providing the necessary reserves for
both high availability and high capacity factors.

(4) MHTGR

In 1983, the U.S. organization representing


utility/user interests in the HTGR program, the Gas Cooled
Reactor Associates, conducted a survey to determine the
utility nuclear generation preference for the future. This
survey resulted in a strong interest for smaller generation
increments. This was an important input leading to the
evaluation and subsequent selection of the modular HTGR
in 1985 3). Following a detailed evaluation in the spring
and summer of 1985, a side-by-side concept similar in
configuration to a German module design was chosen as
the reference concept for further design and development
by the U.S. program. The basic module was designed to
deliver superheated steam at 17.3MPa and 538°C. An
initial module power level of 250MWt was selected, but
subsequent detailed safety analyses showed that this power
Fig. 2 HTR-MODULE arrangement level could be increased with the hexagonal graphite block
core design without compromising margins. Adopting an
annular core allowed the power level to be increased
(2) HTR-100
initially to 350MWt. Other reactor design changes and
analysis refinements subsequently allowed the power to be
With the objective that nuclear power plants
increased to 450MWt, while maintaining adequate margins
utilizing small HTGRs can provide economic,
to component and safety limits 10).
environmentally favorable and reliable electricity and heat
for community and industrial purposes, Brown, Boveri und
Central to the Modular HTGR (MHTGR) passive
Cie and Hochtemperatur-Reacktorbau initiated the design
safety approach was the annular reactor core of prismatic
of the HTR-100 pebble bed plant. This design featured a
fuel elements within a steel reactor vessel. A low-enriched
285MWt HTGR with a net electrical output of 100 MW on
uranium, once-through fuel cycle was used. For a standard
the basis of the AVR concept and utilized the advanced
steam cycle MHTGR plant, the steam output from each of
technologies of THTR-300 components and systems. The
the four modules was connected to an individual turbine
primary system included the reactor, steam generator and
generator. The four module plant consists of two separate
helium circulator in a single, vertical steel pressure vessel.
areas, the nuclear island and the energy conversion area.
The reactor core included 317,500 spherical elements of
TRISO type particles and a power density of 4.2 MW/m3.
The most fundamental characteristic of the
In the equilibrium cycle, 55% of the spherical elements
MHTGR that separated it from previous reactor designs
were fuel, with the remainder being graphite. The basic
was the unique safety philosophy embodied in the design
design for this plant incorporated two HTR-100 units with 11)
. First, the philosophy requires that control of
overall capability of producing 170 to 500 t/hr of industrial
radionuclides be accomplished with minimal reliance on
steam at 270°C and 16 bar, with 100 to 175MW(e) gross
active systems or operator actions; the approach to safety
output 9).
is to rely primarily on the natural processes of thermal
radiation, conduction, and convection and on the integrity
(3) VGM
of the passive design features. Arguments need not center
on an assessment of the reliability of pumps, valves, and
Analysis of the heat energy market in Russia their associated services or on the probability of an
revealed a need for the development of small nuclear operator taking various actions, given the associated
power energy sources whose power utilization factor and uncertainties involved in such assessments.
high degree of safety could meet the requirements of high
Second, the philosophy requires control of It was the development of the above mentioned
releases by the retention of radionuclides primarily within modular HTGR steam plants that provided the key
the coated fuel particle rather than reliance on secondary emphasis to initiation of the HTGR coupled to a gas
barriers (such as the primary coolant boundary or the turbine power conversion system. With few exceptions, it
reactor building). Thus, ensuring that the safety criteria are is the German HTR-MODUL and the HTR-100 reactor
met is the same as ensuring that the retention capability of designs that are being utilized by ESKOM as the base for
the coated fuel particles is not compromised. the PBMR. The MHTGR forms the basis for the GT-MHR
reactor design 7). Both PBMR and GT-MHR reactors
utilize an annular core arrangement.

III. Current and Projected HTGR Development


Activities 2)

It was during the 1980s and early 1990s that a


major focus of the international HTGR community was
directed towards investigation of the industrial heat
applications and co-generation capabilities provided by the
modular HTGR. Investigation into the capabilities of this
nuclear energy source to supply high temperature process
heat as well as the need to evaluate the safety and
technological features of the HTGR were contributing
factors in the decisions by the Japan Atomic Energy
Research Institute (JAERI) and China’s Institute of
Nuclear Energy Technology (INET) to construct the High
Temperature Engineering Test Reactor (HTTR) and High
Temperature Gas Cooled Reactor Test Module (HTR-10),
respectively.

It was also in the early 1990s that the emphasis of


HTGR development moved from a balance of plant that
incorporated the Rankine Steam Cycle to the gas turbine
(Brayton Cycle) plant for the generation of electricity. This
major re-direction in research and development is the
Fig. 3 MHTGR arrangement 3)
outgrowth of the notable improvement in net cycle
efficiency through the use of the Brayton Cycle coupled
The assessment of the capability of the MHTGR
with the corresponding projected decrease in cost brought
to control accidental radioactivity releases shows that the
about by plant simplification and modularization of the
doses are a small fraction of the U.S.10CFR100
HTGR.
requirements even for the bounding analyses which
consider only the systems, structures and components that
The current and projected development activities
require neither operator action nor other than battery
of research, design and testing the next generation of
power. In fact, the exposures are so low that the protective
HTGR plants is the subject of the following sections. It is
action guidelines would require no evacuation or sheltering
anticipated that the focus of nuclear power development
plans for the public as specified in the utility/user
will include a much greater emphasis on use of this energy
requirements. The evaluation confirms that accident dose
source for process heat applications and not continue the
criteria can be met with a containment system that places
present, almost exclusive, role of electricity production.
primary emphasis on fission product retention within the
fuel barriers.
1. HTGR Powered Process Heat Applications
Consistent between the modular HTGR designs Nuclear energy is now being used to produce
of the HTR-MODULE, MHTGR and the VGM are side- about 17% of the world’s electricity. As of 1998, this
by-side steel vessels housing the reactor and the helium included 442 nuclear reactors, with a total capacity of
circulator and steam generator in a common configuration. about 354 gigawatts-electric (GWe). Yet, only a few of
Fig. 3 depicts the U.S. MHTGR. The VGM is similar with these plants are being used to supply hot water and steam.
the inclusion of another vessel housing an auxiliary The total capacity of these plants is about 5 GWt, and they
cooling system. are operating in just a few countries, mostly in Canada,
China, Kazakhstan, Russia and the Ukraine. Water cooled be connected independently to a steam turbine and/or other
reactors offer heat up to 300°C. These reactor types steam utilizing systems 13).
include PWRs, BWRs, pressurized heavy water reactors,
and light water cooled graphite moderated reactors. The production of hydrogen and subsequent
Organic cooled heavy water moderated reactors reach synthesis to alternative, more environmentally acceptable
temperatures of about 400°C, while liquid metal fast fuels such as methanol, is the primary focus of current
breeder reactors produce heat up to 540°C. Gas cooled research into the process heat applications that would
reactors reach even higher temperatures, about 650°C for effectively utilize the high temperature capabilities of the
the AGR, and 950°C for the HTGR. HTGR.

For heat applications, specific temperature Many international organizations are focusing on
requirements vary greatly. They range from low the modular HTGR as the energy source for the co-
temperatures (~ room temperature), for applications such generation applications of high temperature industrial
as hot water and steam for agro-industry, district heating, processes and electricity production. In addition to
and seawater desalination, to ~ 1000°C for process steam hydrogen production, processes such as heavy oil recovery,
and heat for the chemical industry and high pressure coal liquification and gasification are being explored. The
injection steam for enhanced oil recovery, oil refinery capability for high temperature process heat applications is
processes, and refinement of coal and lignite. The process key to the selection of the GFR and VHTR as Generation
of water splitting for the production of hydrogen is at the IV advanced reactor designs (see section 4).
upper end. Up to about 550°C, the heat can be supplied by
steam; above that, requirements must be served directly by
process heat due to the need for high steam pressures. An 2. High Temperature Test Reactors
upper limit of 1,000°C for nuclear supplied process heat is
set on the basis of the long-term strength capabilities of Interest in the HTGR as an advanced nuclear
metallic reactor materials 12). power source for co-generation applications of electricity
production and high temperature heat for industrial
It is this unique capability of the HTGR as a processes has resulted in the construction of the HTTR by
nuclear energy source to provide the broad range of JAERI and the HTR-10 by INET of Tsinghua University
temperatures required to support a myriad of industrial in Beijing, China. These nuclear test facilities have the
heat applications that is the emphasis for scientific capability of achieving core outlet temperatures to 950°C
investigation and development currently being pursued on and 900°C, respectively, and will be utilized to support
an international basis throughout the HTGR community. research and development activities including validation of
An example of the use of the modular HTGR for industrial HTGR safety and general performance characteristics,
applications is the MHTGR by General Atomics (GA). electricity generation via the gas turbine and validation of
high temperature process heat applications. Key design
GA is investigating the capabilities and flexibility characteristics of the HTTR and HTR-10 test reactor plants
of the MHTGR to provide superheated steam for a are located herein in Appendix A.
multitude of industrial applications. Energy requirements
of industrial process complexes vary widely, according to (1) HTTR
varying steam conditions, capacity requirements, and the
ratio of thermal to electric power. The high temperature Construction of the HTTR at JAERI’s research
and pressure steam at 17.3MPa and 540°C produced by the facilities in Oarai, Japan, began in 1991. First criticality
Process Steam/Co-generation Modular Helium Reactor was obtained November 1998 with full power (at an
(PS/C-MHR) can provide energy for heat cycles in a wide average core outlet temperature of 850°C) achieved in
range of process applications and industrial complex sizes December 2001. This plant includes a 30MWth graphite-
and capacities. The PS/C-MHR is being designed to meet moderated, helium cooled reactor comprised of hexagonal
the rigorous requirements established by the U.S. NRC and fuel elements with TRISO coated fuel particles in compact
the electric utility-user industry for a second generation form. Cooling of the HTTR consists of a main cooling
power source for the future. system, an auxiliary cooling system and a vessel cooling
system. The main cooling system is composed of a
The most economic PS/C-MHR plant primary cooling system, a secondary helium gas cooling
configuration includes an arrangement of several identical system and a pressurized water cooling system. The
modular reactor units, each located in a single reactor primary cooling system has two heat exchangers, an
building. The plant is divided into two major areas: the intermediate heat exchanger and a primary water cooler 14).
energy conversion area, containing turbine generators, a
nuclear island containing the several reactor modules, and The HTTR will be utilized to establish and
other balance of plant equipment. Each reactor module can improve on HTGR related technology, for the performance
of innovative research, as a test facility for fuel and
materials irradiation, and to demonstrate process heat • The HTGR reactor size had been reduced in
applications such as hydrogen production. Relative to developing the passively safe module design. At
commercialization of the closed cycle gas turbine HTGR the same time, the size of industrial gas turbines
plant, the HTTR will be a valuable facility in had increased. The technology was now available
demonstrating the safety features of the HTGR, for a single turbo-machine to accommodate the
performance and qualification of materials and heat energy from a single HTGR module. Highly
components and in fuel and fission product behavior 15). effective compact recuperators had been
developed. Recuperator size and capital
(2) HTR-10 equipment cost are key economic considerations.
• Highly effective plate-fin recuperators are much
The HTR-10 Test Module is located at the INET smaller than equivalent tube and shell heat
research site northwest of Beijing and is a major project in exchangers, provide for substantially less
the Chinese National High Technology Program. complexity and capital cost, and are a key
Construction of this plant was completed in the fall of requirement for achieving high plant efficiency.
2000. Initial criticality was achieved on 1 December with • The technology for large magnetic bearings had
full power obtained in February 2003. been developed. The use of oil lubricated bearings
for the turbo-machine with the reactor coolant
The HTR-10 is a pebble bed 10MWth HTGR directly driving the turbine was problematic with
with a primary helium circuit pressure of 3.0MPa. This test regard to the potential coolant contamination by
reactor is the first step of the HTGR development strategy the oil. The availability of magnetic bearings
in China. The objectives of the HTR-10 are to verify and eliminates this potential problem 19).
demonstrate the technical and safety features of the
modular HTGR and to establish an experimental base for A major requirement was for the plant to become
developing nuclear process heat applications, including substantially simplified in order to provide a significant
testing of electricity/heat co-generation and gas turbine reduction in the capital expenditure for new capacity
technology 16). additions. Figs. 4 and 5 provide a comparison of nuclear
power plant efficiencies and the simplification that can be
3. Modular HTGR Gas Turbine Plant Development achieved in moving from the HTGR steam cycle to the
basic direct gas turbine cycle, respectively.
It has long been recognized that substantial gains
in the generation of electricity from nuclear fission can be
achieved through the direct coupling of a gas turbine to a
HTGR. This advanced nuclear power plant is unique in its
use of the Brayton cycle to obtain a net electrical
efficiency approaching 50% 17). This plant provides a
promising alternative for the utilization of nuclear energy
to produce electricity. Although evaluation of this concept
was initiated over twenty years ago, it was initially
terminated due to the technical risks primarily in the
component areas of magnetic bearing, compact plate-fin
heat exchanger and turbo machinery development.
Subsequent technological advancements in the design and
operation of these components, coupled with the
international capability for their fabrication and testing has
Fig. 4 Plant efficiency comparison 3)
resulted in renewed interest in this HTGR concept 18).
The possibilities presented by the gas turbine
In order to be competitive, the thermal efficiency modular HTGR for substantial improvement in nuclear
of nuclear power had to be markedly improved to compete power plant efficiency coupled with the potential for
with modern, high efficiency fossil plants. HTGR significant gains in lowering capital and operating costs
technology has always held the promise for electricity due to plant simplification have brought about an
generation at high thermal efficiency by means of a direct increasing interest by international research organizations
Brayton cycle and fortuitously, technological and plant developers. Overviews of the PBMR and GT-
developments during the past decade provided the key MHR are provided in the following sub-sections.
elements to realize this promise. These key elements are as Appendix A contains plant characteristics of many gas
follows: turbine plant designs under investigation by Member
States of the IAEA.
recuperator, precooler, intercooler and turbomachine as
shown in Fig. 6.

(a) Steam cycle

(b) Closed cycle

Fig. 5 System simplification, steam cycle to the closed


cycle gas turbine plant 3)

(1) Gas Turbine-Modular Helium Reactor (GT-MHR)

Renewed interest in the nuclear powered closed


cycle gas turbine system within the U.S. resulted in the
present GT-MHR developmental program beginning in Fig. 6 GT-MHR PCS arrangement 25)
early 1993. Subsequent discussions with organizations of
the Russian Federation resulted in GA and MINATOM Work performed in the preliminary design phase
entering into a Memorandum of Understanding to has included full scale tests of a recuperator heat exchange
cooperate on the development of the GT-MHR with the element, development of lab-scale technologies for
goal, following design and development, to construct, test production of coated plutonium fuel and testing of
and operate a prototype in Russia 22). FRAMATOME materials for the high temperature elements of the
joined this program in 1996 with Fuji Electric becoming a turbomachine. Work continues in 2003 on the detailed
participant and sponsor in 1997. The US government also design of selected systems and components including
provides limited financial support on a matching resource initiation of the reactor system and power conversion unit
basis with MINATOM for the destruction of weapons development tests, fabrication of initial test fuel and
plutonium. Most of the design work on the GT-MHR is carbon-carbon composites, initiation of pre-licensing
being performed within the nuclear organizations of the activities with the Russian licensing authorities and
Russian Federation with financial and development of the safety analysis and environmental
management/technical support from all members of the impact reports. The schedule for the GT-MHR includes
consortium. commissioning of the first module in 2010 23).

The conceptual design is complete on this Although the GT-MHR is initially to utilize a
600MWt/293MWe plant. The basic primary system of this plutonium fuel cycle which has the capability of achieving
closed cycle gas turbine plant includes two side-by-side a burn-up approaching 95%, the versatility and flexibility
steel vessels with an outside appearance similar to the of this core will allow for the application of a wide range
MHTGR (Fig. 3). The reactor vessel houses a 600MWt of diverse fuel cycles. Fuel derived from uranium, thorium
annular core comprised of hexagonal fuel elements. The and a variety of plutonium grades is under consideration
power conversion system (PCS) vessel houses the for long term applications in the GT-MHR 15).
pressure turbo/compressor unit and intercooler; the low
(2) Pebble Bed Modular Reactor (PBMR) pressure turbo/compressor unit and precooler; and the
power turbine/generator unit and recuperator, respectively.
Table 1 provides key design characteristics for the
The PBMR was first identified by ESKOM, the demonstration PBMR plant.
electric utility of South Africa, in 1993 as an option for
expansion of their electrical generation capacity.
Subsequently, ESKOM contracted with Integrators of
System Technology to perform a technical and economic
study of the feasibility of the PBMR for the generation of
electricity. This study, which was completed in early 1997,
supported the continued development of the PBMR.
Reactor development follows the HTR-MODULE pebble
bed which was previously licensed in Germany for
commercial operation. However, the PBMR utilizes an
annular core with a fixed central column.

A series of internal reviews by ESKOM and


subsequent independent reviews of this feasibility study by
international entities have generally acknowledged that the
PBMR is technically and economically capable of meeting
the requirements originally set by ESKOM for
commercialization. These requirements included: a.) New
generation capacity capable of being located where the
load growth is taking place in South Africa (coastal
regions); b.) Small, modular increments of electrical
generation capacity corresponding to system growth needs;
c.) Reduced exposure to negative environmental issues
such as carbon dioxide emissions and capable of providing Fig. 7 PBMR primary cycle
a strategy for economic mitigation of greenhouse gas
reductions; d.) Generating plants placed where there would Table 1 PBMR demonstration plant characteristics 26)
be a limited need for extensive transmission system Plant Parameter Value
additions, and; e.) Cost of capital and plant operation to be Reactor Output 400 MWt
within those costs presently being achieved at ESKOM's Net Electrical Output ~ 170 MWe
largest coal fired stations (with targets of capital cost less Cycle Efficiency 41.6% avg.
than US$ 1,000/installed kw and overall generation, Core Inlet Temperature 489°C
transmission and distribution costs of utility operations Core Outlet Temperature 900°C
within 2.0 cents/kwhr 15) ) (Note: as of May 2003, the Helium Pressure 9MPa at 100% power
overnight cost requirement is < $1500/kW installed 29)). Avg. Core Power Density 4.78 MW/m3
High and Low Pressure 91%
Over the past five years ESKOM, British Nuclear Turbine Efficiency
Fuel and the Industrial Development Corporation of South High and Low Pressure 90.5%
Africa have been developing the PBMR design and Compressor Efficiency
performing detailed assessments for the introduction of Power Turbine Generator 92.5%
this advanced nuclear power plant as additional generation Efficiency
capacity on the ESKOM electric grid and for
commercialization in the international market place 7).
4. International Research and Development Activities
On 16 May 2003 the decision was made to
proceed with the final design development and The technological and economic possibilities
construction of a demonstration unit at the ESKOM presented by the modular HTGR gas turbine plant for the
Koeberg nuclear plant site north of Cape Town. This generation of electricity as well as high temperature
demonstration plant features a pebble bed annular core process heat for applications such as hydrogen production
reactor housed within a steel vessel connected to a direct are currently under investigation by many Member States
cycle gas turbine power conversion system. Fig. 7 is a of the IAEA. A tabulation of plant characteristics for these
depiction of the PBMR primary cycle. The power plants is provided in Appendix A.
conversion system includes three major steel vessels with
associated interconnecting piping housing the high
Examples of these diverse plant designs include a.) Topics within the area of reactor physics and fuel
the GTHTR 300 being developed by JAERI and the cycle studies (HTR-N) include;
ACACIA plant in the Netherlands. • the qualification of tools and methodologies
for HTR applications,
The Japanese GTHTR 300 plant incorporates a • the analysis of the physics of HTR cores and
600MWt hexagonal fuel block core. The power conversion of possible HTR fuel cycles, mostly focused
system includes a vertical heat exchanger vessel and a on the feasibility of cores fed only with civil
horizontal turbo-machine vessel to allow for bearing plutonium from the 1st or 2nd generation,
support and stable rotor operation. The cycle configuration • the comparison of the wastes from LWRs and
is considerably simplified in comparison to the GT-MHR HTRs,
and PBMR by elimination of compressor unit(s) and • the behaviour of irradiated HTR fuel in the
corresponding intercooler. The overall net efficiency for conditions of deep geological disposal.
this electricity producing plant is projected at ~45%.
b.) Within the area of fuel technology, the HTR-F
The ACACIA plant is being designed by NRG as objectives have included;
a small combined heat and electricity producer for industry. • to restore the state-of-the-art technology on
This plant incorporates a 40MWt pebble bed HTGR to HTR fuel fabrication,
produce 14MW of electricity and 17 tonnes of 10 bar, • to develop a competitive HTR fuel, that is
220°C steam per hour. with very good performances in terms of high
burnup and temperature, with very low
(1) HTR Technology Network (HTR-TN) Programme 21) fission product releases and with a
competitive fuel cycle cost,
In Europe about 20 industrial and research
• to verify the past tests on the ability of HTR
organisations created the HTR Technology Network
fuel to reach extremely high burnups
(HTR-TN), to pool their effort of development of the (~ 700 GWd/tHM) needed to exploit the
technologies needed for a first industrial deployment of
potential of HTRs for burning plutonium
modular direct cycle HTRs in the next decade and for
efficiently.
longer term improvements of this type of reactor.
Significant support has been received from the European
c.) The objective of the material development (HTR-
Commission in its 5th Euratom Framework Programme
M) project is to qualify the key materials for HTR
(FP5) for the development of HTR technology in the fields applications: the reactor vessel material, the high
of reactor physics, fuel and fuel cycle, materials,
temperature (~ 850°C) materials for the turbine and
components and licensing issues. In this context an
reactor internal structures (e.g., control rod cladding)
important programme of irradiation of HTR fuel, vessel
and the graphite. The graphite grades used in the
material and graphite is under preparation, and the
former HTR projects are no longer available and the
technology of fabrication of coated particle fuel is being
suitability for HTR applications of the present
mastered. International co-operation is also being
industrial products is not known. Therefore a
developed with the main organisations active in HTR
programme of selection of appropriate grades was
development outside of Europe. undertaken and in particular an irradiation of samples
from different manufacturers started in the 2nd half of
The objectives shared by HTR-TN partners are:
2002 in HFR. For the vessel, two design options exist:
• to create the technological basis for an industrial
emergence of HTR in Europe by 2010,
• the cooled vessel (PBMR), for which existing
• to incite long term evolutions (design PWR vessel materials can be used without
optimisation, temperature increase, opening of R&D,
new application areas...) for improved
• the hot vessel (GT-MHR), kept at the coolant
competitiveness and fullfilment of the goals of
inlet temperature (~450°C). Modified
sustainable development.
9Cr1Mo steel has been selected for this
option. This material has many records of
The following areas of research and development
industrial applications but few nuclear ones,
have been selected by the HTR-TN partners with a budget
in particular in large thickness.
of ~ 17 M€, of which 50% is funded by the EC:
d.) The objective of the HTR-E project is to assess
the feasibility issues related to the components and
technologies of the power conversion system (PCS)
and to make recommendations for further
developments. The key issues are identified from the
existing industrial projects (GT-MHR and PBMR).
These issues include: (2) Generation IV Nuclear Power Technology

• The feasibility of a 300 MWe high-efficiency Ten countries have been involved in an
helium turbine operating at 850°C. A preliminary international cooperative effort to assure that advanced
design will be made and a programme of tests on nuclear energy systems are available for worldwide
a mock-up for the validation of the performances deployment by 2030. These countries have agreed on a
of this design will be defined. The realisation of framework of international cooperation in research known
these tests will be proposed later for the follow-up as Generation IV.
of the project in the 6th Framework Programme
(FP6). Through the Generation IV International Forum
• The recuperator, which is a key component for (GIF) these participating countries are defining the
the thermal efficiency of the PCS, with heavy framework of research and development that will bring
operating loads (temperature transients and about a future generation of nuclear energy systems that
differential pressure) and stringent compactness can be licensed, constructed, and operated in a manner that
requirements. A concept will be selected and a will provide competitively priced and reliable energy
mock-up designed, fabricated and tested in CEA products while satisfactorily addressing nuclear safety,
Grenoble, to validate the performances of the waste, proliferation and public perception concerns. The
design in steady and transient conditions. mission of these energy systems will be electricity
• Active magnetic bearings (and the necessary generation, hydrogen and process heat production, and
related catcher bearings) are the solution proposed actinide management 20).
for supporting the turbo-machine in order to avoid
lubrication of bearings, with the related risks of The very-high-temperature reactor and the gas-
lubricant ingress. This technology exists, but the cooled fast reactor have been identified by the GIF as two
mechanical and thermal loads for the GT-MHR of the six systems comprising Generation IV.
are above the levels met in present industrial
applications. Therefore a prototype of magnetic (a) Very High Temperature Reactor (VHTR)
and catcher bearing will be designed, fabricated
and tested on a test bench of the University of Development of a VHTR to achieve economically
Dresden. competitive hydrogen production is a high priority of the
• A leak tight rotating seal would allow the ability U.S. Department of Energy’s (DOE) nuclear programme.
to have classical bearings outside of the PCS A bill authorizing the research, design and construction of
vessel for the vertical support of the turbo- an advanced nuclear plant (anticipated as a VHTR) with
machine and therefore to reduce the loads on the the capability for co-generation applications of electricity
magnetic and catcher bearings and to make their generation and hydrogen production is under consideration
design less challenging. It would also allow the in the U.S. Congress. Table 2 provides the design
capability to put the alternator outside the primary characteristics for the VHTR.
circuit, facilitating its design and maintenance.
Different concepts are being assessed, but it Table 2 VHTR design parameters 20)
seems that no existing technology can provide an Reactor Parameters Reference Value
acceptable leakage. The possible ways of Reactor power 600 MWth
improvement will be explored and a solution will Coolant inlet/outlet 640°/1,000°C
be developed. Tests will be prepared for FP6. Temperature
Core inlet/outlet pressure Dependent on process
e.) The objective of HTR-L is to establish a European Helium mass flow rate 320 kg/s
safety approach for modular direct-cycle HTRs. A large Average power density 6-10 MWth/m3
consensus on an approach taking into account the specific Reference fuel compound ZrC-coated particles in
safety features of modular HTRs and leading to a blocks, pins or pebbles
simplification in the reactor design (e.g., suppression of Net plant efficiency >50%
engineered safety systems, limitation of the number of
components with a safety classification, reduction of the The VHTR system utilizes a graphite moderated,
loads on the third barrier…) is very important for helium cooled reactor with a thermal neutron spectrum and
consolidating the economic competitiveness of HTRs. a once-through uranium cycle. This plant is primarily
Therefore the results of HTR-L will not only be presented aimed at high temperature process heat applications, such
to European safety authorities, but HTR-TN will also take as coal gasification and thermochemical hydrogen
initiatives to incite large international discussions on these production with excellent efficiency. The VHTR has a
results, in order to broaden the consensus. coolant outlet temperature of 1,000°C and therefore can
supply a broad spectrum of high temperature, non-electric the GFR and VHTR through the viability and performance
applications. The reference 600MWth VHTR dedicated to phases of development. Table 4 provides an overview of
hydrogen production can yield >2,000,000 m3 of hydrogen these costs broken down into general categories.
per day. Also, the VHTR has the capability to be an
attractive heat source for co-generation applications in Table 4 R&D costs for the GFR and VHTR 20)
large industrial complexes. Area of Development GFR R&D VHTR R&D
Cost-$ Cost-$
The goal set for the VHTR is for a demonstration Fuels & Materials 300 M 170 M
plant in 2015. The summary schedule to achieve this goal Reactor Systems 100 M 20 M
includes: Balance of Plant 50 M 280 M
• An accelerated preconceptual/conceptual design Safety 150 M 80 M
• Two step 10CFR license with the construction Design & Evaluation 120 M 90 M
license in 2010 Fuel Cycle 220 M 30 M
• An estimated construction time frame of 5 years Total 940 M 670 M
and $600 M with an NRC operating license in
2015 The development requirements of each Gen. IV
• A 2007 start date for procurement of long lead plant vary considerably. An example of some of the R&D
items needs for the VGTR include the following:
• Cost estimates include an average of $40 M/year • Fuel including the following:
in 2004-2011 for design work ($25 M in FY04 o demonstration of the TRISO fuel to
and rising to $80 M in FY09) required quality level and performance
o fabricate test particles and test in
(b) Gas-cooled Fast Reactor (GFR) prototypic reactor conditions (and
accident conditions)
The GFR features a fast neutron spectrum and o extend to high burnup
closed fuel cycle for efficient conversion of fertile uranium (>200,000MWD/Mtu)
and management of actinides. The referenced reactor is a o For core outlet temperatures >900°C,
600 MWth/288 MWe, helium cooled system operating fuel temperatures >1,300°C may be
with an outlet temperature of 850°C using a direct Brayton needed. Examine higher temperature
cycle gas turbine for high thermal efficiency 20) (Table 3). coatings such as ZrC and repeat fuel
This high helium coolant temperature makes it possible to testing as indicated above.
generate electricity or for hydrogen production and other
process heat applications, all with high conversion. • Develop, test and design new control rod
materials
Table 3 GFR design parameters 20) • Graphite fabrication and qualification
Reactor Parameter Reference Value • Decommissioning issues such as graphite disposal
Reactor power 600 MWth • Select/qualify materials for high temperature
Net plant efficiency 48% applications in key components such as the
(direct cycle helium) reactor vessel, hot gas ducts and components,
Coolant inlet/outlet 490°C/850°C recuperator, intermediate heat exchanger, etc.
temperature and pressure at 90 bar • Test for effects on materials due to impurities in
Average power density 100 MWth/m3 the primary coolant helium
Referenced fuel compound UPuC/SiC (70/30%) • Define and demonstrate the hydrogen production
With about 20% Pu content processes
Volume fraction, 50/40/10% • Complete R&D on the Power Conversion System
Fuel/Gas/SiC components including the turbocompressor,
Conversion ratio Self-sufficient magnetic bearings, recuperator, precooler and
Burnup, Damage 5% FIMA; 60 dpa intercooler, seals and couplings, etc.

(3) Additional U.S. HTGR R&D Programmes


(c) R&D for Generation IV Gas Cooled Reactors
Along with Generation IV work mentioned above,
Significant R&D will be necessary to achieve the a primary focus within the DOE advanced gas reactor
goal of bringing any Generation IV plant to (AGR) programme is the continued development and
commercialization. The GIF, through the technical qualification of coated fuel particles. This fuel programme
working group on gas-cooled reactors, has provided a includes supporting the near term deployment of an AGR
general quantification of the costs associated with bringing for energy production in the U.S. by reducing market entry
risks associated with fuel production and qualification and IV. Conclusions
to establish a bridge to VHTR concepts and more
advanced fuels 27). Deployment of the HTGR as an advanced source
of nuclear energy for the 21st century incorporates a strong
The DOE AGR fuel programme requirements developmental base spanning the past four decades
include: including Dragon, the AVR, Peach Bottom, Fort St. Vrain,
• Manufacture of high quality coated fuel particles and the THTR power plants. This base exhibited an
(LEU with a prismatic gas cooled reactor design, excellent foundation for demonstrating the safety and
GT-MHR focus) environmental aspects of the HTGR, particularly the high
• Complete the design and fabrication of reactor temperature performance of UO2 kernel TRISO coated fuel
test rigs for irradiation testing of coated fuel particle.
forms
• Demonstrate fuel performance during normal and This developmental base has been recently
accident conditions via irradiation, safety tests enhanced by the construction of the HTTR and the HTR-
and PIE 10 test reactors in Japan and China, respectively. These
• Improve predictive fuel performance/behaviour plants are currently undergoing testing to further
and fission product transport models demonstrate the safety and environmental capabilities of
the HTGR to average core outlet temperatures approaching
Within EPRI, cost reduction has been adopted as the 950°C. These plants will also be used to investigate and
theme for their R&D programme specific to future nuclear validate materials and components for future high
plants. R&D projects have been initiated on a prioritized temperature process heat applications.
cost reduction basis as funding increments are available.
Of the categories for this programme, EPRI projects The major emphasis of HTGR development in the
leading to new products such as the HTGR gas turbine past two decades has been with the small, modular HTGR
reactor and advancing the technology of the potentially with the flexibility of being coupled to a gas turbine for the
competitive HTGR alternatives to the LWR are being generation of electricity or to other process outputs such as
investigated. Projects that have been initiated include: steam for a multitude of high temperature industrial heat
• Inspectability and maintainability (I&M): This applications. The current focus on the modular HTGR
project applied EPRI’s LWR experience to an with an annular core is expected to contributed
evaluation of the I&M associated with the HTGR substantially to the goals of reduced capital and operating
gas turbine PCS. Detailed recommendations were costs by plant simplification and a significant improvement
provided to the GT-MHR and PBMR projects in in cycle efficiency over existing nuclear plant designs.
2001 and 2002, respectively
• Graphite endurance: This project details the It is significant to note that the constituency in the
challenges of graphite irradiation, manufacture development of the HTGR has changed substantially from
capabilities, oxidation, availability, etc. which the single nationalism of the past (i.e., Germany, Russia or
must be addressed for a 60 year lifetime. the US) to the international involvement of many nations
working together in the investigative research required to
• Silver retention: This continuing project
addresses the challenge posed by radioactive bring this advanced nuclear energy source to fruition. The
reasons for this are obvious; the HTGR is a design that
silver deposits on the PCS components.
shows promise for significant improvements in nuclear
Development of a deposition/penetration
resistant coating for the most vulnerable plant economics and attendant plant efficiency, with the
long-term prospect of achieving substantial marketability
equipment surfaces is currently underway.
and associated financial reward. However, the task ahead
• Catcher bearings: This on-going project is
to commercialize this advanced nuclear plant must
addressing the requirements and test facility to
overcome significant hurdles including: A modular HTGR
validate the bearings required in the event of
has not been licensed or constructed, and the size and
failure of the magnetic bearings in the PCS.
environmental application of major components such as
• Helium seals: This project has now identified the
plate-fin recuperators and turbomachines utilizing
preferred helium seal for the PCS and has
magnetic bearings has yet to be achieved for the gas
contracted for the laboratory testing of this seal
turbine plant.
• Hydrogen production: The HTGR has a strong
potential to be a major energy source for However, successful commercial deployment of
hydrogen separation. EPRI has initiated a project this plant has the potential of significantly advancing
that investigates the economic potential of the nuclear power as a world-wide primary energy source for
HTGR in this role 28). the future with corresponding financial reward to the
investors willing to take the risks associated with its 15.) H.L. Brey (Ed), “Helium gas turbine reactor
development. technical challenges; A characterization for use
in focusing R&D resources,” Electric Power
References Research Institute TP-11490, Palo Alto,
California, USA, January (2000).
1.) H.L. Brey, “Development history of the gas tur 16.) D. Zhong, Z. Qin, Y. Xu, “Present status of the
2.) bine modular high temperature reactor,” IAEA- HTR-10 project,” IAEA-TECDOC-1210,
TECDOC-1238,Vienna, 21-44, (2001). November (1998).
3.) H.L. Brey, Historical background and future 17.) International Atomic Energy Agency, “Design
development of the high temperature gas cooled and development of GCRs with closed cycle gas
reactor,” Proc. Seminar on HTGR Application turbines”, IAEA-TECDOC-899, Vienna, August
and Development, Tsinghua University, Beijing, (1996).
China, March 19-21, 2001. 18.) International Atomic Energy Agency, “High
4.) P. M. Williams, et al., “MHTGR development in temperature gas cooled reactor technology
the United States”, Progress in Nuclear Energy, development,” IAEA-TECDOC-988, Vienna,
ISSN 0149-1970, Vol. 28, No. 3, pp. 265-346, December (1997).
(1994). 19.) M.P. Labar, W.A. Simon, “International
4.) International Atomic Energy Agency, Gas Cooled Cooperation in developing the GT-MHR,” IAEA-
Reactor Design and Safety, Technical Report TECDOC-988, Vienna, pp. 59-71, December
Series No. 312, Vienna (1990). (1997).
5.) C.A. Rennie, “Achievements of the Dragon 20.) U.S. DOE Nuclear Energy Research Advisory
Project”, Ann. Nuclear Energy 5 (8), pp.305-320, Committee and the Generation IV International
(1978) Forum, “A technology roadmap for generation IV
6.) R. A. Moore, et al., “HTGR experience, programs, nuclear energy systems,” GIF002-00, (2002).
and future applications”, Nuclear Engineering 21.) D. Hittner, “HTR-TN and the European
and Design 72, pp. 153-174, (1982). programme for the development of HTR
7.) H.L. Brey, (Ed), “Current status and future technology,” Paris, France, (2002).
development of modular HTGR technology”, 22.) W.A. Simon, A.S. Shenoy, “International
IAEA-TECDOC-1198, Vienna, (2000). cooperation in developing the GT-MHR,
8.) R. Baumer, I. Kalinowski, “THTR commissioning evolution and program status, ECN-R-98-004,
and operating experience”, Energy, Vol. 16, Petten, the Netherlands, pp. 67-81, November
No.1/2, pp. 59-70, (1991). (1997).
9.) S. Brandes, W. Kohl, “HTR 100 industrial, 23.) N. Kuzavkov, “Status of the international GT-
nuclear power plant for generation of heat and MHR program”, Presented at the 4th meeting of
electricity”, IAEA-TECDOC-436, Vienna, pp. the IAEA Coordinated Research Program on
213-234, (1987). Evaluation of HTGR Performance, Vienna,
10.) F.A. Silady, H. Gotschall, “The 450 MWt (2002).
MHTGR: More power with the same high level of 24.) J. Cleveland, I. Lewkowicz, “Status of the IAEA
safety”, Third International Seminar on Small and coordinated research programme on design and
Medium Sized Nuclear Reactors, New Delhi, evaluation of heat utilization systems for the
India, August (1991). HTTR”, Presented at the 2nd International
11.) F.A. Silady, L.L. Parme, “The safety approach of Conference on Multiphase Flow, Kyoto, Japan,
the modular high temperature gas-cooled reactor April (1995).
(MHTGR), 11th International Conference on the 25.) International GT-MHR Report, “International
HTGR, Dimitrovgrad, USSR, June (1989). GT-MHR Project”, Report 100025, Rev. 0,
12.) J. Kupitz, et. al., “Status and prospects for small March (1998).
and medium sized reactors,” IAEA, Vienna, 26.) A. Koster, Personal Communication, PBMR (Pty)
(1998). Ltd. 29 May (2003).
13.) A. Shenoy, “Modular helium reactor for non- 27.) M. Feltus, “Overview of the DOE advanced
electric applications”, IAEA-TECDOC-923, reactor fuel development and qualification
Vienna, pp. 253-277, January (1997). program”, Penn. State Lecture, USA, April
14.) K. Sanokawa, T. Fujishiro, T. Tanaka, Y. (2003)
Miyamoto, S. Shiozawa, M. Okubo, “Status of 28.) E. Rodwell, “EPRI’s technical path towards new
HTGR development in Japan,”ECN-R-98-004, US nuclear plants”, EPRI, USA, May (2003)
Petten, the Netherlands, pp. 49-61, November 29.) E. Mulder, “Marketing and financial aspects”,
(1997). IAEA-ICTP Workshop, Trieste, Italy, PBMR
(Pty) Ltd., July (2003).
Appendix A: Selected Characteristics of HTGR Plants

Steam Cycle HTGRs


AVR Peach Ft. St. THTR- HTR-500 VGM- HTR- MHTGR
Bottom Vrain 300 400 Module
Country/Origin Germany U.S. U.S. Germany Germany Russia Germany U.S.
Thermal Pwr, MWt 46 115 842 750 1,390 1,060 200 350
Net Elec. Pwr, MWe 13 40 330 300 550 Co-Gen. 80 139
Pwr Density, 2.5 8.3 6.3 6.0 6.6 6.9 3.0 5.9
MW/m3
Core Out Temp, °C 950 725 775 750 700 950 700 686
Helium Pres, MPa 1.1 2.25 4.8 3.9 5.5 5.0 6.6 6.4
Steam Temp. °C 505 538 538/538 530/530 530 535 530 538
Elec. Gen., MWh ~ 1,670 ~ 1,380 ~ 5,500 ~ 2,890 N/A N/A N/A N/A
Reactor Type Pebble Sleeve Block Pebble Pebble Pebble Pebble Block
Fuel Enrichment Various HEU HEU HEU LEU LEU LEU LEU
Fuel Composition Oxide Carbide Carbide Oxide Oxide Oxide Oxide Ox-Carb
Fuel Coating Various BISO TRISO BISO TRISO TRISO TRISO TRISO
Vessel Material Steel Steel PCRV PCRV PCRV PCRV Steel Steel

HTGR Test Reactors


HTTR HTR-10: GT-ST
Configuration
Country/Origin Japan China
Thermal Pwr, MWt 30 10
Elec. Pwr, MWe -------- GT~2, ST~1.4
Cycle Eff., % N/A 34.4
Core Out Temp, °C 950 max. 900
Helium Pres, MPa 4.0 3.0
GT Cycle Type N/A In-Direct
Core Type Block Pebble
Fuel Enrichment LEU LEU
Fuel Composition Oxide Oxide
Fuel Coating TRISO TRISO
Vessel Material Steel Steel

Modular HTGR Gas Turbine Plants


GT-MHR PBMR- MHTGR- ACACIA GTHTR- 600MW- MPBR
demo. IGT 300 HTGR-GT
Country/Origin Russia/U.S. S. Africa China Netherlands Japan Japan U.S.
Thermal Pwr, MWt 600 400 200 40 600 600 250
Net Ele Pwr, MWe 278 ~ 170 ~ 96 Co-Gen. 273 287 112
Pwr. Den, MW/m3 6.5 4.78 3.0 ---------- --------- 5.77 --------
Core Out Temp, °C 850 900 900 800 850 850 850
Helium Pres, MPa 7.15 9.0 6.0 2.3 6.8 6.0 7.9
Cycle Type Direct Direct In-Direct Direct Direct Direct In-Direct
Core Type Block Pebble Pebble Pebble Block Pin/Block Pebble
Fuel Enrichment HE-Pu LEU LEU LEU LEU LEU LEU
Fuel Composition PuO Oxide Oxide Oxide Oxide Oxide Oxide
Fuel Coating TRISO TRISO TRISO TRISO TRISO TRISO TRISO
Vessel Material Steel Steel Steel Steel Steel Steel Steel

You might also like