Box Culverts Method Statement PDF
Box Culverts Method Statement PDF
SCOPE OF WORK
As cross‐main drainage structures, box culverts will be constructed at instructed locations by the
Supervisor’s Representative to replace hydraulically inadequate pipe culverts.
METHOD
A site store has been set‐up to stock materials including cement and reinforcing steel. Mobilization of
plant and equipment will commence upon receipt of a go ahead/ site instruction to commence work on
the culverts.
The main works will include activities such as setting out, excavations, blinding, reinforcement and
formwork, batching, mixing and casting, curing and backfilling.
All works will only commence upon acceptance and/or approval of previously completed work at every
stage of the construction.
Safety precautions are to be adhered by ensuring that, all plants are operated by authorized operators.
Besides, all workers in the concrete section will be provided with safety gears including dust masks,
hand gloves, gumboots, helmets, goggles and others as applicable.
DESCRIPTION OF OPERATIONS