Professional Documents
Culture Documents
BIDDER
CONSTRUCTION METHODOLOGY
1. Site Survey will be done for taking block levels, establishing Benchmarks and
grid pillars will be erected.
2. Excavation will be taken up in the basement and surplus earth will be disposed
elsewhere.
3. Area required for building foundations will be excavated first and will be
completed in a month’s time. Balance earthwork will be done subsequently.
4. Shoring shall protect required slopes. Dewatering pumps shall do necessary de
watering.
5. Care to be taken for neighbors’ property.
6. While initial excavation is in progress materials like steel, cement, concrete
blocks etc will be procured.
7. Foundation work in all towers will start simultaneously and further work will
continue non – stop till completion.
8. Minimum of two floors centering materials will be mobilized for all the
towers. Besides these additional centering materials will be mobilized for
retaining walls, frontal buildings, lifts shafts etc.
9. Foundations for podium slab structure/Blocks will also start simultaneously as
and when the excavation in the area is completed.
10. Horizontal waterproofing in basement will start after completion of column
foundations.
11. Retaining walls construction will commence immediately after excavation.
12. Vertical waterproofing of the works will be taken up after construction of
the retaining walls.
13. Basement floor concreting will be done after horizontal waterproofing.
14. Shuttering works for columns, beams and slabs will start as and when Work
progresses after which concreting will take off.
15. Block work, Door frame, Lintels & Chajjas will commence in all Blocks after de-
shuttering the form work (21 days after slab Concreting.)
16. Plastering, Floor concreting, flooring, fixing of Doors, Windows and Painting
works etc will follow.
17. Batching plant will be established at the site.
18. Concrete pumps will be deployed for Pumping concrete.
BIDDER
19. Tire mounted Tower cranes with 30 to 35 m of radius coverage will be erected
for two or three towers as per coverage of booms.
20. Building hoists and passenger lifts will be provided separately for all the
blocks.
21. Conventional steel formwork (steel plates, spans and props) will be used for
columns, beams and slabs.
22. Concrete is transported to the site by transit mixers and pumped from there.
23. Some of the activities may be rescheduled/modified at he site to give
allowance for the work.
BIDDER
SAFETY MEASURES AT WORKPLACES
SAFETY OF WORKPLACES
1. All appropriate precautions shall be taken to ensure that all workplaces are
safe and without any risk of injury to the safety and health of workers.
2. Safe means of access to and egress from all workplaces shall be provided and
maintained, and indicated wherever necessary.
3. All appropriate precautions shall be taken to protect persons present at or in
the vicinity of the construction site from all risks, which may arise from such
site.
EXCAVATIONS
Adequate precautions shall be taken in any excavation -
(a) by suitable shoring or otherwise to guard against danger to workers
from a fall or dislodgement of earth, rock or other material;
(b) to guard against dangers arising from the fall of persons, materials or
objects or the inrush of water into the excavation;
(c) to secure adequate ventilation at every workplace so as to maintain an
atmosphere fit for respiration and to limit any fumes, gases, vapors, dust or
other impurities to levels which are not dangerous or injurious to health and
are within limits laid down by Safety Measures;
(d) to enable the workers to reach safety in the event of fire, or an inrush
of water or material;
(e) to avoid risk to workers arising from possible underground dangers
such as the circulation of fluids or the presence of pockets of gas, by
undertaking appropriate investigations to locate them.
BIDDER
HEALTH HAZARDS
1. Where a worker is liable to be exposed to any chemical, physical or biological
hazard to such an extent as is liable to be dangerous to health, appropriate
preventive measures shall be taken against such exposure.
2. The preventive measures referred to in paragraph 1 above shall comprise-
a. the replacement of hazardous substances by harmless or less hazardous
substances wherever possible; or
b. technical measures applied to the plant, machinery, equipment or
process; or
c. Where it is not possible to comply with subparagraphs (a) or (b) above,
other effective measures, including the use of personal protective
equipment and protective clothing.
3. Where workers are required to enter any area in which a toxic or harmful
substance may be present, or in which there may be an oxygen deficiency, or
a flammable atmosphere, adequate measures shall be taken to guard against
danger.
4. Waste shall not be destroyed or otherwise disposed of on a construction site
in a manner that is liable to be injurious to health.
FIRST AID
Arrangements shall be made for medical attention of workers who have suffered an
accident or sudden illness.
BIDDER
SAFETY FACTORS
Safety nets will be used.
Guardrails will be provided around the periphery during concreting of the
slab.
Opening in floors, walls will be cardoned with M.S Pipes, Ply or GI sheets.
Workers will be provided with safety belts and helmets.
Wire ropes of all the hoisting machinery will be inspected periodically.
All the machinery will be regularly serviced and maintained.
Experienced senior staff will be supervising the safety aspects.
Adequate lighting will be provided for night work.
QUALITY ASPECTS
We have our own Quality Management System, which ensures the delivery of quality
goods at the clients.
1. SURVEY
Since it is a high rise residential complex, the survey work is equally important.
Buildings will be located on the ground with high precision theodolites
by establishing grid pillars.
A senior surveyor will crosscheck location of Blocks independently.
All levels will be established and controlled using dumpy leveling
instruments.
Column location and verticality will be checked with utmost care.
Well-qualified and experienced survey staff will be deployed at the site.
All survey equipment will be calibrated.
2. EXCAVATION
Founding strata will be got approved by the designer / consultants
Any excess earth cut will be filled with lean concrete / well-compacted
sand.
BIDDER
3. FORM WORK
Good quality props, spans, plates will be used.
Props will be spaced as per the load distribution and are adequately
braced for lateral stability.
De- shuttering oil will be used for easy removal of formwork.
Quality records for formwork passing will be maintained.
4. CONCRETING
Good quality aggregates will be procured.
Design mix will be carried out from a reputed laboratory/Institute
Concrete cubes will be tested for the strength of concrete.
Curing will be done by ponding water on the slabs and other horizontal
surfaces and by continuously wetting the tied jute bags on the vertical
surfaces.
Plasticizers will be used for getting dense concrete and to avoid
honeycombing.
Vibrators will be used for getting dense concrete and to avoid
honeycombing.
Any minor honeycombing noticed after the removal of formwork will
be touched upon with rich mortar.
Production, Transportation and Placing of concrete will be done by
mechanized means, which ensure a superior quality.
Checking for embedded parts will be done and records maintained.
5. REINFORCEMENT
Samples will be tested in reputed laboratories.
Highly skilled bar-benders will be deployed.
Cover blocks will be provided to ensure adequate concrete cover to
reinforcement.
Reinforcement passing certificates will be maintained.
6. BLOCK WORK
Cement concrete blocks will be procured from reputed manufacturers.
Block work will be cured by wetting with water.
BIDDER
Tests for compressive strength will be conducted at the site to ensure
quality.
QUALITY POLICY
Jampana Construction Private Limited strives to achieve enhanced customer
satisfaction by delivering quality product through timely completion with safe
working environment. We dedicate ourselves for continual improvement in all fields
of our business.
QUALITY OBJECTIVES
To consistently deliver quality product by adhering to the set specifications,
contractual, regulatory and statutory requirements.
To achieve enhanced customer satisfaction through cost-effective and timely
completion.
To motivate and train the staff for continual improvement of quality
standards.
To update and implement the procedures complying with international
standards.
SYSTEMS DESCRIPTION
The system consists of following elements:
Quality Management System
BIDDER
This manual is not subject to the client’s approval, when required under a contract
specific project quality plans are submitted for approval. Any system amendments
necessary to meet particular contract requirements will be incorporated in the
project quality plan with the approval of the Project Director or his representative.
CONSTRUCTION MANUALS
Management Control Systems
Plant and Machinery
Finance and Administration
BIDDER
SYSTEM REVIEW
The quality system is subject to annual review by the Managing Director with the
Project Director. The review shall include a appraisal of the quality system including
the results, quality audits and any submission from the quality system.
DESIGN CONTROL
To ensure that all design inputs are available for developing design
and detailed engineering drawings.
To ensure that design output meets the requirements of IS codes
and specifications.
To ensure that the design specification shall be covered and that the
design meets the requirements of specification/codes.
To ensure that the new designs are documented and communicated
to site. Manager Quality will ensure that the quality system for design control
is followed.
CONTRACT REVIEW
Tenders are prepared in accordance with the procedure in the tenders and contracts
manual. Prior to submission, each tender is subject to review by Managing Director
at a tender review meeting to ensure that:
All the necessary information is available to undertake the work.
Any difference in the tender requirements is resolved.
Sufficient resources are available to carryout the contract.
PURCHASING
Process of purchasing goods from process of requisition to delivery, is the
responsibility of materials department. Seeking advice and assistance when required
from the Planning and Engineering Department.
BIDDER
The material management manual outlines the required procedure including
evaluation.
DOCUMENT CONTROL
Documents relating to a specific project are controlled under the project quality
plan. Each quality plan gives total correspondence, drawings and other documents
including proper documentation and storage.
All the documents before dispatch or after receipt are checked for accuracy and
updated.
All changes in drawings and specifications are incorporated shall be recorded and a
master list and latest applicable revisions are maintained.
Any third party or independent inspection and/or testing shall be carried out by
competent personnel.
All the items which are not under gone the process of testing to be kept separately
and to be released for concerned areas only after testing with a “good for use” mark.
BIDDER
CONTROL OF MEASURING AND TEST EQUIPMENT
Equipment at site can be divided in two categories.
1. Field Equipment
2. Lab Equipment.
Field Equipment shall be controlled by a plant engineer/controller. He shall maintain
a register with a minimum of following date.
Identify number and name of the equipment indicating the date of site
entry and removal, mentioning the reasons for dispatch.
Calibration details and evidence.
Current location and users name.
Required calibration frequency.
Filed check requirements.
Records of any repairs.
Plant engineer/controller should advice the user regarding field check requirements
and ensure that he understands the same. The user shall maintain records of all field
checks.
Laboratory equipment shall be controlled by person in charge of laboratory. Usage
of lab equipment generally is in accordance with the relevant IS codes or code
applicable to project.
QUALITY AUDITS
Internal Quality Audits shall be conduct on a planned basis. Project Director is
responsible for auditing the company quality system.
1. Quality Management System
2. Project Quality Plans
3. Work and Project specific procedures
He may delegate the responsibility to qualified personnel. Auditors shall not have
a direct responsibility for project.
AUDIT PREPARATION
Prior to the execution of the audit following procedure is prepared as a agenda.
1. Audit Scope
BIDDER
2. Objectives
3. Identification of reference documents
4. Organizational unit to be audited
5. Persons to be interviewed
6. Date and Time of various audit activities
WORK METHODS
Project Manager in consultation with DGM/AGM (P&M) shall prepare project
execution plan describing methods of construction.
Any time in course of operation, any one discovering non-conformity shall report to
the appropriate authority, which shall record it. Using the non-conformity report
from, the person in charge designated for the quality plan shall be informed of all
non-conformity.
QUALITY RECORDS
Maintaining of quality records to the required standards shall be taken care. Project
Quality Management team shall ensure that all quality records are readily identified,
collected, achieved when required
TRAINING
Jampana Construction Private Limited recognizes that personnel employed on the
project should be suitably qualified for the task that they are required to fulfill. Each
employee undergoes an annual appraisal, on one to one bases, with his immediate
Manager. The employees training needs identified at his appraisal, are recorded in
the appraisal form and sent to the Personnel Department. Training needs, identified
at other time are also conveyed to the Personnel Department by the Manager
concerned.
BIDDER
The Personnel Department gets in touch with the department where applicable,
concerning any proposed training courses.
Skilled and highly skilled workers shall also be trained at maintenance depots/ job
sites and depending upon specific project requirement is issued competency
certificate.
BIDDER