You are on page 1of 6

International Journal of Power and Energy Systems, Vol. 23, No.

3, 2003

DESIGN PARAMETERS OF HV TESTING


STATION AT QATRANA SUBSTATION
H. Obeid∗

Abstract The applied voltage to the primary winding of the voltage


regulator (VR) is phase-to-phase voltage (380 V).
This article presents the procedure implemented to calculate The voltage applied to the terminals of control system
the design parameters of High-Voltage Pollution Testing Center and instrumentation is single-phase 220 V. In this regard
(HVPTC) at Qatrana substation. These parameters were correctly
there are two possibilities of maintaining that voltage:
defined and verified based on manufacturer’s data in order to
construct a testing facility for the investigation of contaminated 1. From the LV side of the PT (Fig. 1).
insulators. A short-circuit current was evaluated to comply with the
existing regulations in this field.

Key Words

High voltage, testing, pollution, leakage current, Jordan

1. Introduction

The High-Voltage Pollution Testing Center (HVPTC) was


designed to test various types of insulator strings for high- Figure 1. Power supply from LV side.
voltage (HV) transmission lines under natural pollution
conditions. The objectives of these investigations are: In this case, the control system and measuring equip-
ment may be affected when high leakage current appears on
1. to determine the severity of site conditions, which the surface of the polluted insulators before flashover. To
represents the desert in terms of type and degree of avoid that, a shielding transformer seems to be necessary
pollution; to separate the control system and measuring equipment
2. to maintain the proper insulation level of HV trans- from the test circuit.
mission lines (types and number of insulators per
string); 2. The other possibility is to feed the control desk and
3. to accumulate information about the pollution of insu- measuring equipment from the HV side of PT through
lators, which will be used in the future to calculate the pole-mounted transformer 33/0.4 kV (Fig. 2).
probability of flashover and the risk of failure of HV
transmission line insulation.

2. Power Supply

The HVPTC is located at Qatrana substation (south of


Amman) and is connected to 33 kV busbar at substation by
350 m power cable through 33/0.4 kV; 100 kVA, delta–star
connected, transformer.
The measuring and control equipment is connected
to low-voltage (LV) side of the power transformer (PT).
∗ Department of Electrical and Computer Engineering, Applied Figure 2. Power supply from HV side.
Sciences University, Amman, Jordan; e-mail: Hobeid50@yahoo.
com In this case, two phases of the LV side of PT are loaded
(paper no. 203-3249) and the other one will be open circuit.
168
The technical data of the PT is as follows: connection of primary windings of HV HT VHV = 101.2 kV,
and 202.2 kV in the case of parallel connection.
Connection: delta–star
Apparent power: S = 100 kVA
Impedance voltage: UZ% = 5.5% 3.1 Voltage Regulator
Active component of impedance voltage: UR% =
0.081% (estimated value) The primary winding of the VR is connected to line voltage,
Reactive component of impedance voltage: UX% = and the voltage at the secondary winding may be changed
5.4994% in the range of 0–0.38 kV; this winding is connected to the
Single-phase short-circuit level at 33 kV busbar at terminals of primary windings of HV TT. The power of
Qatrana substation is: Ssc = 87 MVA VR is equal to 700 kVA.
The most important characteristics of VR are the
variation of its power and voltage impedance during the
3. Characteristics and Parameters process of regulation.
of HV Equipment Table 1 shows the values of power and voltage
impedance of VR when the voltage is changed from 100%
The most important HV equipment in the testing cir- to 13%.
cuit is the HV transformer and the VR. The parameters It is necessary to point out here that the variation
of HV testing transformer (TT) are primary voltage up of impedance of VR will affect the value of short-circuit
to 0.380 kV, secondary voltage up to 350 kV, apparent current of the testing circuit.
power STT = 700 kVA, impedance voltage UZ% = 14.75%, Table 2 and Fig. 5 show the value of short-circuit
active component of impedance voltage UR% = 1.02%, and current of the regulator with the variation of voltage at the
reactive component of impedance voltage UX% = 14.71%. terminals of secondary winding of the VR.
The primary winding of TT consists of two windings, Table 2 and Fig. 5 show that the process of voltage
and this construction permits the connection of these two regulation is accepted in the range of 100–45%. As the
windings in series or in parallel. In each case we obtain voltage decreases, the short-circuit current increases and
different transformation ratio and values of HV side of will reach its maximum value when the voltage at the
the transformer. For series connection (Fig. 3) the rated terminal of the secondary winding is equal to 54% of its
transformation ratio n will be equal to 460. The value of nominal value, and this is very important in pollution tests.
the HV side is 175 kV. When the VR is operated with HV TT, the variation of
In the case of parallel connection of primary windings short-circuit current at HV side of TT during the process
(Fig. 4), the nominal transformation ratio is equal to 921 of voltage regulation is shown in Table 3.
and the value of voltage at HV side of TT will be 350 kV,
and this is the maximum voltage that might be obtained
from the TT. 4. Short-Circuit Current Calculation
In some cases it is required to change the value of the
applied voltage to the terminals of primary windings of HV In HV testing techniques, the short-circuit current must
TT, and this can be done by means of VR. In case of series be calculated for any testing circuit. As an example, when
the testing object is short circuited due to flashover, the
short-circuit current will cause a voltage drop, which will
affect the actual value of the HV that has been applied to
the test equipment.
In pollution testing, when the surface of insulator is
clean (for natural pollution this is the case at the beginning
of the test), the value of leakage current will be very small
(about a few milliamperes), and therefore the associated
voltage drop is negligible. It has been found that the surface
impedance of an individual unit, as the moisture condition
Figure 3. Series connection of primary winding. progresses, is reduced and changed from capacitive at the
beginning of the test to resistive when the sallination
activity appeared. This means that the value of leakage
current will be of high amplitude before flashover, and
will be raised very much during flashover. Therefore, the
testing voltage will be distorted due to voltage drop in
these conditions.

4.1 Testing Circuit

The testing circuit for the main case is depicted in Fig. 6.


Figure 4. Parallel connection of primary winding. In this case the value of voltage at the terminals of HV
169
Table 1
Values of Voltage Impedance during Regulation

Voltage Voltage Apparent Impedance Active Reactive


V (V) Regulation V (%) Power* S (kVA) Voltage* (Z% ) Component* (R) Component* (X)
380 100 700 5.7 6.9 7.2
205 54 378 5.1 3.2 3.4
141 37 259 10.1 4.5 4.7
87 23 161 20.0 5.6 5.8
49 13 91 43.0 6.8 7.0
∗ These are measured values during testing of VR.

Table 2 Table 3
Values of Short-Circuit Current during Effect of Voltage Regulation on Short-Circuit
Regulation Current of HV Side of TT

Voltage Regulation Short-Circuit Current Voltage Regulation* Short-Circuit Current**


V (%) Isc (%) V (%) Isc (%)

100 100 100 100

90 101 90 80

80 101 70 77

70 103 65 72.5

60 109 54 62

54 113 37 40

50 111 23 23
∗ 100% of voltage corresponds to 380 V and 100% of
45 100
short-circuit current corresponds to 32317.6 A.
∗∗ I
40 65 sc is the short-circuit current at the HV winding of
TT when it is connected in series with VR in testing
30 40 circuit.

20 22
Note: 100% of voltage corresponds to 380 V and 100%
of short-circuit current corresponds to 32317.6 A.

Figure 6. Testing circuit.

and the applied voltage is equal to 380 V. In this case the


testing object is subjected to 350 kV at the HV side of TT.

Figure 5. Short-circuit current as a function of voltage at 4.2 Short-Circuit Calculation


the terminal of VR.
The equivalent circuit for short-circuit current calculation
winding of TT is equal to 350 kV, and the applied voltage is shown in Fig. 7.
to the primary winding of VR is phase-to-phase voltage The reactance of the source in ohms referred to 33 kV
(380 V) and is taken from two phases of 33/0.38 kV PT. side is equal to 12.52 Ω; the resistance and reactance of
The primary windings of TT are connected in parallel, PT in ohms referred to 380 V side are equal to 0.0012 and
170
current delivered by the transformer, if the test object is
short circuited at the test voltage, is not less than 1 A rms.
Expectations for requirement on steady-state short-
circuit current are:

• For dry tests on small samples of solid insulation,


insulating liquids, or combinations of the two, a short-
circuit current of the order of 1 A rms may suffice;
• For tests under artificial pollution, the required short-
circuit current depends on the ratio of series resistance
Figure 7. Equivalent circuit of the testing circuit. Rs to the steady-state reactance Xs of the voltage
source, including the generator or supply network at
the test frequency (Table 4).
0.008 Ω, respectively. The resistance and reactance of VR
at full voltage are equal to 6,900 and 7,200 Ω, respectively.
All parameters of the circuit are referred to 33 kV side Table 4
and expressed in per units (pu). Effect of Source Impedance
The total resistance and reactance of the short- on Short-Circuit Current
circuited circuit are equal, respectively, to 0.0554 and
0.2349 pu, and the R/X ratio is equal to 0.2358 pu. The Rs /Xs 0.1 0.1–0.2 0.2–0.3
short-circuit current is equal to 4.14 pu, which is equivalent Isc (A rms) 6 8 12
to 8.28 A. The reactance in ohms per phase is equal to
42.3 kΩ.
The most important condition for pollution tests is the In IEC publication 507 [4] the requirement for test
maximum permissible voltage drop caused by the leakage voltage is defined as:
current pulse occurring during the whole test. In order to
have consistent and comparable results on all insulators, Throughout the test, the insulator shall be contin-
the test circuit must fulfil the condition that the voltage uously energized at the specified test voltage which
drop during the whole test does not exceed 5% [1]. Then generally is the highest line to earth voltage of the sys-
the voltage drop for our test circuit may be calculated by tem in which the insulator is to be used. The frequency
the following formula [2]: shall lie between 48 Hz and 62 Hz.
s ! The minimum short-circuit current of the testing
I R/X I2 1 plant at the test voltage depends on the ratio resistance/
∆V % = 1 + − 1− 2
Isc 1 + (R2 /X 2 )
p
Isc 1 + (R2 /X 2 ) reactance (R/X) of the test voltage source. Table 5 gives
the limits of the short-circuit current of the testing plant
The voltage drop in our test circuit is 3.5%, which is (Isc ) that are recommended for different values of R/X.
consistent with the above-mentioned requirements.
Table 5
Minimum Short-Circuit Current
5. IEC Recommendations for Pollution Test as a Function of R/X Ratio

At the present time there are two IEC recommendations R/X Minimum
regarding pollution test:
Salt Fog Solid Layer Short Circuit
1. HV test technique, Part 2: test procedure publication Current (A)
Method Method
60-2, 1973
2. Artificial pollution tests on high-voltage insulators to 0.05 0.05 5
be used on AC systems, publication 507, 1975 0.05–0.15 0.05–0.15 7
The first recommendation defines the requirements for 0.15–0.5 0.15–0.3 10
the transformer test circuit as:
0.5–1.5 0.3–0.5 15
The voltage in the test circuit should be stable enough
to be practically unaffected by varying leakage cur-
Various HV laboratories all over the world have dif-
rents. Partial discharges, or pre-discharges in the test
ferent voltage source characteristics. Table 6 shows the
object, should not reduce the test voltage to such an
voltage source characteristics of some testing facilities [5].
extent and for such a time that the measured disrup-
It should be noted here that the above-mentioned
tive discharge voltage of the test object is affected [3].
recommendations, which were in effect in the 1980s, are
This is usually achieved if, simultaneously, (1) the total not sufficient. It is more accurate to relate the creepage
capacitance of the test object and any additional capacitor distance (mm/kV) to short-circuit current of the testing
is not less than about 1000 pF; and (2) the steady-state circuit. Table 7 shows this relationship.
171
Table 6
Voltage Source Characteristics of Some Testing Facilities

Laboratory Voltage Source Characteristics


Nominal Nominal Short- R/X
Voltage Circuit Current
(kV) (A)
Bonneville Power 290 18 0.36
administration
Ceraver 250 18 0.5 Figure 8. Direct connection of two earthing systems.
ENEL 350 50 0.5
6.1 Ground Resistivity at Qatrana Substation
Institute de recherche 200 43 0.2
d’Hydro Quebec Ground resistivity at Qatrana substation (at the site of
Lapp Insulator 500 23 – HV PTC) was measured during May. Four measurements
were performed at various points, and the average value of
NGK Insulator 200 11 0.1 resistivity was found to be equal to 30 Ω m.
The earthing system of HVPTC will consist of two
Ohio Brass Co. 250 16 –
parts:
Ontario Hydro 350 23 0.51
• Direct connection to earthing system of 132/33 kV
Project UHV 150 22 1.78 substation
• Earthing mesh at HVPTC
University of Southern 50 4 –
California To avoid the rise of potential in HVPTC due to faults
in 132/33 kV system, a direct and reliable connection must
be maintained between the two earthing systems through
(1) the sheath of the power cable and (2) two strips of
Table 7
copper, the cross-sectional area of which must be not less
Relationship between
than 95 mm2 each (Fig. 8).
Leakage Distance to
Short-Circuit Current
6.2 Earthing Mesh
Leakage Path Short-Circuit
(mm/kV) Current (A) At HVPTC earth mesh consists of horizontally laid copper
strips as shown in Fig. 8, the cross-sectional area is 95 mm2 ,
16 6
and the contact area between the equipment and the earth
20 9 mesh must not be less than 200 mm2 . The strips must
be laid at 800 mm below the surface of the ground. The
25 12–15
earth resistance of this mesh was calculated and is equal to
31 18–21 0.37 Ω.

6.3 Control of Voltage Gradients


outside the Fence
6. Earthing System
The HVPTC will be protected by means of a metallic
Earthing, fencing, and shielding are very important factors
fence. In this case, the potential outside the metallic fence
in HV facilities and are intended to prevent risk to persons,
during ground faults should be controlled. The best way of
installations, and apparatus. The main function of earthing
reducing the value of this potential is to put a horizontal
systems is to provide safety for the working personnel
copper strip 1 m outside the fence at 1.5 m below the
during ground faults and to protect equipment; therefore,
ground level.
step and touch voltages must be kept at acceptable limits
In HVPTC all tests will be carried out at power fre-
during ground faults.
quency voltage, and it is not necessary to take precautions
For HV substation, standards indicated that the earth-
and protection against impulse voltage.
ing resistance must be less than 0.5 Ω. Some standards
indicate that step and touch voltages must be less than
250 V for clearing time of ground faults less than or equal 7. Measuring the Leakage Current
to 0.5 s. Therefore, step and touch voltages should be kept
less than 125 V for clearing time of ground faults in the There are several methods, in pollution tests, for measuring
range of 0.5–1.0 s. site severity. One of these methods is the leakage current
172
method. The essence of the method is to measure, for a 171–380 V. In this range the effect of the impedance
given insulator, by means of laboratory test, the highest of VR on the short-circuit current of the test is small.
leakage current as a function of the pollution severity at a 4. It is recommended that the leakage distance (path) per
given applied voltage. Usually, the criteria for dimensioning kilovolt of system voltage be related to the short-circuit
insulation for a polluting environment are based on the current of testing circuit.
recording of highest leakage current peak [6]. Two types of 5. The earthing system for HVPTC consists mainly of
measurements must be available: 95 mm2 copper strips installed at 800 mm below ground
level. The centre is surrounded by copper strips at
• a measure of the value of leakage current during the 1.5 m below ground level to control the potential
test; outside the metallic fence.
• a count of the number of leakage current pulses above 6. As the proposed measuring equipment is capable of
a specific value. measuring and recording leakage currents of very low
values, some modifications were suggested so as to
The measuring and recording equipment at the Center extend the range of measuring values from 2 mA up
was initially capable of recording and measuring the value to 2,000 mA; the intermediate values are 20 mA and
of leakage current in the range of microamperes up to 200 mA.
0.5 A. Taking into account that the leakage current may
reach high values, certain modifications were made. The
shunt in the measuring system was changed in order to References
make possible the measuring of leakage currents of various
amplitudes. The measuring range will be 2, 20, 200, and [1] M.P. Verma, Test circuit data for pollution tests, Forschungs-
2,000 mA. The step in the above-mentioned range is 10 due Gemeinschaft Fur Hochspannungs Und Hochstromtecchnik E.V.
[2] I. Kolossa, Zusammenhaenge zwischen den Fremdschichueber-
to the construction of the measuring system. schlag nanhgebenden Kenngroessen von Hochspannungsanla-
Also, to protect the shunts from pollution and atmo- gen, Teil 1 und 2, Archiv fuer technisches Messen, Blatt Z
spheric condition, waterproof boxes of steel sheet covered 734-3 u. Dez.
[3] High voltage test procedure technique, part 2, Test procedure
with hinge opening and age-resisting gaskets were installed.
publication 60-2, 1973.
Each box will contain four shunt resistances with the nec- [4] IEC Publication 507, Artificial pollution tests on high voltage
essary outputs and inputs for measuring cables. The pulse insulators to be used on ac systems, 1975.
counters were installed latter. [5] The AC clean fog test for contaminated insulators, Prepared
by the task force members on testing IEEE insulators, IEEE
working group on insulator contamination, lightning and insu-
lator subcommittee, IEEE Transactions on Power Apparatus
8. Conclusion and Systems, PAS-102 (3), 1983.
[6] J. Riubrugent et al., Design of external insulation for pollution
withstand based on “in situ measurements of leakage current,
1. HVPTC is connected to 33 kV busbar of Qatrana CIGRE Symp., Stockholm, 1981.
substation through 350 m of cable and 33/0.38 kV
three-phase PT. The operating voltage of control sys-
tem and measuring devices is 220 V; they are separated Biography
from the testing circuit by means of shielding trans-
former, which is mounted in the control desk. Control Hani Obeid received his M.Sc.
system and measuring devices are connected to LV and Ph.D. degrees in power
side of PT through distribution board with 2,000 A systems and networks from
isolator. Leningrad Polytechnic Institute in
2. Characteristics and parameters of all HV equipment 1974 and 1980, respectively. He is
were correctly defined based on information and test the author or co-author of eight
results obtained from the manufacturer. The construc- technical books. He is a Senior
tion of HV TT’s permits one to obtain two main values Member of IEEE, PE. Currently
of transformation ratios depending on the connection he is with Applied Sciences Uni-
of HV TT primary windings. versity in Amman and at the same
3. The characteristics of VR show that the process time is a Technical Advisor to a number of consulting firms
of voltage regulating is accepted in the range of in Jordan and Saudi Arabia.

173

You might also like