You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/305827817

An Analysis of Open-Phase Fault in Power Generation Station

Conference Paper · September 2016


DOI: 10.1109/NAPS.2016.7748004

CITATIONS READS
8 1,425

3 authors, including:

Saeed Mohajeryami Zia Salami


University of California, San Diego University of North Carolina at Charlotte
48 PUBLICATIONS   365 CITATIONS    7 PUBLICATIONS   40 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Improving Customer Baseline Load (CBL) calculation for residential customers View project

Lightning Transients Analysis View project

All content following this page was uploaded by Saeed Mohajeryami on 19 October 2017.

The user has requested enhancement of the downloaded file.


An Analysis of Open-Phase Fault in Power
Generation Station
Saeed Mohajeryami, Milad Doostan, Zia Salami
Energy Production and Infrastructure Center (EPIC)
Electrical and Computer Engineering Department
University of North Carolina at Charlotte
Charlotte, NC, USA
Email: {smohajer, mdoostan, zsalami}@uncc.edu

Abstract—This paper attempts to investigate and analyze the tripped by over-current relaying and has not been identified as
electrical characteristics present on the power grid when an an open phase presents a hazard to personnel in the area. This
open-phase event occurs at an off-site transformer. In order hazard would be greatly reduced by the warning presented by
to conduct such task, this paper uses transformer, load, and
connection data obtained from a real power plant to simu- open-phase identification. As a result, various works have been
late several different power system configurations and analyzes carried out for the purpose of detecting such events.
various model responses in EMTP-RV software. Several testing The authors in [6] intend to address different technical
scenarios that encompass a variety of loading conditions that can issues associated with detecting an open-phase condition of a
be encountered at the power plant are also defined. At the end, power plant auxiliary transformer by considering various load
open phase simulation for these scenarios is carried out and all
results are presented and discussed in detail. levels. To carry out such task, they apply different simula-
Index Terms—open phase fault; transformers; voltage study; tion techniques including frequency domain and time domain
sequence currents; EMTP-RV methods. According to their results, the system response to an
open phase event depends on the transformer connection and
I. I NTRODUCTION core configuration.
Several recent events in which protective relaying systems In [7], the authors simulate and examine the terminal behav-
did not correctly detect open-phase conditions on three-phase, ior of a power plant auxiliary transformer under an open phase
which led to safety related issues at many power plants, condition on its primary side by employing electromagnetic
have necessitated the power plants’ operators to address the transient simulations. The transformer is modeled in PSCAD
difficulties inherent in open-phase detection [1]. software by using data gathered from manufacturer report.
A prime example of this situation is the loss-of-phase event Their results provide insight into the per-phase voltage magni-
at the Byron power plant in Jan. 2012, in which a loss of the tude and angles. Besides, positive, negative, and zero sequence
phase C conductor, which was feeding the off-site transformer voltages and currents generated during the loss of one or two
was not detected. This condition led to a voltage imbalance phases of the transformer’s primary side are evaluated. In
that cascaded down to the station buses through the system another attempt, the authors in [8] analyze the open phase con-
off-site transformer. Since this open-phase condition was not ditions in three phase transformers. Their work examines the
detected by any of the protective relays, the condition was impact of transformer’s winding and core construction on the
allowed to exist for an extended period of time [2]. Similar fault voltage and currents of the low-side of the transformer.
open-phase events at other power plants went undetected for According to their results, fault voltage and current on the low-
long periods of time in one case for 21 days [3]. Moreover, in side greatly depend on the winding configuration as well as the
a recent case in which an Emergency Diesel Generator (EDG) transformer’s core construction. Nevertheless, the simplified
failed to start after an undetected loss of two phases, the event test system used by the paper, neglects many other parameters
caused damage to several motors [4]. including the different loading scenarios. Moreover, Authors
Since the specific electrical quantities involved in the loss in [9] analyzed these power transformers’ inrush current in
of one or two phases can vary greatly depending on system the presence of such internal faults. Furthermore, in [10],
configuration, equipment designs, level of loading, and types the authors explored how to detect such faults. Authors in
and connections of loads [5], it has so far proven challenging [11] recommended the application of a positive temperature
for the industry to design a protective relaying system which coefficient (PTC) devices, which can be connected in series
reliably recognizes open-phase conditions and trips appropri- with a circuit breaker and disconnect it. Moreover, authors
ately. As a matter of fact, the ability to detect open-phase in [12] assessed the transient recovery voltages (TRV) in
conditions allows plant operators to respond appropriately order to improve the post-fault situation in the presence of
when they occur. In addition, identifying open-phase events superconducting fault current limiters (SFCL). Besides, there
can reduce dangers to individuals in the vicinity of the are some wide-area control approaches to mitigate the impact
condition. A hanging, high-voltage cable that has not been of disturbance propagations of such faults [13]- [16].
Fig. 1: Schematic of the power system model, modeled in EMTP-RV

This paper attempts to investigate and analyze the electrical plants, which allows flexibility in loading levels and types, as
characteristics present on the power grid when an open-phase well as the potential for various transformer types or other
event occurs at an off-site transformer. Off-site transformers similar changes. The overview of the model can be seen in
typically provide operating power to a power plant from the Fig. 1.
grid when the plant is unable to provide its own power, such All components that are used in the model are discussed in
as upon startup or during accident scenarios. As such, loss of detail as follows.
a phase at the transformer can result in severe unbalances and
• Power Supply: The power supply to the system is a grid
adverse operating conditions for critical plant machinery and
connection modeled using a voltage source set at 345kV,
infrastructure, including safety related equipment. However,
line-to-line.
since different power plants have a variety of configurations in
the way they are connected to the power grid, a loss of phase
• Transformer: A 3x1 phase, 3 winding, 345/6.9/4.16kV,
on one configuration might not produce the same observed
Yg-Yg-Yg connected (solid ground on primary, resistive
conditions as loss of phase on another configuration. The goal
ground on secondary and tertiary), 40/35/5MVA nominal
of this paper, therefore, is to simulate a specific model in
transformer. For the transformer core, a 3-legged core is
a variety of configurations to gather data about the system
selected. The secondary and tertiary grounding resistors
response to open phase conditions. In order to overcome
are calculated to limit the ground current in the event
the problems associated with transient phenomenon, several
of a ground fault to 600A. For the secondary winding,
approaches are suggested in the literature.
The organization of this paper is as follows. In section II, the resistor calculation produces 6.64 ohms, and for the
the test system is presented and its components are described tertiary winding, 4.00 ohms.
in detail. Then, in section III, several testing scenarios that
encompass a variety of loading conditions that can be en- • Buses: Three types of electrical buses are modeled: The
countered at the power plant are defined, and various open switchyard high-side bus, an Engineered Safeguard (ES)
phase types are described. Also, in this section the testing bus, and a Balance of Plant (BOP) bus. The switchyard
procedure is explained. Afterwards, open phase simulation for high-side bus is simply modeled as the connection
these scenarios is carried out and all results are presented and between the transformer and the grid interconnect. It
discussed in section IV. Finally, section V closes the paper by is modeled as an ideal (no impedance), 3-phase bus in
drawing conclusions. EMTP-RV. An ES bus runs safety related equipment,
such as safety injection pumps and critical equipment
II. S YSTEM MODELING for accident situations, and as such, would normally
The power system model is determined based on the generic be lightly loaded during plant normal power operation.
layout of the typical offsite power grid connection at power The BOP bus provides power for non-safety loads
such as steam-side pumps (e.g. feedwater, condensate, is applied and all relevant measurements are taken once the
circulating water), lighting, HVAC, etc. The ES and system reached its new steady state. Similar procedures are
BOP buses are modeled at 4.16 and 6.9kV, respectively, repeated for ”refueling outage”, ”accident”, and ”lowest load
as these are the conditions at Byron power plant. Both conditions”, with the only change being the respective levels
buses are modeled as ideal, 3-phase buses. at which the static loads are set.
According to Table IV, accident conditions with motor start
• Load: Two types of electrical loads are modeled on each on ES are simulated by setting the ES and BOP static loads
bus: asynchronous inductive motor loads, and static PQ to 80% of their nominal operating powers. The BOP motor
loads. load begins the simulation already turned on at 100% power;
A. Motor Loads: An asynchronous, inductive motor load however, the ES motor load is switched on and run at 100%
is modeled on each low-side bus according to the infor- power after the open phase is applied to the system. All
mation provided in Table I. relevant measurements are taken before and after the ES motor
B. Static Loads: Static loads are modeled according to load is switched on. Similar procedures are repeated for lowest
the information presented in Table II. load with motor start on ES, and lowest load with motor start
on BOP with the only change being the load levels and the
• Switches: Open-phase conditions are simulated using an bus on which the motor starts.
ideal, three-phase switch placed at the high-side of the All conditions that are outlined in Tables III and IV are
transformer. The switches are also placed between the repeated for each type of open phase.
buses and motor loads to allow the motors to be switched
on after the occurrence of the open phase. These motor B. Open Phase Types
control switches will be operated as three phase devices, This subsection outlines the exact manner in which the open
all closing simultaneously. phase events are applied to the system. All open phase faults
are applied in simple open phase (case 1), open phase with
III. T ESTING PLAN AND PROCESS line-to-ground fault on the grid side (case 2), open phase with
The testing plan refers to the types of open-phase events that line-to-ground fault on the transformer high-side (case 3), or
will be placed on the power system, and to the configuration double open phase (case 4).
of the power system during each open phase. The individual A further subdivision of cases 2 and 3 is the insertion of
sections of the plan were determined based on various sources resistances in the ground faults in addition to testing solid
and will be discussed individually as follows. ground faults.
The resistances used for the ground faults (0, 100, and
A. Power System Configurations 400 ohms) are decided based on [20]. They represent high,
This subsection outlines the steady state and motor start middle, and low estimates of ground resistance, depending on
conditions. This refers to the conditions on the power system the type of material in contact with the downed line and/or
when the open phase occurs. Motor start means that an open how solid the contact between the line and ground is. Figure
phase will occur on the system and a motor will then be 2 demonstrates the four basic open phase types.
switched into service. Tables III and IV show the steady state
and motor start scenarios that will be tested, respectively. C. Testing Procedure
According to Table III, normal power operation is simulated All faults are placed exactly as described earlier, including
by setting the ES and BOP static loads to 20% and 100%, load values and system configurations for each case. The
respectively, of their nominal operating powers. That is to timing of open phase fault placement and motor start varies
say, load level (%) only refers to the level at which the depending on the exact scenario and case. Before data are
static loads are set. Motor loads are always run at full power. collected for each test, a sample simulation is performed
With all components at steady state, the specific open phase to determine how long the system requires to reach steady
state, before and after fault or motor start initiation. The open
TABLE I: MOTOR LOADS INFORMATION phase fault or motor start is then applied to the system at
the appropriate time and the simulation is run long enough to
Power Apparent Power Efficiency
Bus Type
(hp) (MVA) (%)
ensure that no normal system transients are included as fault

BOP 7000 6.184 99


ES 1000 1.285 99

TABLE II: STATIC LOADS INFORMATION


Real Power Reactive Power Voltage
Bus Type
(MW) (Mvar) (kVLL)

BOP 25.934 12.56 6.2


ES 3.344 1.619 4 Fig. 2: Four basic open phase types
TABLE III: STEADY STATE TESTING CONFIGURATIONS
Condition ES Load Level BOP Load Level

Scenario 1: Normal Power Operation 20% (P=0.6688MW, Q=0.3238MVar) 100% (P=25.934MW, Q= 12.56MVar)
Scenario 2: Refueling Outage 20% (P=0.6688MW, Q=0.3238MVar) 20% (P=5.1868MW, Q= 2.512MVar)
Scenario 3: Accident 100%(P=3.344MW, Q=1.619MVar) 80%(P=20.7472MW, Q= 10.048MVar)
Scenario 4: Lowest Load 10%(P=0.3344MW, Q=0.1619MVar 10%(P=2.5934MW, Q= 1.256MVar)

TABLE IV: MOTOR START TESTING CONFIGURATIONS


Conditions ES Load Level BOP Load Level

Scenario 5: Accident Conditions with


80%(P=2.6752MW, Q=1.2952MVar) 80%(P=20.7472MW, Q=10.048MVar)
Motor Start on ES
Scenario 6: Lowest Load with
10%(P=0.3344MW, Q=0.1619MVar) 10%(P=2.5934MW, Q=1.256MVar)
Motor Start on ES
Scenario 7: Lowest Load with
10%(P=0.3344MW, Q=0.1619MVar 10%(P=2.5934MW, Q=1.256MVar)
Motor Start on BOP

or motor start effects. Because the normal transients change in it is caused by the interaction between the BOP and ES buses
length depending on the exact scenario being tested, the data through the transformer. If the BOP has much heavier load,
sets for each scenario can vary from 2 seconds to 40 seconds. it has a greater effect on sequence currents, which are then
partially forced onto the ES side.
IV. R ESULTS AND DISCUSSION
All other cases and scenarios produce similar results. For
After processing and analyzing the data, the authors have the specific transformer windings, grounding configuration,
drawn some conclusions that can serve as indicators of the and lack of core, tested in this paper, tripping the circuit on
different types of open phases studied. These conclusions detection of I2 would appear to be a legitimate response to
are not intended to be definitive, but rather serve as starting isolate the open phase fault. However, other types of faults
points for anyone seeking to look for signs of an open phase produce I2 ; hence, this is not a guaranteed method to positively
condition. identify an open phase condition. It is possible that using I2
A. Significant negative sequence current for all open phases detection in conjunction with some of the other conclusions
conditions discussed in what follows would be sufficient to make a
positive open phase identification.
All open phase cases produce significant negative sequence
current (I2 ) on the low-side buses, even for lightly loaded B. Zero sequence current is Split Equally Between Buses
(10%) scenarios. The exact level of I2 with respect to positive
sequence current (I1 ) varies depending on the loading scenario For all Cases and Scenarios, the zero sequence current (I0 )
and case; however, I2 is always significant and detectable. flowing through the BOP bus is equal to the I0 flowing through
Examples of I2 behavior for scenario 1 are illustrated in the ES bus, always to within 5A, but usually with less than
Figures 3 and 4. 1A difference. However, the authors believe this behavior is
From Figure 3, it is understood that the negative sequence not specifically related to the open phase condition, but rather
current on the ES bus (scenario 1, case 1) increases from 0 to to the selection of the low-side transformer grounding resistor.
approximately 1100 A upon open phase initiation at t=0.5s.
C. Phase voltage depends on exact open phase application
The negative sequence current is actually greater than the
original positive sequence current in this simulation. The phase voltages for each bus vary substantially depend-
From Figure 4, the negative sequence current on the BOP ing on the specific case being tested. For case 1 and case 2, the
bus (scenario 1, case 3) increases from 0 to approximately three phase voltages settle at three different levels. The basic
1800A upon open phase initiation at t=0.5s. The negative pattern is: the phase B stays close to the pre-fault voltage,
sequence current is less than the positive sequence current in the phase C (open) drops to the lowest, and the phase A
this simulation; however, it is still a significant and detectable approximately falls between B and C. The authors believe
quantity. The general trend of the I1 to I2 ratio is that negative that this behavior is related to phase rotation; that is, if the
sequence current is greater than the positive sequence current phase rotation was reversed (ACB instead of ABC), the phase
for the ES bus and the opposite for the BOP bus. This A would stay at pre-fault voltage, the phase B would fall, and
difference in behavior is likely due to loading levels, since the phase C (open) would remain the same as the previous
100% loading on the ES bus is 5MVA, and 35MVA on the test. Figures 5 and 6 illustrate this behavior for scenario 1,
BOP. Indeed, even light loading on the BOP is larger than the cases 1 and 2.
majority of scenarios on the ES bus. According to Figures 5 and 6, for scenario 1, cases 1 and 2,
With respect to the ES bus having higher negative sequence on the ES bus, the phase B (green) remains at pre-fault voltage,
current than the pre-fault positive sequence, the authors believe the phase C (blue, open) drops by approximately 50%, and the
that this is due to the three winding transformer; that is to say, phase A (red) is roughly the average of B and C.
However, for case 3, phase A and B voltages drop roughly
15-20% from pre-fault voltage, while phase C (open) voltage
drops to approximately half of the A and B levels as illustrated
in Figure 7.
For case 4 (double open phase), all three phase voltages
drop to 15% or less of the pre-fault voltage. While all three
phases are low, the two open phases (B and C) decrease further
than the unopened phase. Figure 8 shows an example of this
system behavior.
From Figure 8, the phase A (red, unopened) has dropped
to 13% of the pre-fault voltage, while the B and C (green and
blue, open phases) have dropped to around 2% of the pre-fault
voltage. Fig. 3: I2 Behavior (Red Line) Fig. 4: I2 Behavior (Red Line)
It is worth mentioning that although the exact levels and on ES bus, scenario 1, case 1 on BOP bus, scenario 1, case 3
percent changes of the phase voltages can vary depending on
the loading and motor conditions, the general pattern of three
different phase voltages holds for all cases.
D. Long motor acceleration times result from double open
phase
Long electrical transient times are observed in the case 4
motor start scenarios. The authors believe that these transient
Fig. 5: ES Phase Voltages for Fig. 6: ES Phase Voltages for
times are likely caused by long motor acceleration times, scenario 1,case1 scenario 1, case 2
which are in turn caused by low voltage and insufficient,
unbalanced current. Figures 9 to 12, show a scenario 7 motor
start on the BOP bus. Figures 9 and 10 show the scenario
with no open phases, while Figures 11 and 12 show the same
scenario with a double open phase on B and C.
Comparing Figures 9 and 11 shows that with no open phase,
the BOP motor draws a peak current of around 4000 A upon
starting at t=2s . However, with a double open phase applied,
the BOP motor has to wait 30 seconds before it can start while Fig. 7: ES Phase Voltages for Fig. 8: ES Phase Voltages for
scenario 1, case 3 scenario 1, case 4
the ES motor is reaching steady state in Figure 11. After the
BOP motor starts at t=30 seconds, the motor is only able to
draw about 220 A of positive sequence current, with severe
unbalances shown by the other sequences.
The voltage graphs tell the same story. Comparing Figures
10 and 12 shows that with no open phase, the BOP bus has
the full pre-fault voltage available after a short startup sag.
However, with the double open phase applied, the ES motor
has unbalanced, low voltages available which drop even further Fig. 9: Sequence Currents for Fig. 10: Phase Voltages for
once the BOP motor switches on at t=30s. scenario 7, No open phase scenario 7, No open phase
The graphs show long, slow changes in the electrical values
while initial motor builds up to speed. Once the initial motor
has reached steady state and the second motor is started, these
values drop even further.
V. C ONCLUSION AND RECOMMENDATION
This paper investigated the electrical response to open-phase
conditions on a power plant. EMTP-RV software was chosen
for simulation of the relevant conditions. Then, a testing plan Fig. 11: Sequence Currents for Fig. 12: Phase Voltages for
scenario 7, case 4 scenario 7, case 4
that included system layout, desired configurations, and equip-
ment to be modeled was developed. The testing plan, also,
covered a range of realistic alignment and loading conditions
at power plant, as well as encompassing the known ways in
which an open phase can develop. All identified alignments,
loading conditions, and open phase types were simulated and [16] J. Lang, S. Pascoe, J. Thompson, J. Woyak, K. Rahimi and R. Broadwa-
the results were presented. At the end, by analyzing the results, ter, ”Smart Grid Big Data: Automating Analysis of Distribution Systems,”
2016 IEEE Rural Electric Power Conference (REPC), Westminster, CO,
the discussions were provided about system behavior during USA, 2016, pp. 96-101.
open phase conditions. The authors believe that the model, [17] M. Rakhshan,et al., ”Design of networked polynomial control systems
data, and conclusions resulting from this study could give with random delays: sum of squares approach,” in International Journal
of Automation and Control, 10(1), 73-86. 2016
insight into open phase conditions, as well as provide a solid [18] M. Dabbaghjamanesh, et al.,”High performance control of grid con-
foundation for researchers who want to extend the study. nected cascaded H-Bridge active rectifier based on type II-fuzzy logic
As a future study, the authors plan to investigate the impact controller with low frequency modulation technique.” International Jour-
nal of Electrical and Computer Engineering (IJECE), Vol.6, no.2, 484-
of various transformer winding types, load connections, and 494. 2016
transformer cores on the open-phase condition. [19] M. Biglarbegian, N. Shah, I. Mazhari and B. Parkhideh, ”Design
considerations for high power density/efficient PCB embedded inductor,”
IEEE 3rd Workshop on Wide Bandgap Power Devices and Applications
ACKNOWLEDGMENT (WiPDA), Blacksburg, VA, 2015.
[20] PSRC Working Group D15 ”High Impedance Fault Detection Technol-
The authors would like to thank Mr. Joel Mathewson, ogy,” March 1, 1996.
Mario Poujol, Volodymyr Habovda, and Lee Easter for their
invaluable contributions to this work.

R EFERENCES
[1] Nuclear Regulatory Commission (NRC), ”Design Vulnerability in Electric
Power System.” Bulletin 2012-03, July 27, 2012
[2] EPRI , ”Nuclear Maintenance Application Center: Development and
Analysis of an Open Phase Detection Scheme for Various Configurations
of Auxiliary Transformers”, 3002000764, May 10, 2013.
[3] Entergy, ”Inoperable 115 kV Line in Excess of Technical Specification
Allowed Out of Service Time” Docket No. 50-333 LER-05-006 (CR-
JAF-2005-05289), February 13, 2006.
[4] International Reporting System For Operating Experience, ”EDG Failed
To Start After Undetected Loss Of Two Phases On 400 kV Incoming
Offsite Supply” IRS No. 8315, June 6, 2013.
[5] S. Khosravani, et al., ”Wide-Area Measurement-Based Fault Tolerant
Control of Power System During Sensor Failure,” Electric Power Systems
Research, Volume 137, pp. 66-75, August 2016
[6] EPRI, ”Analysis of Station Auxiliary Transformer Response to Open
Phase Conditions”, 1025772, June 18, 2012.
[7] N. Y. Abed, F. Ashrafi and K. Chang, ”Simulation and Detection of
Open Phase for Generating Station Auxiliary Three Phase Transformers,”
2014 IEEE PES General Meeting — Conference & Exposition, National
Harbor, MD, 2014
[8] A. Norouzi, ”Open Phase Conditions in Transformers Analysis and
Protection Algorithm,” 66th IEEE Annual Conference for Protective
Relay Engineers, pp. 112-125, College Station, TX, 2013
[9] H. Abniki, et al.,”Identifying inrush currents from internal faults using
symmetrical components in power transformers,” In 2010 IEEE proceed-
ings of the International Symposium on Modern Electric Power Systems
(MEPS), Sept. 2010.
[10] M. Davoudi, J. Sadeh and E. Kamyab, ”Parameter-free fault location for
transmission lines based on optimisation,” in IET Generation, Transmis-
sion & Distribution, vol. 9, no. 11, pp. 1061-1068, 8 6 2015.
[11] V. Sarfi, V. Hemmati and M. M. Arabshahi, ”Simulation of PTC devices
as fault current limiters in power systems by finite element method,”
High Voltage Engineering and Application (ICHVE), 2014 International
Conference on, Poznan, 2014, pp. 1-4.
[12] A. Mohseni, et al., ”Sensitivity analysis and stochastic approach in study
of transient recovery voltage with presence of superconducting FCL,”
Electrical Power and Energy Conference (EPEC), 2011 IEEE, Winnipeg,
MB, 2011, pp. 479-484.
[13] M. Mahmoudi, J. Dong, K. Tomsovic, and S. Djouadi, Application of
distributed control to mitigate disturbance propagations in large power
networks, in North American Power Symposium (NAPS), pp. 16. Oct.
2015.
[14] M. Mahmoudi and K. Tomsovic, ”A Distributed Control Design Method-
ology for Damping Critical Modes in Power Systems” Power and Energy
Conference at Illinois (PECI), IEEE, Feb. 2016.
[15] S. Moghadasi and S. Kamalasadan, ”Optimal Fast Control and Schedul-
ing of Power Distribution System Using Integrated Receding Horizon
Control and Convex Conic Programming,” in IEEE Transactions on
Industry Applications, vol. 52, no. 3, pp. 2596-2606, May-June 2016.

View publication stats

You might also like