METHOD STATEMENT FOR CONSTRUCTION OF BOX CULVERTS 

SCOPE OF WORK 

As cross‐main drainage structures, box culverts will be constructed at instructed locations by the 
Supervisor’s Representative to replace hydraulically inadequate pipe culverts. 

METHOD 

A site store has been set‐up to stock materials including cement and reinforcing steel. Mobilization of 
plant and equipment will commence upon receipt of a go ahead/ site instruction to commence work on 
the culverts.  

The main works will include activities such as setting out, excavations, blinding, reinforcement and 
formwork, batching, mixing and casting, curing and backfilling. 

All works will only commence upon acceptance and/or approval of previously completed work at every 
stage of the construction. 

Safety precautions are to be adhered by ensuring that, all plants are operated by authorized operators. 
Besides, all workers in the concrete section will be provided with safety gears including dust masks, 
hand gloves, gumboots, helmets, goggles and others as applicable. 

DESCRIPTION OF OPERATIONS 

Activity  Details/ Description  Plant  labor 


Setting out   A survey team consisting of one surveyor,  2 No. Pick up  1 No. surveyor 
  two assistances and four chainmen will     
  take levels and set out the excavation  1 No. back hoe  2 No. assistance 
  area by use of pegs to mark points on the  loader   
  ground.     4 No. chainmen 
       
Excavations  Upon acceptance of the setting out by  2 N o. driver 
the S.R, excavations will be done by use   
of a back hoe loader to the satisfaction of  1 No. operator 
the S.R.   
  1 No. foreman 
Excavated levels will be taken after   
acceptance of excavations.   
Blinding,  Teams headed by a concrete foreman will  1 No. 300 ltr.  1 No. foreman 
  start with blinding the base to the  Concrete mixer   
  specified thickness using materials  Or  1 No. self  2 No. operator 
  complying with specifications and of  propelled mixing   
  approved mix design to the acceptance of  plant  3 No. assistance 
  the S.R.    foremen. 
    3 No. pick‐up   
Reinforcement  Reinforcement will be laid and fixed by    5 No. drivers 
  adhering to the bar bending schedule and  1 No. water   
  any other site instruction issued by the  tanker  5‐8 No. artisans 
  S.R regarding bending of steel bars.     
    1 No. tipper truck  10‐20 unskilled 
Formwork   Upon approval of the reinforcement,     
  formwork using wrought and unwrought  1No. poker   
  timber will be firmly fixed to the  vibrator 
  satisfaction of the S.R.  
   
Batching  Batching to the instructed mix design will 
  be done for concrete materials that 
  comply with relevant 
  Specifications. 
   
Mixing and  Upon acceptance of batching, concrete 
casting  mixing will be done by means of a 
  concrete mixer and concrete casted and 
  compacted using a poker vibrator to the 
  satisfaction of the S.R.  
   
Quality control  Concrete cubes at acceptable batch 
  intervals will be cast to monitor quality of 
  concrete laid.  
    
  Similar procedures will be applied to 
construct the walls, end structures and 
finally the deck all to the satisfaction and 
approval  of the S.R. 
Curing and  A team led by the concrete foreman will  1 No. water  2 No. foremen 
Backfilling.  ensure proper curing of the structures  tanker   
with adequate portable water.    2 No. operator 
  1 No. roller   
After curing, a team headed by the    4 No.  drivers 
earthworks foreman will ensure that  1 No. tipper truck   
backfilling with specifications compliant     4‐6 unskilled 
materials is adequately compacted and  2 No. pick up 
accepted by the S.R.    
1 No. back hoe 
loader 