Pruebas y Ajustes
Electronic Modular Control Panel II (EMCP II) For MUI Engines
Número de medio -SENR5809-05 Fecha de publicación -01/10/2001 Fecha de actualización -30/01/2002

i00946745

EMCP Electronic Control (AC Transformer Box) - Replace


SMCS - 1409-510

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sisweb/s... 10/09/2018
3412C Generator Set 81Z14501-UP(SEBP2576 - 66) - Documentación Página 2 de 3

Illustration 1 g00483140

AC Transformer Box (ATB)

The ATB is located on the subpanel within the control panel.

Replacement Procedure

1. Shut down the engine. Remove the positive lead wire from the battery.

2. Make sure that all wires at the terminal strip of the ATB are marked with the respective
termination point. During reassembly, these wires must be reattached to the correct
terminal. Remove all external wires from the terminal strip.

3. Disconnect the ATB connector from the harness connector.

4. Remove all mounting nuts and mounting screws that fasten the ATB to the subpanel.
Remove the ATB.

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sisweb/s... 10/09/2018
3412C Generator Set 81Z14501-UP(SEBP2576 - 66) - Documentación Página 3 de 3

5. Place the new ATB in the subpanel. Install the mounting nuts and mounting screws. Tighten
the mounting nuts and mounting screws.

6. Reconnect the harness connector to the ATB. Reconnect all the wires to the terminal strip
that were removed. Reconnect the positive lead wire to the battery. If necessary, see the
"Generator Set Wiring Diagram" in Testing And Adjusting, "Schematics and Wiring
Diagrams".

7. Program the bar code (calibration value) for the voltmeter/ammeter into the GSC. See
Systems Operation, "Voltmeter/Ammeter Programming OP8".

8. If the genset is operating in parallel with another genset and the voltmeter values match,
then reprogram the AC offset. See Systems Operation, "AC Offset Adjustment OP10".

Copyright 1993 - 2018 Caterpillar Inc. Mon Sep 10 16:57:49 UTC-0300 2018 
Todos los derechos reservados. p230vle 
Red privada para licenciados del SIS.

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sisweb/s... 10/09/2018

You might also like